100762_-_NW_Turk_Road_Bridge_Replacement_(#671374).pdf
PDF 243 KB Posted
- Solicitation number
- 2026.035-LUT CPS
- Issued by
- Washington County, Oregon
About this file
This is a competitive sealed bid document issued by Washington County, Oregon's Department of Land Use & Transportation (DLUT) Capital Project Services for the NW Turk Road Bridge Replacement project (Bid Number 2026.035-LUT). The project encompasses the complete replacement of an existing bridge structure over West Fork Dairy Creek on Turk Road with a new 75-foot precast prestressed concrete slab beam bridge, including temporary traffic control and erosion control installations, roadway approaches spanning 370 feet, guardrails, driveway construction, drainage improvements, and associated incidental work. The bid schedule contains 57 line items across multiple work categories including mobilization, traffic control, erosion control, roadway work, drainage, bridge construction, bases, wearing surfaces, permanent traffic safety devices, and right-of-way development. Key quantities include 455 linear feet of precast prestressed slab beams, 910 linear feet of sediment barriers, 420 square yards of slope matting, six check dams, 730 linear feet of 18-inch pipe piles, 253 cubic yards of aggregate base, and 233 tons of asphalt concrete pavement. Electronic bids must be submitted through the OpenGov Procurement portal by April 15, 2026, at 1:00 p.m., with public opening and reading via Microsoft Teams video conference. Written questions are due by April 10, 2026, at 5:00 p.m. No pre-bid meeting will be held. Bids must remain firm for 30 calendar days from the opening date, and the successful contractor must execute the contract and furnish performance and payment bonds within ten calendar days of the Notice of Award. The contract schedule requires the contractor to reopen Turk Road to two traffic lanes no later than 90 calendar days after closure and complete all work by October 15, 2026, with in-water work limited to July 15 through September 30.
The project cost range is $1,000,000 to $2,000,000, and bids must be accompanied by a bid guaranty equal to at least ten percent of the total bid amount in the form of a surety bond, irrevocable letter of credit, certified check, or cashier's check. Liquidated damages are assessed at $500 per day for the first milestone, $1,000 per day for final completion, or $1,200 per day if both periods overlap. Washington County will retain five percent of the contract price unless the contractor provides a surety bond in lieu of cash retainage under Oregon House Bill 4006. Bidders must be prequalified by the Oregon Department of Transportation, licensed by the Oregon Construction Contractor's Board, and comply with prevailing wage requirements under Oregon Revised Statutes 279C.840. First-tier subcontractors with contracts equal to or greater than five percent of the total project bid or $350,000 must be disclosed on the required First-Tier Subcontractors Disclosure Form within two work hours of bid closing. All contractors and subcontractors must comply with Washington County's Clean Air Construction Standard, including registration of applicable diesel nonroad equipment in The Yard compliance portal prior to bid submission. Workers' compensation insurance is required, along with commercial general liability insurance of $1,000,000 per occurrence and $2,000,000 annual aggregate, and commercial automobile liability insurance of $1,000,000. The project is governed by the 2024 edition of the Oregon Standard Specifications for Construction as modified by the bid documents and is subject to Oregon state law and Washington County ordinances with exclusive jurisdiction in the Circuit Court for Washington County, Oregon, or Federal District Court for the State of Oregon.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bid Documents for
100762 - NW TURK ROAD BRIDGE REPLACEMENT (#671374)
Bid Number: 2026.035-LUT CPS
WASHINGTON COUNTY
DEPARTMENT OF LAND USE & TRANSPORTATION
CAPITAL PROJECT SERVICES
1400 SW WALNUT STREET, MS#18
HILLSBORO, OR 97123-5625
Date Issued: March 30, 2026 DEADLINE FOR QUESTIONS: April 10, 2026
RESPONSE DEADLINE: April 15, 2026, 1:00 pm
RESPONSES MUST BE SUBMITTED ELECTRONICALLY TO:
https://secure.procurenow.com/portal/washington-county-or
Washington County, Oregon
LAND USE AND TRANSPORTATION CAPITAL PROJECT SERVICES BID
100762 - NW Turk Road Bridge Replacement (#671374)
I. Preface II. Introduction
III. Invitation To Bid IV. Program Compliance Requirements V. Bidder Questionnaire
VI. Bid Schedule
Attachments:
A - 100762_13_Book_1 B - 100762_13_Signature_Page_Fillable C - 100762_13_Bid_Guaranty_Fillable D - 100762_13_First_Tier_Subs_Disclosure_Fillable E - 100762_13_Book_2 F - 100762_13_Bid_Turk Road Plans-Final-SIGNED
100762 - NW Turk Road Bridge Replacement (#671374) Powered by ProcureNow
I. 1. Preface
I.A 1.1. Introduction
Work shall comply with the following standards which are hereby incorporated into these bid documents by reference:
A. 2024 edition of the "Oregon Standard Specifications for Construction" Oregon Department of Transportation (ODOT), Oregon Chapter of American Public Works Association (APWA), as modified by these Special Provisions or Addenda.
