This Request for Qualifications (RFQ) is issued by the California Department of Transportation (Caltrans) for Construction Manager/General Contractor (CMGC) services on the I-5/I-805 Express Lanes Corridor Project located in San Diego County. The project involves modernizing existing High-Occupancy Vehicle (HOV) lanes to High-Occupancy Toll (HOT) lanes, referred to as Express Lanes, spanning over 40 miles across Interstate 805 from East Palomar Street to the Junction I-5/I-805 Separation and Interstate 5 from the Junction 5/805 Separation to Harbor Drive, encompassing portions of San Diego, Chula Vista, National City, Del Mar, Solana Beach, Encinitas, Carlsbad, and Oceanside. The procurement follows a single-phase process requiring submission of a Statement of Qualifications (SOQ) with the electronic and hard copy due by 3 p.m. Pacific Time on January 11, 2027, to the Division of Design in Sacramento. The Department anticipates short-listing proposers for in-person interviews scheduled for February 17, 2027, with final rankings announced by February 25, 2027, and award of the Preconstruction Services Contract anticipated by March 18, 2027, with notice to proceed by April 9, 2027. The contract will consist of two parts: a Preconstruction Services Contract for design phase support with a not-to-exceed fee of $2,500,000 at four percent with three percent escalation, and a potential Construction Contract for the construction phase if an Agreed Price is reached, with anticipated construction completion by May 2, 2031.

The estimated project cost is $386,000,000 for construction capital and $1,000,000 for right-of-way capital in 2026 dollars. The Preconstruction Services Contract is a reimbursement contract at specific rates, while the Construction Contract will be a unit price contract. Proposers must demonstrate financial capacity through surety bonding for performance and payment bonds equal to 100 percent and 50 percent of the agreed price, respectively, and provide evidence of commercial general liability, auto liability, workers' compensation/employers liability, and pollution liability insurance. The project is federally funded and subject to Buy America, Build America Buy America Act (BABA), Davis-Bacon wage requirements, and Disadvantaged Business Enterprise (DBE) goals, with proposers required to demonstrate commitment to DBE provisions. State prevailing wages apply to the Preconstruction Services Contract, with federal prevailing wages also applying for federal-aid contracts. No incumbent contractor information is provided. Key evaluation criteria include proposer and major participant experience and past performance, key personnel qualifications, project understanding and approach, legal structure, financial capacity, and safety program, with interviews contributing to final scoring and selection.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATE OF CALIFORNIA

DEPARTMENT OF TRANSPORTATION

REQUEST FOR QUALIFICATIONS

I-5/I-805 EXPRESS LANES CORRIDOR PROJECT

CONSTRUCTION MANAGER/GENERAL

CONTRACTOR SERVICES

FOR DESIGN AND CONSTRUCTION ON STATE HIGHWAY IN

THE COUNTY OF SAN DIEGO

On I-805 from East Palomar Street to Junction 5/805 Separation

On I-5 from Junction 5/805 to Harbor Drive

CONTRACT NO. 112T37CM

11-SD-805-PM 4.4 to 23.9

11-SD-5- PM 30.6 to 54.6

Project ID 1124000106

Dated: 11/06/2026

TABLE OF CONTENTS

1 INTRODUCTION AND GENERAL INSTRUCTIONS

1.1 Abbreviations

1.2 Definitions

1.3 Data Room: RFQ and Addenda

1.4 Project Opportunity

1.4.1 Project Description

1.4.2 Project Goals

1.4.3 Project Authorization

1.5 Construction Manager Responsibilities and Project Status

1.6 Federal Requirements

1.7 Procurement Process

1.7.1 Single-Phase Procurement

1.7.2 Contract Types

1.7.3 Clarification Questions

1.7.4 Communications Between the Department and Proposers

1.7.5 Rules of Contact

1.8 Precontractual Expenses

1.9 Conflict of Interest

1.10 Department Consultants

1.11 Proposer Requirements

1.11.1 Minimum Requirements

1.11.2 Non-Disclosure Requirement

1.11.3 Organizational and Personnel Changes

1.12 Equal Employment Opportunity and Nondiscrimination

1.13 Disadvantaged Business Enterprise Goal

1.14 Labor Policies

1.15 Insurance and Bonds

1.15.1 Bond Requirements

1.15.2 Insurance Requirements

1.16 Work Performed Prior to NEPA Approval

2 PROCUREMENT SCHEDULE

Department of Transportation I-5/I-805 Express Lanes Corridor Project Request for Qualifications Contract No.: 112T37CM

Project ID: 1124000106

Table of Contents

3 CONTENT OF STATEMENT OF QUALIFICATIONS

3.1 Proposer’s Transmittal Letter

3.2 Legal Structure

3.2.1 Minimum Requirement for Legal Structure

3.3 Financial Capacity

3.3.1 Minimum Requirement for Financial Capacity

3.4 Safety Program

3.4.1 Minimum Requirement for Safety Program

3.5 Proposer and Each Major Participant Experience and Past Performance

3.5.1 Proposer and Each Major Participant Experience and Past Performance Evaluation Criteria

3.6 Proposer’s Key Personnel

3.6.1 Key Personnel

3.7 Project Understanding and Approach

3.7.1 Project Understanding and Approach Evaluation Criteria

4 SOQ SUBMITTAL REQUIREMENTS

4.1 General Requirements

4.2 Quantities, Due Date, Time, and Location

4.3 Format Requirements

4.4 Preconstruction Services Cost Proposal

4.5 Challenges

5 EVALUATION PROCESS

5.1 SOQ Evaluation

5.2 Evaluation Objective

5.3 SOQ Evaluation Factors

5.3.1 Initial Responsiveness Review

5.3.2 Non-Scored SOQ Categories

5.3.3 Scored SOQ Categories

5.3.4 Scored Interview

5.4 Evaluation and Scoring Process

5.5 Notification of Rankings

6 PROTEST PROCEDURES AND PUBLIC RECORDS ACT

6.1 Protest Procedures

Department of Transportation I-5/I-805 Express Lanes Corridor Project Request for Qualifications Contract No.: 112T37CM

