Green Mountain & Finger Lakes National Forests Supervisor’s Office Site Construction
Solicitation number
12168120B0001
Issued by

About this file

This solicitation package is for a construction project to build a new Supervisor's Office for the Green Mountain & Finger Lakes National Forests. Key details include:

  • The project involves site work including grading, constructing approximately 1,833 linear feet of roadway with sidewalks and a stream crossing, installing new utilities, site lighting and landscaping.

  • Bids are due by email to the contracting officer by 4:30 PM EST on June 11, 2020. Award will be made to the lowest priced responsive and responsible offeror.

  • The work must be completed by July 1, 2021. Pricing shall be provided for all work in the Schedule of Items with no separate reimbursement for any costs.

  • A 20% bid bond is required for bids over $150,000. Performance and payment bonds of 100% are required upon award for bids over $150,000. Wage determinations for Rutland County, Vermont apply.

View the file

Other files

File Type Posted
AMEND 3_07282020.pdf PDF
AMEND 2_07142020.pdf PDF
AMEND 01_06032020.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

F2

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NUMBER

12168120B0001

2. TYPE OF SOLICITATION

X SEALED BID (IFB)

NEGOTIATED (RFP)

3. DATE ISSUED

05/07/2020

PAGE OF PAGES

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NUMBER 5. REQUISITION/PURCHASE REQUEST NUMBER 6. PROJECT NUMBER

7. ISSUED BY CODE 8. ADDRESS OFFER TO

FOR BID BONDS (ORIGINAL COPIES ONLY): SAME AS BLOCK 7:

ATTN ASHLEY WITMER

All other bid documents must be sent via email to:

ashley.a.witmer@usda.gov

North East Acquisition Team 4 Farm Colony Drive Warren PA 16365

9. FOR INFORMATION

CALL:

a. NAME Ashley Witmer b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS) 814-728-6258 email: ashley.a.witmer@usda.gov

SOLICITATION

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

Green Mountain & Finger Lakes National Forests Supervisor’s Office Site Construction

Submit bid by email to address ashley.a.witmer@usda.gov. Submit completed SF-1442, completed Section B, and completed Section K and bid guarantee. Make sure to annotate the solicitation number in block 1 in the subject of the email. See Bidder Notes and Section L for additional information and instructions.

11. The contractor shall begin performance within calendar days after receiving award, notice to proceed. This performance period is ).

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and electronic copies to perform the work required are due at the place specified in Item 8 by 4:30 PM (EST) local time . If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

b. An offer guarantee is, is not required.

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

STANDARD FORM 1442 (REV. 8/2014)

Prescribed by GSA - FAR (48 CFR) 53.236-1(d)

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES", indicate within how many calendar days after award in Item 12b.)

12b. CALENDAR DAYS

YES NO

X calendar days and complete it within mandatory negotiable. (See by July 1, 2021

X

10X

X

52.211-10

June 11, 2020 mailto:ashley.a.witmer@usda.gov ashleyawitmer Cross-Out

AMOUNTS

OFFER (Must be fully completed by offeror)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NUMBER (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14.)

CODE FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

AWARD (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)

31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA

BY

31c. DATE

STANDARD FORM 1442 (REV. 8/2014) BACK

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) (5 ) 41 U.S.C. 3304(a) ( )

26. ADMINISTERED BY 27. PAYMENT WILL BE MADE BY

CONSTRUCTION RFP 12168120B0001

GMNF

Green Mountain & Finger Lakes National Forests Supervisor’s Office Site Construction

PART I—THE SCHEDULE

SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS

SCHEDULE OF ITEMS

ITEM

NUMBER

DESCRIPTION PRICING INSTRUCTIONS QTY UNIT OF

MEASURE

TOTAL

Green Mountain & Finger Lakes National Forests Supervisor’s Office Site Construction

Work includes, but is not limited to, mobilization, construction management, bonding, insurance, permit fees, field office, traffic controls, temporary utilities (phone, power, sanitation), site clean-up, waste disposal, safety and QC costs, demolition, clearing, grubbing, tree removal, excavation, fill, grading, stormwater structures, catch basins, storm drain lines, erosion control, planting, landscaping, seeding, mulching, sidewalks, aggregate subbase, slope stabilization, asphalt pavement, aggregate shoulders, pavement markings, traffic signage, bollards, security gate, precast concrete culvert, and all costs associated with connecting, constructing and installing the electrical, communication, water, and wastewater utilizes.

This includes all utility connection fees and services.

1 LUMP

SUM $_____________

TOTAL $_____________

Green Mountain & Finger Lakes National Forests Supervisor’s Office Site Construction

B.2 SCHEDULE OF ITEMS NOTES

1. The contractor shall build all costs associated with the contract to include but not limited to; providing labor, superintendence, materials, supplies, equipment, plant, and fees into the Schedule of Items. There will be no separate reimbursement for any costs not included within the schedule of items.

