This is a Fee Sheet for a Construction Manager at-Risk (CMAR) contract issued by the Atlanta Independent School System in Georgia for the renovation of the Phoenix Academy Kitchen. The document outlines the pre-construction services and associated compensation structure for the selected construction manager. Pre-construction services include Schematic Design ($10,000 due 4/30/26), Design Development ($20,000 due 4/30/26), 80% Construction Documents ($15,000 due 5/15/26), and Bidding/GMP Submittal and Negotiations/Award of GMP Amendment ($15,000 due 5/15/26). The total pre-construction fee is $60,000.
The fee sheet indicates a total pre-construction phase compensation of $60,000 with specific task-based lump sum fees. The construction phase compensation structure includes a Construction Manager's Fee based on a percentage of general conditions and an additional percent fee, though the specific percentages were not completed in the submitted document. This fee structure represents the negotiated terms between the Atlanta Independent School System and the selected construction manager for managing the kitchen renovation project from preconstruction through construction completion.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FEE SHEET
Construction Management At-Risk
26-110625-1273-P-AW -Phoenix Academy Kitchen Renovations
FIRM NAME:
DATE:
PRE- CONSTRUCTION
SERVICES
As compensation for pre-construction services, the CM shall receive a fee as negotiated below:
LUMP SUM FEE
(PER TASK)
COMPLETION/ DUE DATES
1. Schematic Design $10,000 4/30/26
2. Design Development. $20,000 4/30/26
3. 80% Construction Documents $15,000 5/15/26
4. Bidding / GMP, Submittal / GMP, Negotiations / Award of
GMP Amendment $15,000 5/15/26
TOTAL PRE- CONSTRUCTION FEE $60,000.00
CONSTRUCTION PHASE
6. Construction Manager’s Fee:
a. percent of general conditions
b. percent fee