1205K319R0003_Attachments.pdf

PDF 3 MB Posted

Attached to
Iron Creek and North Fork CG Water Systems Federal contract opportunity
Solicitation number
1205K319R0003
Issued by
Department of Agriculture Forest Service R6-Pacific Northwest Region

About this file

1205K319R0003 Solicitation Attachments

View the file

Other files for this federal contract opportunity

Other files attached to Iron Creek and North Fork CG Water Systems, newest first.
File Type Posted
1205K319R0003_Iron_Creek_Amendment_01.pdf PDF
1205K319R0003_Iron_Creek_and_N_Fork_Pumphouse.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Iron Creek and North Fork CG Water Systems Page 1 of 32

Contract No. Ag-Xxxx-X-Xx-Xxxx

SECTION 01200

MOBILIZATION PAYMENT PROCEDURES

1 PART 1 - GENERAL

1.01 SUMMARY

A. This work shall consist of preparatory work and operations necessary for the movement of personnel, equipment, supplies, and incidentals to the project site, and for all other work and operations that must be performed or that cause costs to be incurred prior to beginning work on the various items on the project site.

2 PART 2 - PRODUCTS (NOT USED)

3 PART 3 - EXECUTION (NOT USED)

4 PART 4 - MEASUREMENT AND PAYMENT

4.01 PROGRESS PAYMENTS WILL BE MADE AS FOLLOWS:

A. When 5 percent or more of the original contract amount is earned from other pay items, 50 percent of the amount for mobilization, or 5 percent of the original contract amount, whichever is less, will be paid.

B. When 10 percent or more of the original contract amount is earned from other pay items, 100 percent of the amount for mobilization, or 10 percent of the original contract amount, whichever is less, will be paid.

C. Upon completion of all work on the project, any unpaid amount for mobilization will be paid.

D. The total of all payments shall not exceed the original contract amount for this item.

4.02 BASIS OF PAYMENT

A. Payment will be made under:

PAY ITEM DESCRIPTION PAY UNIT

01200 Mobilization Lump Sum

END OF SECTION 01200

Iron Creek and North Fork CG Water Systems Page 2 of 32

SECTION 01621

COLOR SCHEDULE

PART 1 - GENERAL (NOT USED)

PART 2 - MATERIALS

4.03 COLOR SCHEDULE

A. Color.

NO. DESCRIPTION COLOR

1 Metal Roofing Panels Dark Brown

PART 3 - EXECUTION (NOT USED)

PART 4 - MEASUREMENT AND PAYMENT (NOT USED)

END OF SECTION 016221

Iron Creek and North Fork CG Water Systems Page 3 of 32

SECTION 01732

SELECTIVE DEMOLITION

1 PART 1 - GENERAL

1.01 SUMMARY

1. This Section includes demolition and removal of the following:

a. Existing electrical panels and all wiring for controls.

b. Existing generators and wiring to pump house.

1.02 DEFINITIONS

1. Remove: All electrical panels and wiring are to be removed from pump houses, and replaced with up to date panels and wiring to meet code.

1.03 MATERIALS OWNERSHIP

1. Except for items or materials indicated to be reused, salvaged, reinstalled, or otherwise indicated to remain Government property, demolished materials shall become Contractor's property and shall be removed from Project site. This includes existing generators.

1.04 QUALITY ASSURANCE

1. Demolition Firm Qualifications: An experienced firm that has specialized in electrical demolition work similar in material and extent to that indicated for this Project.

2. Regulatory Requirements: Comply with governing EPA notification regulations before beginning selective demolition. Comply with hauling and disposal regulations of authorities having jurisdiction.

1.05 PROJECT CONDITIONS

1. Provide not less than 72 hours' notice to CO of activities that will affect utility operations.

2. Maintain access to existing walkways, campsites, and other adjacent occupied or used facilities.

a. Do not close or obstruct walkways or other occupied or used facilities without written permission from authorities having jurisdiction.

3. Government assumes no responsibility for condition of areas to be selectively demolished.

a. Conditions existing at time of inspection for bidding purpose will be maintained by

Government as far as practical.

4. Hazardous Materials: It is not expected that hazardous materials will be encountered in the Work.

5. Utility Service: Maintain existing utilities indicated to remain in service and protect them against damage during selective demolition operations.

2 PART 2 - PRODUCTS

2.01 REPAIR MATERIAL

1. Use repair materials identical to existing materials.

a. If identical materials are unavailable or cannot be used for exposed surfaces, use materials that visually match existing adjacent surfaces to the fullest extent possible.

b. Use materials whose installed performance equals or surpasses that of existing materials.

Iron Creek and North Fork CG Water Systems Page 4 of 32

3 PART 3 – EXECUTION

3.01 EXAMINATION

1. Verify that utilities have been disconnected and capped.

2. Survey existing conditions and correlate with requirements indicated to determine extent of selective demolition required.

3. When unanticipated mechanical, electrical, or structural elements that conflict with intended function or design are encountered, investigate and measure the nature and extent of conflict. Promptly submit a written report to CO.

3.02 UTILITY SERVICES

1. Existing Utilities: Maintain services indicated to remain and protect them against damage during selective demolition operations.

2. Do not interrupt existing utilities serving occupied or operating facilities unless authorized in writing by CO and authorities having jurisdiction.

a. Provide at least 72 hours' notice to CO of shutdown of service during changeover.

3. Utility Requirements: Locate, identify, disconnect, and seal or cap off indicated utilities serving areas to be selectively demolished.

3.03 PREPARATION

1. Site Access and Temporary Controls: Conduct selective demolition and debris-removal operations to ensure minimum interference with roads, campsites, walkways, and other adjacent occupied and used facilities.

a. Protect existing site improvements, appurtenances, and landscaping to remain.

3.04 POLLUTION CONTROLS

1. Cleaning: Clean adjacent structures and improvements of dust, dirt, and debris caused by selective demolition operations. Return adjacent areas to condition existing before selective demolition operations began.

3.05 SELECTIVE DEMOLITION

1. General: Demolish and remove existing construction only to the extent required by new construction and as indicated. Use methods required to complete the Work within limitations of governing regulations.

3.06 PATCHING AND REPAIRS

1. General: Promptly repair damage to adjacent construction caused by selective demolition operations.

2. Repairs: Where repairs to existing surfaces are required, patch to produce surfaces suitable for new materials.

a. Completely fill holes and depressions in existing masonry walls that are to remain with an approved masonry patching material applied according to manufacturer's written recommendations.

Iron Creek and North Fork CG Water Systems Page 5 of 32

3. Finishes: Restore exposed finishes of patched areas and extend restoration into adjoining construction in a manner that eliminates evidence of patching and refinishing.

4. Floors and Walls: Where walls or partitions that are demolished extend one finished area into another, patch and repair floor and wall surfaces in the new space.

Provide an even surface of uniform finish color, texture, and appearance. Remove existing floor and wall coverings and replace with new materials, if necessary, to achieve uniform color and appearance.

3.07 DISPOSAL OF DEMOLISHED MATERIALS

1. Disposal: All materials removed become property of contractor. This includes existing generators. Transport demolished materials off Government property and legally disposes of them.

5 PART 4 - MEASUREMENT AND PAYMENT (NOT USED)

END OF SECTION 01732

Iron Creek and North Fork CG Water Systems Page 6 of 32

SECTION 02318

EXCAVATION AND BACKFILL FOR UTILITIES

1. PART 1 - GENERAL

1.01 SUMMARY

A. This section specifies excavation and backfill for utilities, including excavation; furnishing, hauling and placing of backfill material; disposal of excess or unsuitable backfill material;

and grading.

B. Class of Material.

1. Material to be excavated for installation of utilities is unclassified.

1.02 SUBMITTALS

A. Excavation.

1. Notify COR when excavation is completed. Do not place pipe, cable or bedding backfill until the excavation is approved by the COR.

2. PART 2 - PRODUCTS

2.01 MATERIALS

A. Backfill Materials.

1. Backfill material shall contain no frozen or organic material.

2. Bedding Material.

a. Fine soil or sand, 100 percent passing the #4 sieve; or crushed rock less than 1/2 inch.

3. Crushed Rock.

a. Crushed aggregate, meeting the requirements of AASHTO M147 grading D.

4. Drain Rock Material.

a. Round, washed gravel, ASTM D448 (AASHTO M43), Size Number 24.

5. Electrical Bedding Material.

a. Natural sand passing the #8 sieve, without sharp chips or points.

6. Select Material.

a. Fine soil or sand, 100 percent passing the #4 sieve.

7. Select Excavated Material.

a. Excavated material containing no rocks larger than 6 inches in largest dimension.

3. PART 3 - EXECUTION

3.01 CONSTRUCTION

A. Excavation.

1. Excavation shall not begin until all clearing and grubbing work is completed except for final debris disposal. Operations shall be in compliance with the requirements and restrictions of OSHA, and the Oregon or Washington Occupational Safety and Health Code.

2. All trenches shall be excavated in reasonably close conformity with the lines and grades shown on the Drawings. Any shifting or change from the alignment and grade shown on the Drawings must receive prior approval by the COR in writing.

3. Lay utilities in continuous open trench. Short tunnel sections or boring may be used in special locations with the approval of the COR.

4. Trim roots flush with trench wall.

Iron Creek and North Fork CG Water Systems Page 7 of 32

B. Overexcavation.

1. Restore to grade any overexcavation by backfilling with select material.

C. Wet Excavation.

1. If water is encountered during trench excavation, provide adequate pumping equipment and piping to keep trench free from water and dispose of the water without damage to adjacent property. Separate payment will not be made for pumping of water from trenches or for excavation of material rendered unsuitable as a result of water encountered.

D. Unsuitable Material.

1. Where unsuitable material is encountered in the trench bottom, as determined by the

COR, excavate the trench below grade to the depth specified by the COR.

E. Backsloping, Sheeting and Shoring.

1. Backsloping of trench walls will be allowed only upon prior written approval of the

COR.

2. Remove all shoring and sheeting when construction is completed. Withdraw to prevent trench wall caving while backfilling.

F. Excavated Material.

1. Pile excavated material at the side of the trench where it will give the best protection for the work. Leave adequate space between the toe of the spoil pile and edge of trench to prevent material from falling into the trench.

G. Backfill.

1. Do not place backfill until installation of pipe or cable has been approved by the COR.

2. Before compacting backfill other than rock or sand, prepare material to a water content that will permit proper compaction by either aerating the material if it is too wet, or spraying the material with water if it is too dry. Thoroughly mix each lift before compaction to assure uniform distribution of water content. Do not compact material above pipe or cable until there are 6 inches of cover over the pipe or cable.

3. Compact each lift (with the required number of passes of a mechanical vibrating tamper over the entire layer) (to the required density).

a. Select Material.

1) Place in 6 inches lifts or less and compact with a minimum of 3 passes over the entire lift surface.

b. Bedding Material.

1) Place in lifts 4 inches or less in thickness and compact with a minimum of 3 passes over the entire lift surface. Compact around pipe barrel and bells by hand tamping.

c. Select Excavated Material.

1) Distribute large rocks so they are individually surrounded by fine materials.

Place select excavated material as follows

a) Class A: Place in 24 inch lifts or less to within 8 inches of finished grade and compact each lift with 3 passes of tamper. On pipe gradients over 30 percent (0.3 foot/foot) place in 12 inch horizontal lifts and compact each lift with 3 passes of tamper.

b) Class B: Place in l2 inch lifts or less and compact each lift with 3 passes of tamper.

c) Class C: Place in l2 inch lifts or less, and compact each lift with 6 passes of tamper. At depths greater than 5 feet, compact each lift with 3 passes of tamper.

d) Class D: Place in l2 inch lifts or less and compact each lift with 6 passes of tamper. At depths greater than 5 feet, compact each lift with 3 passes of tamper.

Iron Creek and North Fork CG Water Systems Page 8 of 32

d. The number of tamper passes required may be reduced upon acceptance by the COR, if approved test method results demonstrate that the backfill compaction meets or exceeds the density of the natural ground adjacent to the trench. Any such testing shall be performed at the Contractor's expense.

4. Water compaction shall not be used.

3.02 REPAIR/RESTORATION

A. Damage to existing underground utilities.

1. Stop all work associated with damage to existing utilities, and notify the COR. Repair utility as directed by the COR.

B. Surface Restoration.

1. Restore all surfaces in kind and in accordance with backfill classes indicated on Drawings:

a. Class A: Mound final uncompacted lift above finished grade.