Contractor Acceptance Statement: By signing the offer, the Contractor agrees to all terms, conditions, and provisions included in the solicitation and agrees to furnish any awarded items at the price set in the schedule unless otherwise excepted as follows:

Bidder Notes:

1. Contractor must be registered in www.sam.gov in order to submit an offer on this project. THIS IS A

FREE REGISTRATION.

2. There is no pre-bid meeting for this project. The Directions to site are included in the attached plans and the site is accessible without notice to the Government. Bidders are urged and expected to inspect the site where the work will be performed.

3. This is a construction project which has the following bonding requirements:

- 20% bid bond for bids over $150,000 required with offer submission.

- 100% performance and payment bonds for bids over $150,000 upon award. See Section I for details.

- See Section I for details. Proper bonding forms must be utilized. Forms can be accessed at https://www.gsa.gov/reference/forms

4. Award will be made to one contractor. You must submit pricing for all items, including any option items and/or option years to be considered.

5. Due to mail/delivery limitations as a result of the COVID-19 pandemic, bid bonds must be submitted electronically via email with bids. The original hardcopy bid bond must be sent to the address in Block 8 of the SF1442 and received by 4:30 PM (EST) on June 11, 2020.

6. All questions must be sent to the Contracting Officer in writing via email.

http://www.sam.gov/ https://www.gsa.gov/reference/forms

Green Mountain & Finger Lakes National Forests Supervisor’s Office Site Construction

SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

Scope of Contract:

The project includes site work associated with the construction of a new Supervisor’s Office for the Green Mountain & Finger Lakes National Forests (GMFL) that will be located in Mendon, Vermont, approximately 5 miles east of the Route 7 and Route 4 intersection. GPS Coordinates of the site are 43°39’6.13”N, 72°53’42.90”W. The new Supervisor’s Office will be approximately 10,000 square feet and house 52 permanent employees and 13 seasonal employees. The existing site is a 10.5-acre vacant lot with forest, wetlands, perennial and intermittent streams; there are no existing permanent or temporary structures located on the site. Site work for this project includes, but is not limited to, site grading; constructing approximately 1,833 linear feet of roadway that includes sidewalks, stream crossing, parking, pavement markings; constructing new utilities including water, sewer/septic, storm pipe, underground electric, and underground telephone lines; site lighting and landscaping.

Project Location: Reference Section J and Attachments (Project Plans)

The magnitude of construction is:

Between $1,000,000 and $5,000,000.

AGAR 452.211-72 Statement Of Work/Specifications (FEB 1988)

The Contractor shall furnish the necessary personnel, material, equipment, services and facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section J.

AGAR 452.211-73 Attachments To Statement Of Work/Specifications (FEB 1988)

The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.

C.1 Sustainable Acquisitions

The Contractor shall comply with FAR Part 23 Sustainable Acquisition Policy and all associated laws, rules, regulations, and executive orders referenced therein. Contracts that include the supply of products and for the acquisition of services (including construction) that include the supply of products, require that the products provided are—

(1) Energy-efficient (ENERGY STAR® or Federal Energy Management Program (FEMP)-designated); (applicable if FAR Clause 52.223-15 is included)

(2) Water-efficient; (applicable if FAR Clause 52.223-15 is included)

(3) Biobased; (applicable if FAR Clause 52.223-2 is included)

(4) Environmentally preferable (e.g., EPEAT®-registered, or non-toxic or less toxic alternatives); (applicable if FAR Clause 52.223-13,14, or 16 are included)

(5) Non-ozone depleting; (applicable if FAR clause 52.223-11,12,20, or 21 are included), and/or

(6) Made with recovered materials (EPA-Designated products) (applicable if FAR clause 52.223- 9 or 17 is included).

Green Mountain & Finger Lakes National Forests Supervisor’s Office Site Construction

(b) The required products in the contract actions for services include products that are—

(1) Delivered to the Government during performance;

(2) Acquired by the contractor for use in performing services at a Federally-controlled facility; or

(3) Furnished by the contractor for use by the Government.

C1.1 Sustainable products identified for this solicitation:

The following is a list of sustainable products that that may be used i n t h e performance of this contract. The list is not all inclusive; the Contractor shall research for available products.

C1.1.1 Energy-efficient and Water-efficient Products ENERGY STAR® at http://www.energystar.gov/; and FEMP at http://www1.eere.energy.gov/femp/procurement/eep_requirements.html www.epa.gov/watersense

Roofing Products, low flow toilets, faucets, appliances

C1.1.2 Biobased Products: (requires reporting at www.sam.gov by 10/31 each year) http://www.biopreferred.gov a Diesel Fuel Additives

(1) Any substance, other than one composed solely of carbon and/or hydrogen, that is intentionally added to diesel fuel (including any added to a motor vehicle's fuel system) and that is not intentionally removed prior to sale or use.