Table of Contents

6.1.1 Protests Regarding RFQ Documents

6.1.2 Protests Regarding Final Rankings Decision

6.2 Public Records Act

7 DEBRIEFING MEETINGS

8 DEPARTMENT RESERVED RIGHTS

8.1 Department Disclaimers

APPENDIX

Appendix A: Project Description, Project Status, and Construction Manager Responsibilities

Appendix B: Format and Organization of Statement of Qualifications

Appendix C: Forms

Appendix D: Disclosure of Potential Conflict of Interest Certification

Appendix E: Prequalification Questionnaire

Appendix F: Criteria Weighting

Department of Transportation I-5/I-805 Express Lanes Corridor Project Request for Qualifications Contract No.: 112T37CM

Introduction and General Instructions 1

1 INTRODUCTION AND GENERAL INSTRUCTIONS

Pursuant to Public Contract Code §6700 et seq., the California Legislature has authorized the Department of Transportation (Department) to engage in a construction manager/general contractor (CMGC) project delivery method as specified for projects for the construction of highways, bridges, or tunnels.

Proposers interested in providing CMGC services, herein referred to as Construction Manager, will partner with the Department’s design team on this Project. As part of the Project team, the selected Construction Manager may provide input on schedule, phasing, constructability, cost and estimates, value engineering, and plan review throughout the design process. In addition to aiding the design process, the selected Construction Manager will be asked to prepare and submit a proposed price for the labor, equipment, and materials that will be required to construct the Project based on the design process, plans, specifications, and estimate packages after the Office Engineer review of the Project. If the proposed price is accepted by the Department, a Construction Contract will be issued to the Construction Manager after the completion of the preconstruction phase so that construction of the Project can begin. If the proposed price is not accepted by the Department, the Department, in its sole discretion, reserves the right to end the Construction Manager’s participation in the project development process at the completion of the design phase and advertise the Project. Although the selected Construction Manager will be contracted for both the design and construction services of this Project through this selection process, the selected Construction Manager is not guaranteed to receive a Construction Contract to perform the construction if services are terminated at the completion of the design phase.

The CMGC process for the Project will consist of the following: Request for Qualifications (RFQ) for preconstruction services, submittal of a Statement of Qualifications (SOQ), evaluation of submittals, in person interviews with short-listed Proposers selection of the Construction Manager, and award and execution of contract for the performance of preconstruction services. Upon the completion of the design phase of the Project or any portion thereof, the Department will begin the price proposal process to determine the price for the construction phase of the Project with the Construction Manager.

The Department hereby requests SOQs from qualified Proposers interested in entering a contract for preconstruction services, with the potential for continuing to a second contract for construction of all or part of the Work, for the I-5/I-805 Express Lanes Corridor (Project).

The Project, further defined in Appendix A, is intended to improve mobility, travel time reliability, throughput, and operational efficiency along the I-5 and I-805 corridors. The projects will modernize the existing High-Occupancy Vehicle (HOV) lanes to High- Occupancy Toll (HOT) lanes, referred to herein as Express Lanes. This project will also close critical gaps in the managed lane network and extend the system to provide greater continuity and connectivity.

1.1 Abbreviations

Department of Transportation I-5/I-805 Express Lanes Corridor Project Request for Qualifications Contract No.: 112T37CM

Introduction and General Instructions 2

The following abbreviations are used in this document and are defined as shown below:

CEQA California Environmental Quality Act

CMGC Construction Manager/General Contractor

DAR Direct Access Ramp

DBE Disadvantaged Business Enterprise

FHWA Federal Highway Administration

ITS Intelligent Transportation Systems

NEPA National Environmental Policy Act

RFQ Request for Qualifications

SANDAG San Diego Association of Governments

SOQ Statement of Qualifications

TSI Toll System Integrator

1.2 Definitions

The following terms are used in this document and are defined as shown below:

Term Definition

Addenda/Addendum Supplemental additions, deletions, and modifications to the provisions of the RFQ issued after the release of the RFQ.

Affiliate Includes parent companies, subsidiary companies and partners (in the reporting entity), and other financially liable parties for that entity. Affiliate is further defined as any one of the following:

a) Any firm other than Proposer which owns 25 percent or more of Proposer, such as parent companies or holding companies.

b) A subsidiary or a firm in which Proposer owns 25 percent or more.

c) A firm in which a major stockholder or owner of Proposer owns controlling interest.

d) A firm with which Proposer has or has had an unseverable business or professional identity.

e) Any permanent or temporary common business enterprise relationship in which the parties share operating responsibility and profits such as joint ventures.

Agreed Price The compensation payable to the CMGC Contractor in performance of the construction of the Project, or portions of the Project, as specified in the Construction Contract documents.

Business Day(s) Day that the Department is officially open for business.

Department of Transportation I-5/I-805 Express Lanes Corridor Project Request for Qualifications Contract No.: 112T37CM

Introduction and General Instructions 3

Term Definition

Calendar Day(s) Every day shown on the calendar, beginning and ending at midnight.