2. Final Finish.

a. After the utility installation and backfill has been completed, finish all disturbed areas, except trench area required to be mounded, to a smooth, uniform grade and texture, well blended to the original contours, showing minimum evidence of construction activity.

C. Seeding.

1. Disturbed areas may be seeded or sodded at the Contractor's option. A Government approved commercial sod may be substituted for replacement sod.

3.03 CLEANING

A. Disposal of Excess of Excavation and Unsuitable Material.

1. Haul excess (and unsuitable) material to the disposal site in accordance with COR instructions, or:

2. Spread excess excavation, without mounding, within the clearing limits.

3.04 SCHEDULES

A. Backfill and restore surface materials of utility line trenches located in existing roadways, parking areas, driveways, and lawns within 7 days after approval to place backfill by COR.

4. PART 4 - MEASUREMENT AND PAYMENT (NOT USED)

END OF SECTION 02318

Iron Creek and North Fork CG Water Systems Page 9 of 32

SECTION 03300

CAST-IN-PLACE CONCRETE

1 PART 1 - GENERAL

1.01 SUMMARY

1. This Section includes cast-in-place concrete, including reinforcement, concrete materials, mix design, placement procedures, and finishes.

a. 0330 Cast-in-place concrete (concrete tube footings)

1.02 SUBMITTALS

1. Design Mix

1.03 QUALITY ASSURANCE

1. Manufacturer Qualifications: A firm experienced in manufacturing ready-mixed concrete products complying with ASTM C 94 requirements for production facilities and equipment.

2. Comply with ACI 301, "Specification for Structural Concrete," including the following, unless modified by the requirements of the Contract Documents.

a. General requirements, including submittals, quality assurance, acceptance of structure, and protection of in-place concrete.

b. Formwork and form accessories.

c. Steel reinforcement and supports.

d. Concrete mixtures.

e. Handling, placing, and constructing concrete.

f. Lightweight concrete.

2 PART 2 - PRODUCTS

2.01 MATERIALS

1. Formwork: Furnish formwork and form accessories according to ACI 301.

2. Steel Reinforcement:

a. Reinforcing Bars: ASTM A 615/A 615M, Grade 60 (Grade 420), deformed.

b. Plain-Steel Wire: ASTM A 82, as drawn.

c. Plain-Steel Welded Wire Fabric: ASTM A 185, fabricated from as-drawn steel wire into flat sheets.

d. Deformed-Steel Welded Wire Fabric: ASTM A 497, flat sheet.

3. Concrete Materials:

a. Portland Cement: ASTM C 150, Type II, use one brand of cement throughout project.

b. Normal-Weight Aggregate: ASTM C 33, uniformly graded, not exceeding 1-1/2-inch (38-mm) nominal size.

c. Lightweight Aggregate: ASTM C 330.

d. Water: Complying with ASTM C 94.

4. Curing Materials:

a. Moisture-Retaining Cover: ASTM C 171, polyethylene film or white burlap-polyethylene sheet.

Iron Creek and North Fork CG Water Systems Page 10 of 32

b. Water: Potable.

2.02 CONCRETE MIXES

1. Comply with ACI 301 requirements for concrete mixtures.

2.03 CONCRETE MIXING

1. Ready-Mixed Concrete: Comply with ASTM C 94.

2. Project-Site Mixing: Measure, batch, and mix concrete materials and concrete according to ASTM C 94. Mix concrete materials in appropriate drum-type batch machine mixer.

a. For mixer capacity of 1 cu. yd. (0.76 cu. m) or smaller, continue mixing at least 1- 1/2 minutes, but not more than 5 minutes after ingredients are in mixer, before any part of batch is released.

b. For mixer capacity larger than 1 cu. yd. (0.76 cu. m), increase mixing time by 15 seconds for each additional 1 cu. yd. (0.76 cu. m).

3. Provide batch ticket for each batch discharged and used in the Work, indicating Project identification name and number, date, mix type, mix time, quantity, and amount of water added. Record approximate location of final deposit in structure.

3 PART 3 - EXECUTION

3.01 INSTALLATION, GENERAL

1. Formwork: Design, construct, erect, shore, brace, and maintain formwork according to ACI 301.

2. Steel Reinforcement: Comply with CRSI's "Manual of Standard Practice" for fabricating, placing, and supporting reinforcement.

3. Joints: Construct joints true to line with faces perpendicular to surface plane of concrete.

4. Tolerances: Comply with ACI 117, "Specifications for Tolerances for Concrete

Construction and Materials."

3.02 CONCRETE PLACEMENT

1. Comply with recommendations in ACI 304R for measuring, mixing, transporting, and placing concrete.

3.03 FINISHING UNFORMED SURFACES

1. General: Comply with ACI 302.1R for screeding, restraightening, and finishing operations for concrete surfaces. Do not wet concrete surfaces.

2. Screed surfaces with a straightedge and strike off. Begin initial floating using bull floats or darbies to form a uniform and open-textured surface plane before excess moisture or bleedwater appears on the surface.

a. Do not further disturb surfaces before starting finishing operations.

3. Trowel and Fine-Broom Finish: Apply a partial trowel finish, stopping after second troweling, to surfaces indicated and to surfaces where ceramic or quarry tile is to be installed by either thickset or thin-set methods. Immediately after second troweling, and when concrete is still plastic, slightly scarify surface with a fine broom.

3.04 CONCRETE PROTECTION AND CURING

Iron Creek and North Fork CG Water Systems Page 11 of 32

1. General: Protect freshly placed concrete from premature drying and excessive cold or hot temperatures. Comply with ACI 306.1 for cold-weather protection, and follow recommendations in ACI 305R for hot-weather protection during curing.

2. Evaporation Retarder: Apply evaporation retarder to concrete surfaces if hot, dry, or windy conditions occur before and during finishing operations. Apply according to manufacturer's written instructions after placing, screeding, and bull floating or darbying concrete, but before float finishing.

3. Begin curing after finishing concrete, but not before free water has disappeared from concrete surface.

4. Cure formed and unformed concrete for at least seven days as follows:

a. Moisture-Retaining-Cover Curing: Cover concrete surfaces with moisture-retaining cover for curing concrete, placed in widest practicable width, with sides and ends lapped at least 12 inches (300 mm), and sealed by waterproof tape or adhesive.

Immediately repair any holes or tears during curing period using cover material and waterproof tape.