(2) Neat biodiesel, also referred to as B100, when used as an additive. Diesel fuel additive does not mean neat biodiesel when used as a fuel or blended biodiesel fuel (e.g., B20). 90% - Minimum Biobased Content.

b Hydraulic Fluids - Mobile Equipment Hydraulic fluids formulated for general use in nonstationary equipment, such as tractors, end loaders, or backhoes. 44% - Minimum Biobased Content.

c Penetrating Lubricants Products formulated to provide light lubrication and corrosion resistance in close tolerant internal and external applications including frozen nuts and bolts, power tools, gears, valves, chains, and cables. 68% - Minimum Biobased Content.

d Greases - Truck Lubricants composed of oils thickened to a semisolid or solid consistency using soaps, polymers or other solids, or other thickeners. Lubricants that are designed for use on the fifth wheel of tractor trailer trucks onto which the semi-trailer rests and pivots. 71% - Minimum Biobased Content.

e Gear Lubricants Products, such as greases or oils, that are designed to reduce friction when applied to a toothed machine part (such as a wheel or cylinder) that meshes with another toothed part to transmit motion or to change speed or direction. 58% - Minimum Biobased Content.

f Fuel Conditioners Products formulated to improve the performance and efficiency of engines by providing benefits such as removing accumulated deposits, increasing lubricity, removing moisture, http://www.energystar.gov/ http://www1.eere.energy.gov/femp/procurement/eep_requirements.html http://www.epa.gov/watersense http://www.sam.gov/ http://www.biopreferred.gov/ increasing the cetane number, and/or preventing microbial growths within the fuel system. 64% - Minimum Biobased Content.

g Erosion Control Woven or non-woven fiber materials manufactured for use on construction, demolition, or other sites to prevent wind or water erosion of loose earth surfaces, which may be combined with seed and/or fertilizer to promote growth. 77% - Minimum Biobased Content.

h 2-Cycle Engine Oils Lubricants designed for use in 2-cycle engines to provide lubrication, decreased spark plug fouling, reduced deposit formation, and/or reduced engine wear. 34% - Minimum Biobased Content.

C1.1.3 Environmentally Preferable Products:

www.epa.gov/epeat.

None

C1.1.4 Non-ozone Depleting Products:

http://www.epa.gov/snap

Foams, refrigeration products, air conditioning products

C1.1.5 EPA Designated Products:

https://www.epa.gov/smm/comprehensive-procurement-guideline-cpg-program

Plastic trash bags, printer ribbons, toner cartridges, print & writing papers, Traffic Barricades, Traffic Cones, Engine Coolants, Rebuilt Vehicular Parts, Re-refined lubricating oils, retread tires, manual grade strapping, signage, sorbents.

SAFETY AND HEALTH: Reference Specifications http://www.epa.gov/epeat http://www.epa.gov/snap https://www.epa.gov/smm/comprehensive-procurement-guideline-cpg-program

SECTION D--PACKAGING AND MARKING

RESERVED

SECTION E--INSPECTION AND ACCEPTANCE

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

52.246-12 Inspection of Construction (AUG 1996)

SECTION F--DELIVERIES OR PERFORMANCE

52.242-14 Suspension of Work (APR 1984)

52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than July 1, 2021. The time stated for completion shall include final cleanup of the premises.

SECTION G--CONTRACT ADMINISTRATION DATA

AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES

AGAR 452.215-73 Post Award Conference (NOV 1996)

A post award conference with the successful offeror is required. It will be scheduled and held within ___30___ days after the date of contract award. The conference will be held at __TBD_________.

G.1 DESIGNATION OF CONTRACTING OFFICER'S REPRESENTATIVE

The contracting Officer will designate a Contracting Officer's Representative (COR) at the time of award.

The COR is responsible for administering the performance of work under this contract. In no event, however, will any understanding, agreement, modification, change order, or other matter deviating from the terms of this contract be effective or binding upon the Government unless formalized by proper contractual documents executed by the Contracting Officer prior to completion of the contract.

On all matters that pertain to the contract terms the contractor must communicate with the Contracting Officer. Whenever, in the opinion of the Contractor, the COR requests effort outside the scope of the contract, the Contractor should so advise the COR. If the COR persists and there still exists a disagreement as to proper contractual coverage, the contracting officer should be notified immediately, preferably in writing if time permits. Proceeding with work without proper contractual coverage could result in nonpayment or necessitate submittal for a contract claim.

G.2 GOVERNMENT-FURNISHED PROPERTY --RESERVED

G.3 INVOICING

The "Submit Invoice-to" address for USDA orders is the Department of Treasury's Invoice Processing Platform (IPP). All invoices are to be submitted online via the electronic Invoice Processing Platform.

This is a mandatory requirement initiated by the U.S. Department of Treasury and you can find more information at this website https://www.ipp.gov/index.htm. Your company must register at https://www.ipp.gov/vendors/enrollment-vendors.htm to establish an account in order to submit an invoice on this project.

G. 4. ORDERING PROCEDURES -RESERVED

G.5 FINAL PAYMENT - RELEASE OF CLAIMS

The Government shall pay the final amount due the Contractor under this contract after—

(1) Completion and acceptance of all work;

(2) Presentation of a properly executed invoice; and

(3) Presentation of release of all claims against the Government arising by virtue of this contract, other than claims, in stated amounts, that the Contractor has specifically excepted from the operation of the release.

