1205K319R0003_Iron_Creek_and_N_Fork_Pumphouse.pdf

PDF 595 KB Posted

Attached to
Iron Creek and North Fork CG Water Systems
Solicitation number
1205K319R0003
Issued by

About this file

1205K319R0003 Solicitation without attachments

View the file

Other files

File Type Posted
1205K319R0003_Iron_Creek_Amendment_01.pdf PDF
1205K319R0003_Attachments.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION, OFFER,

AND AWARD

2. TYPE OF SOLICITATION

6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

PAGE OF PAGES

7. ISSUED BY CODE 8. ADDRESS OFFER TO

SOLICITATION

(Construction, Alteration, or Repair)

1. SOLICITATION NO. 3. DATE ISSUED

IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.

9.

INFORMATION

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."

CALL:

FOR

SEALED BID (IFB)

NEGOTIATED (RFP)

950710

USDA FOREST SERVICE

GIFFORDPINCHOT NATIONAL FOREST

501 E 5TH STREET 404

VANCOUVER WA 98661

05K3

ATTN: STEVONNE FULLER - CONTRACTING

GIFFORD PINCHOT NATIONAL FOREST

501 E. 5TH ST. #404

VANCOUVER, WA 98661

STEVONNE FULLER 360-891-5085

1x

1205K319R0003

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

11. The Contractor shall begin performance

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and is not required.is, b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

d. Offers providing less than

12b. CALENDAR DAYSYES NO

(If "YES", indicate within how many calendar days after award in Item 12b.)

0 60 calendar days and complete it within ________________ ________________ calendar days after receiving

07/24/2019

NSN 7540-01-155-3212

x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________

STANDARD FORM 1442 (Rev. 4-85)

Prescribed by GSA

FAR(48 CFR) 53.236-1(d)

Iron Creek and North Fork Pumphouse Work. E-mail offers are accepted. Submit your email offer no later than July 24, 2019 1200 PT to Stevonne.fuller@usda.gov.

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than item 14.)

CODE FACILITY CODE

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGEMENT OF AMENDMENTS

OFFER (Must be fully completed by offeror)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this document and return (Contractor is not required to sign this document.)

Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.

No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE

BY

2PAGE OF

USDA FOREST SERVICE

GIFFORDPINCHOT NATIONAL FOREST

501 E 5TH STREET 404

VANCOUVER WA 98661

05K3

28. NEGOTIATED AGREEMENT 29. AWARD

Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

STANDARD FORM 1442 (REV. 4-85) BACK

Continued...

INVOICE PROCESSING PLATFORM

www.ipp.gov

1205K319R0003 IRON CREEK AND N. FORK PUMPHOUSE GPNF

PART I – THE SCHEDULE

1 A.1 FOR INFORMATION CALL:

Molly Williams 360-497-1171 COR Telephone No.

Robert Jeter 360-497-1150 Technical Contact Telephone No.

A.2 THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK

DESCRIBED IN THESE DOCUMENTS

Project Name: Iron Creek and North Fork CG Water Systems Gifford Pinchot National Forest Cowlitz Valley Ranger District Lewis County, Washington

Price Range: $25,000 to $100,000.

PART I - SCHEDULE OF ITEMS

SECTION B – SUPPLIES, SERVICES AND PRICES

Iron Creek and North Fork CG Water Systems Gifford Pinchot National Forest Cowlitz Valley Ranger District

Lewis County, Washington NOTE: If Bidder does not intend to charge for a bid Item, a price of "0" or "NO COST" should be shown. If the price is left blank or shown as "No Bid", the entire Bid will be considered Non-Responsive.

Base Item No. 1 – Iron Creek Campground

ITEM NO. Description Estimated Quantity Unit Unit Price TOTAL

PRICE

16050 Basic Electric Materials and Methods All LS $____________ $____________

06100 Rough Carpentry All LS $____________ $____________

TOTAL PRICE BASE ITEMS $____________

*Option Item No. 1 – North Fork Campground

16050 Basic Electric Materials and Methods All LS $____________ $____________

06100 Rough Carpentry All LS $____________ $____________

UNIT MEASUREMENTS: LS = Lump Sum, LF = Linear Foot, SF = Square Foot

*Note: Option item will be exercised based on the availability of funding.

The time at which the Government can unilaterally exercise the option will be between October 1, 2019 through September 30, 2020.

