About this file
These documents represent a comprehensive set of architectural, mechanical, and electrical design plans for the Ben Taub Hospital Green Elevator Modernization project located at 1504 Ben Taub Loop in Houston, Texas, prepared by Spur Design, LLC for Harris Health System. The project involves a complete modernization of the hospital's elevator system, specifically targeting elevators 7-12 across multiple floors (Basement through Level 6 and the Elevator Penthouse). The project scope includes replacing elevator doors, cab interiors, hall stations, lanterns, frames, and associated electrical and mechanical systems, with a 100% submission dated May 16, 2025. The design documents encompass 23 total sheets covering architectural, mechanical, and electrical disciplines, with detailed plans for demolition and new installation.
The project involves significant electrical and mechanical upgrades, including replacing the existing air conditioning unit (ACU-P-1) in the elevator penthouse, updating electrical distribution panels, and modernizing elevator equipment and controls. The design adheres to multiple building codes and standards, including the 2015 International Building Code, 2020 National Electrical Code, and Texas Accessibility Standards. Electrical work includes upgrading power systems, lighting, and control mechanisms for the elevators, with careful attention to maintaining existing circuit continuity and minimizing disruption to hospital operations. The project emphasizes coordination between disciplines, preservation of existing infrastructure where possible, and compliance with healthcare facility design requirements.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REVISIONS
ISSUE DATE
DRAWN BY
SHEET NAME NUMBER
PROJECT NUMBER (SPUR)
CHECKED BY
REGISTRATION
THIS DRAWING IS THE PROPERTY OF
SPUR DESIGN, LLC. THIS DRAWING IS
SUBMITTED UNDER A CONFIDENTIAL
RELATIONSHIP FOR A SPECIFIED
PURPOSE & THE RECIPIENT, BY
ACCEPTING THIS DOCUMENT, ASSUMES
CUSTODY & AGREES THAT THIS
DOCUMENT WILL NOT BE COPIED OR
REPRODUCED IN WHOLE OR IN PART, NOR
ITS CONTENTS BE REVEALED IN ANY
MANNER OR TO ANY PERSON EXCEPT TO
MEET THE PURPOSE FOR WHICH IT WAS
DELIVERED WITHOUT EXPRESS WRITTEN
PERMISSION FROM SPUR DESIGN, LLC.
S P U R D E S I G N
W W W . S P U R - D E S I G N . C O M
312 S W 25 T H S T R E E T ( 4 0 5 ) 8 4 2 - 6 1 0 0
Drawing #
(2291.01)
GI000
23-1FC01327
NR
BGJ
05/16/2025
B E
N T
A U
B H
O S
P
IT
A L
G R
E E
N E
L E
V A
T O
R M
O D
E R
N
IZ
A T
IO
N
B
E N
T A
U B
L O
O P
H O
U S
T O
N T
X
COVER SHEET
S U
B M
IS
S
IO
N
SHEET INDEX
SEQUENCE NUMBER SHEET NAME
[01] GENERAL
1 GI000 COVER SHEET
2 GI001 GENERAL INFORMATION
[02] ARCHITECTURAL
3 AE100 BASEMENT
4 AE101 LEVEL 1
5 AE102 LEVEL 2
6 AE103 LEVEL 3
7 AE104 LEVEL 4
8 AE105 LEVEL 5
9 AE106 LEVEL 6
10 AE107 ROOF LEVEL
11 AF701 FINISH FLOOR PLANS
[03] MECHANICAL
12 M-000 LEGEND AND ABBREVIATIONS
13 MH101 MECHANICAL HVAC PLAN
14 M-501 MECHANICAL DETAILS, SCHEDULES, & CONTROLS
[04] ELECTRICAL
15 E-000 ELECTRICAL LEGEND AND ABBREVIATIONS
16 E-100 ELECTRICAL POWER - BASEMENT
17 E-101 ELECTRICAL POWER - LEVEL 6
18 E-103 ELECTRICAL LIGHTING - BASEMENT
19 E-104 ELECTRICAL LIGHTING - ELEVATOR PENTHOUSE
20 E-501 ELECTRICAL DETAILS
21 E-601 ELECTRICAL - ONE LINE DIAGRAM
22 E-102 ELECTRICAL POWER - ELEVATOR PENTHOUSE
23 E-700 ELECTRICAL SCHEDULES
TOTAL SHEETS: 23
NN
LOCATION
PLAN
AREA
PLAN
PROJECT LOCATION
BEN TAUB HOSPITAL GREEN
ELEVATOR MODERNIZATION
1504 BEN TAUB LOOP
HOUSTON, TX 77030
100% SUBMISSION
ABBREVIATIONS CODES STANDARDS
DOOR AND FIXTURE CLEARANCES
MATERIALS LEGEND
CITY OF HOUSTON BUILDING CODES - WWW.HOUSTONPERMITTINGCENTER.ORG/HELP/CODES
• HOUSTON CONSTRUCTION CODE AMENDMENTS ORDIANCE (REV. APRIL 11, 2022)
• 2015 INTERNATIONAL BUIDLING CODE (REV. MARCH 20, 2023)
• 2020 NATIONAL ELECTRICAL CODE (REV. MARCH 20, 2023)
• 2015 INTERNATIONAL EXISITING BUILDING CODE (REV. APRIL 11, 2022)
• 2015 INTERNATIONAL FIRE CODE (REV. APRIL 11, 2022)
• 2015 UNIFORM MECHANICAL CODE (REV. APRIL 11, 2022)
• 2015 UNIFORM PLUMBING CODE (REV. APRIL 11, 2022)
• CITY CODE AMENDMENTS (REV. APRIL 11, 2022)
TEXAS DEPARTMENT OF LICENSING & REGULATION - ARCHITECTURAL BARRIERS
• 2012 TEXAS ACCESSIBILITY STANDARDS (TAS)
ASHRAE 90.1 - 2019 EDITION
BUILDING LOCATION: HOUSTON, TX
CLIMATE ZONE (TABLE ANNEX 1-1): ZONE 2A
INTERIOR DESIGN CONDITIONS:
THE INTERIOR DESIGN TEMPERATURES FOR HEATING AND COOLING AS DEPICTED IN THE PROJECT DESIGN CONDITIONS SCHEDULE IN THE MECHANICAL CONTROL DRAWINGS SHALL BE THE MAXIMUM AND
MINIMUM VALUES FOR THE ASSOCIATED TEMPERATURE CONTROL ZONES.
BUILDING ENVELOPE REQUIREMENTS (5.5 )
BUILDING ENVELOPE REQUIREMENTS FOR CLIMATE ZONE 4 (A,B,C)
ROOFS REQUIRED DESIGNED
INSULATION: R-30 c.i. EXISTING METAL BUILDINGS: R-19 + R-11 Ls or R-25 + R-8 Ls EXISTING
ATTIC AND OTHER: R-49 EXISTING
WALLS, ABOVE GRADE
MASS: R-9.5 c.i. EXISTING METAL BUILDING: R-0 + R-15.8 c.i. EXISTING STEEL-FRAMED: R-13 + R-7.5 c.i. EXISTING WOOD-FRAMED AND OTHER: R-13 + R-3.8 c.i. or R-20 N/A
WALL, BELOW GRADE
BELOW-GRADE WALL: R-7.5 c.i. N/A
FLOORS
MASS: R-14.6 c.i. EXISTING
STEEL-FRAMED: R-30 EXISTING
WOOD-FRAMED AND OTHER: R-30 N/A
SLAB-ON-GRADE FLOORS
UNHEATED SLABS: R-15 for 24 in. EXISTING HEATED SLABS: R-20 for 24 in. N/A
OPAQUE DOORS
SWINGING: U-0.370 EXISTING
NONSWINGING: U-0.310 EXISTING
FENESTRATION (TABLE 5.5-4):
VERTICAL FENESTRATION, U-FACTOR
FIXED: U-0.36 EXISTING
OPERABLE: U-0.45 EXISTING
ENTRANCE DOOR: U-0.63 EXISTING
DEFINITIONS
c.i = CONTINUOUS INSULATION Ls = LINEAR SYSTEM
NR = NO (INSULATION) REQUIREMENT
ENERGY REQUIREMENTS
N
1. DRAWINGS ARE PART OF A COMPLETE DOCUMENTS SET. CONTRACTOR SHALL CONFIRM ALL ITEMS REQUIRED BASED UPON THE OVERALL DESIGN INTENT
OF THE ENTIRE DOCUMENT SET.