RELEASE OF CLAIMS

(to be submitted with final invoice)

Contract Number:

For and in consideration of payment and pursuant to the terms of the contract cited above, the government of the United States, its officers, agents, and employees are hereby released and discharged from all liabilities, demands, obligations, and claims arising under or by virtue of said contract.

Signature: ________________________________

Printed Name: ________________________________

Title: ________________________________

Company: ________________________________

Date: ________________________________

G.6 INCIDENTAL PAYMENT ITEMS

The intent of the contract is to provide for the complete performance of the project described in the contract. Unless otherwise provided, the Contractor shall furnish all labor, materials, equipment, tools, transportation, and supplies and perform all work required to complete the project in accordance with drawings, specifications, and provisions of the contract. Payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work and materials will be considered as incidental to and included in the payment for items shown.

Green Mountain & Finger Lakes National Forests Supervisor’s Office Site Construction

G.7 CONTRACTOR CERTIFICATION

Contractor will submit this certification with every invoice

CONTRACTOR CERTIFICATION

Page of Unit (Region, Forest, District)

Project: Contract No.

Name and Address of Contractor:

Invoice No. Invoice Date:

I hereby certify, to the best of my knowledge and belief, that--

(1) The amounts requested are only for performance in accordance with the specifications, terms, and conditions of the contract;

(2) Payments to subcontractors and suppliers have been made, and timely payments will be made for the work activities covered by this certification, in accordance with subcontract agreements and the requirements of Chapter 39 of Title 31, United States Code;

(3) This request for progress payments/credits does not include any amounts which the prime contractor intends to withhold or retain from a subcontractor or supplier in accordance with the terms and conditions of the subcontract; and

(4) This certification is not to be construed as final acceptance of a subcontractor's performance.

(Name)

(Title)

(Date)

SECTION H--SPECIAL CONTRACT REQUIREMENTS

52.236-4 Physical Data (APR 1984)

Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor. (a) The indications of physical conditions on the drawings and in the specifications are the result of site investigations by _Engineer of Record__.

(b) Weather conditions _____N/A_____.

(c) Transportation facilities __N/A_______

(d) _____N/A______

H.1 EQUIPMENT CLEANING

All soil moving equipment shall be thoroughly cleaned to make it free of soil, noxious weed seeds, vegetative matter or other debris that could contain or hold seeds prior to being delivered to the project site. Equipment shall be considered free of soil, noxious weed seeds and other such debris when a visual inspection by the C.O.R., prior to the equipment being delivered to the site, does not disclose such material present. Disassembly of equipment components is not required. The Contractor shall notify the Forest Service at least five (5) working days prior to moving each piece of soil moving equipment onto the project site, unless otherwise agreed.

The Contractor shall thoroughly clean all soil moving equipment prior to moving them off a project site or between work areas on a project site that are known to be infested with noxious weed species of concern and other work areas, if any, that are free of noxious weed species of concern. Areas known to be infested with specific noxious weed species of concern to the Forest Service shall be noted in the Schedule of Work. The Contractor and the Forest Service shall agree on the methods of cleaning, location for the cleaning and control of off-site impacts, if any.

When new areas of infestation of noxious weeds of concern to the Forest Service are identified on the project site by either the Forest Service or Contractor they shall be promptly reported to the other party.

H.2 CONTRACTOR PERFORMANCE ASSESSMENT REPORTING SYSTEM

(a) General. This contract is subject to Federal Acquisition Regulations (FAR), Agriculture Acquisition Regulations (AGAR), and Forest Service Acquisition Reference (FSAR) that require past performance evaluations to be completed and entered into the Contractor Performance Assessment Reporting System (CPARS).

(b) Contact Information. Upon award, the name and email address of the Contractor Representative responsible for reviewing the CPARS evaluations will be required.

Green Mountain & Finger Lakes National Forests Supervisor’s Office Site Construction

(c) Assessment. Upon completion of the work associated with the contract/delivery orders, or at the end of the year if the contract exceeds one year, an evaluation will be initiated by the Contracting Officer in the CPARS system and the Contractor Representative will receive an auto-email from CPARS with instructions for review of the evaluation. The contractor will review the government’s evaluation and either concur or disagree and route the evaluation back to the Contracting Officer (Assessing Official). If the evaluation recevied contractor concurrence, it will be finalized by the Assessing Offical. If there is disagreement, further discussion will be intiated prior to finalization.