CSI Specification Section:

Work incidental to item no. 16050 – BASIC ELECTRICAL MATERIAL AND METHODS include:

02318 – EXCAVATION AND BACKFILL FOR UTILITIES

260010 – GENERAL TECHNICAL PROVISIONS

Work incidental to item no. 06100 – ROUGH CARPENTRY include:

01200 – MOBILIZATION

01621 – COLOR SCHEDULE

01732 – SELECTIVE DEMOLITION

07610 – PREFOMED METAL ROOF PANELS

07900 - SEALANTS

SECTION C – DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

Iron Creek and North Fork CG Water Systems

General Tasks and Requirements

C.1 DESCRIPTION OF WORK

The contractor shall complete services in accordance with the requirements specified and in this contract. The project consists of the following major items of work:

GENERAL

The Forest Service is looking to upgrade the electrical and control systems for the Iron Creek Campground (Base Item) and the North Fork Campground (Option Item 1).

The well systems are manually operated by campground personnel. Generators are used to power electric well pumps and the water is pumped to storage tanks located above the campgrounds on nearby slope rises. Water is delivered to the campgrounds by gravity feed from tanks.

PUMP HOUSE ELECTRICAL

Iron Creek Campground and North Fork Campground both have electrical systems that need updating. The following features shall be incorporated:

1. Replace all system components including electric panels, pump control devices, light fixtures, conduits and raceways. All materials shall be suitable for damp locations.

2. Replace electric panel. Panel must have main breaker installed.

3. Pump motor operating switch shall be installed. (Pump is currently controlled with circuit breaker).

4. Install an automated battery-backed-up low pressure alarm. Alarm shall trigger when water system pressure drops below 30 psi.

5. Motor controls for automatic shutoff in case of malfunctioning pump.

6. Pump malfunction alarm with light and horn

7. Install water pipe bonding, well casing to panel.

8. All underground electric conductors shall be placed in non-metallic conduits and installed to a depth of not less than 18 inches. (see specs for additional requirements)

9. Light fixtures shall be replaced with rough use type fixtures. Provide LED lamps.

10. Install suitable switching fixtures as required. Breakers shall not be used as switches.

11. It is anticipated that an automatic control panel for tank level control will be installed in the future. Appropriate sized non-metallic conduit shall be installed parallel to electric conductor conduit to accommodate that need.

GENERATOR

1. Contractor to furnish and install new diesel powered generator at each campground site. Generators to be Generac Towable Mobile Diesel Generator, 9kW, Single Phase, Electric Start, Model #6782 or equivalent.

2. Generators to have NEMA 3R rated container with controls mounted inside, 40-50A integral main breaker.

3. Generator will be provided with a ground that meets applicable codes.

4. Location of generator placement shall be minimum 100 feet from pump head, and shall be approved by COR prior to trenching.

5. Spill containment must be provided to meet state requirements.

6. Generators provided must be able to be serviced within 100 miles from

Randle, WA.

7. Provide wheel lock for trailer security at both sites, Trimax Wheel Lock

TWL100 or equivalent.

GENERATOR PROTECTIVE STRUCTURE

1. Structures to be constructed at each generator location as approved by COR.

The intent of these structures in to provide rain/snow protection. They will be open sided structures in the nature of a simple carport. Dimensions of structure to be 2 feet beyond all sides of generator to provide weather protection. Height clearance of structure to meet generator manufacturer’s requirements for clearance, and provide adequate space to walk under.

2. Structures to be constructed on existing asphalt pads. See designated locations on project area map.

3. Concept for structures shall be submitted for approval by COR prior to construction. Rough drawings, sketches or photos that show building construction are acceptable. Allow 14 days for review and comments.

4. Structure is expected to be gabled 6x6 treated timber post construction placed on four galvanized pier block elevated post bases. Some method of anchoring structure shall be utilized to prevent wind damage. Roofing to be dark brown preformed metal panels.

All work performed shall be in accordance with applicable local, state and federal codes.

Submit product and equipment data for proposed replacement components to Contracting Officer for approval 7 days prior to starting work.

Except for items or materials indicated to be reused, salvaged, reinstalled, or otherwise indicated to remain Government property, demolished materials shall become Contractor's property and shall be removed from Project site. This includes existing generators.

The contractor shall provide any and all labor, equipment, vehicles, services, permits, and licenses, necessary to perform this contract.

ANTICIPATED TIMING OF PROJECT

It is anticipated that work would start first with the Iron Creek project as the work will not interfere with campground operations.

The Northfork project will have to be started after the campground is closed. Anticipated closure date is September 26th, 2019.

C.2 PROJECT LOCATION

This project is located at the North Fork Campground and Iron Creek Campground on the Cowlitz Valley Ranger District, on the Gifford Pinchot National Forest. Directions to campgrounds can be obtained at the Cowlitz Valley Ranger District Office, 10024 US Hwy 12, Randle, WA 98377. See attached drawings.