B. Other standards identified in these Bid Documents by reference.
The Contractor may view or purchase copies of the 2024 edition of the "Oregon Standard Specifications for Construction" from the Oregon Department of Transportation website:
http://www.oregon.gov/ODOT/Business/Pages/Standard_Specifications.aspx
Sectional references in these Bid Documents refer to sections of the Standard Specifications and any applicable modifications to sections or subsections contained herein.
Licensing per ORS 468A.720 (working with asbestos) is not required for this project. Reference ORS 279C.365(1)(j).
I.B 1.2. Applicable Specifications for Bid Submittal
The Bid Documents/Proposed Contract Documents are issued for the information of Bidders submitting bids for this project and the work described herein, at the time and place indicated in the "Invitation to Bid." These Bid Documents, subject to revision by addendum, in accordance with provisions stated below, will be incorporated in and made part of the contract documents for this project.
If the County elects to reject all bids and re-advertise for new bids, to be received at a time later than that indicated in the invitation to bid, these Bid Documents will cease to be applicable and new Bid Documents will be issued by the County. Bidders submitting bids at the newly established bid date and time should obtain the new Bid Documents and base their bids upon them, as they will be bound by it in the event they are awarded a contract.
I.C 1.3. Revisions Prior to Time of Opening of Bids
The County reserves the right to make necessary changes or corrections to the Bid Documents in accordance with 00120.30. The County will provide addenda only by publishing them on the OpenGov website at:
https://procurement.opengov.com/portal/washington-county-or http://www.oregon.gov/ODOT/Business/Pages/Standard_Specifications.aspx https://procurement.opengov.com/portal/washington-county-or
100762 - NW Turk Road Bridge Replacement (#671374) Powered by ProcureNow
Registration for the OpenGov website is required to download addenda. Bidders shall be responsible for checking the OpenGov website for addenda. Bidders should check the site daily during the week designated to receive bids.
Bidders, not Washington County, shall be responsible for failure of Bidders to check and download Addenda. Bids shall incorporate all Addenda. Bids may be rejected if opened and found by the County to not be based on all Addenda published on the web site.
I.D 1.4. Protest Processes Prior to Bid - Specification Protest Process
A. Delivery: A bidder must deliver a protest of specifications to the County in writing no later than ten (10) calendar days prior to the bid date as follows:
Specification Protest Bid Number: 2026.035-LUT CPS Washington County Procurement Division Attn: Procurement Manager 155 N First Avenue, Suite 270, MS 28 Hillsboro, OR 97124-3072
B. Content: A bidder’s Written protest must include
1. A detailed statement of the legal and factual grounds for the protest,
2. A description of the resulting prejudice to the bidder, and
3. A statement of the form of relief requested or any proposed changes to the specifications.
C. County Response: The County may reject without consideration any bidder’s protest after the deadline established for submitting protest. The County shall provide notice to the applicable bidder if it entirely rejects a protest. If the County agrees with the bidder’s protest, in whole or in part, the County shall either issue an addendum reflecting its determination or cancel the solicitation.
D. Extension of Closing: If the County receives a written protest from a bidder in accordance with this rule, the County may extend the bid closing date if the County determines an extension is necessary to consider the protest and to issue addenda, if any, to the Bid Document.
I.E 1.5. Protest of Award - Protests and Judicial Review of Contract Award
A. Purpose: The award by the Washington County Board of Commissioners of the contract shall constitute a final decision of the County to award the contract if no written protest of the award is filed. A Bidder may protest the award of a contract, or the intent to award a contract, whichever occurs first, if the conditions set forth in ORS 279B.410(1) are satisfied. A Bidder must file written protest with the County and exhaust all
100762 - NW Turk Road Bridge Replacement (#671374) Powered by ProcureNow administrative remedies before seeking judicial review of the County's Contract Award decision.
B. Delivery: A Bidder must deliver a written protest to the Washington County Procurement Manager within seven (7) Days after issuance of the Notice of Intent to Award the Contract as follows:
Contract Award Protest Bid Number: 2026.035-LUT CPS Washington County Procurement Division Attn: Procurement Manager 155 N First Avenue, Suite 270, MS 28 Hillsboro, OR 97124-3072
Intent to Award will ONLY be posted on the OpenGov website at: https://procurement.opengov.com/portal/washington-county-or
C. Content of Protest: A Bidder’s written protest shall specify the grounds for the protest to be considered pursuant to ORS 279B.410(2).
D. County Response: The County shall not consider a bidder’s contract award protest after the timeline established for submitting such protest. The County shall issue a written disposition of the protest in a timely manner as set forth in ORS 279B.410(4). If the County upholds the protest, in whole or in part, the County may in its sole discretion either award the contract to the successful protestor or cancel the solicitation.
E. Judicial Review: Judicial review of the Board’s or its designee’s decision relating to a Contract award protest shall be in accordance with ORS 279B.415.
1. No protest against award because of the content of specifications shall be considered after the deadline established for submitting such protest.
2. Judicial review of the County’s decision relating to a specification protest shall be in accordance with ORS 279B.405.
II. 2. Introduction
The project number is 100762
II.A 2.1. Summary
The project name is: 100762 - NW Turk Road Bridge Replacement (#671374).
The project will construct the following for Washington County:
• Install temporary traffic control and erosion control.
• Construct bridge on Turk Road over West Fork Dairy Creek.
100762 - NW Turk Road Bridge Replacement (#671374) Powered by ProcureNow
• Construct roadway approaches, driveways, and guardrail.
• Perform additional and Incidental Work as called for by the Specifications and Plans.
The Project cost range is $1,000,000 - $2,000,000.
II.B 2.2. Contact Information
Kira Furby Engineering Associate 1400 SW Walnut St.
MS 18
Hillsboro, OR 97123 Email: kira_furby@co.washington.or.us Phone: (503) 969-7990 Department:
LUT-CPS
II.C 2.3. Timeline
Bid Advertisement Date March 30, 2026
Question Submission Deadline April 10, 2026, 5:00pm
Bid Opening Date April 15, 2026, 1:00pm
III. 3. Invitation To Bid
III.A 3.1. The Project
The project name is: 100762 - NW Turk Road Bridge Replacement (#671374)
III.B 3.2. Pre-Bid Meeting
The County will not hold a pre-bid meeting for this project.
III.C 3.3. Bids
Bids will be received electronically via the County's OpenGov Procurement Portal before 1:00 pm on Wednesday, April 15, 2026, after which bids will be opened, and publicly read aloud via video conference on Microsoft Teams. A link to the meeting will be provided on the OpenGov website.
All interested parties are invited to attend. Bids received after the above stated time will not be accepted. Because internet connections can be slow or unreliable, the bidder is solely mailto:kira_furby@co.washington.or.us tel:(503)969-7990
100762 - NW Turk Road Bridge Replacement (#671374) Powered by ProcureNow responsible for completing the electronic bid response ahead of the deadline date, regardless of bidder's ability to access the OpenGov online portal at the time of deadline.
Bids must include:
• A residency statement as defined in ORS 279C.365.
• A bid bond on the County's Bid Guaranty form, irrevocable letter of credit issued by an insured institution as defined in ORS 706.008, certified check, or cashier's check, of at least ten percent (10%) of the total bid.
Bids may be rejected by the County for non-compliance with prescribed public bidding procedures and requirements, and for good cause, upon a finding that it is in the public interest to do so.
III.D 3.4. Bid Documents
Bid documents will be available on Monday, March 30, 2026.
Bid documents may be obtained only through the OpenGov website, at https://procurement.opengov.com/portal/washington-county-or, free of charge. No paper copies of Bid Documents will be made available for prospective bidders.