1 PART 4 - MEASUREMENT AND PAYMENT (NOT USED)

END OF SECTION 03300

Iron Creek and North Fork CG Water Systems Page 12 of 32

SECTION 06100

ROUGH CARPENTRY

PART 1 - GENERAL

1.01 SUMMARY

1. This Section includes the following:

a. Wood framing.

b. Wood sheathing.

1.02 SUBMITTALS

1. Product Data: For each type of process and factory-fabricated product indicated.

a. Include data for wood-preservative treatment from chemical treatment manufacturer and certification by treating plant that materials comply with requirements.

2. Research/Evaluation Reports: For the following:

a. Treated wood.

b. Engineered wood products.

c. Power-driven fasteners.

d. Metal framing anchors.

PART 2 - PRODUCTS

2.01 MAUFACTURERS

1. In other Part 2 articles where subparagraph titles below introduce lists, the following requirements apply for product selection:

a. Available Manufacturers: Subject to compliance with requirements, manufacturers offering products that may be incorporated into the work include, but are not limited to, the manufacturers specified.

2.02 WOOD PRODUCTS, GENERAL

1. Lumber: DOC PS 20 and applicable rules of lumber grading agencies certified by the American Lumber Standards Committee Board of Review.

a. Factory mark each piece of lumber with grade stamp of grading agency.

b. For exposed lumber indicated to receive stained or natural finish, mark grade stamp on end or back of each piece, or omit grade stamp and provide certificates of grade compliance issued by grading agency.

c. Provide dressed lumber, S4S, unless otherwise indicated.

Iron Creek and North Fork CG Water Systems Page 13 of 32

d. Provide dry lumber with 15 percent maximum moisture content at time of dressing for 2-inch nominal (38-mm actual) thickness or less, unless otherwise indicated.

2. Wood Structural Panels:

a. Plywood: Either DOC PS 1 or DOC PS 2, unless otherwise indicated.

b. Oriented Strand Board: DOC PS 2.

c. Comply with "Code Plus" provisions in APA Form No. E30K, "APA Design/Construction Guide: Residential & Commercial."

2.03 WOOD-PRESERVATIVE-TREATED MATERIALS

1. Preservative Treatment by Pressure Process: AWPA C2 (lumber), except that lumber that is not in contact with the ground and is continuously protected from liquid water may be treated according to AWPA C31 with inorganic boron (SBX).

a. Wood for Wood Foundation Systems: WPB FDN.

b. Wood for Ground Contact Use: AWPB LP-22.

2. Kiln-dry material after treatment to maximum moisture content of 19 percent.

3. Mark each treated item with treatment quality mark of an inspection agency approved by the American Lumber Standards Committee Board of Review.

4. Application: Treat items indicated on Drawings, and the following:

a. Wood cants, nailers, curbs, equipment support bases, blocking, stripping, and similar members in connection with roofing, flashing, vapor barriers, and waterproofing.

b. Wood sills, sleepers, blocking, furring, stripping, and similar concealed members in contact with masonry or concrete.

c. Wood framing members less than 18 inches (460 mm) above grade.

d. Wood floor plates that are installed over concrete slabs directly in contact with earth.

2.04 DIMENSION LUMBER

1. General: Of grades indicated according to the American Lumber Standards Committee National Grading Rule provisions of the grading agency indicated.

2. Non-Load-Bearing Interior Partitions: Construction, Stud, or No. 2 Standard, Stud, or No. 3 grade and any of the following species:

a. Northern species; NLGA.

b. Western woods; WCLIB or WWPA.

3. Framing Other Than Non-Load-Bearing Partitions: Construction, Stud, or No. 3 grade and any of the following species:

a. Douglas fir-larch, Douglas fir-larch (north), or Douglas fir-south; NLGA, WCLIB, or WWPA.

b. Hem-fir or Hem-fir (north); NLGA, WCLIB, or WWPA.

c. Spruce-pine-fir (south) or Spruce-pine-fir; NELMA, NLGA, WCLIB, or WWPA.

Iron Creek and North Fork CG Water Systems Page 14 of 32

4. Exposed Framing: Hand select material for uniformity of appearance and freedom from characteristics that would impair finish appearance.

a. Species and Grade: Hem-fir or Hem-fir (north), Select Structural grade; NLGA, WCLIB, or WWPA – saw texture.

b. Species and Grade: No. 1 grade; NELMA, NLGA, WCLIB, or WWPA – saw texture.

c. Cedar, “A” grade, saw texture, per western red cedar rules.

2.05 TIMBER AND MISCELLANEOUS LUMBER

1. For timbers of 5-inch nominal size and thicker, provide material complying with the following requirements:

a. Species and Grade: Douglas fir-larch, Douglas fir-larch (north), or Douglas fir-south; Select Structural No. 1 grade; NLGA< WCLIB< or WWPA.

2. Provide miscellaneous lumber for support or attachment of other construction, including the following:

a. Rooftop equipment bases and support curbs.

b. Blocking.

c. Cants.

d. Nailers.

e. Furring.

f. Grounds.

3. For items of dimension lumber size, provide Construction, Stud, or No. 2-grade lumber with 19 percent maximum moisture content of any species.

4. For concealed boards, provide lumber with 19 percent maximum moisture content and any of the following species and grades:

a. Northern species, No. 3 Common grade; NLGA.

b. Western woods, Standard or No. 3 Common grade; WCLIB or WWPA.

2.06 SHEATHING

1. Plywood Roof Sheathing: Exterior

a. Span Rating: 12/0, 5/16” thick.

b. Span Rating: 24/0, ½” thick.

c. Span Rating 24/16, ½” thick.

d. Span Rating 32/16, ½” or 5/8” thick.

e. Span Rating 48/24, ¾” or 7/8” thick.

2. Oriented-Strand-Board Roof Sheathing: Exposure 1 sheathing.

2.07 MISCELLANEOUS MATERIALS

1. Fasteners:

a. Where rough carpentry is exposed to weather, in ground contact, or in area of high relative humidity, provide fasteners [with hot-dip zinc coating complying with ASTM A 153/A 153M] [of Type 304 stainless steel].

b. Power-Driven Fasteners: CABO NER-272.

Iron Creek and North Fork CG Water Systems Page 15 of 32

c. Bolts: Steel bolts complying with ASTM A 307, Grade A (ASTM F 568M, Property Class 4.6); with ASTM A 563 (ASTM A 563M) hex nuts and, where indicated, flat washers.