H.3 UTILITY SERVICES --RESERVED

PART II--CONTRACT CLAUSES

SECTION I--CONTRACT CLAUSES

FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

https://www.acquisition.gov/browse/index/far, https://www.acquisition.gov/agar

52.202-1 Definitions (NOV 2013) 52.203-3 Gratuities (APR 1984) 52.203-5 Covenant Against Contingent Fees (MAY 2014) 52.203-6 Restrictions on Subcontractor Sales to the Government (SEP 2006) 52.203-7 Anti-Kickback Procedures (MAY 2014) 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity (MAY 2014) 52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (MAY 2014) 52.203-12 Limitation on Payments to Influence Certain Federal Transactions (OCT 2010) 52.203-17 Contractor Employee Whistleblower Rights & Requirements to Inform Employees of

Whistleblower Rights (APR 2014) 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements

(JAN 2017)

52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper (MAY 2011) 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards (OCT 2018) 52.204-13 System for Award Management Maintenance (OCT 2018) 52.204-14 Service Contract Reporting Requirement (OCT 2016) 52.204-18 Commercial and Government Entity Code Maintenance (JUL 2016) 52.204-19 Incorporation by Reference of Representations and Certifications (DEC 2014) 52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities (JUL 2018) 52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance

Services or Equipment (AUG 2019) 52.209-6 Protecting the Government's Interest when Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (OCT 2015) 52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters (OCT 2018) 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (NOV 2015) 52.219-6 Notice of Total Small Business Set-Aside (MAR 2020) 52.219-8 Utilization of Small Business Concerns (OCT 2018) 52.219-28 Post Award Small Business Program Rerepresentation (MAR 2020) 52.222-3 Convict Labor (JUN 2003) 52.222-4 Contract Work Hours and Safety Standards Act -- Overtime Compensation (MAY 2018) 52.222-6 Construction Wage Rate Requirements (AUG 2018) https://www.acquisition.gov/browse/index/far https://www.acquisition.gov/agar

Green Mountain & Finger Lakes National Forests Supervisor’s Office Site Construction

52.222-7 Withholding of Funds (MAY 2014) 52.222-8 Payrolls and Basic Records (AUG 2018) 52.222-9 Apprentices and Trainees (JUL 2005) 52.222-10 Compliance with Copeland Act Requirements (FEB 1988) 52.222-11 Subcontracts (Labor Standards) (MAY 2014) 52.222-12 Contract Termination - Debarment (MAY 2014) 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations (MAY 2014) 52.222-14 Disputes Concerning Labor Standards (FEB 1988) 52.222-15 Certification of Eligibility (MAY 2014) 52.222-20 Contracts for Materials, Supplies, Articles, and Equipment Exceeding $15,000 (MAY 2014) 52.222-21 Prohibition of Segregated Facilities (APR 2015) 52.222-26 Equal Opportunity (SEP 2016 52.222-27 Affirmative Action Compliance Requirements for Construction (APR 2015) 52.222-35 Equal Opportunity for Veterans (OCT 2015) 52.222-36 Equal Opportunity for Workers with Disabilities (JUL 2014) 52.222-37 Employment Reports on Veterans (FEB 2016) 52.222-40 Notification of Employee Rights Under National Labor Relations Act (DEC 2010) 52.222-50 Combating Trafficking in Persons (JAN 2019) 52.222-54 Employment Eligibility Verification (OCT 2015) 52.222-55 Minimum Wages Under Executive Order 13658 (DEC 2015) 52.222-62 Paid Sick Leave Under Executive Order 13706 (Jan 2017) 52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts (SEP 2013) 52.223-3 Hazardous Material Identification and Material Safety Data Alt 1 (Jan 1997) 52.223-5 Pollution Prevention and Right-to-Know Information (MAY 2011) 52.223-6 Drug-Free Workplace (MAY 2001) 52.223-15 Energy Efficiency in Energy Consuming Products (DEC 2007) 52.223-17 Affirmative Procurement of EPA-designated Items in Service and Construction Contracts

(AUG 2018)

52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving (AUG 2011) 52.225-13 Restrictions on Certain Foreign Purchases (JUN 2008) 52.227-1 Authorization and Consent (DEC 2007) 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (DEC 2007) 52.227-4 Patent Indemnity -- Construction Contracts (DEC 2007) 52.228-2 Additional Bond Security (OCT 1997) 52.228-5 Insurance – Work on a Government Installation (JAN 1997) 52.228-11 Pledges of Assets (AUG 2018) 52.228-12 Prospective Subcontractor Requests for Bonds (MAY 2014) 52.228-14 Irrevocable Letter of Credit (NOV 2014) 52.228-15 Performance and Payment Bonds—Construction (OCT 2010) 52.229-3 Federal, State, and Local Taxes (FEB 2013) 52.232-5 Payments Under Fixed-Price Construction Contracts (MAY 2014) 52.232-17 Interest (MAY 2014) 52.232-23 Assignment of Claims (MAY 2014) 52.232-27 Prompt Payment for Construction Contracts (JAN 2017) 52.232-33 Payment by Electronic Funds Transfer – System for Award Management (OCT 2018)

Green Mountain & Finger Lakes National Forests Supervisor’s Office Site Construction