Addenda, Plans Holders List, Preliminary Bid Results, and Notice of Intent to Award, will be posted on the OpenGov website. Addenda will ONLY be made available on the OpenGov website.
III.E 3.5. Bidders
Bidders are solely responsible for ensuring actual receipt of the bid by Washington County DLUT.
Bidders must be prequalified by the Oregon Department of Transportation and licensed by the Oregon Construction Contractor's Board pursuant to ORS 701.026, effective on or before date and time of the bid opening.
Bidders must use bid and bid guaranty forms (if electing to use a bid bond) furnished by the county in these bid documents. Otherwise, the bid may be rejected as non-responsive.
Bidders must conform to the requirements of these bid documents and related, applicable laws.
Bidders shall be solely responsible to check for and download all addenda, if any, from the OpenGov web site prior to bidding.
Bidders must sign all Bid Forms, and in doing so agree to comply with the statement in the Bid Form regarding compliance with the provisions of ORS 279C.840 or 40 U.S.C. 276a "Workers on Public Works to be Paid Not Less Than Prevailing Rate of Wage".
Bidders must complete and submit the First-tier Subcontractors Disclosure Form provided, either with the bid, or using a separate, linked solicitation on the OpenGov site. This form shall be submitted no later than two work hours after the time bids are due, per 00120.40(f). First-Tier Subcontractors Disclosure Forms submitted via email will not be accepted.
Licensing per ORS 468A.720 (working with asbestos) is not required for this project.
100762 - NW Turk Road Bridge Replacement (#671374) Powered by ProcureNow
III.F 3.6. The County
The County reserves the right to waive any irregularities or in-formalities.
III.G 3.7. Plan Holder’s List and Bid Results
Information regarding plan holder lists and bid results will only be available on the County's OpenGov Procurement Portal.
III.H 3.8. Questions
Submit questions only in writing on the County's OpenGov Procurement Portal with the Question/Answer feature on the project page.
Replies to these questions will be posted on the County portal as well.
PROJECT STAFF WILL ONLY RESPOND TO QUESTIONS SUBMITTED IN WRITING.
III.I 3.9. Published
Monday, March 30, 2026
OpenGov Procurement
Daily Journal of Commerce
OregonBuys
IV. 4. Program Compliance Requirements
IV.A 4.1. Certified Business Utilization Reporting - B2G Now
A. The County has implemented an online Certified Business utilization tracking system. This web-based software system facilitates Certified Business utilization reporting for all construction, architecture, engineering, and related services contractors doing business with Washington County. The system is designed to streamline and automate subcontractor utilization reporting requirements and includes the following key features:
1. Automated tracking of Certified Business utilization
2. Online verification of subcontractor payments
3. Automated communication with contractors via email regarding reporting status
B. Prime contractors will be required to use the online system to submit monthly subcontractor payment data. Subcontractors will be required to use the online system to verify payments received from prime contractors. Subcontractors will also identify any further tiers of subcontractors and submit monthly subcontractor payment data if
100762 - NW Turk Road Bridge Replacement (#671374) Powered by ProcureNow applicable. Prime contractors and subcontractors must access the system at least monthly, when prompted, to manage contract information and provide the required subcontractor and payment information. Prime contractors are responsible for ensuring that all subcontractors comply with the utilization tracking requirements. The Certified Business utilization tracking system is online at https://washcopurch.mwdbe.com. Access information will be provided to each contractor after contract award.
C. The County anticipates that the time commitment to comply with this requirement would be approximately thirty minutes.
IV.B 4.2. Clean Air Construction – Fleet Registration and Compliance Determination
A. In February of 2020, Washington County adopted the Clean Air Construction (CAC) Standard (www.portlandoregon.gov/cac). As such, all diesel nonroad equipment over 25hp and all diesel concrete mixers and dump trucks used on this project will need to meet the CAC requirements.
B. Best Available Control Technology (BACT) approach means that for that specific vehicle or piece of equipment, that among all potential options, the emission control device that maximizes diesel particulate matter reductions was installed. A “DPF or equivalent” emission control device is defined as capturing diesel particulate matter at a level of 85% or greater.
