This document is a Statement of Work (SOW) for the replacement of a failed Omron Programmable Logic Controller (PLC) and power supply at the USDA-ARS Robert W. Holley Center in Ithaca, New York. The project involves harvesting the program from the existing controller, reconfiguring it, and programming it into a new Omron PLC. The new PLC must meet specific technical requirements, including compatibility with the existing equipment. The work must be performed by an authorized representative of the PLC manufacturer, and the contractor must provide a wiring diagram and manufacturer's warranty information.
The related federal contract opportunity is a solicitation (Solicitation Number: 1125488) for the replacement of the Omron PLC at the USDA facility in Ithaca, NY. This is a full and open solicitation, and the associated NAICS code is 811210. The Government intends to award a Firm Fixed-Price (FFP) contract to the lowest priced offeror that fully meets the specifications, including full compatibility with the existing panel and products. Offerors must submit a firm fixed-price quotation, their Unique Entity ID (UEI), and a completed copy of the provision at 52.212-3, Offeror Representations and Certifications-Commercial Products and Commercial Services. Quotes are due by 5 pm EST on May 10, 2024.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Wiring Diagram.jpg | JPG image | |
| Questions and Responses 1125488.pdf | ||
| SOW.Omron PLC replacment 5.8.24.pdf | ||
| SOW - Controller Repair.pdf | ||
| CLAUSES_PROVISIONS_ (1).pdf | ||
| SCA Wage Determination 2015-4153 R23.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
(Updated 5.9.2024)
1. Project Title: USDA-ARS Robert W. Holley Center Omron Programmable Logic Controller (PLC) repair / replacement.
2. Project Location: 538 Tower Road, Ithaca, N.Y. 14853
3. Introduction: The USDA-ARS Center for Agriculture and Health is located on the Cornell University Campus in Ithaca, N.Y.
4. Project Summary: This small project is needed for replacement of a failed Omron Programmable Logic Controller (PLC) and power supply for control of automatic sump pump operations.
5. Technical Requirements: The existing controller has failed and is in need of replacement to resume automatic operation of tandem sump pumps. The program contained within the existing controller must be harvested, reconfigured and programmed into a new PLC. The existing controller will then be removed and replaced. The contractor shall provide a wiring diagram will be provided to facilitate future diagnostics.
PLC shall be Omron Model CP1L-EM30DR-D or equivalent with the following minimum salient characteristics:
Supply voltage type DC Number of digital inputs 18 Input type PNP/NPN Number of digital outputs 12 Output type Relay Program capacity 20 K steps Data memory capacity 32 K words Communication port(s) Ethernet TCP/IP Number of Ethernet ports 1
Power Supply shall be Omron Model S8VK-S24024 or equivalent with the following minimum salient characteristics:
Power Rating 240W Output Voltage 24 VDC Overload Protection Yes, with automatic reset Overvoltage Protection Yes
All work must be performed by an authorized representative of the PLC manufacturer.
Manufacturer’s warranty information shall be provided to the Government.
Provided equipment for any replacement PLC must be fully compatible and an equivalent replacement for the brand and model pictured below:
If a contractor intends to provide replacement parts that are other than the brand pictured, descriptive literature must be provided on the model being proposed along with statements on how it is 100% compatible with existing equipment.
6. Site Specific Measures: Contractor is to coordinate with Facilities Operations Specialist or their designee.
7. Project Schedule: Negotiable, please provide earliest possible completion date with quote.