10-IFB26010 Division 0.pdf

PDF 1 MB Posted

Attached to
Hopkins Park Service Area Septic to Sewer – a HUD Funded Construction Project
Solicitation number
IFB-26-010
Issued by
Polk County, Florida

About this file

This Invitation for Bids (IFB-26-010) is issued by the Tohopekaliga Water Authority (Toho), an independent special district in Florida, for construction services related to the Hopkins Park Service Area Septic to Sewer project, a HUD-funded initiative. The project involves constructing approximately 965 linear feet of 4-inch PVC force main, 1,175 linear feet of 8-inch PVC gravity main, 51 linear feet of 8-inch HDPE gravity main, six sanitary sewer manholes, asphalt roadway open cuts and repairs with mill and resurfacing, concrete curb removal and replacement, new residential gravity lateral services, septic tank decommissioning, and a duplex submersible lift station with associated site work, electrical, and instrumentation. The question deadline is March 6, 2026 at 5:00 PM, and the submittal deadline is March 26, 2026 at 2:00 PM. Bids must be submitted electronically through the Bonfire portal. The contract time for substantial completion is 240 days after the Notice to Proceed, with an additional 30 days allowed for final completion. Liquidated damages are assessed at $500 per calendar day for failure to achieve substantial completion within the contract time.

The contract will be awarded on a lump-sum basis with unit price work as specified in the bid form. A 5 percent bid security is required, payable to Toho. The project is funded entirely by federal funds from the U.S. Department of Housing and Urban Development under Assistance Listing Number 14.251 (Economic Development Initiative, Community Project Funding) with Federal Award ID B-23-CP-FL-0430, with the City of St. Cloud serving as the pass-through entity. The contractor must comply with HUD requirements, including Section 3 of the Housing and Urban Development Act of 1968 regarding employment opportunities for low- and very low-income persons, environmental review and historic preservation requirements, and various federal certifications regarding debarment, drug-free workplace, and trafficking in persons. The successful bidder will be required to furnish performance and payment bonds equal to the contract price and maintain comprehensive insurance coverage including general liability, automobile liability, and workers' compensation. The contract is subject to Florida Statutes provisions regarding E-Verify, public entity crimes, discriminatory vendors, antitrust violators, and scrutinized companies.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

V.20250303.01

INVITATION FOR BIDS

for Construction Services IFB No.: IFB-26-010 Issue Date: February 22, 2026 Project Title: Hopkins Park Service Area Septic to Sewer – a HUD

Funded Construction Project

DIVISION 0, 1, 2, 3, 4, 5, 7, 9, 11, 13, 15, & 16

BIDDING, CONTRACT REQUIREMENTS and

PROJECT SPECIFICATIONS

TABLE OF CONTENTS

DIVISION 0 BIDDING AND CONTRACT REQUIREMENTS PAGE

00030 Invitation for Bid 00030-1 00100 Instruction to Bidders 00100-1 00300 Construction Bid Form 00300-1 00330 Bid Form Attachments and Index 00300-1 00500 Contract 00500-1 00610 Performance Bond 00610-1 00620 Payment Bond 00620-1 00700 General Conditions 00700-1 00800 Supplementary Conditions 00800-1 00910 Omitted 00910-1 00920 Notice to Proceed 00920-1 00930 Change Order Form 00930-1 00940 Application for Payment Form 00940-1 00950 Request for Information Form 00950-1 00965 Schedule of Values 00965-1 00980 Certificate of Substantial Completion 00980-1 00990 Certificate of Final Inspection 00990-1 00995 Contractor's Release 00995-1

DIVISION 1 GENERAL REQUIREMENTS PAGE

01000 Index of Drawings 01000-1 01010 Summary of Work 01010-1 01020 Geotechnical Data 01020-1 01041 Project Coordination 01041-1 01050 Field Engineering & Controls 01050-1 01070 Abbreviations 01070-1 01150 Measurement and Payment 01150-1 01152 Applications for Progress Payments 01152-1 01200 Project Meetings 01200-1 01310 Project Schedule Using CPM Network Analysis 01310-1 01340 Shop Drawings and Submittals 01340-1 01370 Schedule of Values 01370-1 01380 Construction Photographs and Preconstruction Audio-Video 01380-1 01410 Testing and Testing Laboratory Services 01410-1 01500 Construction Facilities and Temporary Controls 01500-1 01568 Temporary Erosion and Sedimentation Control 01568-1 01570 Traffic Regulation 01570-1 01580 Project Signs 01580-1 01600 Materials and Equipment 01600-1 01650 Pump Station Start-up and Testing 01650-1 01700 Contract Closeout 01700-1 01710 Project Housekeeping 01710-1 01720 Project Record Documents 01720-1 01740 Warranties and Bonds 01740-1

DIVISION 2 SITE WORK

02110 Clearing, Grubbing, and Stripping 02110-1 02140 Dewatering 02140-1 02210 Site Grading 02210-1 02212 Finish Grading 02212-1 02220 Excavating, Backfilling and Compacting 02220-1 02220-A Compaction and Backfill Schedule for Structures 02220A-1 02220-B Backfill Schedule for Gravity and Pressure Piping 02220B-1 02232 Limerock Base Course 02232-1 02269 Temporary Erosion Control 02269-1 02513 Asphaltic Concrete Pavement, Base, and Stabilized Subbase (FDOT) 02513-1 02530 Gravity Sanitary Wastewater Collection Systems 02530-1 02535 Wastewater Force Main Systems 02535-1 02570 Stabilized Subgrade 02570-1 02574 Pavement Removal and Replacement 02574-1 02784 Chain Link Fences and Gates 02784-1 02822 Loaming and Sodding 02822-1

DIVISION 3 CONCRETE

03051 Leakage Testing of Hydraulic Structures 03050-1 03111 Concrete Formwork 03111-1 03151 Concrete Joints, Water Stops, And Sealants 03151-1 03210 Concrete Reinforcement 03210-1 03300 Concrete 03300-1 03350 Concrete Finishing and Curing 03350-1 03401 Precast Concrete Utility Structures 03401-1 03420 Precast Reinforced Concrete Structures 03420-1

DIVISION 4 MASONRY

04200 Unit Masonry 04200-1

DIVISION 5 METALS

05530 Grating, Cover Plates, and Access Hatches 05530-1

DIVISION 7 THERMAL & MOISTURE PROTECTION

07600 Flashing and Metal Sheet 07600-1

DIVISION 9 COATING AND LINING

09240 Cement Plastering 09240-1 09900 Industrial Coatings 09900-1 09970 Specialty Coatings / Lining Systems for Concrete 09970-1

DIVISION 11 EQUIPMENT

11305 Submersible Pumps and Appurtenances 11305-1 11305-A Pump Station Submersible Pump Schedule 11305-A 11310 Packaged Odor Control System 11310-1

DIVISION 13 INSTRUMENTATION

13410 Basic Instrumentation Requirements 13410-1 13423 Level Measurement 13423-1 13430 Control Panels and Consoles 13430-1

DIVISION 15 MECHANICAL

15050 Process Piping, Fitting, Valves, And Accessories 15050-1

DIVISION 16 ELECTRICAL

16050 Basic Electrical Requirements 16050-1 16060 Grounding 16060-1 16075 Electrical Identification 16075-1 16120 Wires and Cables 16120-1 16130 Raceways 16130-1 16410 Circuit and Motor Disconnects 16410-1 16420 Motor Controllers 16420-1

APPENDICES

Appendix A – Toho Submittal Forms Appendix B – (B.1) HUD Grant Agreement B-23-CP-FL-0430

(B.2) Subrecipient Agreement (B.3) Community Program Funding Contractor Requirements (B.4) FY2023 Economic Development Initiative, CPF Grant Guide

Appendix C – Geotechnical Report Appendix D – List of Materials and Approved Manufacturers Appendix E – Drawings

SECTION 00030

00030-1 for Construction Services IFB No.: IFB-26-010 Issue Date: February 22, 2026 Project Title: Hopkins Park Service Area Septic to Sewer – a HUD

Funded Construction Project

Tohopekaliga Water Authority (“Toho”), an independent special district established pursuant to Chapter 189, Florida Statutes, by special act of the Florida Legislature, hereby issues this Invitation for Bids (“IFB”) from qualified construction firms with the experience to construct a duplex submersible lift station along with new gravity sewer mains, manholes, and discharge force main for the Hopkins Park Service Area Septic to Sewer – a HUD Funded Construction Project (the “Project”). For more information about the Project, please review Divisions 0, 1, 2, 3, 4, 5, 7, 9, 11, 13, 15, & 16 of the Bidding Documents and any attachments thereto.

SOLICITATION SCHEDULE

(Times and Dates Subject to Change by Addenda)

Event Date Time Pre-Bid Conference N/A N/A Question Deadline March 6, 2026 5:00 PM Submittal Deadline March 26, 2026 2:00 PM

Bidders are advised to closely review Article 17: Opening of Bids in Section 00100: Instructions to Bidders of the Bidding Documents for the time, date, and location of Bid Opening.

NOTICE OF ELECTRONIC BID SUBMITTAL REQUIREMENT

Toho Water Authority issues its solicitations electronically through its contracted vendor, Bonfire.

Bidders shall not be permitted to hand-deliver, mail, telephone, fax, or email responses. Bids that are either received after the above-noted Submittal Deadline or transmitted outside of the designated Bonfire online portal will be rejected. If you have obtained this solicitation from a source other than Bonfire, you will not be listed on the document takers list and may not receive notification of any Addenda(s) issued. Failure to receive any issued Addenda shall not relieve the Bidder from any obligation(s) contained in the Addenda.

To access Toho Water Authority’s solicitations, any resulting Addenda, or Bid results, please go to:

https://tohowater.bonfirehub.com. Any prospective Bidder requiring assistance with registering with Bonfire is directed to send an email to: Support@GoBonfire.com or to visit Bonfire’s online help forum at https://vendorsupport.gobonfire.com/hc/en-us.

NOTICE OF STRUCTURE RECORD RELEASE ACKNOWLEDGEMENT

Vendors must fully complete Appendix A: FORM TOH-140, Structure Record Release Acknowledgement, to obtain copies of solicitation related building plans, blueprints, schematics, or diagrams pursuant to Chapter 119, Florida Statutes. Submit completed forms to procurement@tohowater.com by the question submittal deadline stated in this solicitation.

https://tohowater.bonfirehub.com/ mailto:Support@GoBonfire.com https://vendorsupport.gobonfire.com/hc/en-us mailto:procurement@tohowater.com

SECTION 00030

00030-2

SOLICITATION POINT OF CONTACT

Name: Damaris Nazario / Brian Grover Email: Procurement@tohowater.com Title: Procurement Supervisor / Coordinator Phone: (689) 688-2815

Notice of State/Federal Financial Assistance The award to be issued through this solicitation will be funded with federal funds as follows:

Federal Awarding Agency: U.S. Department of Housing and Urban Development (“HUD”) Assistance Listing Number:

14.251, Economic Development Initiative, Community Project Funding, and Miscellaneous Grants

Federal Award ID Number: B-23-CP-FL-0430

The City of St. Cloud (the “City”) is the pass-through entity to which such federal financial assistance was directly awarded. As a result, the Project that the successful Respondent will be assisting Toho in carrying out will be subject to the contracting requirements of 2 CFR Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards, any other federal requirements as provided by HUD, and the Subrecipient Agreement entered into between the City and the Toho Water Authority.

