F.Whitman_Final_Call_Order.pdf

PDF 167 KB Posted

Attached to
Tri-Forest Road Maintenance Federal contract opportunity
Solicitation number
1204M318Q0002
Issued by
Department of Agriculture Forest Service R6-Pacific Northwest Region

About this file

F. Whitman Call Order

View the file

Other files for this federal contract opportunity

Other files attached to Tri-Forest Road Maintenance, newest first.
File Type Posted
LIST_OF_AWARDEES_FOR_THE.docx DOCX document
Amendment1.docx DOCX document
M.FireSuppressionCommunicationR6630054.pdf PDF
A.Quoters_Package.pdf PDF
G.Whitman_Blading_Maps.pdf PDF
H.West_Chicken_Call_Order_CULVERT.pdf PDF
C.Umatilla_Brushing_Final_Call_Order.pdf PDF
D.Umatilla_Brushing_Maps.pdf PDF
K.FireProtectionandSuppressionr6_fS_6300_52.pdf PDF
B.FinalTriSolicitation.pdf PDF
L.FireSuppressiontanktruckR6630053.pdf PDF
I.West_Chicken_Specs.pdf PDF
E.Malheur_Final_Call_Order.pdf PDF
J.West_Chicken_Drawings.pdf PDF
Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CALL ORDER NO.

IF THIS ORDER IS GREATER THAN $2,500.00, IT IS

NOT VALID UNTIL SIGNED BY THE CONTRACTING OFFICER

Contract No. Project Name:

Whitman Blading FY

County: Baker, Grant

Contractor:

Issuing and Billing Office:

Wallowa-Whitman National Forest 1550 Dewey Ave, Suite A

Baker City, OR 97814

Item No.

Subitem No.

Description

Quantity to Date

Quantity Order

Unit

Amount

01 Base Items Roadway Surface Maintenance

57.3 Mile

02 Optional

Items Roadway Surface Maintenance

67.4 Mile

Required Delivery Date: All work shall be completed by November 30, 2018, base items shall be completed in the spring. Work is estimated to begin May 01, 2018.

Total Price:

Contractor: (Name and Signature)

Requested By: (Name and Signature)

COR Dan Story Fund Authorization: (Name and Signature)

Line Officer SEE IAS REQUISITION Ordered By: (Name and Signature)

Contracting Officer Order Date: Job Code:

Original to CO, CC to Contractor, B&F and COR

ITEM

Road Number Beginning and Ending Locations Miles Unit Price Amount

1a 1900-160 19 road to 1940 road 4 1b 1925 19 road to 1940 road 4.7 1c 1940 19 road to 1925 road 4.5 1d 1920 19 road to 19-280 road 2.7 1e 1920 1920-081 to 11 road 2.7 1f 1040 Hwy 7 to 19 road 7.9 1g 1040-060 1040 road to the 2620 road 1.9 1h 1040-020 1040 road to the cattleguard 0.5 1i 1035 Hwy 7 to Greenhorn 6.6 1j 19 Gene Hale road jct to 7380-280 road 6.6 1k 1960 19 road to the 1044 road 4.3 1l 11 Hwy 7 to the cattleguard near the 1170-071 road.

8.9

1m 7380 From 280 road to the 19 road 2.0 Total 57.3

Optional Bid Items below

2a 1940 1925 road to the Forest Boundary 4.0 2b 1920 1900-280 road to the 1920-081 road 2.8 2c 1170 11 road to the cattleguard in Sec 30 6.1 2d 1055 Hwy 7 to the cattleguard at the OHV crossing 5.8

2e 1075 Hwy 7 to the 1055 road 6.1 2f 1060 1055 road to the 7386 road 7.4 2g 1065 1060 road to the 7386 road at Blue Springs

Summit 7.8

2h 7386 Blue Springs Summit to the private property boundary in Sec 9

4.6

2i 7386 private property boundary in Sec 9 to the 1055-075 road

2.1

2j 7380 Blue Springs Summit to the 280 road 6.3 2k 19 7380-280 road to the 13 road 5.4 2l 1044 Greenhorn road to the 1044-120 road 4.9

Total 67.4

1. DESCRIPTION OF WORK:

This work consists of blading, shaping, and rolling approximately 57.3 miles of aggregate surfaced roads. There are also approximately 67.4 miles of OPTIONAL Road reshaping, and rolling of native surfaced roads.

Specific information is listed in the attached Road Listing.

SURFACE MAINTENANCE (Blading and Compaction)

Performance Requirements / Blading:

Performance requirements and standards listed in the parent contract will apply for Surface Maintenance with this call order. Performance requirements are listed on page 6 of the parent contract and performance standards are provided per attached specification 811 – SURFACE MAINTENANCE, provision 811.02.

Performance Requirements / Optional Road Reshaping:

This is a basic road reshaping for roads that need drainage reestablished (inslope, outslope or crown). It is preferred that natural moisture be utilized for these roads. These roads would also need rolled to help pin down the reshaping. If sections of pit run or where improved native material exist that would be damaged by reshaping these sections may be skipped over. If areas of base course rock or where sub-grade boulders are protruding from the road surface the work will consist of pulling material into the road surface from the ditch, cut bank and/or shoulder (if such material exists).

Performance Requirements / Water/Natural moisture:

It is preferred that natural moisture be utilized. If natural moisture is not sufficient then the watering requirement will be applicable.

Watering requirements are not provided with the parent contract and are as follows:

Water is required only to the full extent necessary to prevent segregation of the surfacing materials and to maximize the compaction potential of the surfacing materials as required under Performance Requirements/Compaction.