2. CONTRACTOR SHALL VERIFY ALL EXISTING CONDITIONS, PRIOR TO BEGINNING ANY WORK, TO CONFIRM THE ACCURACY OF THE DRAWINGS AND REPORT ANY DISCREPANCIES TO THE ARCHITECT. DO NOT SCALE THE DRAWINGS. FIELD VERIFY ALL DIMENSIONS AND EXISTING STRUCTURAL CONDITIONS.
3. ALL AREAS NOT INVOLVED IN THE SCOPE OF WORK FOR THIS PROJECT SHALL BE KEPT CLEAN AND FREE OF OBSTRUCTIONS AT ALL TIMES.
4. ERECT BARRICADES AND WARNING SIGNS TO DIVERT AND WARN PASSERS-BY OF THE CONSTRUCTION WORK. PROVIDE DUST PROOFING ENCLOSURES TO
SEPARATE WORK AREAS FROM THE EXISTING FACILITIES.
5. ALL TRASH AND DEBRIS TO BE REMOVED ON A DAILY BASIS.
6. PROVIDE PROTECTION FOR ALL EXISTING SURFACES AND CONDITIONS TO REMAIN IN PLACE DURING THE SCOPE OF WORK. SHOULD ANY DAMAGE OCCUR, PATCH AND REPAIR ANY DAMAGE TO ADJACENT FINISHES TO MATCH EXISTING.
7. ANY DAMAGE CAUSED TO THE BUILDING OR OWNER EQUIPMENT SHALL BE REPAIRED OR REPLACED BACK TO ITS ORIGINAL CONDITIONS AT NO ADDITIONAL
COST TO THE OWNER.
8. COVER ALL RETURN AIR GRILLES WITHIN THE AREA OF CONSTRUCTION TO PREVENT PARTICULATE MATERIAL FROM EXHAUSTING INTO SURROUNDING
SPACES.
9. APPROPRIATE LIGHT FIXTURES SHALL BE TEMPORARILY SUSPENDED TO PROVIDE ADEQUATE LIGHTING LEVELS FOR CONSTRUCTION.
10. CONTRACTOR AND SUBCONTRACTORS ARE REQUIRED TO COORDINATE WITH OTHER DISCIPLINES TO INSTALL COMPLETE AND OPERATIONAL SYSTEMS.
DRAWINGS, AS A WHOLE, REPRESENT A COMPLETE SET AND DEPICT REQUIREMENTS FOR COMPLETE AND OPERATIONAL SYSTEMS. INDIVIDUAL DRAWINGS MAY NOT DEPICT COMPLETE AND ACCURATE INFORMATION TO COORDINATE COMPLETE AND OPERATIONAL SYSTEMS, BUT DO SO AS AN ENTIRE DOCUMENT TO BE REFERENCED WITH OTHER INDIVIDUAL DRAWINGS. CONTRACTOR AND SUBCONTRACTORS ARE REQUIRED TO REFERENCE OTHER SHEETS AND SPECIFICATIONS AS AN ENTIRE SET OF CONSTRUCTION DOCUMENTS THAT REFLECT WORK REQUIRED TO ACHIEVE A COMPLETE AND OPERATIONAL GOAL.
LACK OF COORDINATION AND REVIEW OF DRAWINGS AND SPECIFICATIONS AS AN ENTIRE DOCUMENT TO INSTALL COMPLETE AND OPERATIONAL SYSTEMS, BEING OBVIOUS AND TYPICAL INDUSTRY STANDARD, IDENTIFIED IN THE DRAWINGS AND SPECIFICATIONS, SHALL NOT BE IN ANY WAY AN ADDITIONAL COST
TO THE OWNER.
11. CONTRACTOR SHALL SUBMIT A REQUEST, IN WRITING, TO INTERRUPT ANY SUCH SERVICES TO THE HOSPITAL PROJECT MANAGER, 48 HOURS IN ADVANCE OF PROPOSED INTERRUPTION. REQUEST SHALL STATE REASON, DATE, EXACT TIME OF, AND APPROXIMATE DURATION OF SUCH INTERRUPTION. MAJOR INTERRUPTIONS OF ANY SYSTEM MUST BE REQUESTED, IN WRITING, AT LEAST 60 CALENDAR DAYS PRIOR TO THE DESIRED TIME AND SHALL BE PERFORMED AS DIRECTED BY THE COR. MAJOR INTERRUPTIONS SHALL BE COORDINATED WITH OTHER MAJOR INTERRUPTIONS AND MAY NOT BE SCHEDULED FOR ONE DISCIPLINE MORE THAN TWICE THROUGHOUT THE OVERALL CONSTRUCTION SCHEDULE UNLESS REQUESTED IN WRITING AND APPROVED BY THE OWNER PROJECT MANAGER. CONTRACTOR WILL BE ADVISED, IN WRITING, OF APPROVAL OF REQUEST, OR OF WHICH OTHER DATE AND/OR TIME SUCH INTERRUPTION WILL CAUSE THE LEAST INCONVENIENCE TO OPERATIONS OF THE MEDICAL CENTER. INTERRUPTION TIME APPROVED BY THE MEDICAL CENTER MAY OCCUR AT TIMES OTHER THAN CONTRACTOR'S NORMAL WORKING HOURS. SCHEDULE INTERRUPTION MAY BE ON WEEKENDS OR LATE HOURS AND MAY NOT BE AN ADDITIONAL COST TO THE OWNER. COORDINATE ALL INTERRUPTIONS THAT MAY AFFECT THE NORMAL OPERATION OF THE FACILITY WITH THE OWNER PROJECT MANAGER WHEN SUBMITTING THE CONSTRUCTION SCHEDULE OR UPDATES TO THE CONSTRUCTION SCHEDULE.
12. NO ASBESTOS CONTAINING MATERIALS ARE TO BE USED ON THIS PROJECT. SPUR DESIGN, THE A/E OF RECORD, CAN CERTIFY THAT NO ASBESTOS CONTAINING BUILDING MATERIALS (ACBM) OR LEAD BASED PAINT (LBP) PRODUCTS WERE DESIGNED/SPECIFIED AS BUILDING MATERIAL IN ANY OF THE
CONSTRUCTION DOCUMENTS.