C.3 PROSECUTION OF WORK

(a) General:

The contractor shall conduct activities so that interference with the public is kept to a minimum and existing level of safety is maintained.

C.4 AVAILABILITY OF SPECIFICATIONS OR PRODUCT DESCRIPTIONS NOT

LISTED IN THE GSA INDEX OF FEDERAL SPECIFICATIONS AND

STANDARDS (FAR 52.210-3) (APR 1984)

Specifications or product descriptions cited herein, but not attached to this solicitation nor listed in the General Services Administration Index of Federal Specifications and Standards (GSAIFSS), may be obtained from:

ASTM Standards American Society for Testing and Materials 100 Bar Harbor Drive West Conshohocken, PA 19428

(610) 832-9585 http://www.astm.org

C.5 APPLICABLE SPECIFICATIONS AND MATERIAL CERTIFICATIONS

(a) Applicable Specifications:

http://www/

References to Standard Specifications in the contract refer to the Construction Specifications Institute, Inc. standard specifications for construction and are physically included in Section J of the Contract under the title “LIST OF ATTACHMENTS.”

(b) Product Substitution:

a. Any modification of other items, designs, materials, products or equipment

(including Government-Furnished Property), made necessary because of a substitution, will be the responsibility of the Contractor without adjustment in contract price or time. The Contracting Officer’s approval of any substitute will not affect the Contractor’s responsibility for such modification. Any and all substitutions will be requested by the Contractor after award of the contract has been made. No approvals will be made prior to award.

(c) Submittals: Submittals are required by the following specifications:

Brief Title

Basic Reference Specificatio n

Detailed Regulations Specificatio n

Copie s To Submi t

Time For Government Approval After Total Submittal

Work Schedule F.3 (a) 52.236- 15 1 7 days

Electrical Equipment 16050 1.02 1 7 days Generator Specs C.1 Page 4 1 7 days

Work requiring submittals shall not begin until submittals have been approved.

Submittals shall include:

Date and Revision Dates.

Project Name and Contract Number.

Names of Contractor, Subcontractor, Supplier, and Manufacturers.

Contractor's stamp, initialed or signed, certifying review of submittal, verification of field measurement and compliance with contract documents.

Samples:

Physical examples shall illustrate materials, equipment, or workmanship, and establish standards by which completed work shall be judged. Samples shall be of sufficient size and quantity to illustrate the functional characteristics of product or material, with integrally related parts and devices.

Manufacturer's requirements:

Supply manufacturer's catalog sheets or brochures with diagrams, schedules, or performance charts. Illustrations shall be clearly marked to identify pertinent materials or models, dimensions, and clearances required. Supplement standard drawings to provide information unique to this project.

Approval or Rejection Time Allowance: Submittals will be reviewed and either approved or rejected within _7_ calendar days of receipt by the Contracting Officer or

COR.

SECTION D – PACKAGING AND MARKING

(For this Solicitation, there are NO clauses in this Section)

SECTION E – INSPECTION AND ACCEPTANCE

E.1 CLAUSES INCORPORATED BY REFERENCE (FAR 52.252-2) (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.arnet.gov/far/

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

52.246-12 Inspection of Construction (AUG 1996)

E.2 INSPECTION OF ELECTRICAL AND CONTROL IMPROVEMENTS

Work not meeting contract requirements will cause the Contractor to:

• Rework at no cost to the government

• Repair or replace damaged infrastructure/utilities at no cost to the government

• Acceptance with a price reduction http://www.arnet.gov/far/

SECTION F - DELIVERIES AND PERFORMANCE

F.1 CLAUSES INCORPORATED BY REFERENCE (FAR 52.252-2)(FEB 1998)

effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.arnet.gov/far/

52.242-14 Suspension of Work (APR 1984)

F.2 FAR 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF

WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 60 days after the date the Contractor receives the Notice to Proceed. The time stated for completion shall include final cleanup of the premises.

Estimated start work date:

• Iron Creek CG: July 26th, 2019.

• Northfork CG: After campground closure, approximately September 26th, 2019.

F.3 MAXIMUM WORKWEEK – CONSTRUCTION SCHEDULE (AGAR 452.236-

75)(NOV 1996)

Within 7 calendar days after receipt of a written request from the Contracting Officer, the Contractor must submit the following information in writing for approval:

(a) A schedule as required by FAR clause 52.236-15, Schedules for Construction Contracts, and

(b) The hours (including the daily starting and stopping times) and days of the week the Contractor proposed to carry out the work.