2. Metal Framing Anchors: Made from hot-dip, zinc-coated steel sheet complying with ASTM A 653/A 653M, G60 (Z180) coating designation.

a. Available Manufacturers:

1) Alpine Engineered Products, Inc.

2) Cleveland Steel Specialty Co.

3) Harlen Metal Products, Inc.

4) KC Metals Products, Inc.

5) Silver Metal Products, Inc.

6) Simpson Strong-Tie Company, Inc.

7) Southeastern Metals Manufacturing Co., Inc.

8) United Steel Products Company, Inc.

b. Research/Evaluation Reports: Provide products acceptable to authorities having jurisdiction and for which model code research/evaluation reports exist that show compliance of metal framing anchors, for application indicated, with building code in effect for Project.

c. Allowable Design Loads: Meet or exceed those indicated per manufacturer's published values determined from empirical data or by rational engineering analysis and demonstrated by comprehensive testing performed by a qualified independent testing agency.

3. Building Paper: Asphalt-saturated organic felt complying with ASTM D 226, Type I (No. 15 asphalt felt), unperforated.

4. Adhesives for Field Gluing Panels to Framing: Formulation complying with APA AFG-01 or ASTM D 3498 that is approved for use with type of construction panel indicated by both adhesive and panel manufacturers.

PART 3 - EXECUTION

3.01 INSTALLATION

1. Set rough carpentry to required levels and lines, with members plumb, true to line, cut, and fitted. Fit rough carpentry to other construction; scribe and cope as needed for accurate fit.

Locate furring, nailers, blocking, grounds and similar supports to comply with requirements for attaching other construction.

2. Apply field treatment complying with AWPA M4 to cut surfaces of preservative-treated lumber and plywood.

3. Securely attach rough carpentry work to substrate by anchoring and fastening as indicated, complying with the following:

a. Table 2306.1, "Fastening Schedule," in the Standard Building Code.

4. Framing Standard: Comply with AFPA's "Manual for Wood Frame Construction," unless otherwise indicated.

Iron Creek and North Fork CG Water Systems Page 16 of 32

5. Comply with applicable recommendations contained in APA Form No. E30K, "APA Design/Construction Guide: Residential & Commercial," for types of structural-use panels and applications indicated.

a. Comply with "Code Plus" provisions in above-referenced guide.

6. Fastening Methods:

a. Sheathing: Nail to wood framing.

7. Apply building paper horizontally with 2-inch (50-mm) overlap and 6-inch (150-mm) end lap;

fasten to sheathing with galvanized staples or roofing nails. Cover upstanding flashing with 4-inch (102-mm) overlap.

4 PART 4 - PAYMENT BASIS OF PAYMENT

4.01 PAYMENT WILL BE MADE UNDER:

PAY ITEM DESCRIPTION PAY UNIT

06100 Rough Carpentry Lump Sum

END OF SECTION 06100

Iron Creek and North Fork CG Water Systems Page 17 of 32

SECTION 07610

PREFORMED METAL ROOFING

1 PART 1 - GENERAL

1.01 SECTION INCLUDES

A. Preformed, prefinished metal roofing and flashings.

B. Miscellaneous trim, flashing, closures, drip flashing, vent caps and dams, and accessories.

C. Fastening devices.

D. Underlayment.

1.02 RELATED SECTIONS

A. Section 01732 - Selective Demolition B. Section 06100 - Rough Carpentry.

C. Section 07900 - Sealants.

D. Section 06100 – Cast-in-place concrete

1.03 ASSEMBLY DESCRIPTION

A. The roofing assembly includes preformed sheet metal panels, related accessories, vented ridge, valleys, hips, eaves, corners, rakes, miscellaneous flashing and attaching devices.

1.04 SUBMITTALS

A. Submit technical specifications for roofing material proposed to be used. Include the following information.

1. Manufacturer’s cut/specification sheets

2. Manufacturer’s installation instructions.

3. Manufacturer’s technical specifications for underlayment material.

1.05 QUALITY ASSURANCE

A. Manufacturer: Company specializing in Architectural Sheet Metal Products with ten (10) years minimum experience.

B. No product substitutions shall be permitted without meeting specifications.

C. Substitutions shall be submitted to CO. Decision of acceptance or rejection shall made by

CO within seven (7) days

1.06 DELIVERY, STORAGE AND HANDLING

A. Upon receipt of panels and other materials, installer shall examine the shipment for damage and completeness.

B. Panels should be stored in a clean, dry place. One end should be elevated to allow moisture to run off.

C. Panels with strippable film must not be stored in the open, exposed to the sun.

D. Stack all materials to prevent damage and to allow for adequate ventilation.

1.07 WARRANTY

A. Paint finish shall have a thirty year guarantee against fading, chalking, chipping, cracking, and peeling.

B. Galvalume material shall have a twenty year guarantee against failure due to corrosion, rupture or perforation.

Iron Creek and North Fork CG Water Systems Page 18 of 32

C. Applicator shall furnish guarantee covering watertightness of the roofing system for the period of two (2) years from the date of substantial completion

2 PART 2 - PRODUCTS

2.01 SHEET MATERIALS

A. Panels: 1.5” Mechanical Seam Metal Roof Panel

1. Material: Steel

a. 24 Gauge: minimum thickness of .0236”

2. Thickness and yield strength as required for performance indicated: ASTM A-653-94: Steel Sheet

3. Zinc Coated (Galvanized) Class G90 by the Hot Dip Process.

4. Panel Width and Pattern: 12-3/4” with smooth pattern.

5. Panel Seam Height: 1.5”

6. Panel Finish:

a. Polyvinylidine Fluoride, full 70 percent Kynar 500® consisting of a baked-on 0.15-0.20 mil corrosion resistant primer and a baked-on 0.70-0.80 mil finish coat with a specular gloss of 8 to 15 when tested in accordance with ASTM D523 at 60 degrees.

b. Color: Color samples to be submitted to CO and approved prior to ordering materials.

1) Dark Brown B. Seam Sealant: Factory apply high-grade butyl mastic sealant within the confines of panel’s female leg, designed to seal against adjacent male panel leg.

2.02 ACCESSORY MATERIALS

A. Fasteners: Galvanized Steel, Stainless Steel, Cadmium Plated Steel with washers where required by manufacturer.

B. Sealant: As specified by manufacturer’s instructions.

2.03 FABRICATION

A. All exposed adjacent flashing shall be of the same material and finish as the roof panels.

B. Hem all exposed edges of flashing on underside, 1/2 inch.

2.04 PREFORMED METAL PANELS

A. STANDING SEAM TEE-PANEL

1. Panels shall have a 12-3/4” standard panel width. Minimum seam height of 1-1/2" and shall have no exposed fasteners.

2. Panels shall be site-formed in continuous lengths from eave to ridge or factory fabricated to 40' max.

3. Concealed anchor clips shall be spaced as required to meet uplift loads. Fasteners shall be installed in accordance with manufacturer’s instructions.

4. When required, Panel assembly shall bear Underwriter’s Laboratories Label UL90, pursuant to Construction Number 296 and applicable Fire Ratings.

5. Certification shall be submitted, based on independent testing laboratory, indicating no measurable water penetration or air leakage beyond allowable tolerances through the system when tested in accordance with ASTM E-331-86 and E-283-84.

3 PART 3 - EXECUTION

3.01 INSPECTION

A. Substrate.

Iron Creek and North Fork CG Water Systems Page 19 of 32

1. Examine plywood to ensure proper attachment to framing.

2. Examine substrate for presence of rotten or weakened members. Repair/replace ae necessary.

3. Roof venting shall be accomplished by ridge venting. Existing turbo-vents shall be removed, disposed of and openings properly filled.

4. Inspect roof deck to verify deck is clean and smooth, free of depressions, waves or projections, level to ¼" in 20', and properly sloped to eaves.

5. Verify roof openings, curbs, pipes, sleeves, ducts or vents through roof are solidly set, and nailing strips located.

6. Verify deck is dry and free of snow or ice. Joints in wood deck to be solidly supported and nailed.

B. Underlayment:

1. Ensure underlayment is installed horizontally, starting at eave to ridge with a 6" minimum overlap and 18" endlaps.

2. Ensure that all nail heads are totally flush with the substrate. Nails shall be galvanized roofing nails.

3.02 INSTALLATION

A. Panels and Trim: Comply with manufacturer's instructions for assembly, installation and erection for weather tight installation.

1. Install panels in accordance with manufacturer’s instructions and recommendations.

Anchor securely in place using clips and fasteners spaced in accordance with manufacturer’s recommendations for design wind load criteria.

2. Form seams with manufacturer-approved motorized seaming tool; completely engage panel, clip, and factory-applied sealant in seam.

3. Comply with methods and recommendations of SMACNA Architectural Sheet Metal Manual for flashing configurations required.

4. Discrepancies between job site conditions and shop drawings shall be brought to the attention of the COR for resolution.

5. Cutting and Fitting:

a. Cut panels neat, square, and true with shearing action cutters. Torch or power saw cutting is prohibited.

b. Openings 6 inches and larger: Shop fabricate and reinforce to maintain original load capacity.

c. Openings less than 6 inches: Field cutting is acceptable.

6. Dissimilar Metals or Materials:

a. Where panel or trim may come in contact with dissimilar metals or treated lumber, fabricate transition to facilitate drainage and minimize possibility of galvanic action. Galvanic action can cause panels and trim to fail prematurely.

b. At points of contact with dissimilar metal or treated lumber, coat panel and trim with protective paint or separate materials with a weatherproof underlayment.

c. Direct contact or run-off from CCA, ACQ, CA, or other treated lumber (outdoor wood) or fire retardant impregnated or treated wood shakes or siding can cause panels and trim to fail prematurely. Avoid contact with these materials.

B. Accessories: Install trims, flashings, and roofing specialties according to Drawings and manufacturer's recommended details.

C. Sealant Installation: Apply according manufacturer’s instructions and approved shop drawings.

1. Provide airtight and waterproof installation.

Iron Creek and North Fork CG Water Systems Page 20 of 32

3.03 CLEANING

A. Clean any grease, finger marks or stains from the panels per manufacturer’s recommendations.

B. Remove all scrap and construction debris from the site

4 PART 4 - MEASUREMENT AND PAYMENT (NOT USED)

END OF SECTION 07610

Iron Creek and North Fork CG Water Systems Page 21 of 32

SECTION 07900

SEALANTS

1 PART 1 - GENERAL

1.01 SUMMARY

A. The work of this section consists of furnishing and installing sealants to provide a barrier against air, water, moisture, or dirt, and where needed for appearance.

1.02 SUBMITTALS

A. Manufacturer's technical data and application instructions.

B. Samples of sealant colors.

1.03 QUALITY ASSURANCE

A. Contractor shall have copies of referenced ASTM standards available on the job site.

1.04 DELIVERY, STORAGE, AND HANDLING

A. Deliver materials in manufacturer's original, unopened containers and store in a protected area at temperatures recommended by manufacturer.

1.05 PROJECT/SITE CONDITIONS

A. Environmental.

1. Install sealants only in favorable weather conditions as defined in ASTM C962.

To help balance extension and compression of sealants in exterior working joints, install sealants at substrate temperatures as near as possible to 55 degrees F.

2 PART 2 - PRODUCTS

2.01 APPROVED MANUFACTURERS

A. Other manufacturer's products may be used provided they are approved as equal.

1. Backer Rod Manufacturing and Supply Company, Denver, Colorado.

2. Dow Chemical Company, Midland, Michigan.

3. Dow Corning Corporation, Midland, Michigan.

4. General Electric Company, Waterford, New York.

5. Pecora Corporation, Harleysville, Pennsylvania.

6. Sika Chemical Corporation, Lyndhurst, New Jersey.

7. Sonneborn-Contech, Minneapolis, Minnesota.

8. Tremco, Cleveland, Ohio.

9. Williams Products, Inc., Troy, Michigan.

2.02 MATERIALS

A. Exterior Sealants.

1. Sealants shall be as per manufacturer’s instructions.

B. Joint Fillers.

1. ASTM C962, Type A, rod stock closed cell polyethylene foam, closed cell neoprene foam, or open cell urethane foam, recommended by sealant manufacturer for compatibility with sealant and primer.

a. Polyethylene: Ethafoam SB by Dow Chemical.

b. Neoprene: Neocord by Williams Products.

c. Urethane: Denverfoam by Backer Rod Manufacturing and Supply.