CMGC Contractor Entity that performs as the Construction Manager during the design phase and as the general contractor during the construction phase if an Agreed Price is reached and a Construction Contract is issued.

CMGC Program The State’s construction manager/general contractor program codified in California Public Contract Code § 6700 et seq.

Construction Contract

The written agreement between the Department and the Construction Manager setting forth the obligations of the parties with respect to the construction of the Project, including the performance of the Work, the furnishing of labor and materials, and the basis of payment.

Construction Manager

A partnership, corporation, or other legal entity that is able to provide appropriately licensed contracting and engineering services as needed pursuant to a Construction Manager/General Contractor method contract.

Construction Manager/General Contractor

A project delivery method where a Construction Manager is procured to provide preconstruction services during the design phase of the Project and construction services during the construction phase of the Project. The execution of the design and the construction of the Project may be in sequential phases or concurrent phases.

Data Room The Department has established an electronic data room (Data Room) for the distribution of RFQ documents and Addenda to Proposers.

Department California Department of Transportation

Designated Contact The Department’s sole contact person and addressee for receiving all communications about the Project during the RFQ procurement process.

Evaluation Team Committees that review and assess individual SOQs using the criteria set forth in this RFQ.

Good Faith Efforts All necessary and reasonable steps to achieve a DBE goal or other requirements which could reasonably be expected to obtain sufficient DBE participation, even if they were not fully successful.

Key Personnel Proposer identified qualified personnel for key positions with demonstrated experience and expertise and a record of producing quality work on projects of a similar nature to the Project. The key positions as determined by the Department are identified in Section 3.6.1.

Department of Transportation I-5/I-805 Express Lanes Corridor Project Request for Qualifications Contract No.: 112T37CM

Introduction and General Instructions 4

Major Participant(s) Each of the following entities on the Proposer’s team:

a) All partners or joint venture members.

b) All individuals, persons, proprietorships, partnerships, limited liability partnerships, corporations, professional corporations, limited liability companies, business associations, or other legal entity however organized, holding (directly or indirectly) a 15 percent or greater equity interest in the Proposer.

All Major Participants shall be jointly and severally liable to the Department for performance under the Preconstruction Services Contract. Any entity on the Proposer’s team which is not jointly and severally liable to the Department for performance under the Preconstruction Services Contract, does not constitute a Major Participant.

Preconstruction Services Contract

The written agreement between the Department and the Construction Manager setting forth the obligations of the parties with respect to the performance of certain services during the design phase, including scheduling, pricing, and phasing to assist the Department to design a more constructible Project.

Preconstruction Services Cost Proposal

The rates proposed by Construction Manager for performance of preconstruction services as indicated on Form H.

Project I-5/I-805 Express Lanes Corridor Project as described in Appendix A.

Proposer The entity, comprised of an individual, person, proprietorship, firm, partnership, professional corporation, business association, corporation, joint venture, combination thereof, or other legal entity however organized, participating in the procurement process for the Project and that, if successful, will enter into the Preconstruction Services Contract with the Department to provide CMGC services for the Project. All member entities making up the Proposer shall be jointly and severally liable to the Department for performance under the Preconstruction Services Contract. Proposer includes any Major Participant thereof but does not include other entities which do not fall within the definition of Major Participant.

Proposer Representative

The contact person identified in the Statement of Qualifications submitted in response to the RFQ.

Department of Transportation I-5/I-805 Express Lanes Corridor Project Request for Qualifications Contract No.: 112T37CM

Introduction and General Instructions 5

Request for Qualifications

The written solicitation issued by the Department to solicit Statements of Qualifications to provide CMGC services to the Department for the Project.

Right of Way The real property (which term is inclusive of all estates and interests in real property, as well as licenses and permits authorizing occupancy) that is necessary for ownership and operation of the Project.

State The State of California acting through its elected officials and their authorized representative, or the State of California in the geographic sense, depending on the context.

Statement of Qualifications

The information prepared and submitted by a Proposer in response to this RFQ.

Subconsultants, Subcontractors

Any person with whom Construction Manager has entered into any subcontract and any other person with whom any Subcontractor or Subconsultant has further subcontracted any part of the Work, at any tier.

Toll System Integrator (TSI)

An independent contractor contracted by SANDAG to design and install the new toll collection system.

Work The furnishing of labor, materials, equipment, and other incidentals necessary to, or convenient for the successful completion of, the CMGC services for the Project and the carrying out of the duties and obligations imposed by the Preconstruction Services Contract.

1.3 Data Room: RFQ and Addenda

The Department has established an electronic data room (Data Room) for the distribution of RFQ documents and Addenda and the posting of other documents in the Department’s discretion at the Cal eProcure Web site address: https://caleprocure.ca.gov. Access to the Data Room will be permitted on approximately the date set out in Section 2.

The Department may add, delete, or amend documents in the Data Room at any time.

Each Proposer is solely responsible to ensure that it has the appropriate software to view and download the materials from the Data Room. Registration to the Web site will enable Proposer to receive notifications of any updates or new documents uploaded to the Data Room; however, each Proposer is solely responsible for checking the Data Room frequently for the addition, deletion, or amendment of the materials in the Data Room.

Proposers are responsible for monitoring the Web site identified above for information concerning this procurement as Proposers responding to this RFQ shall acknowledge in the Transmittal Letter (Appendix C, Form A) that they have reviewed all materials posted thereon.

