This is a Preliminary Development Schedule exhibit for a detailed master plan and design project for the New Mexico State Fair Grounds and EXPO New Mexico in Albuquerque, NM. The schedule outlines a multi-phase development program commencing with the award of a Professional Services Agreement (PSA) on August 3, 2026, and extending through 2029. Phase 1 encompasses multiple work streams including a Detail Master Plan with programming and schematic design, horizontal development with demolition design and construction, civil infrastructure design and construction, public park design and construction, State Fair improvements design and construction, and budget tracking and cost control. Phase 1 also includes anchor development commercial viability assessments and qualification surveys for both residential multi-use and stadium developments, land acquisition status tracking, development schedule refinement, and Development and Disposition Agreement (DDA) preparation. Phase 2 addresses the anchor developments themselves, including residential multi-use and stadium components with separate RFP, award, and construction phases. The project culminates with Phase 1 completion and transition to master plan implementation events and land acquisition activities.
The schedule identifies key responsible parties for various task components, including a Detail Master Planner for planning and design services, Demo Contractor for demolition construction, Civil Contractor for infrastructure construction, Park Contractor for park improvements, and State Fair Contractor for fair-related improvements. Most tasks are scheduled for five-day effort periods with the same start and end dates (August 3-8, 2026 shown as template dates), indicating this is a preliminary schedule template requiring refinement. The compressed timeline presentation suggests coordination among multiple stakeholders and concurrent workstreams necessary to advance the comprehensive redevelopment program from master planning through design entitlements to vertical and horizontal construction phases.
View the file
Other files for this state and local contract opportunity
| File | Type | Posted |
|---|---|---|
| 2-Appendix E.pdf | ||
| 1-Appendix A.pdf | ||
| 5-Appendix H.pdf | ||
| 8-Appendix F.pdf | ||
| 12-State Fair Grounds Master Detailed Master Plan RFP 26-350-26-0001 2.pdf | ||
| 3-Appendix G.pdf | ||
| 9-Appendix C Draft Contract.pdf | ||
| 10-State Fair Grounds Master Detailed Master Plan RFP 26-350-26-0001 2.pdf | ||
| 4-Appendix I.pdf | ||
| 6-Appendix B.pdf | ||
| 7-Appendix D.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ID Task Name
1 Phase 1 Project Start (Award of PSA)
2 Basic Services
3 Phase 1 Detail Master Plan
4 DMP Programming
5 DMP Schematic Design
6 Horizontal Development
7 Demolition
8 Demo Design
9 Demo Construction
10 Civil Infrastructure
11 Civil Design
12 Civil Construction
13 Public Park
14 Park Design
15 Park Construction
16 State Fair Improvements
17 Improvements Design
18 Improvements Construction
19 Additional Services
20 Phase 1 Budget Tracking & Cost Control (develop and Update)
0% Mon Aug 3, '26 Phase 1 Project Start (Award of PSA)
GSD
Mon Aug 3, '26 Sat Aug 8, '26 Basic Services - Detail Master Planner (0%)
Mon Aug 3, '26 Sat Aug 8, '26 Phase 1 Detail Master Plan - Detail Master Planner (0%)
Mon Aug 3, '26 Sat Aug 8, '26 DMP Programming - Detail Master Planner (0%)
5 edays
Mon Aug 3, '26 Sat Aug 8, '26 DMP Schematic Design - Detail Master Planner (0%)
5 edays
Mon Aug 3, '26 Sat Aug 8, '26 Horizontal Development - Detail Master Planner (0%)
Mon Aug 3, '26 Sat Aug 8, '26 Demolition - Detail Master Planner (0%)
Mon Aug 3, '26 Sat Aug 8, '26 Demo Design - Detail Master Planner (0%)
5 edays
Mon Aug 3, '26 Sat Aug 8, '26 Demo Construction - Demo Contractor (0%)
5 edays
Mon Aug 3, '26 Sat Aug 8, '26 Civil Infrastructure - Detail Master Planner (0%)
Mon Aug 3, '26 Sat Aug 8, '26 Civil Design - Detail Master Planner (0%)