GENERAL NOTES
AREA NAME
150 SF
A101
A101
SIM
A
00.0
A101
1 1
A101
LEVEL NAME
00'-00"
00'-00" 4B
3A
FIBERGLASS BATT
INSULATION
RIGID INSULATION
CONCRETE / PRECAST
CONCRETE
EARTH / SOIL
SAND, EIFS FINISH, OR
PLASTER FINISH
GYPSUM BOARD FINISH
BRICK
CONCRETE MASONRY
UNIT
STONE / CAST STONE
GYPSUM BOARD SECTION
EXTERIOR SHEATHING
BOARD SECTION
PLYWOOD SECTION
CLEAN UTILITY
000A
150 SF
/1 A101
X0000
ROOM TAG
AREA TAG
SPECIALTY EQUIPMENT TAG
DOOR TAG
KEYED NOTE TAG
WALL TAG
WINDOW TAG
A101
SIM
A101
SIM
A
ACB ACOUSTIC CEILING BAFFLE
ACP ACOUSTIC CEILING PANEL
ACST ACOUSTIC
ADA AMERICANS WITH DISABILITIES ACT
ACT ACOUSTICAL CEILING TILE
ADDL ADDITIONAL
ADDN ADDITION
ADJ ADJACENT, ADJOINING, OR
ADJUSTABLE
ADMIN ADMINISTRATION
AE ARCHITECT/ENGINEER
AF ACCESS FLOORING
AFF ABOVE FINISHED FLOOR
AFG ABOVE FINISHED GRADE
AHJ AUTHORITY HAVING JURISDICTION
AIA AMERICAN INSTITUTE OF
ARCHITECTS
ALT ALTERNATE
ALT NO ALTERNATE NUMBER
ALUM ALUMINIUM (TRIM)
AMT AMOUNT
APPROX APPROXIMATE
ARCH ARCHITECT
ASC ABOVE SUSPENDED CEILING
AT ACOUSTIC CEILING TILE
AVG AVERAGE
B
BD BOARD
BLDG BUILDING
BLKG BLOCKING
BLT IN BUILT-IN
BOS BOTTOM OF STEEL
BOT BOTTOM
BRKT BRACKET
BTWN BETWEEN
C
CAB CABINET
CAV CAVITY
CBB CONCRETE BACKER BOARD
CD CONSTRUCTION DOCUMENTS
CFM CUBIC FEET PER MINUTE
CFS CUBIC FEET PER SECOND
CG CORNER GUARD
CH BD CHALK BOARD
CIP CAST-IN-PLACE
CJ CONTROL JOINT
CL CENTER LINE
CLG CEILING
CLG HT CEILING HEIGHT
CLR CLEAR
CMU CONCRETE MASONRY UNIT
COL COLUMN
COMM COMMUNICATION
CONC CONCRETE
CONT CONTINUOUS
COORD COORDINATE
CP CONTRACTOR PROVIDED
CP/CI CONTRACTOR PROVIDED /
CONTRACTOR INSTALLED
CPT CARPET/CARPET TILE
CS CONCRETE SEALED
CSWK CASEWORK
CT CERAMIC TILE
CTB CERAMIC TILE BASE
CTR CENTER
CU FT CUBIC FEET
D
DBL DOUBLE
DEMO DEMOLITION
DEPT DEPARTMENT
DET DETAIL
DIA DIAMETER
DIR DIRECTION
DIST DISTANCE
DOC DOCUMENT
DR DOOR
DS DOWNSPOUT
DWG DRAWING
DWP DIMENSIONAL WALL PANEL
E
EA EACH
EJ EXPANSION JOINT
EL ELEVATION
ELEV ELEVATOR
ENTR ENTRANCE
EPY EPOXY FLOORING
EQ EQUAL
ETR EXISTING TO REMAIN
EX EXISTING
EXP EXPOSED
EXT EXTERIOR
F
FAB FABRIC
FED FEDERAL
FF FINISH FACE
FF EL FINISH FLOOR ELEVATION
FIN FINISH
FIN BS FINISH BOTH SIDES
FIN FLR FINISH FLOOR
FIN GR FINISH GRADE
FIXT FIXTURE
FLDG FOLDING
FLEX FLEXIBLE
FLG FLOORING
FLMT FLUSH MOUNT
FLR FLOOR
FOC FACE OF CONCRETE
FOM FACE OF MASONRY
FP FIRE PROTECTION
FR FIRE RESISTANT
FT FEET
FTG FOOTING
FV FIELD VERIFY
FWC FABRIC WALL COVERING
G
GDR GUARDRAIL
GL GLASS/GLAZING
GRAN GRANITE
GR FL GROUND FLOOR
GT GROUT
GSM GALVANIZED SHEET METAL
GYP BD GYPSUM BOARD
H
HDW HARDWARE
HEPA HIGH EFFICIENCY
PARTICULATE AIR (FILTER)
HM HOLLOW METAL
HORIZ HORIZONTAL
HR HANDRAIL
HT HEIGHT
I
IBC INTERNATIONAL BUILDING CODE
INSUL INSULATION
INT INTERIOR
ILO IN LIEU OF
J
J-BOX JUNCTION BOX
L
LAV LAVATORY
LBS POUND
LDG LANDING
LF LINEAR FEET (FOOT)
LIN LINEAR
LN LINOLEUM
LOC LOCATION
LT LIGHT
LVR LOUVER
LVT LUXURY VINYL TILE
M
MAT CARPET MAT / WALK-OFF MAT
MATL MATERIAL
MAX MAXIMUM
MECH MECHANICAL
MEMB MEMBRANE
MFR MANUFACTURER
MID MIDDLE
MIN MINIMUM
MISC MISCELLANEOUS
MO MASONRY OPENING
MOD MODIFY
MTG MOUNTING
MTL METAL
MVBL MOVABLE
N
NA NOT APPLICABLE
NIC NOT IN CONTRACT
NO NUMBER
NOM NOMINAL
NTS NOT TO SCALE
O
OA OVERALL
OC ON CENTER
OD OUTSIDE DIAMETER
OPNG OPENING
OPP OPPOSITE
OPR OPERABLE
ORD OVERFLOW ROOF DRAIN
ORIG ORIGINAL
P
P PAINT
PA PUBLIC ADDRESS
PBD PARTICLE BOARD
PCF POUNDS PER CUBIC FOOT
PCT PERCENT
PERF PERFORATED
PERIM PERIMETER
PERP PERPENDICULAR
PL PROPERTY LINE
PLAM PLASTIC LAMINATE
PLBG PLUMBING
PNL PANEL
PR PAIR
PRB PROFILE BASE
PRKG PARKING
PSF POUNDS PER SQUARE FOOT
PSI POUNDS PER SQUARE INCH
PT PORCELAIN TILE
PWR POWER
Q
QA QUALITY ASSURANCE
QC QUALITY CONTROL
QTY QUANTITY
REFERENCE SYMBOLS IDENTIFICATION TAGS
GRID HEAD AND
LINE
LEVEL INDICATOR
MATCH LINE AND
VIEW REFERENCE
NORTH ARROW W/
PROJECT NORTH
SPOT ELEVATION
DETAIL
SECTION
WALL
SECTION
BUILDING
SECTION
DETAIL
ELEVATION
INTERIOR
ELEVATION
BUILDING
ELEVATION
1 1
R
RAF RESILIENT ATHLETIC FLOORING
RB RUBBER BASE/RESILIENT BASE
RCP REFLECTED CEILING PLAN
RD ROOF DRAIN
REC RECESSED
REF REFERENCE
REM REMOVABLE
REP REPAIR
REPL REPLACE
REQ REQUIRE
REQD REQUIRED
RES RESINOUS FLOORING
RES-W RESINOUS / EPOXY WALL / CEILING
RF RUBBER FLOORING
RFG ROOFING
RM ROOM
RO ROUGH OPENING
RP RESIN PANEL
RSF RESILIENT SHEET FLOORING
RV ROOF VENT
RWC RIGID VINYL WALLCOVERING
S
SC SPECIALTY COATING
SD STATIC DISSIPATIVE FLOORING/TILE
SCHED SCHEDULE
SECT SECTION
SF SQUARE FOOT (FEET)
SGL SINGLE
SIM SIMILAR
SJ SCORED JOINT
SLNT SEALANT
SM SHEET METAL
SPEC SPECIFICATION
SQ SQUARE
SQ IN SQUARE INCH
SQ YD SQUARE YARD
SS SOLID SURFACE
ST STONE
STD STANDARD
STOR STORAGE
SV SHEET VINYL (ROLLED OR TILE)
T
TEL TELEPHONE
TEMP TEMPORARY
TER TERRAZZO
TOF TOP OF FOOTING/ FOUNDATION
TOM TOP OF MASONRY
TOS TOP OF SLAB/ STEEL
U
UNO UNLESS NOTED OTHERWISE
UTIL UTILITY
V
VAR VARIES
VCT VINYL COMPOSITION TILE
VFAT VINYL FACED ACOUSTICAL TILE
VP VENEERED PLASTER
VT VINYL TILE
VWC VINYL WALLCOVERING
VWF VINYL WALL FABRIC
W
W/ WITH
W/O WITHOUT
W/C WATER CLOSET
WC WHEELCHAIR
WD WOOD
WFAB WALL FABRIC
WPM WATERPROOF MEMBRANE
WSF WELDED SHEET FLOOR
X
X BRACE CROSS BRACE
TRUE
NORTH
4' -0
M
A X
4' -0
M
A X
1. GENERAL CONTRACTOR TO PROVIDE METAL SUPPORT
BLOCKING FOR ALL WALL MOUNTED ACCESSORIES,
FIXTURES, AND EQUIPMENT.