Department of Transportation I-5/I-805 Express Lanes Corridor Project Request for Qualifications Contract No.: 112T37CM

Introduction and General Instructions 6

1.4 Project Opportunity

1.4.1 Project Description

The Project is located in San Diego County on Interstate 805 in the Cities of San Diego, Chula Vista, and National City from East Palomar Street to the Junction I-5/I-805 Separation and on I-5 in the Cities of San Diego, Del Mar, Solana Beach, Encinitas, Carlsbad, and Oceanside from the Junction 5/805 Separation to Harbor Drive.

The Project is a set of defined work packages that will modernize existing roadway infrastructure along the I-5 and I-805 corridors to create over 40 miles of continuous Express Lanes. The work packages will construct the necessary pavement striping, signage, traffic safety elements, paving, and electrical items in coordination with SANDAG’s TSI contract. A more detailed description of the Project is contained in Appendix A.

The estimated cost of this CMGC Project (in 2026 US dollars) is $386,000,000 for construction capital and $1,000,000 for Right of Way capital (including utility relocation).

1.4.2 Project Goals

The Department’s goals for the Project are:

a) Safety: No lost time injuries for the Department and CMGC Contractor employees, and no accidents involving the public during construction of Project.

b) Mobility: Minimize planned impacts to the traveling public, businesses and emergency services; no unplanned events that adversely affect the public;

maintain access to all modes of transportation; and maintain proper signs and delineation during construction.

c) Quality: Deliver a completed facility using high quality materials and workmanship.

d) Public Interaction: Minimize impacts to quality of life such as dust, noise, road closures and elimination of parking, and always provide accurate and advance information to the public.

e) Environmental Compliance: Meet or exceed all environmental commitments and permits.

f) Project Delivery: Complete the Project from design through construction with all lanes to open traffic without further impacts to the traveling public by May 2031.

g) Innovation: Use the expertise of the Project team to continually evaluate the design and construction methods to reduce costs, shorten schedule, and deliver a quality Project.

h) Local Requirements: Work with Project team to incorporate and meet local and city requirements.

1.4.3 Project Authorization

The Department is using the CMGC project delivery method contemplated under the authority established in Public Contract Code §6700 et seq.

1.5 Construction Manager Responsibilities and Project Status

Department of Transportation I-5/I-805 Express Lanes Corridor Project Request for Qualifications Contract No.: 112T37CM

Introduction and General Instructions 7

See Appendix A for general descriptions of the Project, the Construction Manager’s responsibilities, and current Project status. These general descriptions are currently under further development by the Department and could be changed, modified, reduced, or expanded with the release of subsequent Addenda.

1.6 Federal Requirements

Proposers are advised that the RFQ is being released based on the assumption that the Project and the Department’s plan of finance for the Project will remain eligible for Federal-aid funds. Consequently, the procurement documents and any agreements thereunder shall conform to requirements of applicable federal law, regulations, and policies. These include, but are not limited to, Equal Employment Opportunity (Title VI of the Civil Rights Act of 1964, as amended), Disadvantaged Business Enterprises (Title 49 Code of Federal Regulations Part 26, as amended), Small Business requirements (United States Code § 631 et seq.), Buy America requirements, including 23 U.S.C. § 313 and 23 CFR § 635.410, and the Build America, Buy America Act (BABA), enacted as part of the Infrastructure Investment and Jobs Act (Public Law 117-58), including applicable requirements under 2 CFR Parts 184 and 200, as amended, and Davis-Bacon wage rates. Details as to the extent and applicability of federal requirements to the entire Project will be set forth in this RFQ. The Department reserves the right to modify the procurement process described in this RFQ to address any concerns, conditions, or requirements of federal agencies, including the FHWA. Since this is a Federal-aid contract, FHWA Form 1273 will apply and shall be physically incorporated into each resultant Construction Contract, subcontract, and lower-tier subcontracts.

1.7 Procurement Process

1.7.1 Single-Phase Procurement

The Department will use a single-phase procurement process to select a CMGC Contractor to deliver the Project. The RFQ is issued to solicit information, in the form of a SOQ and Proposer interviews that the Department will evaluate to determine which Proposers are qualified to successfully deliver the Project in a two-part contract:

1. Part one: A “Preconstruction Services Contract” which includes consulting services to assist with the design of the Project.

2. Part two: A “Construction Contract” to build the Project, if an Agreed Price is reached.

1.7.2 Contract Types

The Preconstruction Services Contract will be a reimbursement contract at specific rates not to exceed $2,500,000. As shown in Appendix C, Form H, the Preconstruction Services Contract fee is set at four (4) percent and the Preconstruction Services Contract escalation is set at three (3) percent. The Construction Contract will be a unit price contract.

Department of Transportation I-5/I-805 Express Lanes Corridor Project Request for Qualifications Contract No.: 112T37CM

Introduction and General Instructions 8

1.7.3 Clarification Questions

Proposers may submit written clarification questions to the Department at any time before 3 p.m. Pacific Time (PT) on the last day for clarification questions listed in Section 2.

Written clarification questions from Proposers may be presented to the Department by submitting them to the Department’s Designated Contact. The Department will provide responses to Proposer written clarification questions within a reasonable time following receipt, subject to the cut off dates set forth in Section 2. The Department will post responses to those inquiries that the Department deems to be material and that are not adequately addressed in previously provided documents on Cal eProcure.

1.7.3.1 Responses and Confidential Information

1.7.4 The Department may, in its sole discretion, respond to all, some, or none of the questions submitted under this Section 1.7.3. Any responses to questions submitted under this Section 1.7.3 will be in writing and the Department will make available these responses electronically to all Proposers, except that the Department may in its discretion respond individually to those questions identified by a Proposer or deemed by the Department as containing confidential or proprietary information. The Department reserves the right to disagree with a Proposer’s characterization of the confidentiality of any information it may provide.