The approved regular workweek is Monday through Friday, 8:00 a.m. to 5:00 p.m. Work hours outside of the regular workweek hours shall be approved by the COR at least 24 hours prior to extending work hours. Requests for weekend work will be entertained in the interest of public safety and minimizing employee disruptions.

SECTION G – CONTRACT ADMINISTRATION DATA

G.1 GOVERNMENT-FURNISHED PROPERTY

The Government will provide the following item(s) of Government property to the Contractor for use in the performance of this contract. This property shall be used and maintained by the Contractor in accordance with the provisions of the "Government Property" FAR clause contained elsewhere in the contract:

• None

G.2 DESIGNATION OF CONTRACTING OFFICER'S REPRESENTATIVE

The Contracting Officer will designate a Contracting Officer's Representative (COR) at the time of contract award.

The COR is responsible for administering the performance of work under this contract.

In no event, however, will any understanding, agreement, modification, change order, or other matter deviating from the terms of this contract be effective or binding upon the Government unless formalized by proper contractual documents executed by the Contracting Officer prior to completion of the contract.

The Contracting Officer should be informed as soon as possible of any actions or inactions by the Contractor or the Government which will change the required delivery or completion times stated in the contract, and the contract will be modified accordingly.

(This does not apply to individual task assignments which were issued by the COR provided they do not affect the delivery schedule or performance period stated in the contract).

On all matters that pertain to the contract terms the Contractor must communicate with the Contracting Officer. Whenever, in the opinion of the Contractor, the COR requests effort outside the scope of the contract, the Contractor should so advise the COR. If the COR persists and there still exists a disagreement as to proper contractual coverage, the Contracting Officer should be notified immediately, preferably in writing if time permits.

Proceeding with work without proper contractual coverage could result in nonpayment or necessitate submittal of a contract claim.

SECTION H – SPECIAL CONTRACT REQUIREMENTS

H.1 EMERGENCY CONTROL (USDA 452.236-77) (JUL 1985)

(a) Maintenance of Existing Facilities:

1. The Contractor shall conduct operations to minimize disruptions to office visitors and employees.

2. The Contractor shall request permission in writing to the COR for any planned disruption of utilities. Such requests shall be submitted at least seven days prior to the planned disruption.

3. Utility disruptions shall be limited to a maximum of 12 hours duration at a time. Do not proceed with utility interruptions without Government’s written permission.

H.2 LANDSCAPE PRESERVATION

(a) The Contractor shall confine operations to the immediate vicinity of buildings.

Measures shall be taken to protect pathways, shrubbery, attachments, and etc. from damage and/or disturbance by contractor’s operations.

(b) All materials or garbage generated as a result of contractor’s operations shall be picked up and removed from the work areas and disposed of properly.

(c) Prevention of Oil Spills - Spilled product and other chemicals shall be immediately cleaned up

PLAN FOR WEATHER-CAUSED SUSPENSIONS OF WORK

The Contractor shall prepare a plan for weather-caused suspensions of work to ensure protection of structures affected by long or short term precipitation events. The plans shall be consistent with the requirements in the LANDSCAPE PRESERVATION clause contained in this contract. The plan shall be submitted in writing to the Contracting Officer for review and, if acceptable, approval no later than 14 days after contract award.

If rejected by the Contracting Officer, the Contractor shall revise the plan and re-submit it for consideration within three working days of verbal or written notification by the Contracting Officer. The Contractor shall take action consistent with the plan before suspending activity on the site(s). Acceptance of the plan by the Contracting Officer in no way waives any of the requirements of the LANDSCAPE PRESERVATION clause.

H.3 USE OF PREMISES

(a) A storage site will be permitted within the project area. The Forest Service assumes no liability for materials stored within the storage site. The Contractor will be allowed to erect a temporary fence to secure materials and equipment, however, the fence shall be removed and the site restored prior to final acceptance of the contract.

(b) Potable water is available for use during construction.

(c) Electric power is available on site for construction use.

(d) Sanitary facilities are available for use during construction.

H.4 PROSECUTION OF WORK

(a) The Contractor shall conduct activities so that interference with office visitors, employees and their daily activities shall be kept at a minimum. The work site shall be kept free of contractor’s work related hazards as much as possible at all times. Any activities requiring closure of an entrance shall be scheduled with the COR at least 7 days in advance and shall not be in effect more than eight (8) consecutive hours.

(b) The Contractor shall use measures and precautions necessary to warn and protect office visitors and Government personnel during work at the project site. Such actions include, but are not limited to, furnishing and maintaining barricades and signs around the work site and roping off the area.