2. PROVIDE ADA SUPPORT BRACKETS PLACED AT ALL OPEN
COUNTERTOPS @ 36"-48" MAX ON CENTER.
3. SPECIFIED MAXIMUMS ARE MEASURED FROM AFTER
FINISHED FLOOR TO THE OPERABLE PART OF THE FIXTURE.
4. FIXTURES SHOWN ARE REPRESENTATIONAL ONLY. NOT ALL
FIXTURES MAY BE USED. REFER TO SPECIFICATIONS FOR
FIXTURE TYPES USED IN THIS PROJECT.
5. FIXTURES MAY OVERLAP WAINSCOT. WHERE APPLICABLE,
BACKING TO BE PROVIDED AS SHIM FOR FLUSH
APPLICATION. SHIM TO MATCH SCHEDULED WALL FINISH.
PAPER TOWEL
DISPENSER
SANITARY
NAPKIN
DISPENSER
4' -0
"M A
X
WASTE
RECEPTACLE
4' -0
M
A X
SOAP
DISPENSER
4' -0
M
A X
WALL HOOK
7' -0
CLOCK
FIRE EXTINGUISHER
CABINET
WEIGHT > 40LBS
4' -0
"M A
X
TOILET SEAT
COVER
DISPENSER
HANDRAILS AND
BUMPER GUARDS
6"
3' -0
M
A X
NOTE: NOT ALL ABBREVIATIONS OR SYMBOLS WILL BE UTILIZED FOR THIS PROJECT.
3' -6
M
A X
REVISIONS
ISSUE DATE
DRAWN BY
SHEET NAME NUMBER
PROJECT NUMBER (SPUR)
CHECKED BY
REGISTRATION
THIS DRAWING IS THE PROPERTY OF
SPUR DESIGN, LLC. THIS DRAWING IS
SUBMITTED UNDER A CONFIDENTIAL
RELATIONSHIP FOR A SPECIFIED
PURPOSE & THE RECIPIENT, BY
ACCEPTING THIS DOCUMENT, ASSUMES
CUSTODY & AGREES THAT THIS
DOCUMENT WILL NOT BE COPIED OR
REPRODUCED IN WHOLE OR IN PART, NOR
ITS CONTENTS BE REVEALED IN ANY
MANNER OR TO ANY PERSON EXCEPT TO
MEET THE PURPOSE FOR WHICH IT WAS
DELIVERED WITHOUT EXPRESS WRITTEN
PERMISSION FROM SPUR DESIGN, LLC.
S P U R D E S I G N
W W W . S P U R - D E S I G N . C O M
312 S W 25 T H S T R E E T ( 4 0 5 ) 8 4 2 - 6 1 0 0
Drawing #
(2291.01)
GI001
23-1FC01327
NR
BGJ
05/16/2025
B E
N T
A U
B H
O S
P
IT
A L
G R
E E
N E
L E
V A
T O
R M
O D
E R
N
IZ
A T
IO
N
B
E N
T A
U B
L O
O P
H O
U S
T O
N T
X
GENERAL INFORMATION
S U
B M
IS
S
IO
N
P neumatic Tube
N
KEY PLAN
GREEN ELEVATORS
10 11 12
2.08 2.082.08
2.07
2.06
2.09
2.05
2.11
2.22
2.05
2.21
2.05
2.222.22
2.08
2.05
2.082.08
2.06
2.052.05
2.09
2.21
2.21 2.22
2.222.22
10 11 12
10.32 10.3210.32
10.30
8.03
10.31
8.03
8.03
2.09
2.11
2.21
2.22
2.222.22
10.32 10.3210.32
10.30
8.038.038.03
2.09
2.21
2.21
2.22 2.222.22
GENERAL DEMOLITION NOTES
1. ALL EXISTING WALL DIMENSIONS ARE TO FINISH FACE, UNLESS OTHERWISE NOTED
2. THE CONTRACTOR SHALL VERIFY DIMENSIONS OF AS-BUILT CONDITIONS, AND NOTIFY THE
ARCHITECT IN WRITING OF ANY DISCREPANCIES. ALL INFORMATION SHOWN ON THE
CONSTRUCTION DOCUMENTS IS BASED ON FIELD OBSERVATIONS AND/OR THE ORIGINAL
CONSTRUCTION DOCUMENTS OF THE FACILITY.
3. DEMOLITION AND CONSTRUCTION WORK MUST BE DONE UNDER NEGATIVE PRESSURE UTILIZING
HEPA FILTRATION UNITS. REFER TO HARRIS HEALTH STANDARDS FOR CONTAINMENT.
4. DO NOT REMOVE BARRIERS FROM WORK AREA UNTIL COMPLETED PROJECT OR AREA HAS BEEN
INSPECTED BY THE SAFETY OFFICER AND INFECTION CONTROL COORDINATOR AND
THOROUGHLY CLEANED BY ENVIRONMENTAL MANAGEMENT SERVICES.
5. CONTRACTOR TO COORDINATE ANY SHUT DOWNS WITH THE OWNER PRIOR TO AND WITH
ADVANCE NOTICE.
6. THE CONTRACTOR SHALL PROVIDE PROTECTIVE COVERING FOR EXISTING FLOOR, WALL AND
CEILING FINISHES IN EXISTING AREAS NOT DESIGNATED FOR DEMOLITION OR NEW
CONSTRUCTION. THE CONTRACTOR SHALL BE RESPONSIBLE FOR THE REPAIR OF ANY DAMAGE
CAUSED BY THIER WORK OR ANY SUBCONTRACTOR.
7. CONTRACTOR TO PROTECT ALL EXISTING ITEMS, WHICH INCLUDE BUT NOT LIMITED TO: WALL
FINISHES, WALL PROTECTION, FLOOR BASE, ELEVATOR DOOR FRAME, CEILINGS, ETC.
NEW DOOR, FRAME AND
HARDWARE IN EXISTING
PARTITION
FLOOR PLAN LEGEND
AREA NOT IN CONTRACT
NEW PARTITION
EXISTING PARTITION TO
REMAIN
NOTE: ALL SYMBOLS MAY NOT BE USED.
EXISTING DOOR & FRAME
EXISTING WINDOW
EXISTING MILLWORK
NEW MILLWORK
NEW WINDOW
NEW DOOR, FRAME AND
HARDWARE IN NEW
PARTITION
EXISTING DOOR, FRAME AND
HARDWARE TO BE
DEMOLISHED
DEMOLITION FLOOR PLAN LEGEND
AREA NOT IN CONTRACT
EXISTING PARTITION TO BE
DEMOLISHED
EXISTING PARTITION TO
REMAIN
NOTE: ALL SYMBOLS MAY NOT BE USED.
EXISTING DOOR & FRAME TO
REMAIN
EXISTING WINDOW & FRAME
TO REMAIN
EXISTING WINDOW & FRAME
TO BE DEMOLISHED
EXISTING MILLWORK TO
REMAIN
EXISTING MILLWORK TO BE
DEMOLISHED
GENERAL PLAN NOTES
1. ELEVATOR DOOR, CAB INTERIORS, CALL LANTERNS, AND ELEVATOR EQUIPMENT
REPLACEMENTS.
2. PATCH AND REPAIR ANY ELEVATOR LOBBY WALLS WITH MATCHING FINISHES.
3. CONTRACTOR TO COORDINATE ANY SHUT DOWNS WITH THE OWNER PRIOR TO AND WITH
ADVANCE NOTICE.
9 10
G
H
J
K
9.18.6 9.7 10.2
ELEV. LOBBY
B513
'-0
'-0
'-0
'-0
36'-10"
8'-11" 1'-6" 16'-0" 5'-6" 4'-11"
5'-0"
2.12
ELEV. 7
ELEV. 8
ELEV. 9 ELEV. 12
ELEV. 11
ELEV. 10
2.23
2.23
2.23
2.23
2.23
2.23
12'-0"
M
IN
4' -0
4'
-0
AE1004 3
9 10
G
H
J
K
AE1006 5
9.18.6 9.7 10.2
ELEV. LOBBY
B513
'-0
'-0
'-0
'-0
36'-10"
8'-11" 1'-6" 16'-0" 5'-6" 4'-11"
AF701
ELEV. 7
ELEV. 8
ELEV. 9
ELEV. 10
ELEV. 11
ELEV. 12
9.88
9.88
9.88
9.88
9.88
9.88
PARTITION LEGEND
EXISTING WALL TO REMAINEXISTING 2 HOUR FIRE
CONSTRUCTION
CONTAINMENT BARRIER
REVISIONS
ISSUE DATE
DRAWN BY
SHEET NAME NUMBER
PROJECT NUMBER (SPUR)
CHECKED BY
REGISTRATION
THIS DRAWING IS THE PROPERTY OF
SPUR DESIGN, LLC. THIS DRAWING IS
SUBMITTED UNDER A CONFIDENTIAL
RELATIONSHIP FOR A SPECIFIED
PURPOSE & THE RECIPIENT, BY
ACCEPTING THIS DOCUMENT, ASSUMES
CUSTODY & AGREES THAT THIS
DOCUMENT WILL NOT BE COPIED OR
REPRODUCED IN WHOLE OR IN PART, NOR
ITS CONTENTS BE REVEALED IN ANY
MANNER OR TO ANY PERSON EXCEPT TO
MEET THE PURPOSE FOR WHICH IT WAS
DELIVERED WITHOUT EXPRESS WRITTEN
PERMISSION FROM SPUR DESIGN, LLC.
S P U R D E S I G N
W W W . S P U R - D E S I G N . C O M
312 S W 25 T H S T R E E T ( 4 0 5 ) 8 4 2 - 6 1 0 0
Drawing #
(2291.01)
AE100
23-1FC01327
KJW
NR
08/09/2023
B E
N T
A U
B H
O S
P
IT
A L
G R
E E
N E
L E
V A
T O
R M
O D
E R
N
IZ
A T
IO
N
B
E N
T A
U B
L O
O P
H O
U S
T O
N T
X
BASEMENT
S U
B M
IS
S
IO
N
3/8" = 1'-0" 1/ AE100
ELEVATOR LOBBY (B513) - DEMO ELEVATION - #10, #11, & #1233/8" = 1'-0" 1/ AE100
ELEVATOR LOBBY (B513) - DEMO ELEVATION - #7, #8, & #94
3/8" = 1'-0" 2/ AE100
ELEVATOR LOBBY (B513) - NEW ELEVATION - #10, #11, & #1253/8" = 1'-0" 2/ AE100
ELEVATOR LOBBY (B513) - NEW ELEVATION - #7, #8, & #96
KEYNOTE LEGEND
2.05 REMOVE ELEVATOR DOOR AND REPLACE WITH NEW ELEVATOR DOOR
2.06 EXISTING HALL STATION TO BE REMOVED AND REPLACED.
2.07 EXISTING ICON RISER TO BE REMOVED AND REPLACED.
2.08 EXISTING HALL LANTERNS TO BE REMOVED AND REPLACED.
2.09 EXISTING WAYFINDING MAP TO REMAIN.
2.11 EXISTING HAND SANITIZER TO REMAIN.
2.12 PROVIDE FULL HEIGHT CONSTRUCTION BARRIER WHILE RENOVATION IS TAKING PLACE. PER
HARRIS HEALTH, ONLY ONE ELEVATOR BANK (GROUP OF 3 ELEVATORS) WILL BE DONE AT A
TIME FOR RENOVATION. CONSTRUCTION BARRIER TO BE MOVED TO THE NEXT ELEVATOR
BANK ONLY WHEN CONSTRUCTION IS COMPLETE AND APPROVED TO BE MOVED BY THE
HOSPITAL.
2.21 EXISTING WALL PROTECTION TO REMAIN.
2.22 EXISTING ELEVARTOR DOOR FRAME TO REMAIN.
2.23 CAB INTERIORS TO BE REMOVED AND PREPARED FOR NEW FINISHES. THIS INCLUDES:
FLOORING, WALL PANELS, RAILS, AND CEILINGS.
8.03 NEW STAINLESS STEEL ELEVATOR DOOR
9.88 NEW ELEVATOR FINISHES. REFER TO SHEET AF701 AND SPECIFICATIONS.
10.30 PROVIDE NEW HALL STATION. REFER TO SPECIFICATIONS.
10.31 PROVIDE NEW ICON RISER. REFER TO SPECIFICATIONS.
10.32 PROVIDE NEW HALL LANTERNS. REFER TO SPECIFICATIONS.
N
1/8" = 1'-0"
BASEMENT - DEMOLITION PLAN1
N
1/8" = 1'-0"
BASEMENT - REFERENCE PLAN2
1 Addendum 01
8/7/25
9 10
G
H
J
K
ELEV. LOBBY
AE101AE101 56
9.18.6 9.7 10.2
'-0
'-0
'-0
'-0
36'-10"
8'-11" 1'-6" 16'-0" 5'-6" 4'-11"
ELEV. 7
ELEV. 8
ELEV. 9
ELEV. 10
ELEV. 11
ELEV. 12
9.88
9.88
9.88
9.88
9.88
9.88
N
KEY PLAN
GREEN ELEVATORS
10 11 12
2.08
2.052.05
2.06
2.09
2.08 2.08
2.05
2.10
2.10
2.10
2.11 2.07
2.052.05 2.05
2.08 2.08
2.06
2.08
2.09
2.10
2.10 2.10
10 11 12 2.09
10.32
8.038.03
10.30
10.32 10.32
8.03
2.10 2.10 2.10
2.11 10.31
10.32
8.038.038.03
10.32 10.32
2.09
10.30
2.10
2.102.10
GENERAL DEMOLITION NOTES
1. ALL EXISTING WALL DIMENSIONS ARE TO FINISH FACE, UNLESS OTHERWISE NOTED
2. THE CONTRACTOR SHALL VERIFY DIMENSIONS OF AS-BUILT CONDITIONS, AND NOTIFY THE
ARCHITECT IN WRITING OF ANY DISCREPANCIES. ALL INFORMATION SHOWN ON THE
CONSTRUCTION DOCUMENTS IS BASED ON FIELD OBSERVATIONS AND/OR THE ORIGINAL
CONSTRUCTION DOCUMENTS OF THE FACILITY.
3. DEMOLITION AND CONSTRUCTION WORK MUST BE DONE UNDER NEGATIVE PRESSURE UTILIZING
HEPA FILTRATION UNITS. REFER TO HARRIS HEALTH STANDARDS FOR CONTAINMENT.
4. DO NOT REMOVE BARRIERS FROM WORK AREA UNTIL COMPLETED PROJECT OR AREA HAS BEEN
INSPECTED BY THE SAFETY OFFICER AND INFECTION CONTROL COORDINATOR AND
THOROUGHLY CLEANED BY ENVIRONMENTAL MANAGEMENT SERVICES.
5. CONTRACTOR TO COORDINATE ANY SHUT DOWNS WITH THE OWNER PRIOR TO AND WITH
ADVANCE NOTICE.
6. THE CONTRACTOR SHALL PROVIDE PROTECTIVE COVERING FOR EXISTING FLOOR, WALL AND
CEILING FINISHES IN EXISTING AREAS NOT DESIGNATED FOR DEMOLITION OR NEW
CONSTRUCTION. THE CONTRACTOR SHALL BE RESPONSIBLE FOR THE REPAIR OF ANY DAMAGE
CAUSED BY THIER WORK OR ANY SUBCONTRACTOR.
7. CONTRACTOR TO PROTECT ALL EXISTING ITEMS, WHICH INCLUDE BUT NOT LIMITED TO: WALL
FINISHES, WALL PROTECTION, FLOOR BASE, ELEVATOR DOOR FRAME, CEILINGS, ETC.
NEW DOOR, FRAME AND
HARDWARE IN EXISTING
PARTITION
FLOOR PLAN LEGEND
AREA NOT IN CONTRACT
NEW PARTITION
EXISTING PARTITION TO
REMAIN
NOTE: ALL SYMBOLS MAY NOT BE USED.