The Project that the successful Respondent will be assisting Toho in carrying out will also be “federally assisted construction” as defined by E.O. 11246 and implementing Department of Labor regulations, as well as subject to the requirements of Section 3 of the Housing and Urban Development Act of 1968, as amended, 12 U.S.C. 1701u (Section 3), as implemented at 24 CFR Part 75. The purpose of Section 3 is to ensure that employment and other economic opportunities generated by HUD assistance or HUD-assisted projects covered by Section 3, shall, to the greatest extent feasible, be directed to low- and very low-income persons, particularly persons who are recipients of HUD assistance for housing.

The construction services the successful Respondent will furnish will entail assisting Toho in compliance with National Environmental Policy Act (NEPA) and National Historic Preservation Act (NHPA) requirements as such requirements are implemented by HUD at 24 CFR Parts 50 and 58 and the Economic Development Initiative CPF Guide for FY2023 provided with this solicitation.

Finally, Toho hereby confirms that the HUD funding for the Project that the successful Respondent will be assisting Toho in carrying is subject to the requirements listed in Appendices B.1, B.2, B.3 and B.4.

PRE-BID CONFERENCE

There is no Pre-Bid Conference for this IFB.

SECTION 00100

INSTRUCTIONS TO BIDDERS

00100-1

Introduction

Tohopekaliga Water Authority (“Toho”), an independent special district established pursuant to Chapter 189, Florida Statutes, by special act of the Florida Legislature, hereby issues this Invitation for Bids (“IFB”) from qualified construction firms with the experience to construct a duplex submersible lift station along with new gravity mains, manholes, and force mains for the Hopkins Park Service Area Septic to Sewer – a HUD Funded Construction Project (the “Project”) all-inclusive of the following:

A. Includes the construction of approximately 965 lineal feet of 4” PVC (C900/DR-18) force main, 1,175 lineal feet of 8” PVC (SDR 35) gravity main, 51 lineal feet of 8” HDPE (DR 32.5) gravity main, six manholes, asphalt roadway open cut and repair with final mill and resurfacing, concrete curb removal and replacement, new residential gravity lateral services and decommissioning of septic tanks (requiring access to private property), construction of a duplex submersible lift station (including associated site work and electrical/instrumentation), odor control system, and Osceola County applicable permits and the usual appurtenances.

Toho is the largest provider of water, wastewater, and reclaimed water services in Osceola County, Florida, and provides such services to portions of Orange and Polk counties as well. Our promise is “Our Customers, Our Community, Our Employees Trust that Toho Cares” and our priorities are providing safe and reliable services, protecting the environment, delivering value, and investing in the future. Bidders can familiarize themselves with our agency at www.tohowater.com.

U.S. Department of Housing and Urban Development (“HUD”) Requirements

A. Community Program Funding Contractor Requirements: See Appendix B.3 CPGC Requirements for HUD Grant Construction Contract Requirements.

B. Certification of Debarment requirements: See Appendix B.3 CPGC Requirements for HUD Grant Construction Contract Requirements and IFB Section 00500 Contract Article 10.1.6.

C. Anti-lobbying certification requirements: See Appendix A Form #TOH-310.

D. MBE/WBE documentation of efforts requirements: See Appendix B.3 CPGC Requirements.

A. Hiring Section 3 employees’ documentation of efforts requirements: See IFB Section 00500 Contract Article 10, Appendix B.3 CPGC Requirements and Appendix B.1 Grant Agreement B-23-CP-FL-0430

B. HUD Environmental Review and Release of Funds requires all work to occur in the improved right of way or on improved City property or properly recorded public utility easement: See Appendix B.2 Subrecipient Agreement.

C. Drug Free Workplace certification requirement: See Appendix A Form #TOH- 320.

D. Conflict of Interest requirements: See Appendix B.3 CPGC Requirements and Appendix B.1 Grant Agreement B-23-CP-FL-0430.

E. Trafficking of Human Persons: See Appendix A Form #TOH-240 and Appendix http://www.tohowater.com/

00100-2

B.1 Grant Agreement B-23-CP-FL-0430.

F. Civil Rights 24CFR Part 5 compliance requirement: See IFB Section 00500 Contract Article 10 and Appendix B.3 CPGC Requirements.

Defined Terms

Terms used in these Instructions to Bidders which are defined in Section 00700: General Conditions have the meanings assigned to them in the General Conditions.

Submittal Requirements

Electronic submittals are required. Bids shall comply with the requirements provided in this IFB, and shall be timely submitted electronically via Toho’s e-procurement portal at https://tohowater.bonfirehub.com. All forms provided by Toho must be completed and appropriately incorporated into the Bid.

To submit responses electronically, Bidders must register with Bonfire and follow the instructions in the portal. Minimum system requirements: Microsoft Edge, Google Chrome, Safari, or Mozilla Firefox. Javascript and browser cookies must be enabled. Maximum upload file size is 1000 MB.

Documents should not be embedded within uploaded files as the embedded files will not be accessible. Bidders will have the ability to modify their submissions up to the Submittal Deadline in Bonfire.

Bids must be uploaded, submitted, and finalized prior to the Submittal Deadline indicated in Section 00030: Invitation for Bids. It is strongly recommended that Bidders give themselves sufficient time before the Submittal Deadline to begin the uploading process and finalize submissions.

Toho is not responsible for any technical problems in the electronic transmission and/or delay in receipt due to technical problems. Such electronic transmittal errors will not alter or effect the Submittal Deadline date or time for receipt of Bids. If you require assistance please contact Bonfire at Support@GoBonfire.com.

Late Bids, or Bids submitted by means other than provided above, will not be considered.

No Bids may be withdrawn after the Submittal Deadline without the written permission of Toho’s Procurement Director.

Pre-Bid Conference

No Pre-Bid Conference is being held for this solicitation.

Questions and Communications

Toho is committed to a fair, open process for interested parties to receive information about the Project and this competitive procurement process. As such, all procurement-related communications must comply with the requirements of this Article.

To ask questions concerning this IFB solicitation process, required submittals, the drawings or design specifications, evaluation criteria, selection process, or any other matter regarding this solicitation, Bidders must register with Toho’s public purchasing portal at https://tohowater.bonfirehub.com and initiate the questions electronically through https://tohowater.bonfirehub/ mailto:Support@GoBonfire.com

00100-3 the “Vendor Discussion” feature. If you require assistance registering with Bonfire, please contact Bonfire at Support@GoBonfire.com.

Bidders are required to advise TOHO of any conflicts in the Contract Documents or any discrepancies between conditions noted at the project site and those shown on the Drawings or described in the Specifications.

All questions, advisements, and any other IFB-related inquiries or comments must be submitted by use of the “Vendor Discussion” feature in Bonfire prior to the time and date of the “Question Deadline” provided in Section 00030: Invitation for Bids.

Thereafter Bidders raising critical concerns must email the Procurement Department at procurement@tohowater.com. Please note that untimely questions may not be considered or addressed and that any IFB-related communications sent to Toho by means other than the “Vendor Discussion” feature will be subject to public distribution.

Bidders are instructed not to contact the initiating division directly. Any contact with Board of Supervisors members and other key Project stakeholders by a Bidder concerning any matter relating to this procurement is prohibited and is grounds for disqualification.

Any responses to questions or additional IFB-related information provided by Toho will be provided to all Bidders either through the “Vendor Discussion” feature on Bonfire, or via a written addendum through https://tohowater.bonfirehub.com.

Answers for timely questions and other IFB-related requests may be addressed in the Bonfire Vendor Discussion feature or as an addendum to this IFB depending on volume.

Prospective Bidders are encouraged to register in Bonfire so that they may monitor all notifications.

No oral interpretation of the meaning of the plans, specifications, or other documents related to the Project or the IFB Package shall be considered binding. Toho shall be bound by information and statements only when such information or statements are written and executed under the authority of the Procurement Director.

This provision exists solely for the convenience and administrative efficiency of Toho. No Bidder or other third party gains any rights by virtue of this provision or the application thereof, nor shall any Bidder or third party have any standing to sue or cause of action arising there from.

Copies of Bidding Documents

Complete sets of the Bidding Documents may be obtained in the manner defined in the Invitation for Bids.

Complete sets of Bidding Documents shall be used in preparing Bids; neither TOHO nor ENGINEER nor DESIGN PROFESSIONAL assume any responsibility for errors or misinterpretations resulting from the use of incomplete sets of Bidding Documents.

TOHO in making copies of Bidding Documents available on the above terms does so only for the purpose of obtaining Bids on the Work and does not confer a license or grant for any other use.

mailto:Support@GoBonfire.com mailto:procurement@tohowater.com

00100-4

Contract

The draft of the contract Toho will use to issue the award (the “Contract”) may be found in Section 00500: Contract of this IFB. Bidders with any questions, comments, or modification requests regarding any provision of the Contract may timely submit them by the Question Deadline through the Bonfire’s “Vendor Discussion” feature, as further discussed in Article 5: Questions and Communications of these Instructions to Bidders.

Toho will review such Contract related questions, comments, and modification requests and issue its responses by addenda. Toho reserves the right to reject any and all requests to modify the provisions of the Contract.

Bidders, please note that this contract is a sample and is intended to provide you an opportunity to review the contents and specifically the terms and conditions, associated bonds and anticipated insurance requirements based on current cost estimates. There may be references to specific Attachments and/or Exhibits that are intended to be or may be incorporated into the final Agreement depending on possible negotiations that are NOT present in the sample.

By submitting a Bid, each Bidder: (a) agrees to accept the terms and conditions of the Contract “as is”, with no modifications other than those that Toho may have agreed to by Addenda; and (b) waives any objection it may have to any term of provision found in the Contract.

Time is of the essence; therefore, firms should be prepared to execute the Contract in a timely manner upon selection in order to begin the work required within the timeframe established.

Bidder Qualification Requirements

The successful Bidder shall comply with all local, State, and Federal statutes, regulations, directives and orders as applicable to the services provided and offered to Toho.

Florida Business Registration. The Awarded Bidder must be eligible and registered to do business in the State of Florida. Information regarding registration can be found at the Florida Department of State, Division of Corporations website at http://dos.myflorida.com/sunbiz.

Public Entity Crimes, Discriminatory Vendors, Antitrust Violators, and Scrutinized Companies

A. Public Entity Crimes. Pursuant to Subsections 287.133(2) and (3), Florida Statutes, a person or affiliate who has been placed on the convicted vendor list following a conviction for a public entity crime may not submit a bid or proposal on a contract to provide any goods or services to a public entity, may not submit a bid or proposal on a contract with a public entity for the construction or repair of a public building or public work, may not submit bids or proposals on leases of real property to a public entity, may not be awarded or perform work as a contractor, supplier, subcontractor, or consultant under a contract with any public entity, and may not transact business with any public entity in excess of the threshold amount provided in Section 287.017, Florida Statutes, for CATEGORY TWO for a period of 36 months from the date of being placed on the convicted vendor list.

B. Discriminatory Vendors. Pursuant to Subsection 287.134(2)(a), Florida Statutes, http://dos.myflorida.com/sunbiz

00100-2 an entity or affiliate who has been placed on the discriminatory vendor list may not submit a bid, proposal, or reply on a contract to provide any goods or services to a public entity; may not submit a bid, proposal, or reply on a contract with a public entity for the construction or repair of a public building or public work; may not submit bids, proposals, or replies on leases of real property to a public entity; may not be awarded or perform work as a contractor, supplier, subcontractor, or consultant under a contract with any public entity; and may not transact business with any public entity.

C. Antitrust Violators. Pursuant to Subsection 287.137(2)(a), Florida Statutes, a person or an affiliate who has been placed on the antitrust violator vendor list following a conviction or being held civilly liable for an antitrust violation may not submit a bid, proposal, or reply for any new contract to provide any goods or services to a public entity; may not submit a bid, proposal, or reply for a new contract with a public entity for the construction or repair of a public building or public work; may not submit a bid, proposal, or reply on new leases of real property to a public entity; may not be awarded or perform work as a contractor, supplier, subcontractor, or consultant under a new contract with a public entity; and may not transact new business with a public entity.

D. Scrutinized Companies. Pursuant to Section 287.135, Florida Statutes, a company is ineligible to, and may not, bid on, submit a proposal for, or enter into or renew a contract with an agency or local governmental entity for goods or services of:

A. Any amount if, at the time of bidding on, submitting a proposal for, or entering into or renewing such contract, the company is on the Scrutinized Companies that Boycott Israel List, created pursuant to Section 215.4725, Florida Statutes, or is engaged in a boycott of Israel; or

B. One million dollars or more if, at the time of bidding on, submitting a proposal for, or entering into or renewing such contract, the company: (a) is on the Scrutinized Companies with Activities in Sudan List or the Scrutinized Companies with Activities in Iran Terrorism Sectors List, created pursuant to Section 215.473, Florida Statutes; or (b) is engaged in business operations in Cuba or Syria.

E. Foreign Countries of Concern. Pursuant to Section 287.138, Florida Statutes, Toho may not enter into a contract with an entity that gives access to an individual’s personal identifying information if the entity is owned, controlled, or organized under the laws of a Foreign Country of Concern which includes: the People’s Republic of China, the Russian Federation, the Islamic Republic of Iran, the Democratic People’s Republic of Korea, the Republic of Cuba, the Venezuelan regime of Nicolas Maduro, the Syrian Arab Republic, or any other entity or agency under the significant control of such Foreign Country of Concern.

F. Required Certification. Bidders shall be required to certify to their eligibility to submit a solicitation response to this IFB in accordance with Section 8.2 of these Instructions to Bidders by use of the forms found in Section 00330: Bid Form Attachments, as attached to this IFB, which must be completed and submitted with each Bid.

E-Verification Requirement. In accordance with Section 448.095, Florida Statutes, the Awarded Bidder shall be registered with and utilize the U.S. Department of Homeland

00100-3

Security’s E‐Verify system to verify the employment eligibility of all new employees hired during the term of the Contract for the services specified in the Contract. To ensure compliance with this provision, each Bidder must complete and submit the applicable form found in Section 00330: Bid Form Attachments, as found attached to this IFB, with their Bid. Bidders are advised that evidence of their registration with the E-Verify system must be attached to the applicable form.

Social/Political/Ideological Interests. Bidders are hereby notified that Section 287.05701, Florida Statutes, requires that Toho may not request documentation of or consider a Bidder’s social, political, or ideological interests when determining if the vendor is a responsible Bidder and may not give preference to a Bidder based on the Bidder’s social, political, or ideological interests.

Additional Qualification Requirements. To demonstrate qualifications to perform the Work, each Bidder must be prepared to submit, following receipt of written request by TOHO, information including but not limited to financial data, previous experience including references and evidence of authority to conduct business in the jurisdiction where the Project is located. This information must be received by TOHO within 10 days of Bidder receiving the written request. Submittals requested pursuant to this paragraph are in addition to those required elsewhere.

Examination of Contract Documents and Site

Before submitting a Bid, each Bidder must: (a) examine the Contract Documents thoroughly; (b) visit the site to familiarize himself with local conditions that may in any manner affect cost, progress or performance of the Work; (c) familiarize himself with federal, state and local laws, ordinance, rules, regulations and policies that may in any manner affect cost, progress or performance of the Work; and (d) study and carefully correlate Bidder's observations with the Contract Documents; and (e) make written requests for interpretations promptly after discovering any conflicts, errors, ambiguities or inconsistencies.

Reference is made to the General Requirements for the identification of those reports of investigations and tests of subsurface and latent physical conditions at the site or otherwise affecting cost, progress or performance of the Work which have been relied upon by DESIGN PROFESSIONAL in preparing the Drawings and Specifications. TOHO shall make copies of such reports available to any Bidder requesting them. These reports are not guaranteed as to accuracy or completeness, nor are they part of the Contract Documents; they are provided for guidance only. If this information is used by Bidder in preparing his Bid, he shall assume all risks resulting from actual conditions differing from the conditions set out in the reports.

When a log of test borings showing a record of the data obtained by the investigation of subsurface conditions by TOHO, the DESIGN PROFESSIONAL or their consultants is included with the plans or other documents, it is expressly understood and agreed that said log of test borings does not constitute a part of the contract, represents only the opinion of TOHO, or the DESIGN PROFESSIONAL or their consultants as to the character of the materials encountered by them in the test borings, is included in the plans or other documents only for the convenience of bidders, and its use is subject to all of the conditions and limitations set forth in this article.

Before submitting a Bid, each Bidder shall, at Bidder's own expense, make or obtain any

00100-4 additional investigations, examinations, explorations and tests and obtain any additional information which pertain to the physical conditions (surface, subsurface and Underground Facilities) at or contiguous to the site or otherwise which may affect cost, progress or performance of the Work and which Bidder deems necessary to determine its Bid for performing the Work in accordance with the time, price and other terms and conditions of the Contract Documents.

On request, TOHO will attempt to provide each Bidder reasonable access to TOHO owned sites to conduct such investigations and tests as each Bidder deems necessary for submission of his Bid. If access is provided, Bidder shall restore site to condition existing prior to conducting said investigations and tests.

The lands upon which the Work is to be performed, rights-of-way for access thereto and other lands designated for use by CONTRACTOR in performing the Work are identified in the Contract Documents. All additional lands and access thereto required for temporary construction facilities or storage of materials and equipment are to be provided by

CONTRACTOR.

The submission of a Bid shall constitute a conclusive representation by the Bidder that he has complied with every requirement of this Article and that the Contract Documents are sufficient in scope and detail to indicate and convey understanding of all terms and conditions for performance of the Work.

The submission of the Bid shall be an indication that the Bidder has considered normal local weather conditions (daily and monthly variations) for the previous ten years from the date of the Bid as compiled by the National Weather Service and measured at Orlando International Airport.

Bid Security

A Bid Security shall be made payable to TOHO, in an amount of 5% of the Bidder's maximum Bid price and in the form of a certified or cashier's check, a Bid Bond on the form provided (or substantial equivalent) issued by a Surety meeting the requirements of Article 5: Bonds and Insurance of Section 00700: General Conditions, or other security as provided by law.

The Bid Security of the Low Bidder shall be retained until such Bidder has executed the Contract, furnished the required Payment and Performance Bonds and Insurance Certificates, and complied with all applicable requirements, whereupon it will be returned;

if the Low Bidder fails to execute and deliver the Contract, furnish the required Payment and Performance Bonds and Insurance Certificates, and/or comply with all applicable requirements within 15 days of the Notice of Award, TOHO may annul the Notice of Award and the Bid Security may be forfeited.

The Bid Security of any Bidder whom TOHO believes to have a reasonable chance of receiving the award may be retained by TOHO until the earlier of the 7th day after the "effective date of the Contract" (which term is defined in Section 00700: General Conditions) or the 91st day after Bid Opening.

Contract Time

The time of completion is the essence of the Contract, and the Bidder awarded the Contract shall proceed with the Work in accordance with the Contract Time period specified in the Contract

00100-5

Documents. In the event of failure to complete the Work within the time specified, TOHO may assess damages as provided by law or the Contract Documents, unless an appropriate extension of time has been granted by TOHO.

Liquidated Damages

Provisions for liquidated damages, if any, are set forth in Article 3: Contract Time; Liquidated Damages of Section 00500: Contract.

Substitute Material and Equipment

The Contract, if awarded, will be on the basis of material and equipment described in the Drawings or specified in the Specifications without consideration of possible substitute or "or-equal" items. Whenever it is indicated in the Drawings or specified in the Specifications that a substitute or "or-equal" item of material or equipment may be furnished or used by CONTRACTOR if acceptable to ENGINEER, application for such acceptance will not be considered by ENGINEER until after the "effective date of the Contract". The procedure for submittal of any such application by CONTRACTOR and consideration by ENGINEER is set forth in Section 6.7 of Section 00700: General Conditions which may be supplemented in the General Requirements.

If a substitution list is provided as part of the prescribed Bid Form, Bidders must identify proposed substitute materials and a deductive amount representing 50% of the cost difference between the specified item and the proposed item. These substitute materials and equipment shall be evaluated after "effective date of the Contract". In all cases, the Low Bidder shall be determined on the basis of the Base Bid which shall reflect the cost for the materials and equipment specified.

Subcontractors

TOHO shall receive from the Apparent Low Bidder (or the Low Bidder), within 10 days after receipt of written notification by TOHO, a list of all Subcontractors and other persons and organizations, including those who are to furnish the principal items of material and equipment. This list shall include the name and address of the Subcontractor, person or organization, a description of the services, materials, or equipment to be supplied, estimated time required for the preparation and submittal of shop drawings, and estimated lead times required for the fabrication of any long lead items and concurrence thereof.

Such list shall be accompanied by a statement of experience with pertinent information as to similar projects and other evidence of qualification for each such Subcontractor, person or organization.

If TOHO or ENGINEER has reasonable objection to any proposed Subcontractor, other person or organization, either may, before the Notice of Award, request the Apparent Low Bidder (or the Low Bidder) to submit an acceptable substitute without an increase in Bid price. If the Apparent Low Bidder (or the Low Bidder) declines to make any such substitution, the contract may not be awarded to such Bidder at the TOHO's sole discretion, but his declining to make any such substitution may not constitute grounds for sacrificing his Bid Security. Any Subcontractor, other person, or organization so listed and to whom TOHO or ENGINEER does not make written objection prior to the Notice of Award will be deemed acceptable to TOHO and ENGINEER, but TOHO and ENGINEER do not thereby waive any right they may have against CONTRACTOR because of the actions or omissions of said Subcontractor, other person or organization.

00100-6

Construction Bid Form

Each Bidder must submit their Bid using the Construction Bid Form found in Section 00300:

Construction Bid Form of these Bidding Documents. Bids shall be submitted in the manner indicated in the in Article 3 of these Instructions to Bidders and must be accompanied by the forms as listed in the Construction Bid Form. Bids received after the time and date specified in the IFB Coversheet shall not be considered. Failure to fully complete the Bid and any associated Bid Documents may result in the Bidder being found non-responsive and may result in rejection of the Bid.

Modification and Withdrawal of Bids

Bids may be modified or withdrawn by an appropriate document duly executed (in the manner that a Bid must be executed) and delivered to the place where Bids are to be submitted at any time prior to the opening of Bids. Withdrawal of a bid will not prejudice the rights of Bidder to file a new Bid.

If within 24 hours after bids are opened, any Bidder files a duly signed written notice with TOHO, and within 48 hours thereafter demonstrates to the reasonable satisfaction of TOHO that: (a) there has been a material and substantial mistake in the preparation of the Bid; (b) the mistake is of such great consequence that to enforce the Contract would be unconscionable; and (c) the mistake occurred notwithstanding the exercise of reasonable care in the preparation of the Bid; the Bidder may withdraw its Bid, and the Bid Security will be returned provided that TOHO is not seriously prejudiced, except for the loss of its bargain. Bidder shall not be allowed to correct a bid with a material and substantial mistake. Thereafter, that Bidder shall be disqualified from further bidding on the work to be provided under the Contract Documents.

Opening of Bids

Public Bid openings are held each Thursday at 2:00 P.M. local time. Public opening of all Bids submitted in response to this IFB will be conducted at the next posted Procurement Public Meeting following the Submittal Deadline. In the event of a Toho Holiday or unforeseen delay, responses shall remain sealed until the next available public meeting.

Bidders and members of the public will be able to attend the public opening virtually. To do so, see the following instructions:

Join by use of the following meeting link:

https://teams.microsoft.com/l/meetup-join/19%3ameeting_OGY3YWMzMjEtOGRjNi00M2JjLTkyNzAtMzc4NThkYWJlYTNk%40th read.v2/0?context=%7b%22Tid%22%3a%2258393785-b5ab-45f6-9f23- 0c44b1c20aa2%22%2c%22Oid%22%3a%222171abd6-d665-439e-a7aa- 04d0117fed76%22%7d

Meeting ID: 219 200 025 995 Passcode: cPzUbM

Dial in by phone

+1 872-256-3959, United States, Chicago

Phone conference ID: 509 407 264# tel:+18722563959,,509407264

00100-7

An abstract of the amounts of the base Bids and major alternates (if any) will be prepared and made available within a reasonable time after the opening of Bids.

More than one Bid received for the same work from an individual, firm, partnership, corporation, association, or other legal entity under the same or different names shall not be considered. Reasonable grounds for believing that any Bidder has an interest in more than one Bid for the same work will cause the rejection of all such Bids in which the Bidder is interested. If there are reasonable grounds for believing that collusion exists among the Bidders, the Bids of the participants believed to be in such collusion shall not be considered.

Notwithstanding any other provision contained in the Contract Documents, TOHO reserves the right to reject any and all bids and waive any and all irregularities and the right to disregard any or all nonconforming, unbalanced, or conditional bids or counter proposals. TOHO may reject as non-responsive any or all bids where bidders fail to acknowledge receipt of addenda as prescribed. If TOHO elects not to reject a bid which fails to acknowledge receipt of any addendum, the Bid shall be construed as though the addendum had been received and acknowledged by the Bidder.

Discrepancies between words and figures shall be resolved in favor of words.

Discrepancies between the indicated sum of any column of figures and the correct sum thereof shall be resolved in favor of the correct sum. Discrepancies in the extension of the unit price times the estimated quantity for any line item shall be resolved in favor of the correct extension.

Bids to Remain Open

As of the bid opening date, Bids received shall be considered irrevocable offers in full force and effect for a period of 90 days after the bid opening date. The forgoing notwithstanding, TOHO may, in its sole discretion, release any Bid and return the Bid Security prior to that date.

Extensions of time when bids shall remain opened beyond the ninety-day period may be made only by mutual agreement between TOHO, the low Bidder, and the Surety, if any, for the low Bidder.

Award of Contract

Award shall be based on products, equipment, and materials named in the Contract Documents. Consideration of and decisions regarding substitution shall not be made until after Award of the Contract. Bid award can be made based on any combination of Base Bids and Alternates, either Additive or Deductive, that is most advantageous to Toho.

In evaluating Bids, TOHO shall consider the qualifications of the Bidders, and whether or not the Bids comply with the prescribed requirements. Bidders are hereby notified that Section 287.0501, Florida Statutes, provides that TOHO may not request documentation or consider a vendor’s social, political, or ideological interests when determining if a vendor is a responsible vendor.

In evaluating Bids, TOHO shall consider the information provided by the Low Bidder as described in these Instructions to Bidders.

00100-8

The Low Bidder shall submit, upon request of TOHO, documentation evidencing its capability to perform classes of work contemplated, and the necessary plant and sufficient capital to execute the Work properly within the time specified. This information must be received by TOHO within ten days of Bidder receiving written request.

TOHO may require the Low Bidder to submit a certified statement describing his organization, plant, manpower, financial resources and list all previous and/or ongoing construction contracts over the last five years regardless of amount or completion status.

Information shall be submitted on the Associated General Contractors of America Form "Standard Questionnaires and Financial Statement for Bidders" available from AGC, 1957 "E" Street, N.W., Washington, D.C. 20006, or other form acceptable to TOHO. The information shall be certified by a Certified Public Accountant for bids over $25,000.

TOHO, at its discretion, may require any or all of the above listed information from any other Bidder.

TOHO may consider the qualifications and experience of Subcontractors and other persons and organizations (including those who are to furnish the principal items of material or equipment) proposed for those portions of the Work as to which the identify of Subcontractors and other persons and organizations must be submitted as provided in the Supplementary Conditions and Article 14: Subcontractors of these Instructions to Bidders. Operating costs, maintenance, considerations, performance data, and guarantees of materials and equipment may also be considered by TOHO.

TOHO may conduct such investigations and require supplemental information as it deems necessary to assist in the evaluation of any Bid and to establish the responsibility, qualifications, and financial ability of the Bidders, proposed Subcontractors, proposed equipment and material suppliers, and other persons and organizations to do the Work in accordance with the Contract Documents to TOHO's satisfaction within the prescribed time.

TOHO reserves the right to reject the Bid of any Bidder who does not pass any such evaluation to TOHO's satisfaction.

TOHO reserves the right to reject the Bid of any Bidder which is behind on the approved completion schedule for any existing contracts with TOHO, or in litigation with TOHO, or has previously defaulted on a contract with TOHO.

Bids shall be analyzed to determine whether they are unbalanced bids with respect to unit priced or individually priced line items. Bids that are materially unbalanced may be rejected. A Bid may be mathematically unbalanced if it is based on prices that are significantly less than the cost for certain line items, significantly overstated in relation to the cost for certain line items, or a combination of both. A bid may be materially unbalanced and:

A. There is reasonable doubt that the bid would result in the lowest overall cost to the Authority, even though it is the lowest evaluated bid; or

B. The bid is so grossly unbalanced that its acceptance would be tantamount to allowing an advance payment.

TOHO reserves the right to reject all Bids.

If the Contract is to be awarded, TOHO will give the Bidder a Notice of Award within 90 days after the day of the bid opening subject to the terms and conditions of these Instructions

00100-9 to Bidders.

TOHO, while reviewing the Bid of the apparent successful Bidder, may reasonably require other Bidders to submit promptly for TOHO inspection, information, including, but not limited to, their responsibility, qualifications, financial ability, proposed Subcontractors and Suppliers, and other necessary information.

Bonds and Insurance

Article 5 of the General Conditions sets forth TOHO's requirements as to Bonds and Insurance.

When the successful Bidder delivers the executed Contract to TOHO, it shall be accompanied by the required Bonds and Insurance Certificates as prescribed by TOHO. TOHO must receive within 45 days after the successful Bidder executed the Contract, copies of all insurance policies for the insurance requirements set forth in the General Conditions. Attorneys-in-fact who sign Bid Bonds, Performance Bonds and Payment Bonds must file with such Bonds a certified copy of their power-of-attorney to sign the Bonds.

Signing of Agreement

When TOHO gives a Notice of Award to the successful Bidder, it will be accompanied by two unsigned counterparts of the Contract and all other Contract Documents. Within 15 days of receipt thereafter, successful Bidder shall sign and deliver at least two counterparts of the Contract to TOHO together with the documents described in Articles 19 and 20 above attached.

Failure by a successful Bidder to whom the Contract is awarded to execute the Contract or to correctly complete or furnish the required Bonds or insurance certificates or to comply with other requirements of the Contract Documents shall be just cause for the annulment of the award and the forfeiture of the Bid Security.

A successful Bidder who is awarded the Contract and fails to execute the agreement or correctly complete, furnish the required Bonds and insurance certificates within the time period specified in Article 20 above, and/or fails to comply with any other requirements shall be liable to TOHO for all damages resulting therefrom including reasonable attorneys' fees and costs, and attorneys' fees and cost on appeal. The Bid Security forfeited shall not be limitation thereon.

Schedule Submittals

Within 10 days following receipt of written request by TOHO, the bidder shall submit a preliminary progress schedule in accordance with appropriate formats set forth in the General Requirements. This schedule shall show in a summary fashion the order in which the Bidder proposes to perform the work and shall indicate approximate starting and completion dates for the major work elements.

This progress schedule shall not replace, but serve as a basis for, the progress schedule submittals to be developed as required in the Specifications. Failure by the Bidder to furnish these Schedule Submittals, as required in a sufficiently complete and responsible manner shall void evaluation of the Bid, and will constitute proof that the Bidder has abandoned all his rights and interests in the award, and his Bid Security may be declared forfeited to the TOHO as liquidated damages and the work may be awarded to another Bidder.

00100-10

Concurrent Work by Others

Bidders are advised that there are or may be other contractors working at the project site concurrent with the construction of the Work described in this solicitation. Accordingly, Bidders should consider the limitations to site access and the construction sequencing described in the Contract Documents when preparing this Bid.

If areas are designated in the Contract Documents which are to be shared with other contractors and these areas must be disrupted, the CONTRACTOR shall provide alternate acceptable access for other contractors.

CONTRACTOR is required to coordinate his activities in the designated areas described above with other contractors working at the project site. CONTRACTOR must submit to the ENGINEER a description and schedule as to how the designated areas will be utilized, recognizing the required coordination with other contractors.

Special Warranty, Guaranty, Guarantee, Bonds Insurance Maintenance, and Correction Period Requirements

There may be special requirements pertaining to Warranty, Guarantee, Bonds, Insurance, Maintenance and the Correction Period, which are described in the Contract Documents. Bidders should review these special requirements, if applicable, and reflect in their bids all costs associated therewith.

END OF SECTION 00100

SECTION 00300

CONSTRUCTION BID FORM

00300-1

IFB No.: IFB-26-010 Issue Date: February 6, 2026 Project Title: Hopkins Park Service Area Septic to Sewer – a HUD

Funded Construction Project

Bidder Name:

Submittal Instructions To respond to the IFB with the above-referenced number and Project title, each Bidder must complete this Section 00300 – Construction Bid Form in a manner compliant with the provisions, terms, and conditions of the IFB Package and other Contract Documents. The terms used in this form shall have the same meanings as provided in the General Conditions.

Bidders must enter the information requested throughout this form into the available fields, make selections by checkbox when prompted, and, when requested or otherwise necessary, attach additional documentation.

Bidders must:

1. Use this Section 00300 – Construction Bid Form as the “cover document” (first document) of their Bid submittals;

2. Attach all other requisite forms, attachments, and documents hereto; and

3. Combine all such attachments and documents into one PDF document for electronic submittal.

Sealed electronic Bids will be accepted as provided in the Invitation for Bids and Instructions

Bidders shall not be permitted to hand-deliver, mail, telephone, fax, or email offers. Bids received after the Submittal Deadline or that are transmitted outside of the designated Bonfire portal will be rejected.

See Section 00030 – Invitation for Bids and 00100 – Instructions to Bidders of the Bidding Documents for more information.

00300-2

Name of…

This is the start of the file's text. The full file is on GovTribe.