C. Prior to the submission deadline, the bidder/proposer shall register their CAC-applicable construction nonroad equipment and on-road vehicles in The Yard, https:/heyard.clean-air.app/, the CAC equipment registration and compliance portal. Details on how to register can be found online at: [enter link]. Failure to register may result in bid/proposal rejection. Registration involves knowing the following about each piece of applicable equipment/vehicle in your fleet:
1. Equipment Type (e.g. excavator, dozer, loader)
2. Fuel Type (diesel, electric, gasoline, hybrid electric, propane, etc.)
3. On-Road or Nonroad
4. Make
5. Model Year
6. Horsepower
7. For diesel engines: Any aftermarket emissions control devices installed? (if yes, indicate type of control device, e.g. DOC, DPF, etc.).
D. After the Notice of Intent to Award is posted, the successful Contractor will be invited to assign all applicable subcontractors and suppliers (including any equipment rental firms) to the project through The Yard. Subcontractors and suppliers will need to register the equipment and vehicles from their fleets in The Yard. At this time, the successful http://www.portlandoregon.gov/cac https://theyard.clean-air.app/
100762 - NW Turk Road Bridge Replacement (#671374) Powered by ProcureNow
Contractor and their applicable subcontractors and suppliers may request an exemption for a specific piece of equipment or vehicle if it meets one of the following exemption request criteria:
1. After following a BACT approach, the required emission control device would obscure operator lines of sight or otherwise impact worker safety or the equipment is not able to be retrofit with a verified emission control device; or
2. No compliant rental equipment is available within 100 miles of the job site; or
3. After following a BACT approach, the Contractor can demonstrate that due to the uniqueness of the equipment/vehicle or similar special circumstances, it is not reasonable to comply with the diesel engine requirement for a specific piece of equipment/vehicle.
4. Exemptions may also be granted during the course of the project when a noncompliant piece of equipment/vehicle is required to respond to an emergency. In such cases, the Contractor shall notify the Owner’s Representative and request approval for an exemption via The Yard.
Such exemptions shall be valid only for the duration of the emergency, repair timeframe, or similar temporary timeframe as applicable.
E. Approved exemptions shall be valid for the calendar year, at which time contractors may request to extend exemptions. Requests shall be reviewed by the CAC Program and will either be retired or renewed for another calendar year.
F. Through this process, the Contractor shall certify that all applicable equipment and vehicles used on the project are in compliance with the Clean Air Construction requirements or have a valid exemption.
G. The Yard can be accessed here https:/theyard.clean-air.app/
IV.C 4.3. Clean Air Construction – Continual Compliance, On-Site Inspections, and Violations
A. The Clean Air Construction requirements progress over time, and the Contractor shall ensure applicable equipment and vehicles used on the project are in compliance with the current requirement throughout the course of the project.
B. During the course of the project, the County may conduct an on-site inspection of CAC-applicable equipment and vehicles to confirm accuracy of fleet information submitted to The Yard.
100762 - NW Turk Road Bridge Replacement (#671374) Powered by ProcureNow
C. Should the Owner’s Representative or authorized third-party discover, during the course of the project, that the Contractor, Subcontractor, or Supplier is violating the CAC engine requirements, the Owner’s Representative may issue a Notice to Cure to the Contractor.
The Notice to Cure will state the specifics of the violation and the timeframe within which the Contractor has to remedy the violation. The remedy timeframe shall not exceed seven (7) calendar days. If the Contractor fails to remedy the violation per the Notice to Cure, the Owner’s Representative may issue a Stop Work notice, authorizing the stoppage of work until the violation is remedied.
V. 5. Bidder Questionnaire
V.A 1. Bid Form
V.A.1 1.1. Resident Bidder* The Bidder hereby represents that they are a resident bidder per ORS 279A.120 and ORS 279C.365. A "resident bidder" means a bidder that has paid unemployment taxes or income taxes in this state during the 12 calendar months immediately preceding submission of the bid, has a business address in this state, and has stated in the bid whether the Bidder is a "resident bidder".
☐ Yes
☐ No *Response required
V.A.2 1.2. Construction Contractors Board* The Bidder is licensed by the Construction Contractor's Board in accordance with ORS 701.026.