The Department may rephrase or consolidate questions as it deems appropriate.Communications Between the Department and Proposers

1.7.4.1 Designated Contact

The Department’s Designated Contact will serve as the primary point of contact during the RFQ procurement phase of the Project. As the Department point of contact, the Designated Contact is the Department’s sole contact person and addressee for receiving all communications about the Project during the RFQ procurement process, and Proposers are prohibited from contacting any Department employee, or any of the groups listed in Section 1.10, regarding the Project or this RFQ. Address any and all inquiries and comments regarding the Project by e-mail or letter. Only written inquiries will be accepted:

California Department of Transportation Division of Procurements and Contracts

1727 30th Street Sacramento, California 95816-7006

Attention: Alma Cortez, Contract Analyst e-mail: alma.cortez@dot.ca.gov

1.7.5 Rules of Contact

Proposers are required to conduct the preparation of their SOQs with professional integrity and free of lobbying activities. Proposers and their respective agents and consultants are not permitted to contact, directly or indirectly, any member of the Evaluation Team, or officers, administrators, staff or consultants of the Department regarding the subject matter of this RFQ after the issuance date of this RFQ, except as specifically permitted hereby or approved in advance by the Department. Any verified

Department of Transportation I-5/I-805 Express Lanes Corridor Project Request for Qualifications Contract No.: 112T37CM

Introduction and General Instructions 9 allegation that a responding Proposer team or team member or an agent or consultant of the foregoing has made such contact or attempted to influence the evaluation, ranking, and/or selection of Proposers may be cause for the Department to disqualify the Proposer team from submitting a SOQ, to disqualify the team member from participating in a Proposer team and/or to discontinue any further consideration of such Proposer team.

Except for communications expressly permitted by this RFQ, the Designated Contact, or a representative hereafter designated in writing by the Department, is the Department’s single contact and source of information for this procurement. The rules of contact set forth in this Section 1.7.5 shall apply during the Project procurement process. The procurement process begins on the date of issuance of this RFQ and is anticipated to be completed with the award of the Preconstruction Services Contract. These rules are designed to promote a fair and unbiased procurement process. Contact includes face-to-face, telephone, electronic-mail (e-mail), or formal written communication.

The specific rules of contact are as follows:

a) Unless otherwise specifically noted in this RFQ or authorized by the Designated Contact, all Proposer communication with the Department will be between the Proposer Representative and the Designated Contact. All such communication shall be in writing (by mail or e-mail).

b) Under normal circumstances, the Designated Contact will contact a Proposer in writing through the Proposer Representative.

c) Commencing with the Department’s release of this RFQ and continuing until the earliest of (i) execution and delivery of the Preconstruction Services Contract, (ii) the Department’s rejection of all SOQs, or (iii) cancellation of the Project procurement, neither a Proposer nor its agents may have ex parte communications with State officials, the Department employees, members of the Evaluation Team or any other person who will evaluate SOQs, California Transportation Commission, Federal Highway Administration, U.S. Department of Transportation, or any person identified in RFQ Section 1.10, regarding the Project, except for communications expressly permitted in this RFQ or through the process identified above. The foregoing restriction shall not preclude or restrict communications regarding matters unrelated to the Project or from participating in public meetings or any public or Department workshops related to the Project. The Department may, in its sole discretion, disqualify any Proposer engaging in such prohibited communications.

d) Any contact by a Proposer determined to be improper may result in disqualification of the Proposer.

e) The Department will disseminate written communications regarding the Project from the Department on Department letterhead. The Designated Contact will sign such communications. Alternatively, the Designated Contact may communicate via e-mail originating from the Department’s server or post information on https://caleprocure.ca.gov.

f) The Department will not be responsible for or bound by (i) any oral communication, or (ii) any other information or contact that occurs outside the official

Department of Transportation I-5/I-805 Express Lanes Corridor Project Request for Qualifications Contract No.: 112T37CM

Introduction and General Instructions 10 communication process specified herein, unless confirmed in writing by the Designated Contact.

g) If Proposer has meetings or discussions with agencies or entities other than the Department during the procurement phase, Proposer shall be responsible for verifying with the Department’s Designated Contact any Project-related information it so receives.

1.8 Precontractual Expenses

Proposers are solely responsible for all costs and expenses of any nature associated with responding to this RFQ, including attending briefing(s) and providing supplemental information.

1.9 Conflict of Interest

The Department has developed a conflict of interest policy for the CMGC Program. The Proposer, Major Participant, other Subconsultants and Subcontractors, and employees of such entities shall conform to federal and State conflict of interest rules and regulations.

The following entities and individuals are precluded from submitting a SOQ and from participating in the Preconstruction Service Contract for the Project:

a) A Proposer, Major Participant or other Subconsultant or Subcontractor, that has done any of the following:

i. Consulted to the Department in the development of the CMGC Program.

ii. Managed or assisted in the management of this Project.

iii. Conducted preliminary design services for this Project.

iv. Performed design Work related to this Project for the Department or other stakeholders.

v. Performed work on a previous contract that specifically excludes them from participating as a bidder, Proposer, or joining a CMGC team.

vi. Contracted with any other entity or stakeholder to perform oversight on this Project after award.

vii. Obtained any advice from, or discussed any aspect relating to this Project or award of this Preconstruction Services Contract with, any person or entity with an organizational conflict of interest, including a consultant of any entity who has provided technical support to the Department on this Project or the CMGC Program.

b) Any entity that is a parent, Affiliate, or subsidiary of any of the foregoing entities, or that is under common ownership, control or management with any of the foregoing entities.

c) An employee or former employee of any of the foregoing entities who was involved with this Project while serving as an employee of such entity.