52.232-39 Unenforceability of Unauthorized Obligations (JUN 2013) 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (DEC 2013) 52.233-1 Disputes (MAY 2014) Alt 1 (DEC 1991) 52.233-3 Protest After Award (AUG 1996) 52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004) 52.236-2 Differing Site Conditions (APR 1984) 52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984) 52.236-5 Material and Workmanship (APR 1984) 52.236-6 Superintendence by the Contractor (APR 1984) 52.236-7 Permits and Responsibilities (NOV 1991) 52.236-8 Other Contracts (APR 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements

(APR 1984)

52.236-10 Operations and Storage Areas (APR 1984) 52.236-11 Use and Possession Prior to Completion (APR 1984) 52.236-12 Cleaning Up (APR 1984) 52.236-13 Accident Prevention (NOV 1991)

Alternate I (NOV 1991) 52.236-15 Schedules for Construction Contracts (APR 1984) 52.236-17 Layout of Work (APR 1984) 52.236-21 Specifications and Drawings for Construction (FEB 1997)

Alternate II (APR 1984) 52.236-26 Preconstruction Conference (FEB 1995) 52.242-13 Bankruptcy (JUL 1995) 52.243-4 Changes (JUN 2007) 52.244-6 Subcontracts for Commercial Items (SEP 2019) 52.246-21 Warranty of Construction (MAR 1994)

Alternate I (MAR 1994) 52.248-3 Value Engineering – Construction (OCT 2015) 52.249-2 Termination for Convenience of the Government (Fixed-Price) (APR 2012)--Alternate I

(SEP 1996)

52.249-10 Default (Fixed-Price Construction) (APR 1984) 52.253-1 Computer Generated Forms (JAN 1991)

AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES

452.232-70 Reimbursement for Bond Premiums – Fixed-Price Construction Contracts (NOV 1996)

(Applicable if contract is over $35,000) 452.236-71 Prohibition Against the Use of Lead-Paint (NOV 1996) 452.236-72 Use of Premises (NOV 1996) 452.236-73 Archeological or Historic Sites (FEB 1988) 452.236-74 Control of Erosion, Sedimentation and Pollution (NOV 1996) 452.236-76 Samples and Certificates (FEB 1988) 452.236-77 Emergency Response (NOV 1996)

Green Mountain & Finger Lakes National Forests Supervisor’s Office Site Construction

52.204-21 Basic Safeguarding of Covered Contractor Information Systems (Jun 2016)

(a) Definitions. As used in this clause– “Covered contractor information system” means an information system that is owned or operated by a contractor that processes, stores, or transmits Federal contract information.

“Federal contract information” means information, not intended for public release, that is provided by or generated for the Government under a contract to develop or deliver a product or service to the Government, but not including information provided by the Government to the public (such as on public websites) or simple transactional information, such as necessary to process payments.

“Information” means any communication or representation of knowledge such as facts, data, or opinions, in any medium or form, including textual, numerical, graphic, cartographic, narrative, or audiovisual (Committee on National Security Systems Instruction (CNSSI) 4009).

“Information system” means a discrete set of information resources organized for the collection, processing, maintenance, use, sharing, dissemination, or disposition of information (44 U.S.C. 3502).

“Safeguarding” means measures or controls that are prescribed to protect information systems.

(b) Safeguarding requirements and procedures.

(1) The Contractor shall apply the following basic safeguarding requirements and procedures to protect covered contractor information systems. Requirements and procedures for basic safeguarding of covered contractor information systems shall include, at a minimum, the following security controls:

(i) Limit information system access to authorized users, processes acting on behalf of authorized users, or devices (including other information systems).

(ii) Limit information system access to the types of transactions and functions that authorized users are permitted to execute.

(iii) Verify and control/limit connections to and use of external information systems.

(iv) Control information posted or processed on publicly accessible information systems.

(v) Identify information system users, processes acting on behalf of users, or devices.

(vi) Authenticate (or verify) the identities of those users, processes, or devices, as a prerequisite to allowing access to organizational information systems.

(vii) Sanitize or destroy information system media containing Federal Contract Information before disposal or release for reuse.

(viii) Limit physical access to organizational information systems, equipment, and the respective operating environments to authorized individuals.

(ix) Escort visitors and monitor visitor activity; maintain audit logs of physical access; and control and manage physical access devices.

(x) Monitor, control, and protect organizational communications (i.e., information transmitted or received by organizational information systems) at the external boundaries and key internal boundaries of the information systems.

(xi) Implement subnetworks for publicly accessible system components that are physically or logically separated from internal networks.

(xii) Identify, report, and correct information and information system flaws in a timely manner.

http://uscode.house.gov/

(xiii) Provide protection from malicious code at appropriate locations within organizational information systems.

(xiv) Update malicious code protection mechanisms when new releases are available.

(xv) Perform periodic scans of the information system and real-time scans of files from external sources as files are downloaded, opened, or executed.

(2) Other requirements. This clause does not relieve the Contractor of any other specific safeguarding requirements specified by Federal agencies and departments relating to covered contractor information systems generally or other Federal safeguarding requirements for controlled unclassified information (CUI) as established by Executive Order 13556.

