Clarification Items – RFQ 12010920Q0065

1. Government Furnished supplies – any additional amounts needed for completion of the project are to be provided by the contractor.

2. Page 3 of RFQ in Supplies/Services(B) column –

• Delivery: 06/25/2020 should read Delivery: 09/30/2020 as this refers to completion of the project and the period of performance end date.

3. Bid Bond – form SF24-16D is required at time quotes are due.

4. Performance/Payment Bonds – form SF25-16A/B are required from the successful quoter 10 days after award.