The California Board for Professional Engineers and Land Surveyors has established conflict of interest rules applicable to those professionals licensed by the Board (Board Rules 475 and 476).

Department of Transportation I-5/I-805 Express Lanes Corridor Project Request for Qualifications Contract No.: 112T37CM

Introduction and General Instructions 11

The Proposer shall complete the Disclosure of Potential Conflict of Interest Certification included as Appendix D in this RFQ for each Major Participant, or other Subconsultant or Subcontractor, and include it as part of the SOQ submittal. If the Proposer determines a potential conflict of interest exists for itself or a Major Participant, or other Subconsultant or Subcontractor, or an employee, the Proposer shall disclose the relevant facts relating to the potential conflict, including the Work performed or to be performed by the entity associated with the potential conflict, and propose measures to avoid, neutralize, or mitigate the potential conflict. The Department will review the Disclosure of Potential Conflict of Interest Certification and the proposed mitigation measures to determine if the Proposer may submit a SOQ or be awarded the Preconstruction Services Contract.

Disclosure of a potential conflict of interest will not necessarily disqualify a Proposer.

If an organizational conflict of interest is identified after award of the Preconstruction Services Contract, the Proposer shall make an immediate and full written disclosure to the Department that includes a description of the action that the Proposer has taken or proposes to take to avoid or mitigate the potential conflict.

The Proposer, Major Participant, other Subconsultants or Subcontractors, and employees of such entities who provide design services for this Project are prohibited from competing or participating in an agreement to provide construction engineering and inspection services for this Project. Subconsultants for surveying and materials testing may provide construction services for other Proposers.

Determination of whether a conflict of interest exists, resulting in an unfair competitive advantage and the resolution of a potential or actual conflict of interest are at the sole discretion of the Department. The Department reserves the right to cancel or amend the resulting Preconstruction Services Contract if the successful Proposer failed to disclose a potential conflict which it knew or should have known about, or if the Proposer provided information on the Disclosure of Potential Conflict of Interest Certification that is false or misleading.

If a Proposer requests to use any Department consultants listed in Section 1.10 as participant(s) on the Proposer’s team, the Proposer must provide a written legal opinion from a licensed California attorney advising of whether any actual or potential conflict(s) of interest exist with respect to the consultant’s potential participation on this Project. The legal opinion should address whether any actual or potential conflict(s) of interest, exist pursuant to any applicable State or Federal authorities, including without limitation, California Government Code section 1090 et seq. Additionally, the legal opinion must include, without limitation, the following information:

a) Disclose all of the work performed in relation to the CMGC Program and/or the Project.

b) Provide all records of such work performed for the Department so that all information can be evaluated and made available to all potential CMGC Proposers, if necessary.

c) Provide a list of all Project documents the consultant had access to in connection with their participation on this Project. The Department may request these documents for review, evaluation, and/or dissemination.

Department of Transportation I-5/I-805 Express Lanes Corridor Project Request for Qualifications Contract No.: 112T37CM

Introduction and General Instructions 12

The above information must be provided by email to the Department’s Designated Contact by 12 p.m. seven (7) business days prior to the Final Date for Receipt of Proposers’ Questions specified in Section 2. Submittal of this information in a form other than email will not be accepted.

Upon review of the information provided above, the Department will determine if, in the Department’s opinion, the consultant may participate in the Project’s procurement. As between the proposers and the Department, the Department will have sole discretion as to this determination.

1.10 Department Consultants

The Department has engaged several consultants to assist and participate in the project development stages and/or assist the Department during the procurement process for the Project. These consultant firms are prohibited from participating in any of the Proposer organizations relating to this Project; providing technical, legal, or financial advice to Proposers; or directly discussing any aspect of the RFQ with any Proposer. The consultant firms prohibited from participating include, but are not limited to, the following:

a) Kimley Horn and Associates, Inc.

b) CDM Smith, Inc.

c) Silicon Transportation Consultants, LLC

d) Parsons Corporation

e) West Coast Civil, Inc.

f) Lewis Jones, Inc.

1.11 Proposer Requirements

Only the most highly qualified Proposers that have demonstrated the capability to complete this Project in its entirety will be eligible for short-listing. The number of Proposers that will be short-listed is at the Department’s sole discretion.

1.11.1 Minimum Requirements

The Proposer shall submit a completed and verified CMGC Prequalification Questionnaire, Appendix E. Instructions for completing the CMGC Prequalification Questionnaire are included in Appendix E. The Proposer shall also meet all SOQ responsiveness requirements as set forth in Section 5.3.1 and meet the minimum passing criteria for legal, financial, and safety requirements as set forth in Section 5.3.2 for non-scored elements of the SOQ.

1.11.2 Non-Disclosure Requirement

The Proposer may be given access to records, which are confidential under State laws, solely for the purpose of performing the required services under the Preconstruction Services Contract. The Proposer shall be required to sign a non-disclosure statement prior to its receipt of such documents obligating each employee, agent, or Subcontractor of the Proposer not to make inappropriate use of or improperly disclose any of the contents of such documents.