(c) Subcontracts. The Contractor shall include the substance of this clause, including this paragraph (c), in subcontracts under this contract (including subcontracts for the acquisition of commercial items, other than commercially available off-the-shelf items), in which the subcontractor may have Federal contract information residing in or transiting through its information system.

52.214-29 ORDER OF PRECEDENCE—SEALED BIDDING (JAN 1986)

Any inconsistency in this solicitation or contract shall be resolved by giving precedence in the following order:

(a) The Schedule (excluding the specifications);

(b) Representations and other instructions;

(c) Contract clauses;

(d) Other documents, exhibits, and attachments; and

(e) The specifications.

52.219-14 Limitations on Subcontracting (MAR 2020)

(a) This clause does not apply to the unrestricted portion of a partial set-aside.

(b) Applicability. This clause applies only to—

(1) Contracts that have been set aside for small business concerns or 8(a) participants;

(2) Part or parts of a multiple-award contract that have been set aside for small business concerns or 8(a) participants;

(3) Orders set aside for small business concerns or 8(a) participants under multiple-award contracts as described in 8.405-5 and 16.505(b)(2)(i)(F); and

(4) Orders issued directly to small business concerns or 8(a) participants under multiple-award contracts as described in 19.504(c)(1)(ii).

(c) Limitations on subcontracting. By submission of an offer and execution of a contract, the Contractor agrees that in performance of the contract in the case of a contract for—

(1) Services (except construction). At least 50 percent of the cost of contract performance incurred for personnel shall be expended for employees of the concern.

(2) Supplies (other than procurement from a nonmanufacturer of such supplies). The concern shall perform work for at least 50 percent of the cost of manufacturing the supplies, not including the cost of materials.

Green Mountain & Finger Lakes National Forests Supervisor’s Office Site Construction

(3) General construction. The concern will perform at least 15 percent of the cost of the contract, not including the cost of materials, with its own employees.

(4) Construction by special trade contractors. The concern will perform at least 25 percent of the cost of the contract, not including the cost of materials, with its own employees.

(d) The Contractor shall comply with the limitations on subcontracting as follows:

(1) For contracts, in accordance with paragraph (b)(1) and (2) of this clause—

[Contracting Officer check as appropriate.] _X__ By the end of the base term of the contract and then by the end of each subsequent option period; or ___By the end of the performance period for each order issued under the contract.

(2) For orders, in accordance with paragraphs (b)(3) and (4) of this clause, by the end of the performance period for the order.

52.223-9 Estimate of Percentage of Recovered Material Content for EPA-Designated Items (May 2008)

(a) Definitions. As used in this clause— “Postconsumer material” means a material or finished product that has served its intended use and has been discarded for disposal or recovery, having completed its life as a consumer item. Postconsumer material is a part of the broader category of “recovered material.”

“Recovered material” means waste materials and by-products recovered or diverted from solid waste, but the term does not include those materials and by-products generated from, and commonly reused within, an original manufacturing process.

(b) The Contractor, on completion of this contract, shall—

(1) Estimate the percentage of the total recovered material content for EPA-designated item(s) delivered and/or used in contract performance, including, if applicable, the percentage of post-consumer material content; and

(2) Submit this estimate to to the contracting officer.

52.223-11 Ozone-Depleting Substances and High Global Warming Potential Hydrofluorocarbons (Jun 2016)

(a) Definitions. As used in this clause--

“Global warming potential” means how much a given mass of a chemical contributes to global warming over a given time period compared to the same mass of carbon dioxide. Carbon Dioxide’s global warming potential is defined as 1.0.

“High global warming potential hydrofluorocarbons” means any hydrofluorocarbons in a particular end use for which EPA’s Significant New Alternatives Policy (SNAP) program has identified other acceptable alternatives that have lower global warming potential. The SNAP list of alternatives is found at 40 CFR part 82, subpart G, with supplemental tables of alternatives available at (http://www.epa.gov/snap/ ).

“Hydrofluorocarbons” means compounds that only contain hydrogen, fluorine, and carbon.

Green Mountain & Finger Lakes National Forests Supervisor’s Office Site Construction

“Ozone-depleting substance” means any substance the Environmental Protection Agency designates in 40 CFR Part 82 as--

(1) Class I, including, but not limited to, chlorofluorocarbons, halons, carbon tetrachloride, and methyl chloroform; or

(2) Class II , including, but not limited to hydrochlorofluorocarbons.

(b) The Contractor shall label products which contain or are manufactured with ozone-depleting substances in the manner and to the extent required by 42 U.S.C. 7671j (b), (c), (d), and (e) and 40 CFR Part 82, Subpart E, as follows:

Warning

Contains (or manufactured with, if applicable) *_______, a substance(s) which harm(s) public health and environment by destroying ozone in the upper atmosphere.

* The Contractor shall insert the name of the substance(s).