H.5 FINAL CLEANUP

Contractor shall remove and dispose all of its own trash and refuse from the contract area.

This Cleanup is a subsidiary item for which no special payment will be made. All debris shall be disposed off National Forest Land and in accordance with State and Local disposal requirements.

H.6 POTENTIAL SAFETY HAZARDS

(a) Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor. This list shall not be deemed to be all-inclusive. The Contractor shall bear the sole responsibility for taking all appropriate actions necessary to prevent accidents and injuries to individuals at the worksite.

(b) The following checked activities have been identified by the Government as potential safety hazards.

[ ] Confined space entry.

[ ] Temporary excavation/deep trenching/slope stability.

[ ] Tree falling.

[X] Fall hazard from work heights exceeding six feet.

[ ] Blasting.

[ ] Traffic control on high-volume and/or high-speed and/or limited visibility roads.

[X] Heavy equipment operation.

[ ] Tree climbing and/or tower climbing.

[ ] Fire hazards.

[ ] Hazardous materials handling.

[X] Electrical hazard.

[ ] Hydraulic and/or pneumatic and/or other high pressure hazards.

[ ] Mechanical hazards such as pulleys, springs, etc.

[ ] Other __________________________________

H.7 DEFINITIONS AND ABBREVIATIONS

Wherever in these provisions, or in other contract documents, the following terms, or pronouns in place of them are used, the intent and meaning shall be interpreted as follows:

Building Limits - A line 5 feet outside foundations of the structure.

Calendar Day - Every day shown on the calendar, Sundays and holidays included.

Change Order - A written order issued by the Contracting Officer, to the Contractor documenting modifications within the scope of the contract.

Contract Amendment - A bilateral written supplemental agreement between the Government and the Contractor.

Contract Time - The number of calendar days allowed by the contract for the completion of the work.

Contracting Officer's Representative (COR) - The duly authorized representative of the Contracting Officer, responsible for on-site administration of the contract within the limits of specific written delegation of authority.

Contractor - The individual, partnership, joint venture, or corporation undertaking the execution of the work under the terms of the contract and acting directly or through their agent, employees, or subcontractors.

Equipment - All machinery and equipment, together with the necessary supplies for upkeep and maintenance, including tools and apparatus necessary for the proper construction and acceptable completion of the work.

Forest Supervisor - The person, or designated representative, responsible for administration of a National Forest.

Inspector - The Government authorized representative designated in writing by the COR responsible for detailed inspections of contract performance, within delegation of authority.

Materials - Any substances specified for use in the construction of the project and its appurtenances.

Notice of Non-Compliance - Written notice issued detailing specific area(s) of Non- Compliance with contract requirements.

Original Contract Quantities - Those quantities shown in the Schedule of Items.

Right-of-way - A general term denoting land, property, or interest therein acquired for or devoted to a road or a construction site.

Schedule of Items - Schedule in the contract which contains a listing and description of construction items, quantities, units of measure, method of measurement, unit price and amount.

Specifications - A general term applied to all written directions and requirements pertaining to performance of the work.

Utility Services - Services such as electricity, gas, steam, water and sewerage.

Work Order - A written instruction directing the Contractor to fulfill contract requirements.

Reference to a specific standard or specification shall mean the latest edition or amendment in effect on date of invitation to bid.

––-–––– ACRONYMS –––––––

AA Aluminum Association

AASHTO

American Association of State Highway and Transportation Officials

ACI American Concrete Institute ADA Americans With Disabilities Act AGC Associated General Contractors AI Asphalt Institute AISC American Institute of Steel Construction

AISI American Iron and Steel Institute AITC American Institute of Timber Construction ALSC American Lumber Standards Committee ANSI American National Standards Institute APA American Plywood Association API American Petroleum Institute ARTBA American Road and Transportation Builders Association

ASHRAE

American Society of Heating, Refrigerating & Air Conditioning Engineers

ASME American Society of Mechanical Engineers ASTM American Society for Testing and Material ATCC American Type Culture Collection AWPA American Wood Preservers Association AWPB American Wood Preservers Bureau AWS American Welding Society AWWA American Water Works Association CFR Code of Federal Regulations CRSI Concrete Reinforcing Steel Institute CS Commercial Standard issued by U.S. Department of Commerce CSI Construction Specifications Institute DEMA Diesel Engine Manufacturers Association DOT U.S. Department of Transportation FAR Federal Acquisition Regulations

FED. SPEC.