5 edays
Mon Aug 3, '26 Sat Aug 8, '26 Civil Construction - Civil Contractor (0%)
5 edays
Mon Aug 3, '26 Sat Aug 8, '26 Public Park - Detail Master Planner (0%)
Mon Aug 3, '26 Sat Aug 8, '26 Park Design - Detail Master Planner (0%)
5 edays
Mon Aug 3, '26 Sat Aug 8, '26 Park Construction - Park Contractor (0%)
5 edays
Mon Aug 3, '26 Sat Aug 8, '26 State Fair Improvements - Detail Master Planner (0%)
Mon Aug 3, '26 Sat Aug 8, '26 Improvements Design - Detail Master Planner (0%)
5 edays
Mon Aug 3, '26 Sat Aug 8, '26 Improvements Construction - State Fair Contractor (0%)
5 edays
Mon Aug 3, '26 Sat Aug 8, '26 Additional Services - Detail Master Planner (0%)
Mon Aug 3, '26 Sat Aug 8, '26 Phase 1 Budget Tracking & Cost Control (develop and Update) - Detail Master Planner (0%)
5 edays
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep arter 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter 4
2026 2027 2028 2029
Exhibit C – Preliminary Development Schedule Phase 1 - State Fair Master Plan
Thu 5/28/26, 10:42 AM Page 1 of 2 Pages Exhibit E – Preliminary Development Schedule (Template) - All Tasks
Exh ibi t C
- M
S Proh ec t S ch ed ule
Tem pla te
ID Task Name
21 Residential (Multi use) Anchor Development Commercial Viability
22 Stadium Anchor Development Commercial Viability
23 Residential (Multi use) Anchor Interest and Qualification Survey
24 Stadium Anchor Interest and Qualification Survey
25 Land Acquisition Status
26 Development Schedule
27 Development Schedule Refinement and State Fair Improvements Scope
28 Develop Development and Disposition Agreement (DDA) - Anchor Developers
29 Anchor Development
30 Residential- Multi Use
31 Residential RFP & Award
32 Residential Construction
33 Stadium Development
34 Stadium RFP & Award
35 Stadium Construction
36 Other Master Plan Events
37 Land Acquisition
38 Phase 1 Complete
Mon Aug 3, '26 Sat Aug 8, '26 Residential (Multi use) Anchor Development Commercial Viability - Detail Master Planner (0%)
5 edays
Mon Aug 3, '26 Sat Aug 8, '26 Stadium Anchor Development Commercial Viability - Detail Master Planner (0%)
5 edays
Mon Aug 3, '26 Sat Aug 8, '26 Residential (Multi use) Anchor Interest and Qualification Survey - Detail Master Planner (0%)
5 edays
Mon Aug 3, '26 Sat Aug 8, '26 Stadium Anchor Interest and Qualification Survey - Detail Master Planner (0%)
5 edays
Mon Aug 3, '26 Sat Aug 8, '26 Land Acquisition Status - Detail Master Planner (0%)
5 edays
Mon Aug 3, '26 Sat Aug 8, '26 Development Schedule - Detail Master Planner (0%)
5 edays
Mon Aug 3, '26 Sat Aug 8, '26 Development Schedule Refinement and State Fair Improvements Scope - Detail Master Planner (0%)
5 edays
Mon Aug 3, '26 Sat Aug 8, '26 Develop Development and Disposition Agreement (DDA) - Anchor Developers - Detail Master Planner (0%)
5 edays
Mon Aug 3, '26 Sat Aug 8, '26 Anchor Development - Detail Master Planner (0%)
Mon Aug 3, '26 Sat Aug 8, '26 Residential- Multi Use - Residential Anchor (0%)
Mon Aug 3, '26 Sat Aug 8, '26 Residential RFP & Award - Detail Master Planner (0%)
5 edays
Mon Aug 3, '26 Sat Aug 8, '26 Residential Construction - Detail Master Planner (0%)
5 edays
Mon Aug 3, '26 Sat Aug 8, '26 Stadium Development - Stadium Anchor (0%)
Mon Aug 3, '26 Sat Aug 8, '26 Stadium RFP & Award - Detail Master Planner (0%)
5 edays
Mon Aug 3, '26 Sat Aug 8, '26 Stadium Construction - Detail Master Planner (0%)
5 edays
Mon Aug 3, '26 Sat Aug 8, '26 Other Master Plan Events - GSD (0%)
Mon Aug 3, '26 Sat Aug 8, '26 Land Acquisition - GSD (0%)
5 edays
0% Mon Aug 3, '26 Phase 1 Complete
GSD
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep arter 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter 4
2026 2027 2028 2029
Exhibit E – Preliminary Development Schedule Phase 1 - State Fair Master Plan
Thu 5/28/26, 10:42 AM Page 2 of 2 Pages Exhibit E – Preliminary Development Schedule (Template) - All Tasks
Exh ibi t C
- M
S Proh ec t S ch ed ule
Tem pla te