Iron Creek and North Fork CG Water Systems Page 22 of 32

3 PART 3 - EXECUTION

3.01 INSTALLATION

A. Sealants.

1. Follow sealant manufacturer's instructions for installation of sealants, and joint fillers.

Tool joints concave.

2. Install latex sealants in accordance with ASTM C790.

3. Install elastomeric sealants in accordance with ASTM C962.

4 PART 4 - MEASUREMENT AND PAYMENT (NOT USED)

END OF SECTION 07900

Iron Creek and North Fork CG Water Systems Page 23 of 32

SECTION 16050

BASIC ELECTRICAL MATERIALS AND METHODS

1 PART 1 - GENERAL

1.01 SUMMARY

1. This Section includes the following:

a. Raceways.

b. Building wire and connectors.

c. Supporting devices for electrical components.

d. Electrical identification.

e. Concrete equipment bases.

f. Electrical demolition.

g. Cutting and patching for electrical construction.

1.02 SUBMITTALS

1. Shop Drawings: Dimensioned plans and sections or elevation layouts and single-line diagram of electricity-metering component assemblies specific to this Project.

1.03 QUALITY ASSURANCE

1. Electrical Components, Devices, and Accessories: Listed and labeled as defined in

NFPA 70, Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for intended use.

2. Devices for Utility Company Electricity Metering: Comply with utility company published standards.

3. Comply with NFPA 70.

1.04 COORDINATION

1. Coordinate chases, slots, inserts, sleeves, and openings for electrical supports, raceways, and cable with general construction work.

2. Sequence, coordinate, and integrate installing electrical materials and equipment for efficient flow of the Work. Coordinate installing large equipment that requires positioning before closing in the building.

3. Coordinate electrical service connections to components furnished by utility companies.

a. Coordinate installation and connection of exterior underground and overhead utilities and services, including provision for service entrances and electricity-metering components.

4. Coordinate location of access panels and doors for electrical items that are concealed by finished surfaces. Access doors and panels are specified in Division 8 Section "Access Doors and Frames."

5. Where electrical identification devices are applied to field-finished surfaces, coordinate installation of identification devices with completion of finished surface.

PART 2 – PRODUCTS

2.01 RACEWAYS

1. EMT: Electrical metallic tubing; ANSI C80.3, zinc-coated steel, with set-screw fittings.

Iron Creek and North Fork CG Water Systems Page 24 of 32

2. FMC: Flexible metal conduit; zinc-coated steel.

3. IMC: Intermediate metal conduit; ANSI C80.6, zinc-coated steel, with threaded fittings.

4. LFMC: Liquid tight flexible metal conduit; zinc-coated steel with sunlight-resistant and mineral-oil-resistant plastic jacket.

5. RMC: Rigid metal conduit; galvanized rigid steel; ANSI C80.1.

6. RNC: Rigid nonmetallic conduit; NEMA TC 2, Schedule 40 PVC, with NEMA TC3 fittings.

7. Raceway Fittings: Specifically designed for raceway type with which used.

2.02 WIRES, CABLES, AND CONNECTIONS

1. Conductors, No. 10 AWG and Smaller: Solid or stranded copper.

2. Conductors, Larger than No. 10 AWG: Stranded copper.

3. Insulation: Thermoplastic, rated 600 V, 75 deg C minimum, Type THW, THHN-

THWN, or USE depending on application..

4. Cable: Type MC or ACTH or NM-B and NMC-B with ground wire.

5. Wire Connectors and Splices: Units of size, ampacity rating, material, type, and class suitable for service indicated.

2.03 SUPPORTING DEVICES

1. Material: Cold-formed steel, with corrosion-resistant coating.

2. Metal Items for Use Outdoors or in Damp Locations: Hot-dip galvanized steel.

3. Slotted-Steel Channel: Flange edges turned toward web, and 9/16-inch- (14-mm-) diameter slotted holes at a maximum of 2 inches (50 mm) o.c., in webs. Strength rating to suit structural loading.

4. Nonmetallic Slotted Channel and Angle: Structural-grade, factory-formed, glass-fiber-resin channels and angles with 9/16-inch- (14-mm-) diameter holes at a maximum of 8 inches (203 mm) o.c., in at least one surface. Strength rating to suit structural loading.

5. Slotted Channel Fittings and Accessories: Recommended by the manufacturer for use with the type and size of channel with which used.

a. Materials: Same as channels and angles, except metal items may be stainless steel.

6. Raceway and Cable Supports: Manufactured clevis hangers, riser clamps, straps, threaded C-clamps with retainers, ceiling trapeze hangers, wall brackets, and spring-steel clamps or click-type hangers.

7. Pipe Sleeves: ASTM A 53, Type E, Grade A, Schedule 40, galvanized steel, plain ends.

8. Cable Supports for Vertical Conduit: Factory-fabricated assembly consisting of threaded body and insulating wedging plug for nonarmored electrical cables in riser conduits. Plugs have number and size of conductor gripping holes as required to suit individual risers. Body constructed of malleable-iron casting with hot-dip galvanized finish.

9. Expansion Anchors: Carbon-steel wedge or sleeve type.

10. Toggle Bolts: All-steel springhead type.

11. Powder-Driven Threaded Studs: Heat-treated steel.

2.04 ELECTRICAL IDENTIFICATION

Iron Creek and North Fork CG Water Systems Page 25 of 32

1. Identification Device Colors: Use those prescribed by ANSI A13.1, NFPA 70, and these Specifications.

2. Colored Adhesive Marking Tape for Raceways, Wires, and Cables: Self-adhesive vinyl tape, not less than 1 inch wide by 3 mils thick.

3. Tape Markers for Conductors: Vinyl or vinyl-cloth, self-adhesive, wraparound type with preprinted numbers and letters.

4. Color-Coding Cable Ties: Type 6/6 nylon, self-locking type. Colors to suit coding scheme.

5. Underground Warning Tape: Permanent, bright-colored, continuous-printed, vinyl tape compounded for permanent direct-burial service, and with the following features:

a. Not less than 6 inches wide by 4 mils thick.

b. Embedded continuous metallic strip or core.

c. Printed legend that indicates type of underground line.

6. Engraved-Plastic Labels, Signs, and Instruction Plates: Engraving stock, melamine plastic laminate punched or drilled for mechanical fasteners 1/16-inch minimum thickness for signs up to 20 sq. in. and 1/8-inch minimum thickness for larger sizes.