Department of Transportation I-5/I-805 Express Lanes Corridor Project Request for Qualifications Contract No.: 112T37CM

Introduction and General Instructions 13

1.11.3 Organizational and Personnel Changes

For the duration of the procurement process, there shall be no change in Proposers’ Major Participant(s), Subcontractor(s), Subconsultant(s), or Key Personnel, as identified in the SOQ, without prior written approval by the Department. To qualify for Department approval of a proposed personnel substitution, Proposers shall immediately submit a written personnel substitution request to the Department’s Designated Contract, which explains the reason(s) for proposed substitution and demonstrates that the proposed replacement will be equal to or better than the personnel identified in the SOQ that is intended to be replaced. The Department may provide written approval of a request if, in the Department’s sole discretion, it determines that the proposed personnel substitution will be equal to or better than the personnel identified in the SOQ that is intended to be replaced. If any personnel substitution request is approved, the Proposer will still be scored based on its original SOQ. Any Proposer that does not receive approval of a proposed personnel substitution request may be found nonresponsive and ineligible for award.

1.12 Equal Employment Opportunity and Nondiscrimination

Work on the job site shall comply with Labor Code §§ 1727 and 1770-1815 and 8 California Code of Regulations § 16000 et seq. Attention is directed to the "Nondiscrimination Clause" that is required by Chapter 5 of Division 4 of Title 2, California Code of Regulations, and to the Standard California Nondiscrimination Construction Contract Specifications under Gov. Code § 12990.

1.13 Disadvantaged Business Enterprise Goal

This solicitation is subject to 49 CFR 26. Proposers shall be fully informed of the requirements of the regulations and the Department's DBE program developed under the regulations. Construction Manager involved in the performance of Work resulting from this RFQ shall take all necessary and reasonable steps to ensure that DBEs have the maximum opportunity to compete for and perform on any Construction Contract resulting from this Preconstruction Services Contract.

As a part of the SOQ submission, Proposers responding to this RFQ shall include with their submission a signed affidavit acknowledging the Proposer’s commitment to comply fully with U.S. DOT DBE provisions as set forth under Title 49 CFR Part 26 and subsequent publication of the Federal Register dated June 16, 2003 (Volume 68, Number 115) and the Project DBE goal requirements as further defined in the Construction Contract when issued. Proposers shall complete and return Appendix C, Form F as part of the SOQ confirming the Proposer will aggressively exercise Good Faith Efforts to the satisfaction of the Department to meet or exceed the Project DBE goal as set forth in the Construction Contract documents.

1.14 Labor Policies

State prevailing wages will apply to this Preconstruction Services Contract. For Federal-aid contracts, federal prevailing wages will also apply. The applicable prevailing wages will be specified in the Construction Contracts.

Department of Transportation I-5/I-805 Express Lanes Corridor Project Request for Qualifications Contract No.: 112T37CM

Introduction and General Instructions 14

1.15 Insurance and Bonds

1.15.1 Bond Requirements

It is currently anticipated that the selected Proposer shall submit payment and performance bonds upon execution of the Construction Contract. The payment bond shall be equal to 100 percent of the Agreed Price and the performance bond shall be equal to 50 percent of the Agreed Price. Proposers shall demonstrate their capacity to obtain the required bonds.

Proposers shall attach a notarized statement from an admitted surety insurer (approved by the California Department of Insurance) authorized to issue bonds in the State of California that states both:

Proposer’s current bonding capacity is sufficient for the Project and referenced payment and performance bonds.

Proposer’s current available bonding capacity.

1.15.2 Insurance Requirements

Proposers shall provide evidence of capability to provide insurance as provided in Section 3.3b. In addition, the selected Construction Manager shall indemnify the Department, the Department’s consultants and others with respect to claims arising out of the Preconstruction Services Contract or Work.

1.16 Work Performed Prior to NEPA Approval

Prior to completion of the NEPA approval process, any Work done by the Construction Manager shall comply with the following:

Shall include all alternatives identified and considered in the EIR/EA.

Shall not make any commitment to any alternative and all alternatives, including the “no-build” alternative, shall be evaluated and fairly considered.

Shall not include preparation of any NEPA documentation nor include any decision-making authority.

Shall not include the development of shop drawings or fabrication plans.

The Department will not proceed with the award of a Construction Contract (including early Work packages such as advanced material acquisition or site Work) and will not proceed, or permit any consultant or contractor to proceed, with construction until the completion of the NEPA approval process for Project.

Department of Transportation I-5/I-805 Express Lanes Corridor Project Request for Qualifications Contract No.: 112T37CM

Content of Statement of Qualifications 15

2 PROCUREMENT SCHEDULE

The Department anticipates the following dates as Project milestones leading to Preconstruction Services Contract award. This schedule is subject to revision by the future Addenda.

Milestone Date

Issue RFQ 11/16/2026

Data Room, Access Permitted 11/16/2026

Final Date for Receipt of Proposers’ Questions 12/16/2026

SOQ Due Date for Electronic and Hardcopy Submittal

1/11/2027

Notice of Short List 2/10/2027

Proposer Interviews 2/17/2027

Anticipated Ranking Determination 2/25/2027

Anticipated Award of Preconstruction Services Contract

3/18/2027

Anticipated Notice to Proceed 4/09/2027

Request to Return Cost Proposal Deadline 4/30/2027

Request Debriefing Meeting Deadline 4/30/2027

Anticipated Award of Construction Contract 6/30/2027

Construction Complete 5/02/2031

3 CONTENT OF STATEMENT OF QUALIFICATIONS

This Section 3 describes specific information that shall be included in the SOQ.