(c) Reporting. For equipment and appliances that normally each contain 50 or more pounds of hydrofluorocarbons or refrigerant blends containing hydrofluorocarbons, the Contractor shall—

(1) Track on an annual basis, between October 1 and September 30, the amount in pounds of hydrofluorocarbons or refrigerant blends containing hydrofluorocarbons contained in the equipment and appliances delivered to the Government under this contract by—

(i) Type of hydrofluorocarbon (e.g., HFC-134a, HFC-125, R-410A, R-404A, etc.);

(ii) Contract number; and

(iii) Equipment/appliance;

(2) Report that information to the Contracting Officer for FY16 and to www.sam.gov, for FY17 and after--

(i) Annually by November 30 of each year during contract performance; and

(ii) At the end of contract performance.

(d) The Contractor shall refer to EPA’s SNAP program (available at http://www.epa.gov/snap ) to identify alternatives. The SNAP list of alternatives is found at 40 CFR part 82, subpart G, with supplemental tables available at http://www.epa.gov/snap .

52.223-20 Aerosols (Jun 2016)

(a) Definitions. As used in this clause--http://www.sam.gov/

Green Mountain & Finger Lakes National Forests Supervisor’s Office Site Construction

“Global warming potential” means how much a given mass of a chemical contributes to global warming over a given time period compared to the same mass of carbon dioxide. Carbon dioxide’s global warming potential is defined as 1.0.

“High global warming potential hydrofluorocarbons” means any hydrofluorocarbons in a particular end use for which EPA’s Significant New Alternatives Policy (SNAP) program has identified other acceptable alternatives that have lower global warming potential. The SNAP list of alternatives is found at 40 CFR part 82, subpart G. with supplemental tables of alternatives available at http://www.epa.gov/snap/).

“Hydrofluorocarbons” means compounds that contain only hydrogen, fluorine, and carbon.

(b) Unless otherwise specified in the contract, the Contractor shall reduce its use, release, or emissions of high global warming potential hydrofluorocarbons, when feasible, from aerosol propellants or solvents under this contract. When determining feasibility of using a particular alternative, the Contractor shall consider environmental, technical, and economic factors such as--

(1) In-use emission rates, energy efficiency;

(2) Safety, such as flammability or toxicity;

(3) Ability to meet technical performance requirements; and

(4) Commercial availability at a reasonable cost.

(c) The Contractor shall refer to EPA’s SNAP program to identify alternatives. The SNAP list of alternatives is found at 40 CFR part 82, subpart G, with supplemental tables available at http://www.epa.gov/snap/.

52.223-21 -- Foams. (Jun 2016)

(a) Definitions. As used in this clause--

“Global warming potential” means how much a given mass of a chemical contributes to global warming over a given time period compared to the same mass of carbon dioxide. Carbon dioxide’s global warming potential is defined as 1.0.

“High global warming potential hydrofluorocarbons” means any hydrofluorocarbons in a particular end use for which EPA’s Significant New Alternatives Policy (SNAP) program has identified other acceptable alternatives that have lower global warming potential. The SNAP list of alternatives is found at 40 CFR part 82, subpart G. with supplemental tables of alternatives available at http://www.epa.gov/snap/).

“Hydrofluorocarbons” means compounds that contain only hydrogen, fluorine, and carbon.

(b) Unless otherwise specified in the contract, the Contractor shall reduce its use, release, and emissions of high global warming potential hydrofluorocarbons and refrigerant blends containing hydrofluorocarbons, when feasible, from foam blowing agents, under this contract. When determining http://www.epa.gov/snap/ http://www.epa.gov/snap/ http://www.epa.gov/snap/

Green Mountain & Finger Lakes National Forests Supervisor’s Office Site Construction feasibility of using a particular alternative, the Contractor shall consider environmental, technical, and economic factors such as--

(1) In-use emission rates, energy efficiency, and safety;

(2) Ability to meet performance requirements; and;

(3) Commercial availability at a reasonable cost.

(c) The Contractor shall refer to EPA’s SNAP program to identify alternatives. The SNAP list of alternatives is found at 40 CFR part 82, subpart G, with supplemental tables available at http://www.epa.gov/snap/.

52.225-9 Buy American-Construction Materials (MAY 2014)

(a) Definitions. As used in this clause— “Commercially available off-the-shelf (COTS) item”—

(1) Means any item of supply (including construction material) that is—

(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.

“Component” means an article, material, or supply incorporated directly into a construction material.

“Construction material” means an article, material, or supply brought to the construction site by the

Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

“Cost of components” means—

(3) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(4) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

“Domestic construction material” means— http://www.epa.gov/snap/ https://acquisition.gov/far/current/html/Subpart%202_1.html#wp1145508

(1) An unmanufactured construction material mined or produced in the United States;

(2) A construction material manufactured in the United States, if—

(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic; or

(ii) The construction material is a COTS item.

“Foreign construction material” means a construction material other than a domestic construction material.

“United States” means the 50 States, the District of Columbia, and outlying areas.

(b) Domestic preference.

(1) This clause implements 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the component test of the Buy American statute is waived for construction material that is a COTS item. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.

(2) This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows:

[Contracting Officer to list applicable excepted materials or indicate “none”]

(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that—

(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;

(ii) The…