Questions and Answers 1202SA22R9201 TYPE 1 HSS MATOC.pdf
PDF 155 KB Posted
- Solicitation number
- 1202SA22R9201
- Issued by
-
Department of Agriculture Forest Service
About this file
This document contains Questions and Answers related to Solicitation 1202SA22R9201 for Helicopter Support Services (HSS) - Type 1. The solicitation requires offerors to submit a letter of intent by August 11, 2022 and full proposals by September 12, 2022. The questions address clarification on the 24-month weight and balance requirement, which is based on the original solicitation proposal due date, and instructions on how to fill out the proposal submission forms. Offerors are advised that they may need to resubmit their entire proposal, even if no changes were made, to ensure the submission is correct. The solicitation is being issued by the Department of Agriculture Forest Service.
View the file
Other files
Show all 35
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1202SA22R9201 – Type I HSS MATOC solicita�on
Questions and Answers
No solicitation change is generated from these questions, they are for clarification only.
Q1: What date is the requirement for the 24 month W&B, is it from the solicitation date or original solicitation date?
A1: According to B.3(b)(1)(iii) - Weighing shall be: Accomplished within 24 months prior to the due date of proposal submission, and for aircraft on the companies operating certificate that are currently operating outside of the US, the current operating weight and balance will be submitted. These aircraft will be required to be weighed no later than the initial contract inspection.
That 24 Months goes by original solicitation proposal due date of September 12, 2022.
Q2: How come I cannot fill in the line items tab on the PWB?
A2: You are to fill in the offered aircraft tab. The line item locations will be solicitated after base MATOC award via the TORP process for those exclusive use line items.
Q3: Do we need to resubmit our entire proposal, even if we did not change anything?
A3: It is suggested that it be done to ensure that the submission is correct and has updated anything that may have changed during the time we were unable to proceed with evaluations during the protest period.