amendment 01.docx
DOCX document 61 KB Posted
- Solicitation number
- 1066228
- Issued by
-
Department of Agriculture Forest Service
View the file
Other files
| File | Type | Posted |
|---|---|---|
| combined amendment2.pdf | ||
| GAOA_JerseydaleCG_Rehab_Phase4_Specifications_060722_Revised_FINAL.pdf | ||
| WAGE DETERMINATION.pdf | ||
| GAOA_JerseydaleCG_Rehab_Phase4_PlanDrawings_060722_Revised_FINAL.pdf | ||
| RFP -.docx | DOCX document | |
| GAOA_JerseydaleCG_Rehab_Phase4_SectionC_040622_FINAL.rtf | RTF text file | |
| GAOA_JerseydaleCG_Rehab_Phase4_Fire Plan 2013_040622_FINAL.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2. AMENDMENT/MODIFICATION NUMBER
| 3. EFFECTIVE DATE |
| 4. REQUISITION/PURCHASE REQUISITION NUMBER |
| 5. PROJECT NUMBER (If applicable) |
| A00001 |
| 08/05/22 |
| 1066228 |
| 6. ISSUED BY |
| CODE |
| 7. ADMINISTERED BY (If other than Item 6) |
| CODE |
11. (
AMENDMENT
OF
SOLICITATION/MODIFICATION
OF
CONTRACT
1.
CONTRACT
ID
CODE
PAGE
OF
PAGES
Greg Cunningham
USDA,
Forest
Service
Peacekeeper
Way
Suite
McClellan Park, Ca. 95652 USDA Forest Service Construction
Contracting
Peacekeeper
Way, Suite McClellan, CA
95652 8.
NAME AND
ADDRESS
OF
CONTRACTOR
(Number, street, county, State and
ZIP Code)
ALL
PROSPECTIVE
OFFERORS
(X)
9A.
AMENDMENT
OF
SOLICITATION
NUMBER
127EAW22R0053
9B.
DATED
(SEE
ITEM
11) 07/22/2022 10A.
MODIFICATION
OF
CONTRACT/ORDER
NUMBER
10B.
DATED
(SEE
ITEM
13)
CODE
FACILITY
CODE
x
)THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required) N/A
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
| CHECK ONE |
| A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NUMBER IN ITEM 10A. |
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not is required to sign this document and return 1 copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
GAOA Jerseydale CG Rehabilitation Phase 4, Sierra National Forest, California
See Attachment 1 to this amendment for RFI responses and information.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
| 15A. NAME AND TITLE OF SIGNER (Type or print) |
| 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print) |
| 15B. CONTRACTOR/OFFEROR |
| 15C. DATE SIGNED |
| 16B. UNITED STATES OF AMERICA |
| 16C. DATE SIGNED |
(Signature of person authorized to sign)
(Signature of Contracting Officer)
Previous edition unusable STANDARD FORM 30 (REV. 11/2016)
ATTACHMENT NO.1
RFI RESPONSE AMENDMENT NO. 1
1. I have reached out to the sign manufacturer listed on the documents for the above project and they are requesting a picture of both equestrian signs. Is this something you can provide? I have given them the description as shown on Sheet G-4, but they are wanting pictures, see below. We do not have pictures of the signs. They will have to submit proofs during the approval process. All the information needed is within the drawing below which is contained in the plans.
2. The plan sheet G-3 shows 31 steps, but the Schedule of Items shows 20 steps. Which should we use to provide the manufacturer for their quote? 31 Steps is correct. The schedule of items is in two parts due to funding. Scroll down to page 2 of the Schedule of Items the other 11 are there.
| 3. | We are actively gathering bids for this project. With the ramifications of the Oak Fire, do you anticipate there will be added scope to this project, or will it bid as is, as scheduled on 8/22/2022? Answer: No changes anticipated at this time. |
| 4. | Who is responsible for providing the certified testing laboratory for compaction, concrete, etc., Owner or Contractor? Answer: Per section 1442 of the specifications, the contractor is responsible for providing the certified testing laboratory for compaction, concrete, etc. |
5. Refer to Plan Sheet G-11: Section 1 indicates “Wood Step Tread 6”x 6”x5’…”; Section 2 indicates 4’-0” and detail 1/G-11 indicates 4’-0”. Can you please confirm the wood step tread size, 4’-0” or 5’-0”? Answer: The width of the wood step tread is 4'-0".
6. I would like to formally request an onsite Job walk scheduled for Friday July 29th, between the time of 1:30pm- 2:00pm. I called the number with ext. 4845 a few times throughout yesterday and left one voice message. I will follow up this email with an additional phone call today in hopes to get a positive conformation of the requested scheduled time of approximately 1:30pm- 2:00pm tomorrow Friday July 29th. SITE VISIT: ALL ROADS ARE OPEN IN THE AREA, PLEASE VISIT THE SITE AT YOUR CONVENIENCE. AN ESCORTED VISIT WILL NOT BE ACCOMMODATED BY THE FOREST SERVICE. PLEASE SUBMIT RFI(S) IF YOU NEED CLARIFICATIONS.
7. Are electronic bids acceptable or do we need to mail or drop off in person? If not electronic, can you please provide the information as to where the bids shall be mailed or dropped off in person? Submit bid/proposals to both addressees set forth on SF-1442, Block 8, via email attachment.
8. Is the "Buy American Act - Construction Materials" a requirement of this solicitation. Clause 52.225-10, “Notice of Buy American Act Requirement- Construction Materials” (May 2014) is applicable to this solicitation, page 32.
9. What is the last day to submit bid questions and when can we expect to have our bid questions answered? Last date to submit RFIs is 8/12/22.
10. Regarding Attachment Section C, C.3 Contract Time, What is the Governments updated start of work timeline? Immediately after Contract award and weather permitting the anticipated contract start time is Mid- September. Work shall commence within 5 calendar days of the NTP and be completed within 120 calendar days.
11. What Phase of work is currently being performed at the jobsite location? Phase 2 and 3 are currently in progress, which is living areas, tent pads, trails, steps, table installation, bear box installation and fire ring installation.
image1.png image2.png image3.jpeg