☐ Please confirm *Response required
V.A.3 1.3. ODOT Prequalification* The Bidder acknowledges that it shall be prequalified to bid in this class of work by Oregon Department of Transportation (ODOT) per 00120.00
☐ Please confirm *Response required
V.A.4 1.4. Bid Guaranty Form and Bid Bond* The Bidder has completed and signed the Washington County Bid Guaranty Form provided under "Attachments", attached an electronic copy, and mailed the original by the Bid Opening Date. Bids not accompanied by the Washington County Bid Guaranty Form may be deemed non-responsive and rejected.
100762 - NW Turk Road Bridge Replacement (#671374) Powered by ProcureNow
In addition, the Bidder has mailed and will attach, with the Bid, a copy of a bid security in the form of a certified check, cashier's check, or bid bond in the sum of at least ten (10) percent of the total bid, payable to Washington County, Oregon, which is to be forfeited as liquidated damages in accordance with 00130.60. The original Bid Bond form, with original signatures and the Surety's seal affixed, shall be submitted by mail, or other delivery service per 00120.40(e-2).
*Response required
V.A.5 1.5. First-Tier Subcontractors Disclosure Form Complete and submit the First-tier Subcontractors Disclosure Form provided under "Attachments". This form may be submitted using the upload box below prior to the bid closing time, OR
Submit via the corresponding linked solicitation on the OpenGov website. The linked solicitation will be activated at the Bid Closing Time and will only be accessible for two hours following the bid opening time. An invitation to the linked solicitation will be sent to the email address used to submit this bid. The linked solicitation will be titled with the project name along with the words “First‐Tier Subcontractors Disclosure Form Submittal”.
First-Tier Subcontractors Disclosure Forms MUST be submitted via OpenGov using one of the two above options. The County will NOT accept First-Tier Subcontractors Disclosure Forms via email, fax, phone, hand-delivery, mail, or parcel service.
V.B 2. Bidder Agreements Russell Knoebel
Division Manager
Washington County Department of Land Use and Transportation
Capital Project Services Division
1400 SW Walnut Street
Hillsboro OR 97123.
V.B.1 2.1. The undersigned, hereinafter called the Bidder, declares:* That the only person or parties interested in this bid are those named herein; that this bid is, in all respects, fair and without fraud; that it is made without collusion with any official of Washington County, Oregon; and that the bid is made without any connection or collusion with any person making another bid on this contract.
☐ Please confirm *Response required
100762 - NW Turk Road Bridge Replacement (#671374) Powered by ProcureNow
V.B.2 2.2. The Bidder Further Declares:* That the Bidder has read and thoroughly understands the bid documents governing the work embraced in this improvement and the method by which payment will be made for said work;
that the Bidder has visited the site and made such investigation as is necessary to determine the character of the materials and conditions to be encountered in the work; that if this bid is accepted, the Bidder will contract with Washington County, Oregon, for the construction of the proposed improvement in a form of contract herein outlined, and provide the necessary equipment, materials, tools, apparatus, and labor, as specified in conformance with the requirements of the contract, and at the prices established by this Agreement.
☐ Please confirm *Response required
V.B.3 2.3. The Bidder further agrees:* That the Bidder has exercised its own judgment regarding the interpretation of subsurface information and has utilized all data which it believes pertinent from the Engineer, County, and other sources in arriving at its conclusion.
☐ Please confirm *Response required
V.B.4 2.4. The Bidder agrees:* To do any extra work and furnish other materials which cannot properly be classified under bid items, and to accept as full compensation therefore, such prices as may be determined according to the provisions of the Contract. See 00140.60 "Extra Work".
☐ Please confirm *Response required
V.B.5 2.5. The Bidder agrees:* That this bid is firm and shall not be withdrawn or revoked by the Bidder for a period of thirty
(30) calendar days from the date of the bid opening and that within ten (10) calendar days from the date of the "Notice of Award" of this bid, to execute the Agreement, and to furnish Washington County with satisfactory performance and payment bonds in the sum of the total amount of the contract guaranteeing the faithful performance of the work and payment of all bills.
☐ Please confirm *Response required
V.B.6 2.6. The Bidder agrees:* To begin work within ten (10) days after the date of the County's "First Notice Notification" and to complete work in all respects within the contract time specified herein. See 00180.50.