FS

Federal Specifications

FHWA Federal Highway Administration FLH Federal Lands Highway (Federal Highway Administration) FSS Federal Specifications and Standards GSA General Services Administration ICBO International Conference of Building Officials ISSA International Slurry Surfacing Association MIL Military Specifications MSHA Mine Safety and Health Administration MUTCD Manual on Uniform Traffic Control Devices NBFU National Board of Fire Underwriters NBS National Bureau of Standards

NEMA National Electrical Manufacturers Association NESC National Electrical Safety Code NFPA (Fire) National Fire Protection Association NFPA (Forest) National Forest Products Association NWMA National Woodwork Manufacturers Association OSHA Occupational Safety and Health Act PCA Portland Cement Association PCI Prestressed Concrete Institute PS Product Standard Issued by the U.S. Department of Commerce PTI Post-Tensioning Institute RIS Redwood Inspection Service SAE Society of Automotive Engineers SF Standard Form SI International System of Units SMACNA Sheet Metal & Air Conditioning Contractors National Association SSPC Steel Structures Painting Council UBC Uniform Building Code UFC Uniform Fire Code UL Underwriter's Laboratories, Inc.

UMC Uniform Mechanical Code UPC Uniform Plumbing Code USASI United States of America Standards Institute WCLIB West Coast Lumber Inspection Bureau WWPAA Western Wood Products Association WWPI Western Wood Preservation Institute

PART II – CONTRACT CLAUSES

SECTION I – CONTRACT CLAUSES

I.1 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.arnet.gov/far/ & www.usda.gov/procurement/plolicy/agar.html

52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards (OCT 2016)

52.209-6 Protecting the Government's Interest when Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (OCT 2015)

52.215-8 Order of Precedence--Uniform Contract Format (OCT 1997) 52.219-6 Notice of Total Small Business Set-Aside (NOV 2011) 52.222-3 Convict Labor (JUN 2003) 52.222-21 Prohibition of Segregated Facilities (APR 2015) 52.222-26 Equal Opportunity (SEPT 2016) 52.222-36 Affirmative Action for Workers with Disabilities (JUL 2014) 52.222-50 Combating Trafficking in Persons (MAR 2015) 52.223-5 Pollution Prevention and Right-to-Know Information (MAY 2011) 52.223-6 Drug-Free Workplace (MAY 2001) 52.223-17 Affirmative Procurement of EPA-designated Items in Service and Construction

Contracts (MAY 2008) 52.223-18 Contractor Policy to Ban Text Messaging While Driving (AUG 2011) 52.225-13 Restrictions on Certain Foreign Purchases (JUN 2008) 52.227-1 Authorization and Consent (DEC 2007) 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (DEC

2007) 52.232-23 Assignment of Claims (MAY 2014) 52.232-33 Payment by Electronic Funds Transfer – System for Award Management (JUL

2013) 52.233-1 Disputes (MAY 2014) 52.233-3 Protest After Award (AUG 1996) 52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004) 52.244-6 Subcontracts for Commercial Items (NOV 2017) 52.245-1 Government Property (APR 2012) Alternate I (JAN 2017) 52.253-1 Computer Generated Forms (JAN 1991) 52.211-18 Variation in Estimated Quantity (APR 1984) 52.222-6 Construction Wage Rate Requirements (MAY 2014) 52.222-7 Withholding of Funds (MAY 2014)

52.222-8 Payrolls and Basic Records (MAY 2014) 52.222-9 Apprentices and Trainees (JUL 2005) 52.222-10 Compliance with Copeland Act Requirements (FEB 1988) 52.222-11 Subcontracts (Labor Standards) (MAY 2014) 52.222-12 Contract Termination -Debarment (MAY 2014) 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations

(MAY 2014)

52.222-14 Disputes Concerning Labor Standards (FEB 1988) 52.222-15 Certification of Eligibility (MAY 2014) 52.222-27 Affirmative Action Compliance Requirements for Construction (APR 2015) 52.222-30 Construction Wage Rate Requirements – Price Adjustment (None or Separately

Specified Method (MAY 2014) 52.228-2 Additional Bond Security (OCT 1997) 52.228-12 Prospective Subcontractor Requests for Bonds (MAY 2014) 52.228-14 Irrevocable Letter of Credit (NOV 2014) 52.232-5 Payments under Fixed-Price Construction Contracts (MAY 2014) 52.232-27 Prompt Payment for Construction Contracts (JAN 2017) 52.236-2 Differing Site Conditions (APR 1984) 52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984) 52.236-5 Material and Workmanship (APR 1984) 52.236-6 Superintendence by the Contractor (APR 1984) 52.236-7 Permits and Responsibilities (NOV 1991) 52.236-8 Other Contracts (APR 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and

Improvements (APR 1984) 52.236-10 Operations and Storage Areas (APR 1984) 52.236-11 Use and Possession Prior to Completion (APR 1984) 52.236-12 Cleaning Up (APR 1984) 52.246-21 Warranty of Construction (MAR 1994) 52.249-10 Default (Fixed-Price Construction) (APR 1984)

I.2 FAR 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (MAY 2014)

(a) Definitions. As used in this clause— “Commercially available off-the-shelf (COTS) item”—

(1) Means any item of supply (including construction material) that is—

(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.

