10-Liquidated Damages Form.pdf
PDF 84 KB Posted
- Attached to
- Police Station Improvements
- Solicitation number
- ITB No. 2026-010
- Issued by
- Palm Beach County, Florida
About this file
This is a Liquidated Damages Form from the Town of Palm Beach, Florida, establishing financial penalty terms for contractor performance on the Police Station Improvements project. The form documents the Town's requirement that work achieve timely completion, with time expressly identified as essential to the contract. The contractor and contractor's surety acknowledge the difficulty in calculating actual damages from delayed completion and agree to pay liquidated damages according to a schedule adopted from the Florida Department of Transportation (paragraph 8-10). Liquidated damages accrue daily for each calendar day after the scheduled completion date, including any time extensions granted through approved written change orders, until the work is fully completed. If the contractor is terminated for default before completion, liquidated damages continue to accrue and are charged against the contractor until the work is completed by another party or remedied.
The form requires the contractor's authorized representative to sign and confirm understanding of and compliance with the liquidated damages terms prior to contract execution. The document provides space for company name, authorized signatory name, date, and signature to formalize the contractor's acknowledgment of these penalty provisions. By signing, the contractor demonstrates awareness that failure to meet the completion schedule will result in daily financial penalties assessed against the contractor and bonding company, establishing a clear financial incentive for timely project delivery on the Town of Palm Beach Police Station renovation and expansion work.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TOWN OF PALM BEACH
Liquidated Damages Form
Contractor is aware of Town's requirement that the Work achieve timely Completion, time being of the essence. Town and Contractor recognize and hereby acknowledge the difficulty and uncertainty of computing the damages that would be realized by Town in the event the Completion is not timely achieved. It is therefore agreed by Town and Contractor, that the Contractor and the Contractor's surety, shall be liable to and shall pay Town liquidated damages in the amount per attached list - Town adopted Florida Department of Transportation schedule, paragraph 8-10, see attached - for each calendar day after the date on which Completion was to have been achieved (including any Time Extension in approved, written Change Order(s) until Completion of the Work is achieved. In the event Contractor is terminated by reason of default prior to Completion being achieved, any liquidated damages shall continue to accrue and be charged against Contractor until Completion is achieved.
I hereby confirm that our company understands and will comply with Liquidated Damages Term above:
Company Name: Name:
Date: Authorized Signature: