10-Maynard Jackson High School- Fee Sheet.pdf

PDF 122 KB Posted

Attached to
Maynard Jackson HS Building Addition and Site Improvements
Solicitation number
26-040126-53-P-AW
Issued by
Fulton County, Georgia

About this file

This is a fee sheet for a Construction Manager at Risk (CMAR) engagement with the Atlanta Independent School System for the Maynard Jackson High School Building Addition and Site Improvements project in Georgia. The project encompasses preconstruction and construction services. The preconstruction phase includes four distinct tasks: Schematic Design due June 5, 2026; Design Development due June 15, 2026; 100% Construction Documents due July 10, 2026; and Bidding/GMP, Submittal/GMP, and Negotiations/Award of GMP Amendment due August 10, 2026. All dates are tentative. The contract is structured to proceed into a construction phase following the preconstruction services.

The preconstruction services are compensated on a lump sum basis with $7,500 allocated per task, totaling $30,000 for the preconstruction phase. The Construction Manager's Fee for the construction phase is to be negotiated and expressed as either a percentage of general conditions or as a percentage fee, with the specific rates to be determined. The fee sheet indicates this is contract number 26-040126-53-P-AW and identifies the FIRM NAME and DATE fields as requiring completion by the responding contractor.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FEE SHEET

Construction Manager at – Risk

26-040126-53-P-AW -Maynard Jackson HS Building Addition and Site Improvements

FIRM NAME:

DATE:

PRE- CONSTRUCTION SERVICES

As compensation for pre-construction services, the CM shall receive a fee as negotiated below:

LUMP SUM

FEE

(PER TASK)

COMPLETION/

DUE DATES

1. Schematic Design (NTP DATE) $7,500.00 6/05/2026 (Tentative)

2. Design Development. $7,500.00 6/15/2026 (Tentative)

3. 100% Construction Documents $7,500.00 7/10/2026 (Tentative)

4. Bidding / GMP, Submittal / GMP, Negotiations / Award of GMP

Amendment $7,500.00 8/10/2026 (Tentative)

TOTAL PRE- CONSTRUCTION FEE $30,000.00

CONSTRUCTION

PHASE

6. Construction Manager’s Fee:

a. percent of general conditions

b. percent fee

PPAB 7401255v1