Proposers shall provide brief, concise information that addresses the requirements of the Project consistent with the evaluation criteria described in this RFQ. Failure of a Proposer to submit a complete SOQ may result in the SOQ submittal being determined nonresponsive. Proposers shall only submit the information requested. Details pertaining to the organization and format of the SOQ are outlined in Appendix B.

3.1 Proposer’s Transmittal Letter

Department of Transportation I-5/I-805 Express Lanes Corridor Project Request for Qualifications Contract No.: 112T37CM

Content of Statement of Qualifications 16

The Proposer shall complete Appendix C, Form A. A duly authorized representative of the Proposer’s organization shall sign the letter. For Proposers that are joint ventures, partnerships, or other associations, authorized representatives of the Proposer and all Major Participant(s) of the Proposer shall sign the Transmittal Letter.

The Proposer shall complete Appendix C, Form G, verifying the accuracy of the information submitted as part of the SOQ. For Proposers that are joint ventures, partnerships, or other associations, authorized representatives of the Proposer and all Major Participant(s) of the Proposer shall sign the Proposer SOQ Certification.

3.2 Legal Structure

In order to demonstrate that Proposer’s organization, legal structure, team members, and history demonstrate an ability to remain stable and viable for the duration of the Project, and be contractually bound to the Department, Proposers shall address all the following and submit it under Section 1 of the SOQ (narrative in Section 1 shall be a maximum of two (2) pages):

a) Legal structure of the Proposer and its organization. If the Proposer organization has already been formed, provide the following:

i. Complete copies of the organizational documents that allow, or would allow by the time of Preconstruction Services Contract award, the Proposer and all Major Participant(s) thereof to conduct business in the State of California.

ii. Complete documentation of the executed agreement between the Proposer and any Major Participant that shows the Major Participant meets the definition of Major Participant in Section 1.2

If the Proposer organization has not yet been formed, provide a brief description of the proposed legal structure and draft copies of the underlying agreements. In the event that final agreements between Major Participants have not been finalized at the time of the SOQ submittal, Major Participants shall submit letters of agreement signed by an authorized officer of each Major Participant noting the type of relationship to be entered into prior to Preconstruction Services Contract (e.g., joint venture, partnership), and the commitment of the parties to finalize the organizational documents prior to execution of the Preconstruction Services Contract. If Proposer is a partnership, joint venture, or other association, the SOQ shall identify the percentage equity interest of each member.

b) If the Proposer is a partnership, limited partnership, joint venture, or other association, all members of the Proposer shall agree to be jointly and severally liable to the Department for the performance under the Preconstruction Services Contract by executing the Transmittal Letter in Appendix C, Form A.

c) Name and describe all Major Participants as defined in this RFQ.

d) A statement from the Proposer identifying any actual and/or potential conflicts of interests the firm may have (refer to Section 1.9).

e) In cases where Major Participants on different Proposer organizations belong to the same parent company, each Proposer shall describe how conflicts of interest would be avoided by the participants through the qualification and proposal phases

Department of Transportation I-5/I-805 Express Lanes Corridor Project Request for Qualifications Contract No.: 112T37CM

Content of Statement of Qualifications 17 of the Project. The Department may disqualify a Proposer if any of its Major Participants belong to more than one Proposer organization.

f) Proposer and any Major Participant(s) shall complete Form E found in Appendix C.

g) Proposer and any Major Participant(s) shall complete Form F found in Appendix C.

3.2.1 Minimum Requirement for Legal Structure

A Proposer shall demonstrate all the following:

a) The Proposer has the legal capability to carry out the Project responsibilities potentially allocated to it, as demonstrated by the materials provided in Section 1 of the SOQ.

b) All Major Participants of the Proposer have agreed to be jointly and severally liable to the Department for performance under the Preconstruction Services Contract, as reflected in the executed Transmittal Letter (Appendix C, Form A).

c) The Proposer has agreed to adhere to the Project’s DBE requirements as provided in Appendix C, Form F.

d) The information disclosed in the SOQ (including Form D and Form E in Appendix C) does not materially adversely affect the Proposer’s ability to carry out the Project responsibilities potentially allocated to it.

3.3 Financial Capacity

To demonstrate that the Proposer’s team members possess the financial capacity to enter into a Construction Contract with the Department and possess the resources to successfully complete the Project, the Proposer shall address the following and submit under Section 2 of the SOQ:

a) Provide a letter or other written documentation from a surety or insurance company stating that the Proposer is capable of obtaining a Performance Bond and Payment Bond (refer to Section 1.15 for bond amounts) covering the Project. Letters indicating “unlimited” bonding capability are not acceptable.

b) Proposers shall provide insurance certifications, either a certificate of insurance evidencing current policies of, or written evidence from an insurance company or broker indicating that the Proposer is capable of obtaining the following types of insurance: Commercial General Liability, Auto Liability, Workers’ Compensation/ Employers Liability, and Pollution Liability. Policy limit requirements will be specified in the Preconstruction Services Contract.

3.3.1 Minimum Requirement for Financial Capacity

A Proposer shall demonstrate its financial capability to carry out the Project responsibilities potentially allocated to it, as demonstrated by the materials provided in Section 2 of the SOQ, including but not limited to all the following:

a) The surety or insurance company shall be admitted to do business in the State of California.

Department of Transportation I-5/I-805 Express Lanes Corridor Project Request for Qualifications Contract No.: 112T37CM

Content of Statement of Qualifications 18

b) The surety or insurance company shall be rated in the top two categories by two nationally recognized rating agencies or have a rating from A.M.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .