10-Scope of Work.doc

DOC document 51 KB Posted

Attached to
26B-049 Belleview Heights Estates Unit 8 (SE 44th Avenue)
Solicitation number
26-049
Issued by
Marion County, Florida

About this file

This Scope of Work document pertains to a state and local contract opportunity in Florida for the construction of roadway infrastructure in Belleview Heights Estates Unit 8. The project involves the new construction of 0.11 miles of 20-foot-wide paved roadway with roadside swales on unimproved SE 44th Avenue. The scope of work includes clearing and grubbing of the right of way, installation of stabilized subgrade and limerock base, excavation and grading of drainage swales, installation of swaled concrete driveway aprons, thermoplastic striping, and stabilization of all areas disturbed during construction. The contract will be effective for 90 days from the date of the Notice to Proceed, which will not be issued until all required documentation is received by the County. All contract work except thermoplastic striping must be completed within 60 days, with the final 30 days reserved for placement of thermoplastic striping only. Liquidated damages will be imposed for any incomplete contract items remaining after 90 days, excluding thermoplastic striping. Prospective contractors are highly recommended to visit the project work location prior to submitting a bid.

No specific information regarding pricing terms, set asides, incumbents, funding sources, or other financial details is provided in this Scope of Work document.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Scope of Work

DESCRIPTION OF PROJECT

This project involves the new construction of 0.11 miles of 20’ wide paved roadway with roadside swales on unimproved Belleview Heights Estates Unit 8 (SE 44th Avenue). The project includes clearing and grubbing of the right of way, stabilized subgrade and limerock base. It also includes excavation and grading of drainage swales, installing of swaled concrete driveway aprons, thermoplastic striping and stabilizing all areas disturbed during construction.

CONTRACT TERM

This contract will be in effect for 90 days from the date of the NOTICE TO PROCEED. The NOTICE TO PROCEED will not be issued until all required documentation is received by the COUNTY. The last 30 days of the contract is to accommodate the placement of thermoplastic striping only. All other contract related work must be completed within 60 days. Liquidated damages will begin to be imposed if there are any outstanding contract items remaining incomplete except for thermoplastic striping after 90 days.

PRIOR TO SUBMITTING BID

It is in the CONTRACTOR’s best interest and highly recommended for CONTRACTOR to visit the project work location before submitting a bid.