Engraved legend in black letters on white background.

7. Warning and Caution Signs: Preprinted; comply with 29 CFR 1910.145, Chapter XVII. Colors, legend, and size appropriate to each application.

a. Interior Units: Aluminum, baked-enamel-finish, punched or drilled for mechanical fasteners.

b. Exterior Units: Weather-resistant, nonfading, preprinted, cellulose-acetate butyrate with 0.0396-inch (1-mm), galvanized-steel backing. 1/4-inch (6-mm) grommets in corners for mounting.

8. Fasteners for Nameplates and Signs: Self-tapping, stainless-steel screws or No. 10/32 stainless-steel machine screws with nuts and flat and lock washers.

PART 3 – EXECUTION

3.01 ELECTRICAL EQUIPMENT INSTALLATION

1. Headroom Maintenance: If mounting heights or other location criteria are not indicated, arrange and install components and equipment to provide maximum possible headroom.

2. Materials and Components: Install level, plumb, and parallel and perpendicular to other building systems and components, unless otherwise indicated.

3. Equipment: Install to facilitate service, maintenance, and repair or replacement of components. Connect for ease of disconnecting, with minimum interference with other installations.

4. Right of Way: Give to raceways and piping systems installed at a required slope.

3.02 RACEWAY APPLICATION

1. Outdoor Installations:

a. Exposed: RNC.

b. Concealed: RNC.

c. Underground, Single Run: RNC.

Iron Creek and North Fork CG Water Systems Page 26 of 32

d. Underground, Grouped: RNC.

e. Connection to Vibrating Equipment: LFMC.

f. Boxes and Enclosures: NEMA 250, Type 3R or Type 4, unless otherwise indicated.

2. Indoor Installations:

a. Exposed: EMT except in wet or damp locations, use IMC.

b. Connection to Vibrating Equipment: FMC; except in wet or damp locations:

LFMC.

c. Boxes and Enclosures: NEMA 250, Type 1, unless otherwise indicated.

3.03 RACEWAY AND CABLE INSTALLATION

1. Keep legs of raceway bends in the same plane and keep straight legs of offsets parallel.

2. Use RMC elbows where RNC turns out of slab.

3. Install pull wires in empty raceways. Use No. 14 AWG zinc-coated steel or woven polypropylene or monofilament plastic line with not less than 200-lb (90-kg) tensile strength. Leave at least 12 inches (300 mm) of slack at each end of pull wires.

4. Connect motors and equipment subject to vibration, noise transmission, or movement with a maximum of 72-inches (1830-mm) flexible conduit. Install LFMC in wet or damp locations. Install separate ground conductor across flexible connections.

5. Set floor boxes level and trim after installation to fit flush to finished floor surface.

3.04 WIRING METHODS FOR POWER, LIGHTING, AND CONTROL CIRCUITS

1. Application: Use wiring methods specified below to the extent permitted by applicable codes as interpreted by authorities having jurisdiction.

2. Exposed Feeders: Insulated single conductors in raceway.

3. Exposed Branch Circuits: Insulated single conductors in raceway.

4. Underground Feeders and Branch Circuits: Insulated single conductors in nonmetalic raceway.

3.05 WIRING INSTALLATION

1. Make splices and taps that are compatible with conductor material and that possess equivalent or better mechanical strength and insulation ratings than unspliced conductors.

3.06 ELECTRICAL SUPPORTING DEVICE APPLICATION

1. Damp Locations and Outdoors: Hot-dip galvanized materials or nonmetallic, slotted channel system components.

2. Dry Locations: Steel materials.

3. Strength of Supports: Adequate to carry present and future loads, times a safety factor of at least four with, 200-lb (90-kg) minimum design load for each support element.

3.07 SUPPORT INSTALLATION

1. Support parallel runs of horizontal raceways together on trapeze- or bracket-type hangers.

2. Size supports for multiple raceway or cable runs so capacity can be increased by a

25 percent minimum in the future.

Iron Creek and North Fork CG Water Systems Page 27 of 32

3. Support individual horizontal single raceways with separate, malleable-iron pipe hangers or clamps.

4. Install sleeves for cable and raceway penetrations of concrete slabs and walls unless core-drilled holes are used. Install sleeves for cable and raceway penetrations of masonry and fire-rated gypsum walls and of all other fire-rated floor and wall assemblies. Install sleeves during erection of concrete and masonry walls.

5. Secure electrical items and their supports to building structure, using the following methods unless other fastening methods are indicated:

a. Wood: Wood screws or screw-type nails.

b. Gypsum Board: Toggle bolts. Seal around sleeves with joint compound, both sides of wall.

c. Masonry: Toggle bolts on hollow block and expansion bolts on solid block. Seal around sleeves with mortar, both sides of wall.

d. New Concrete: Concrete inserts with machine screws and bolts.

e. Existing Concrete: Expansion bolts or threaded studs driven by powder charge and provided with lock washers.

f. Light Steel Framing: Sheet metal screws.

g. Fasteners for Damp, Wet, or Weather-Exposed Locations: Stainless steel.

h. Light Steel: Sheet-metal screws.

6. Fasteners: Select so load applied to each fastener does not exceed 25 percent of its proof-test load.

3.08 IDENTIFICATION MATERIALS AND DEVICES

1. Install at locations for most convenient viewing without interference with operation and maintenance of equipment.

2. Coordinate names, abbreviations, colors, and other designations used for electrical identification with corresponding designations indicated in the Contract Documents or required by codes and standards. Use consistent designations throughout Project.

3. Self-Adhesive Identification Products: Clean surfaces before applying.

4. Tag and label circuits designated to be extended in the future. Identify source and circuit numbers in each cabinet, pull and junction box, and outlet box. Color-coding may be used for voltage and phase identification.

5. Install continuous underground plastic markers during trench backfilling, for exterior underground power, control, signal, and communication lines located directly above power and communication lines. Locate 6 to 8 inches (150 to 200 mm) below finished grade. If width of multiple lines installed in a common trench or concrete envelope does not exceed 16 inches (400 mm), overall, use a single line marker.

6. Install warning, caution, and instruction signs where required to comply with 29 CFR 1910.145, Chapter XVII, and where needed to ensure safe operation and maintenance of electrical systems and of items to which they connect.

This is the start of the file's text. The full file is on GovTribe.