*Response required
100762 - NW Turk Road Bridge Replacement (#671374) Powered by ProcureNow
V.B.7 2.7. The Bidder agrees:* In compliance with ORS 279C.840 and as part of this bid, the Bidder herein agrees that it shall be a condition of its bonds that in performing this contract it shall pay and cause to be paid not less than the prevailing rate of wages as of the date of advertisement for this bid to each and every worker who may be employed in and about the performance of this contract. If the County determines at any time that the prevailing rate of wages has not been or is not being paid as required by the contract, the County may retain from the monies due to the Contractor an amount sufficient to make up the difference between the wages actually paid and the prevailing rate of wages, and may also cancel this contract.
☐ Please confirm *Response required
V.B.8 2.8. The Bidder agrees:* That all of the applicable provisions of Oregon law relating to public contracts (ORS Chapters 279A and 279C) are, by this reference, incorporated in and made a part of this bid.
☐ Please confirm *Response required
V.B.9 2.9. The Bidder agrees:* It is agreed that if the Bidder revokes or withdraws its bid within the 30-day period following the bid opening date or if the Bidder is awarded the contract for the work herein proposed and shall fail or refuse to execute the contract and furnish the specified performance and payment bonds within ten (10) calendar days after the date of the “Notice to Award” of its bid, then, in either of these events, the bid security deposited herewith according to the conditions of this Bid shall be forfeited to and retained by the County as liquidated damages in accordance with 00130.60; and it is agreed that the said sum is a fair measure of the amount of damages the County will sustain in case the Bidder shall so withdraw its bid or fail or refuse to execute the contract for the said work and to furnish the performance and payment bonds as specified in the Contract Documents. Bid security in the form of a cashier's or certified check drawn on a lending institution of Oregon shall be subject to the same requirements as a bid bond.
☐ Please confirm *Response required
V.B.10 2.10. The Bidder agrees:* In accordance with the provisions of the 2024 edition of the "Oregon Standard Specifications for Construction", as modified by these Bid Documents, the undersigned Bidder submits the Bid Schedule (Pricing Table) with the understanding that unit rates and prices are independent of quantities and that the County reserves the right to increase, decrease, or completely eliminate quantities as set forth in 00120.20. Also, the Bidder offers to do the work, whether quantities are changed (increased or decreased) in accordance with 00195.20, or not changed, at the unit rate or price stated in the Bid Schedule (Pricing Table).
100762 - NW Turk Road Bridge Replacement (#671374) Powered by ProcureNow
*Response required
V.C 3. LIMITING STATEMENTS:
THE UNDERSIGNED AGREES If you desire to limit the number of contracts to be awarded to your firm at this opening of bids as permitted by subsection 00120.50 of the specifications, please complete one of the following limiting statements:
V.C.1 3.1. No. 1:
This bid is conditioned upon my (our) not being awarded more than _____ of the contracts on which I (we) have bid at this opening of bids.
☐ N/A
☐ 1
☐ 2
☐ 3
V.C.2 3.2. No. 2 This bid is conditioned upon my (our) not being awarded contracts at this opening of bids for an aggregate total amount in excess of the dollar amount below:
V.D 4. Signature Page
V.D.1 4.1. Signature Page* Complete, print, sign, and upload the Signature Page provided under "Attachments" using the upload box below.
The original must be mailed to the Walnut Street office on or before the bid opening date.
*Response required
V.E 5. Optional
V.E.1 5.1. How did you hear about this Bid?
Select all that apply
☐ Washington County's OpenGov portal, or other OpenGov notification
☐ OregonBuys
☐ DJC Oregon, Portland Tribune, or other printed media
☐ Plan Room, Planning Center, etc.