“Component” means an article, material, or supply incorporated directly into a construction material.

https://www.acquisition.gov/sites/default/files/current/far/html/Subpart%202_1.html#wp1145508 http://uscode.house.gov/

“Construction material” means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

“Cost of components” means—

(3) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(4) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

“Domestic construction material” means—

(1) An unmanufactured construction material mined or produced in the United States;

(2) A construction material manufactured in the United States, if—

(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic;

or

(ii) The construction material is a COTS item.

“Foreign construction material” means a construction material other than a domestic construction material.

“United States” means the 50 States, the District of Columbia, and outlying areas.

(b) Domestic preference.

(1) This clause implements 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the component test of the Buy American statute is waived for construction material that is a COTS item. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.

(2) This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows:

_______None_________________________________________ http://uscode.house.gov/ http://uscode.house.gov/ https://www.acquisition.gov/sites/default/files/current/far/html/Subpart%2012_5.html#wp1077123

(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that—

(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;

(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or

(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.

(c) Request for determination of inapplicability of the Buy American statute.

(1)(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including—

(A) A description of the foreign and domestic construction materials;

(B) Unit of measure;

(C) Quantity;

(D) Price;

(E) Time of delivery or availability;

(F) Location of the construction project;

(G) Name and address of the proposed supplier; and

(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.

(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.

(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).

(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.

(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.

(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.

(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:

FOREIGN AND DOMESTIC CONSTRUCTION MATERIALS PRICE COMPARISON

Construction Material Description Unit of Measure Quantity Price (Dollars)* Item 1:

Foreign construction material _______ _______ _______ Domestic construction material _______ _______ _______ Item 2: _______ _______ _______ Foreign construction material _______ _______ _______ Domestic construction material [List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.] [Include other applicable supporting information.] [* Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued).]

(End of Clause)

I.3 FAR 52.228-13 ALTERNATIVE PAYMENT PROTECTIONS (JULY 2000)

(a) The Contractor shall submit one of the following payment protections:

____Payment Bond____________________________________________

______Irrevocable Letter of Credit__________________________________

(b) The amount of the payment protection shall be 100 percent of the contract price.

(c) The submission of the payment protection is required within ___15____ days of contract award.

(d) The payment protection shall provide protection for the full contract performance period plus a one-year period.

(e) Except for escrow agreements and payment bonds, which provide their own protection procedures, the Contracting Officer is authorized to access funds under the payment protection when it has been alleged in writing by a supplier of labor or material that a nonpayment has occurred, and to withhold such funds pending resolution by administrative or judicial proceedings or mutual agreement of the parties.

(f) When a tripartite escrow agreement is used, the Contractor shall utilize only suppliers of labor and material that signed the escrow agreement.

(End of clause)

I.4 FAR 52.217-7 OPTION FOR INCREASED QUANTITY—SEPARATELY

PRICED LINE ITEM (MAR 1989)

The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option by written notice to the Contractor within 30 days of the end of the contract. Delivery of added items shall continue at the same rate that like items are called for under the contract, unless the parties otherwise agree.

(End of clause)

PART III – LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS

SECTION J - LIST OF ATTACHMENTS

J.1 LIST OF ATTACHMENTS (USDA 452.252-70) (JUL 1985)

Title Pages

1. Project Standard Specifications (Separate Attachment) 32

2. Project Drawings (Separate Attachment) 5

Sheet No.

Dwg No.