Contractor may elect to obtain water from sources other than those designated in the Water Source listing, and is responsible to obtain the right to use the water from all sources. Some water sources may not be adequate late in the season.

Draft hoses used to extract water shall be tightly fitted with screens having openings no larger than 3/32 inch.

Water shall be extracted from streams in such a manner that a flow, adequate for fish survival, is maintained at and below the point of extraction.

If a water source is found and not identified on the contract maps a verbal OK can be given from the COR to use the water source.

Performance Requirements / Compaction:

Compaction requirements are not provided with the parent contract and are as follows:

Adequate compaction is defined as that which is normally obtained by the use of a 7 – 9 metric ton vibratory roller operated over the full width two (2) times on material containing moisture sufficient to allow substantial compaction. Specific roads and road segments are listed in the Road Listing.

Measurement:

See attached specification 811.04.

Mobilization, logout, watering and compaction are considered incidental.

Payment:

The accepted quantities will be paid at the awarded bid price per unit of measurement as listed in the attached specification 811.05. All roads will be measured in Road Miles measured along the centerline of the road regardless of the number of lanes.

In summary, payment for blading and compaction will be based on the number of Road Miles adequately maintained, measured along the centerline to the nearest one-tenth (0.1) mile.

2. COMPLETION OF WORK:

Work is estimated to begin May 1, 2018 on the base items and shall be completed within 61 calendar days of the start date. Optional item (if awarded) shall be completed by Nov 30th, 2018.

3. SAFETY PLAN

A job specific safety plan shall be submitted at the pre-work conference addressing, at a minimum, the potentially hazardous working conditions cited in the parent contract.

4. ATTACHMENTS

The following attachments are incorporated into the call order.

TITLE PAGES

Specification 811 Surface Maintenance 2 Road Structure Details Drawing 1 Log Out drawing 1 Service Wage Determination WD 77-0079 (Rev.-54) 3 Vicinity Maps 5

5. Award Determination

The degree of importance of the price will increase with the degree of equality of the proposals in relation to the other factors on which selection is to be based, or when the price is so significantly high it will diminish the value of technical superiority to the Government.

Technical and past performance requested in the base BPA, when combined, is approximately equal when compared to price on this call order.

(b) Options. The Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. The Government may determine that an offer is unacceptable if the option prices are significantly unbalanced. Evaluation of options shall not obligate the Government to exercise the option(s).

(c) A written notice of award or acceptance of an offer, mailed or otherwise furnished to the successful offeror within the time for acceptance specified in the offer, shall result in a binding contract without further action by either party. Before the offer's specified expiration time, the Government may accept an offer (or part of an offer), whether or not there are negotiations after its receipt, unless a written notice of withdrawal is received before award.

52.217-5 Evaluation of Options (July 1990) Except when it is determined in accordance with FAR 17.206(b) not to be in the Government’s best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).

https://www.acquisition.gov/sites/default/files/current/far/html/Subpart%2017_2.html#wp1078150

811 – Surface Maintenance

811 SURFACE MAINTENANCE

811.01 Service Required

Smooth and shape native or aggregate surfaced roads including traveled way, shoulders, turnouts, and intersections. Reshape or recondition ditches, waterbars, and drain dips.

811.02 Performance Standards

A. Maintenance Level 2 through 5 Roads

A road surface is maintained to standard when the travel way is free of washboards, potholes, or other irregularities. The surface is smooth, compact, crowned or sloped to drain, without segregation of the surfacing materials.

Suitable materials have been recovered and incorporated. Unsuitable materials have been removed. Ditches and road surface drainage structures function efficiently. Unpaved shoulders are shaped to provide a smooth transition from the paved surface and drain efficiently.

B. All Roads

When ordered by the Contracting Officer to work in a weed infested area the contractor will be required to prevent spreading the infestation into un-infested areas by cleaning vehicles and equipment. The contractor will use wash stations approved by the Contracting Officer.

811.03 Location of Work

As specified on roads listed on the road listing, shown on the plans, marked on the ground, or as ordered by the Contracting Officer. Locations of weed-infested areas are marked on the ground. Do not operate in the weed-infested areas unless ordered to do so by the Contracting Officer.

811.04 Measurement

Measurement under this Section will be made by the total number of units for each item listed in the SCHEDULE OF ITEMS completed and accepted.

811 – Surface Maintenance

A. Single Lane Roads: Surface maintenance will be measured along the centerline of the roadway. Turnouts are incidental. Measurement will be to the nearest one-tenth (0.1) mile.

B. Double Lane Roads: Surface maintenance will be measured along the centerline of the roadway. Measurement will be to the nearest one-tenth (0.1) mile.

C. Road Mile: Work activity will be measured along the centerline of the road regardless of the number of lanes.

811.05 Payment

The accepted quantities will be paid at the contract price per unit of measurement for the Section 811 pay items listed in the schedule of items.

Payment will be full compensation for the work prescribed in this Section.

Mobilization and Log Out (Typical: LOGOUT) are incidental to pay item.

Pay Item Pay Unit

811(01) Surface Maintenance Level ALL roads Mile

811.06

Acceptable Quality Levels

Acceptance will be determined by visual inspection. If visual inspection finds that all work conforms to performance standards (811.02) the work will be acceptable.

If visual inspection finds that occasional work elements do not completely conform to performance standards but non-conforming work elements are not representative of an overall quality of work problem the work will be acceptable. If visual inspection finds that non-conforming work is representative of an overall quality of work problem, rework will be required.

Whitman Call Order
IF THIS ORDER IS GREATER THAN $2,500.00, IT IS
52.217-5 Evaluation of Options (July 1990)
Surface Maintenance Spec