☐ Washington County Website
☐ Link sent directly to my email
☐ Word of mouth
100762 - NW Turk Road Bridge Replacement (#671374) Powered by ProcureNow
VI. 6. Bid Schedule
BID SCHEDULE
Line Item Description Quantity Unit of Measure
Unit Cost Total
EXTRA WORK (00100)
1 Miscellaneous Field Changes (00196) 100,000 AA $1.00
MOBILIZATION AND TRAFFIC CONTROL (00200)
2 Mobilization (00210) 1 LS
3 Temporary Protection and Direction of Traffic (00221)
1 LS
4 Temporary Signs (00222) 293 SF
5 Flaggers (00223) (minimum bid $82.00)
160 HR
6 Temporary Barricades, Type III (00224) 4 EA
7 Temporary Barrier (00226) 50 FT
8 Erosion Control (00280) 1 LS
9 Plastic Sheeting (00280) 50 SY
10 Matting, Type C (00280) 420 SY
11 Check Dam, Type 3 (00280) 6 EA
12 Sediment Barrier, Type 8 (00280) 910 FT
13 Pollution Control Plan (00290) 1 LS
14 Work Containment Plan (00290) 1 LS
ROADWORK (00300)
15 Construction Survey Work (00305) 1 LS
16 Removal of Structures and Obstructions (00310)
1 LS
17 Clearing and Grubbing (00320) 1 LS
18 General Excavation (00330) 149 CY
19 18 Inch Subgrade Stabilization (00331) 25 SY
100762 - NW Turk Road Bridge Replacement (#671374) Powered by ProcureNow
Line Item Description Quantity Unit of Measure
Unit Cost Total
20 Riprap Geotextile, Type 2 (00350) 160 SY
21 Subgrade Geotextile (00350) 780 SY
22 Loose Riprap Mixture, Class 50 (00390)
4 CY
23 Loose Riprap Mixture, Class 200 (00390)
98 CY
24 Riprap Basins (00390) 1 EA
DRAINAGE AND SEWERS (00400)
25 24 Inch Culvert Pipe, 5 ft Depth (00445)
10.5 FT
26 Sloped End Sections, 24 Inch (00445) 1 EA
27 Concrete Closure Collars (00445) 1 EA
28 Roof or Field Drain Connections (00445)
25 FT
29 Drainage Curbs (00480) 158 FT
BRIDGES (00500)
30 Bridge Removal Work (00501) 1 LS
31 Structure Excavation (00510) 1 LS
32 Granular Structure Backfill (00510) 1 LS
33 Furnish Pile Driving Equipment (00520)
1 LS
34 Furnish 18"x0.625" Pipe Piles (00520) 730 FT
35 Drive 18"x0.625" Pipe Piles (00520) 10 EA
36 18"x0.625" Steel Pipe Pile Splices (00520)
20 EA
37 Reinforcement, Grade 60 (00530) 1 LS
38 General Structural Concrete, Class 4000 (00540)
1 LS
100762 - NW Turk Road Bridge Replacement (#671374) Powered by ProcureNow
Line Item Description Quantity Unit of Measure
Unit Cost Total
39 30 inch Precast Prestressed Slab Beams (00550)
455 FT
40 Fall Arrest System (00564) 1 LS
41 Poured Joint Seal (00585) 1 LS
42 Steel 2-Tube Side Mount Rail (00587) 1 LS
43 Retaining Wall, Sheet Pile, Wall "A" (00596D)
1 LS
44 Retaining Wall, Sheet Pile, Wall "B" (00596D)
1 LS
BASES (00600)
45 Aggregate Base (00641) 253 CY
WEARING SURFACES (00700)
46 Level 2, 1/2 inch ACP Mixture (00744) 233 TN
47 Extra for Asphalt Approaches (00749) 640 SF
PERMANENT TRAFFIC SAFETY AND GUIDANCE DEVICES (00800)
48 Midwest Guardrail System, Type 2A (00810)
50 FT
49 Midwest Guardrail System, Type 3 (00810)
25 FT
50 Guardrail End Pieces, Type B (00810) 2 EA
51 Guardrail Anchors, Type 1 Modified (00810)
4 EA
52 Guardrail Transition (00810) 4 EA
53 Guardrail Terminals, Non-Flared (00810)
2 EA
54 Bridge Identification Markers (00842) 2 EA
PERMANENT TRAFFIC CONTROL AND ILLUMINATION SYSTEMS (00900)
55 Remove Existing Signs (00905) 1 LS
RIGHT OF WAY DEVELOPMENT AND CONTROL (01000)
100762 - NW Turk Road Bridge Replacement (#671374) Powered by ProcureNow
Line Item Description Quantity Unit of Measure
Unit Cost Total
56 Permanent Seeding (01030) 460 SY
57 Single Mailbox Supports (01070) 1 EA
TOTAL
File details come from the government source that posted it. Updated .