This is a Pay Application and Certificate for Payment template used by Marion County, Florida for construction projects. The template standardizes the payment certification process between contractors and the county's Construction Division, establishing a formal mechanism for contractors to request progress payments and for the Department Project Manager to certify earned amounts. The document requires contractors to certify that work has been completed in accordance with contract documents, all previous invoices have been paid, and current payment is due. It accommodates change orders, tracks retainage at 5 percent of both completed work and stored materials, and includes space for documentation of original contract sums, cumulative changes, total earned amounts, previous payments received, and remaining balance to finish.
The payment application requires the contractor to provide project identification details, bid numbers, purchase order numbers, contract dates, and application dates while establishing certification requirements for both the contractor and the county's project manager. The template calculates payment due by subtracting previous certificates for payment and retainage from total completed and stored work to date. A change order summary section tracks monthly additions and deductions approved by the owner, with net changes reflected in the current payment certification. The document includes notarization requirements for the contractor's certification and establishes that the certification is non-negotiable and payable only to the named contractor, without prejudice to any rights of either party under the contract.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pay App - Cover
APPLICATION AND CERTIFICATE FOR PAYMENT
| TO OWNER: | PROJECT: | APPLICATION #: | number | Distribution to: | |
| Marion County BOCC - | Project Name | APPLICATION DATE: | date | Owner: | |
| Addess | PERIOD TO: | time frame | Construction Division: | X | |
| Address | BID NUMBER: | list full number | Architect/Engineer: | ||
| FROM CONTRACTOR: | MC CONSTRUCTION DIVISION: | PO #: | list full number | Contractor: | |
| Name | Attn: | CONTRACT DATE: | BCC approved date | Other: | |
| Address | |||||
| Address |
| CONTRACTOR'S APPLICATION FOR PAYMENT | The undersigned Contractor certifies that to the best of the Contractor's knowledge, information and belief the Work covered by this Application for Payment has been completed in accordance with the Contract Documents, that all amounts have been paid by the Contractor for Work for which previous Certificates for Payment were issued and payments received from the Owner, and that current payment shown therein is now due. |
| Application is made for payment, as shown below, in connection with the Contract. | |
| Continuation Sheet is attached. |
1. ORIGINAL CONTRACT SUM……………………………………………………………….. 0.00 CONTRACTOR:
| 2. Net change by Change Orders…………………………………………………………… | $0.00 | By: | Date: | |||||
| Name | ||||||||
| 3. CONTRACT SUM TO DATE (Line 1 +/- 2)……………………………………………… | $ - 0 | |||||||
| State of: | Florida | |||||||
| 4. TOTAL COMPLETED & STORED TO DATE……………………………………………… | $ - 0 | County of: | Marion | |||||
| (Column M on Continuation Sheet) | Subscribed and sworn to before | |||||||
| me this | day of | |||||||
| 5. RETAINAGE | ||||||||
| a. | 5.0% | of Completed Work | $ - 0 | Notary Public: | ||||
| b. | 5.0% | of Stored Material | $ - 0 | My Commission expires: |
| Total Retainage Line (5a + 5b)……………………………………………………. | $ - 0 | CERTIFICATE FOR PAYMENT | |
| In accordance with Contract Documents, based on on-site observations and the data comprising this application, the Department Project Manager certifies to the Owner that to the best of his/her knowledge, information and belief the Work has progressed as indicated, the quality of the Work is in accordance with the Contract Documents, and the Contractor is entitled to payment of the AMOUNT CERTIFIED. | |||
| 6. TOTAL EARNED LESS RETAINAGE……………………………………………………….. | $ - 0 | ||
| (Line 4 less Line 5 Total) |
| 7. LESS PREVIOUS CERTIFICATES FOR PAYMENT…………………………………….. | $ - 0 | AMOUNT CERTIFIED…………………………………………………………………………. | $0.00 | |
| (Line 6 from prior Certificate) | ||||
| (Attach explanation if amount certified differs from the amount applied for. Initial all figures on this application and on the Continuation Sheet that are changed to conform to the amount certified.) | ||||
| 8. CURRENT PAYMENT DUE………………………………………………………………….. | $ - 0 |
| 9. BALANCE TO FINISH, INCLUDING RETAINAGE | Name of Department Project Manager | ||
| (Line 3 less Line 6) | $ - 0 |
| CHANGE ORDER SUMMARY | ADDITIONS | DEDUCTIONS | By: | Date: |
| Total changes approved in previous months by Owner | $ - 0 | $ - 0 | ||
| Total approved this Month | $ - 0 | $ - 0 | This Certificate is not negotiable. The AMOUNT CERTIFIED is payable only to the Contractor named herein. Issuance, payment and acceptance of payment are without prejudice to any rights of the Owner of Contractor under this Contract. | |
| TOTALS | $ - 0 | $ - 0 | ||
| NET CHANGES by Change Order | $0.00 |
Page &P of &N