Description

A. GENERAL INFORMATION

1 TITLE SHEET 1

2 IRON CREEK CAMPGROUND MAP 1

3 IRON CREEK CAMPGROUND PHOTOS 1

4 NORTH FORK CAMPGROUND MAP 1

5 NORTH FORK CAMPGROUND PHOTOS 1

3. DOL Wage Determination, WA 1(Separate Attachment) 10

4. Fire Plan 9

PART IV--REPRESENTATIONS AND INSTRUCTIONS

SECTION K--REPRESENTATIONS, CERTIFICATIONS, AND

OTHER STATEMENTS OF OFFERORS OR RESPONDENTS

K-1 FAR 52.252-1 Solicitation Provisions Incorporated by Reference (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

www.arnet.gov/far/

K-2 AGAR 452.219-70 SIZE STANDARD AND NAICS CODE INFORMATION (JAN

2005)

The North American Industrial classification System Code(s) and business size standard(s) describing the products and/or services to be acquired under this solicitation are listed below:

Contract line item(s): All --NAICS Code 238210 --Size Standard $15.0 million

The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.

K-4 FAR 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (DEC

2014)

(a)(1) The North American Industry Classification System (NAICS) code for this acquisition is ____238210____.

(2) The small business size standard is _$15.0 million______.

(3) The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.

(b)(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.

(2) If the provision at 52.204-7 is not included in this solicitation, and the offeror is currently registered in the System for Award Management (SAM), and has completed the Representations and Certifications section of SAM electronically, the offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The offeror shall indicate which option applies by checking one of the following boxes:

[ ] (i) Paragraph (d) applies.

[ ] (ii) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.

(c)(1) The following representations or certifications in SAM are applicable to this solicitation as indicated:

(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless—

(A) The acquisition is to be made under the simplified acquisition procedures in Part 13;

(B) The solicitation is a request for technical proposals under two-step sealed bidding procedures; or

(C) The solicitation is for utility services for which rates are set by law or regulation.

(ii) 52.203-11, Certification and Disclosure Regarding Payments to Influence Certain

Federal Transactions. This provision applies to solicitations expected to exceed $150,000.

(iii) 52.204-3, Taxpayer Identification. This provision applies to solicitations that do not include the provision at 52.204-7, System for Award Management.

(iv) 52.204-5, Women-Owned Business (Other Than Small Business). This provision applies to solicitations that—

(A) Are not set aside for small business concerns;

(B) Exceed the simplified acquisition threshold; and

(C) Are for contracts that will be performed in the United States or its outlying areas.

(v) 52.209-2, Prohibition on Contracting with Inverted Domestic Corporations— Representation.

(vi) 52.209-5, Certification Regarding Responsibility Matters. This provision applies to solicitations where the contract value is expected to exceed the simplified acquisition threshold.

https://acquisition.gov/far/current/html/52_200_206.html#wp1137850 https://acquisition.gov/far/current/html/52_200_206.html#wp1137850 https://acquisition.gov/far/current/html/52_200_206.html#wp1137583 https://acquisition.gov/far/current/html/FARTOCP13.html#wp271421 https://acquisition.gov/far/current/html/52_200_206.html#wp1137684 https://acquisition.gov/far/current/html/52_200_206.html#wp1137777 https://acquisition.gov/far/current/html/52_200_206.html#wp1137850 https://acquisition.gov/far/current/html/52_200_206.html#wp1149919 https://acquisition.gov/far/current/html/52_207_211.html#wp1144766 https://acquisition.gov/far/current/html/52_207_211.html#wp1144909

(vii) 52.214-14, Place of Performance—Sealed Bidding. This provision applies to invitations for bids except those in which the place of performance is specified by the Government.

(viii) 52.215-6, Place of Performance. This provision applies to solicitations unless the place of performance is specified by the Government.

(ix) 52.219-1, Small Business Program Representations (Basic & Alternate I). This provision applies to solicitations when the contract will be performed in the United States or its outlying areas.

(A) The basic provision applies when the solicitations are issued by other than DoD, NASA, and the Coast Guard.

(B) The provision with its Alternate I applies to solicitations issued by DoD, NASA, or the Coast Guard.

(x) 52.219-2, Equal Low Bids. This provision applies to solicitations when contracting by sealed bidding and the contract will be performed in the United States or its outlying areas.

(xi) 52.222-22, Previous Contracts and Compliance Reports. This provision applies to solicitations that include the clause at 52.222-26, Equal Opportunity.

(xii) 52.222-25, Affirmative Action Compliance. This provision applies to solicitations, other than those for construction, when the solicitation includes the clause at 52.222-26, Equal Opportunity.

(xiii) 52.222-38, Compliance with Veterans’ Employment Reporting Requirements. This provision applies to solicitations when it is anticipated the contract award will exceed the simplified acquisition threshold and the contract is not for acquisition of commercial items.

(xiv) 52.223-1, Biobased Product Certification. This provision applies to solicitations that require the delivery or specify the use of USDA–designated items; or include the clause at 52.223-2, Affirmative…