EXISTING DOOR & FRAME
EXISTING WINDOW
EXISTING MILLWORK
NEW MILLWORK
NEW WINDOW
NEW DOOR, FRAME AND
HARDWARE IN NEW
PARTITION
EXISTING DOOR, FRAME AND
HARDWARE TO BE
DEMOLISHED
DEMOLITION FLOOR PLAN LEGEND
AREA NOT IN CONTRACT
EXISTING PARTITION TO BE
DEMOLISHED
EXISTING PARTITION TO
REMAIN
NOTE: ALL SYMBOLS MAY NOT BE USED.
EXISTING DOOR & FRAME TO
REMAIN
EXISTING WINDOW & FRAME
TO REMAIN
EXISTING WINDOW & FRAME
TO BE DEMOLISHED
EXISTING MILLWORK TO
REMAIN
EXISTING MILLWORK TO BE
DEMOLISHED
GENERAL PLAN NOTES
1. ELEVATOR DOOR, CAB INTERIORS, CALL LANTERNS, AND ELEVATOR EQUIPMENT
REPLACEMENTS.
2. PATCH AND REPAIR ANY ELEVATOR LOBBY WALLS WITH MATCHING FINISHES.
3. CONTRACTOR TO COORDINATE ANY SHUT DOWNS WITH THE OWNER PRIOR TO AND WITH
ADVANCE NOTICE.
9 10
G
H
J
K
9.18.6 9.7 10.2
ELEV. LOBBY
'-0
'-0
'-0
'-0
36'-10"
8'-11" 1'-6" 16'-0" 5'-6" 4'-11"
2.12
ELEV. 7
ELEV. 8
ELEV. 9 ELEV. 12
ELEV. 11
ELEV. 10
2.23
2.23
2.23
2.23
2.23
2.23
4' -0
12'-0"
AE1014 3
M
IN
4' -0
PARTITION LEGEND
EXISTING WALL TO REMAINEXISTING 2 HOUR FIRE
CONSTRUCTION
CONTAINMENT BARRIER
REVISIONS
ISSUE DATE
DRAWN BY
SHEET NAME NUMBER
PROJECT NUMBER (SPUR)
CHECKED BY
REGISTRATION
THIS DRAWING IS THE PROPERTY OF
SPUR DESIGN, LLC. THIS DRAWING IS
SUBMITTED UNDER A CONFIDENTIAL
RELATIONSHIP FOR A SPECIFIED
PURPOSE & THE RECIPIENT, BY
ACCEPTING THIS DOCUMENT, ASSUMES
CUSTODY & AGREES THAT THIS
DOCUMENT WILL NOT BE COPIED OR
REPRODUCED IN WHOLE OR IN PART, NOR
ITS CONTENTS BE REVEALED IN ANY
MANNER OR TO ANY PERSON EXCEPT TO
MEET THE PURPOSE FOR WHICH IT WAS
DELIVERED WITHOUT EXPRESS WRITTEN
PERMISSION FROM SPUR DESIGN, LLC.
S P U R D E S I G N
W W W . S P U R - D E S I G N . C O M
312 S W 25 T H S T R E E T ( 4 0 5 ) 8 4 2 - 6 1 0 0
Drawing #
(2291.01)
AE101
23-1FC01327
KJW
NR
08/09/2023
B E
N T
A U
B H
O S
P
IT
A L
G R
E E
N E
L E
V A
T O
R M
O D
E R
N
IZ
A T
IO
N
B
E N
T A
U B
L O
O P
H O
U S
T O
N T
X
LEVEL 1
S U
B M
IS
S
IO
N
N
1/8" = 1'-0"
LEVEL 1 - REFERENCE PLAN2
3/8" = 1'-0" 1/ AE101
ELEVATOR LOBBY (1511) - DEMO ELEVATION - #10, #11, & #1233/8" = 1'-0" 1/ AE101
ELEVATOR LOBBY (1511) - DEMO ELEVATION - #7, #8, & #94
3/8" = 1'-0" 2/ AE101
ELEVATOR LOBBY (1511) - NEW ELEVATION - #10, #11, & #1253/8" = 1'-0" 2/ AE101
ELEVATOR LOBBY (1511) - NEW ELEVATION - #7, #8, & #96
KEYNOTE LEGEND
2.05 REMOVE ELEVATOR DOOR AND REPLACE WITH NEW ELEVATOR DOOR
2.06 EXISTING HALL STATION TO BE REMOVED AND REPLACED.
2.07 EXISTING ICON RISER TO BE REMOVED AND REPLACED.
2.08 EXISTING HALL LANTERNS TO BE REMOVED AND REPLACED.
2.09 EXISTING WAYFINDING MAP TO REMAIN.
2.10 EXISTING ELEVATOR FRAME TO REMAIN.
2.11 EXISTING HAND SANITIZER TO REMAIN.
2.12 PROVIDE FULL HEIGHT CONSTRUCTION BARRIER WHILE RENOVATION IS TAKING PLACE. PER
HARRIS HEALTH, ONLY ONE ELEVATOR BANK (GROUP OF 3 ELEVATORS) WILL BE DONE AT A
TIME FOR RENOVATION. CONSTRUCTION BARRIER TO BE MOVED TO THE NEXT ELEVATOR
BANK ONLY WHEN CONSTRUCTION IS COMPLETE AND APPROVED TO BE MOVED BY THE
HOSPITAL.
2.23 CAB INTERIORS TO BE REMOVED AND PREPARED FOR NEW FINISHES. THIS INCLUDES:
FLOORING, WALL PANELS, RAILS, AND CEILINGS.
8.03 NEW STAINLESS STEEL ELEVATOR DOOR
9.88 NEW ELEVATOR FINISHES. REFER TO SHEET AF701 AND SPECIFICATIONS.
10.30 PROVIDE NEW HALL STATION. REFER TO SPECIFICATIONS.
10.31 PROVIDE NEW ICON RISER. REFER TO SPECIFICATIONS.
10.32 PROVIDE NEW HALL LANTERNS. REFER TO SPECIFICATIONS.
N
1/8" = 1'-0"
LEVEL 1 - DEMOLITION PLAN1
1 Addendum 01
PHYS.
LOUNGE
CORR.
GUEST
TRANSP.
N
KEY PLAN
GREEN ELEVATORS
9 10
G
H
J
K
ELEV. LOBBY
AE1026 5
9.18.6 9.7 10.2
36'-10"
8'-11" 1'-6" 16'-0" 5'-6" 4'-11"
'-0
'-0
'-0
'-0
ELEV. 7
ELEV. 8
ELEV. 9
ELEV. 10
ELEV. 11
ELEV. 12
9.88
9.88
9.88 9.88
9.88
9.88
10 11 12
2.052.05
2.08 2.082.08
2.07
2.06
2.05
2.10
2.10
2.10
2.13
2.052.05
2.08
2.082.08
2.06
2.092.10 2.10
2.11
11 1210
10.32
8.03
10.30
10.3210.32
10.31
8.03
2.10
2.10
2.10
2.13
10.32
8.038.03
10.3210.32
10.30
2.09
2.10
2.10
2.11
GENERAL DEMOLITION NOTES
1. ALL EXISTING WALL DIMENSIONS ARE TO FINISH FACE, UNLESS OTHERWISE NOTED
2. THE CONTRACTOR SHALL VERIFY DIMENSIONS OF AS-BUILT CONDITIONS, AND NOTIFY THE
ARCHITECT IN WRITING OF ANY DISCREPANCIES. ALL INFORMATION SHOWN ON THE
CONSTRUCTION DOCUMENTS IS BASED ON FIELD OBSERVATIONS AND/OR THE ORIGINAL
CONSTRUCTION DOCUMENTS OF THE FACILITY.
3. DEMOLITION AND CONSTRUCTION WORK MUST BE DONE UNDER NEGATIVE PRESSURE UTILIZING
HEPA FILTRATION UNITS. REFER TO HARRIS HEALTH STANDARDS FOR CONTAINMENT.
4. DO NOT REMOVE BARRIERS FROM WORK AREA UNTIL COMPLETED PROJECT OR AREA HAS BEEN
INSPECTED BY THE SAFETY OFFICER AND INFECTION CONTROL COORDINATOR AND
THOROUGHLY CLEANED BY ENVIRONMENTAL MANAGEMENT SERVICES.
5. CONTRACTOR TO COORDINATE ANY SHUT DOWNS WITH THE OWNER PRIOR TO AND WITH
ADVANCE NOTICE.
6. THE CONTRACTOR SHALL PROVIDE PROTECTIVE COVERING FOR EXISTING FLOOR, WALL AND
CEILING FINISHES IN EXISTING AREAS NOT DESIGNATED FOR DEMOLITION OR NEW
CONSTRUCTION. THE CONTRACTOR SHALL BE RESPONSIBLE FOR THE REPAIR OF ANY DAMAGE
CAUSED BY THIER WORK OR ANY SUBCONTRACTOR.
7. CONTRACTOR TO PROTECT ALL EXISTING ITEMS, WHICH INCLUDE BUT NOT LIMITED TO: WALL
FINISHES, WALL PROTECTION, FLOOR BASE, ELEVATOR DOOR FRAME, CEILINGS, ETC.
NEW DOOR, FRAME AND
HARDWARE IN EXISTING
PARTITION
FLOOR PLAN LEGEND
AREA NOT IN CONTRACT
NEW PARTITION
EXISTING PARTITION TO
REMAIN
NOTE: ALL SYMBOLS MAY NOT BE USED.
EXISTING DOOR & FRAME
EXISTING WINDOW
EXISTING MILLWORK
NEW MILLWORK
NEW WINDOW
NEW DOOR, FRAME AND
HARDWARE IN NEW
PARTITION
EXISTING DOOR, FRAME AND
HARDWARE TO BE
DEMOLISHED
DEMOLITION FLOOR PLAN LEGEND
AREA NOT IN CONTRACT
EXISTING PARTITION TO BE
DEMOLISHED
EXISTING PARTITION TO
REMAIN
NOTE: ALL SYMBOLS MAY NOT BE USED.
EXISTING DOOR & FRAME TO
REMAIN
EXISTING WINDOW & FRAME
TO REMAIN
EXISTING WINDOW & FRAME
TO BE DEMOLISHED
EXISTING MILLWORK TO
REMAIN
EXISTING MILLWORK TO BE
DEMOLISHED
GENERAL PLAN NOTES
1. ELEVATOR DOOR, CAB INTERIORS, CALL LANTERNS, AND ELEVATOR EQUIPMENT
REPLACEMENTS.
2. PATCH AND REPAIR ANY ELEVATOR LOBBY WALLS WITH MATCHING FINISHES.
3. CONTRACTOR TO COORDINATE ANY SHUT DOWNS WITH THE OWNER PRIOR TO AND WITH
ADVANCE NOTICE.
9 10
G
H
J
K
9.18.6 9.7 10.2
ELEV. LOBBY
36'-10"
8'-11" 1'-6" 16'-0" 5'-6" 4'-11"
'-0
'-0
'-0
'-0
2.12
ELEV. 7
ELEV. 8
ELEV. 9 ELEV. 12
ELEV. 11
ELEV. 10
2.23
2.23
2.23 2.23
2.23
2.23
12'-0" 4'
-0
M
IN
4' -0
AE1024 3
PARTITION LEGEND
EXISTING WALL TO REMAINEXISTING 2 HOUR FIRE
CONSTRUCTION
CONTAINMENT BARRIER
REVISIONS
ISSUE DATE
DRAWN BY
SHEET NAME NUMBER
PROJECT NUMBER (SPUR)
CHECKED BY
REGISTRATION
THIS DRAWING IS THE PROPERTY OF
SPUR DESIGN, LLC. THIS DRAWING IS
SUBMITTED UNDER A CONFIDENTIAL
RELATIONSHIP FOR A SPECIFIED
PURPOSE & THE RECIPIENT, BY
ACCEPTING THIS DOCUMENT, ASSUMES
CUSTODY & AGREES THAT THIS
DOCUMENT WILL NOT BE COPIED OR
REPRODUCED IN WHOLE OR IN PART, NOR
ITS CONTENTS BE REVEALED IN ANY
MANNER OR TO ANY PERSON EXCEPT TO
MEET THE PURPOSE FOR WHICH IT WAS
DELIVERED WITHOUT EXPRESS WRITTEN
PERMISSION FROM SPUR DESIGN, LLC.
S P U R D E S I G N
W W W . S P U R - D E S I G N . C O M
312 S W 25 T H S T R E E T ( 4 0 5 ) 8 4 2 - 6 1 0 0
Drawing #
(2291.01)
AE102
23-1FC01327
KJW
NR
08/09/2023
B E
N T
A U
B H
O S
P
IT
A L
G R
E E
N E
L E
V A
T O
R M
O D
E R
N
IZ
A T
IO
N
B
E N
T A
U B
L O
O P
H O
U S
T O
N T
X
LEVEL 2
S U
B M
IS
S
IO
N
N
1/8" = 1'-0"
LEVEL 2 - REFERENCE PLAN2
3/8" = 1'-0" 1/ AE102
ELEVATOR LOBBY (2513) - DEMO ELEVATION - #10, #11, & #1233/8" = 1'-0" 1/ AE102
ELEVATOR LOBBY (2513) - DEMO ELEVATION - #7, #8, & #94
3/8" = 1'-0" 2/ AE102
ELEVATOR LOBBY (2513) - NEW ELEVATION - #10, #11, & #125
3/8" = 1'-0" 2/ AE102
ELEVATOR LOBBY (2513) - NEW ELEVATION - #7, #8, & #96
N
1/8" = 1'-0"
LEVEL 2 - DEMOLITION PLAN1
KEYNOTE LEGEND
2.05 REMOVE ELEVATOR DOOR AND REPLACE WITH NEW ELEVATOR DOOR
2.06 EXISTING HALL STATION TO BE REMOVED AND REPLACED.
2.07 EXISTING ICON RISER TO BE REMOVED AND REPLACED.
2.08 EXISTING HALL LANTERNS TO BE REMOVED AND REPLACED.
2.09 EXISTING WAYFINDING MAP TO REMAIN.
2.10 EXISTING ELEVATOR FRAME TO REMAIN.
2.11 EXISTING HAND SANITIZER TO REMAIN.
2.12 PROVIDE FULL HEIGHT CONSTRUCTION BARRIER WHILE RENOVATION IS TAKING PLACE. PER
HARRIS HEALTH, ONLY ONE ELEVATOR BANK (GROUP OF 3 ELEVATORS) WILL BE DONE AT A
TIME FOR RENOVATION. CONSTRUCTION BARRIER TO BE MOVED TO THE NEXT ELEVATOR
BANK ONLY WHEN CONSTRUCTION IS COMPLETE AND APPROVED TO BE MOVED BY THE
HOSPITAL.
2.13 EXISTING EMERGENCY EGRESS MAP TO REMAIN.
2.23 CAB INTERIORS TO BE REMOVED AND PREPARED FOR NEW FINISHES. THIS INCLUDES:
FLOORING, WALL PANELS, RAILS, AND CEILINGS.
8.03 NEW STAINLESS STEEL ELEVATOR DOOR
9.88 NEW ELEVATOR FINISHES. REFER TO SHEET AF701 AND SPECIFICATIONS.
10.30 PROVIDE NEW HALL STATION. REFER TO SPECIFICATIONS.
10.31 PROVIDE NEW ICON RISER. REFER TO SPECIFICATIONS.
10.32 PROVIDE NEW HALL LANTERNS. REFER TO SPECIFICATIONS.
1 Addendum 01
D N
U P
D NU P
D N
U P
D N
U P
D N
U P
FEFEFE
OR LEV 2 &
C-SECTION
LABOR &
DELIVERY
STAIR
F
PUBLIC
CIRCULATION
PUBLIC
SPACES
3000- F
DN
UP
DN
UP
N
KEY PLAN
GREEN ELEVATORS
9 10
G
H
J
K
ELEV. LOBBY
AE1036 5
9.18.6 9.7 10.2
36'-10"
8'-11" 1'-6" 16'-0" 5'-6" 4'-11"
'-0
'-0
'-0
'-0
ELEV. 7
ELEV. 8
ELEV. 9 ELEV. 12
ELEV. 11
ELEV. 10
9.88 9.88
9.88
9.889.88
9.88
10 11 12
2.052.05
2.08 2.082.08
2.07
2.05
2.06
2.09
2.10
2.10
2.10
2.112.052.05
2.082.08 2.08
2.05
2.06
2.09
2.10 2.10 2.10
10.3210.3210.32
10 11 12
10.318.038.03
10.30
2.09
2.10
2.10 2.10
2.11
10.32
8.038.03
10.3210.32
10.30
2.09
2.10 2.10
2.10
GENERAL DEMOLITION NOTES
1. ALL EXISTING WALL DIMENSIONS ARE TO FINISH FACE, UNLESS OTHERWISE NOTED
2. THE CONTRACTOR SHALL VERIFY DIMENSIONS OF AS-BUILT CONDITIONS, AND NOTIFY THE
ARCHITECT IN WRITING OF ANY DISCREPANCIES. ALL INFORMATION SHOWN ON THE
CONSTRUCTION DOCUMENTS IS BASED ON FIELD OBSERVATIONS AND/OR THE ORIGINAL
CONSTRUCTION DOCUMENTS OF THE FACILITY.
3. DEMOLITION AND CONSTRUCTION WORK MUST BE DONE UNDER NEGATIVE PRESSURE UTILIZING
HEPA FILTRATION UNITS. REFER TO HARRIS HEALTH STANDARDS FOR CONTAINMENT.
4. DO NOT REMOVE BARRIERS FROM WORK AREA UNTIL COMPLETED PROJECT OR AREA HAS BEEN
INSPECTED BY THE SAFETY OFFICER AND INFECTION CONTROL COORDINATOR AND
THOROUGHLY CLEANED BY ENVIRONMENTAL MANAGEMENT SERVICES.
5. CONTRACTOR TO COORDINATE ANY SHUT DOWNS WITH THE OWNER PRIOR TO AND WITH
ADVANCE NOTICE.
6. THE CONTRACTOR SHALL PROVIDE PROTECTIVE COVERING FOR EXISTING FLOOR, WALL AND
CEILING FINISHES IN EXISTING AREAS NOT DESIGNATED FOR DEMOLITION OR NEW
CONSTRUCTION. THE CONTRACTOR SHALL BE RESPONSIBLE FOR THE REPAIR OF ANY DAMAGE
CAUSED BY THIER WORK OR ANY SUBCONTRACTOR.
7. CONTRACTOR TO PROTECT ALL EXISTING ITEMS, WHICH INCLUDE BUT NOT LIMITED TO: WALL
FINISHES, WALL PROTECTION, FLOOR BASE, ELEVATOR DOOR FRAME, CEILINGS, ETC.
NEW DOOR, FRAME AND
HARDWARE IN EXISTING
PARTITION
FLOOR PLAN LEGEND
AREA NOT IN CONTRACT
NEW PARTITION
EXISTING PARTITION TO
REMAIN
NOTE: ALL SYMBOLS MAY NOT BE USED.
EXISTING DOOR & FRAME
EXISTING WINDOW
EXISTING MILLWORK
NEW MILLWORK
NEW WINDOW
NEW DOOR, FRAME AND
HARDWARE IN NEW
PARTITION
EXISTING DOOR, FRAME AND
HARDWARE TO BE
DEMOLISHED
DEMOLITION FLOOR PLAN LEGEND
AREA NOT IN CONTRACT
EXISTING PARTITION TO BE
DEMOLISHED
EXISTING PARTITION TO
REMAIN
NOTE: ALL SYMBOLS MAY NOT BE USED.
EXISTING DOOR & FRAME TO
REMAIN
EXISTING WINDOW & FRAME
TO REMAIN
EXISTING WINDOW & FRAME
TO BE DEMOLISHED
EXISTING MILLWORK TO
REMAIN
EXISTING MILLWORK TO BE
DEMOLISHED
GENERAL PLAN NOTES
1. ELEVATOR DOOR, CAB INTERIORS, CALL LANTERNS, AND ELEVATOR EQUIPMENT
REPLACEMENTS.
2. PATCH AND REPAIR ANY ELEVATOR LOBBY WALLS WITH MATCHING FINISHES.
3. CONTRACTOR TO COORDINATE ANY SHUT DOWNS WITH THE OWNER PRIOR TO AND WITH
ADVANCE NOTICE.
9 10
G
H
J
K
9.18.6 9.7 10.2
ELEV. LOBBY
36'-10"
8'-11" 1'-6" 16'-0" 5'-6" 4'-11"
'-0
'-0
'-0
'-0
ELEV. 7
ELEV. 8
ELEV. 9 ELEV. 12
ELEV. 11
ELEV. 10
2.23
2.23
2.23
2.23
2.23
2.23
12'-0"
M
IN
4' -0
4'
-0
2.12
AE1034 3
PARTITION LEGEND
EXISTING WALL TO REMAINEXISTING 2 HOUR FIRE
CONSTRUCTION
CONTAINMENT BARRIER
REVISIONS
ISSUE DATE
DRAWN BY
SHEET NAME NUMBER
PROJECT NUMBER (SPUR)
CHECKED BY
REGISTRATION
THIS DRAWING IS THE PROPERTY OF
SPUR DESIGN, LLC. THIS DRAWING IS
SUBMITTED UNDER A CONFIDENTIAL
RELATIONSHIP FOR A SPECIFIED
PURPOSE & THE RECIPIENT, BY
ACCEPTING THIS DOCUMENT, ASSUMES
CUSTODY & AGREES THAT THIS
DOCUMENT WILL NOT BE COPIED OR
REPRODUCED IN WHOLE OR IN PART, NOR
ITS CONTENTS BE REVEALED IN ANY
MANNER OR TO ANY PERSON EXCEPT TO
MEET THE PURPOSE FOR WHICH IT WAS
DELIVERED WITHOUT EXPRESS WRITTEN
PERMISSION FROM SPUR DESIGN, LLC.
S P U R D E S I G N
W W W . S P U R - D E S I G N . C O M
312 S W 25 T H S T R E E T ( 4 0 5 ) 8 4 2 - 6 1 0 0
Drawing #
(2291.01)
AE103
23-1FC01327
KJW
NR
08/09/2023
B E
N T
A U
B H
O S
P
IT
A L
G R
E E
N E
L E
V A
T O
R M
O D
E R
N
IZ
A T
IO
N
B
E N
T A
U B
L O
O P
H O
U S
T O
N T
X
LEVEL 3
S U
B M
IS
S
IO
N
N
1/8" = 1'-0"
LEVEL 3 - REFERENCE PLAN2
3/8" = 1'-0" 1/ AE103
ELEVATOR LOBBY (3539) - DEMO ELEVATION - #10, #11, & #1233/8" = 1'-0"
ELEVATOR LOBBY (3539) - DEMO ELEVATION - #7, #8, & #94
3/8" = 1'-0" 2/ AE103
ELEVATOR LOBBY (3539) - NEW ELEVATION - #10, #11, & #1253/8" = 1'-0" 2/ AE103
ELEVATOR LOBBY (3539) - NEW ELEVATION - #7, #8, & #96
N
1/8" = 1'-0"
LEVEL 3 - DEMOLITION PLAN1
KEYNOTE LEGEND
2.05 REMOVE ELEVATOR DOOR AND REPLACE WITH NEW ELEVATOR DOOR
2.06 EXISTING HALL STATION TO BE REMOVED AND REPLACED.
2.07 EXISTING ICON RISER TO BE REMOVED AND REPLACED.
2.08 EXISTING HALL LANTERNS TO BE REMOVED AND REPLACED.
2.09 EXISTING WAYFINDING MAP TO REMAIN.
2.10 EXISTING ELEVATOR FRAME TO REMAIN.
2.11 EXISTING HAND SANITIZER TO REMAIN.
2.12 PROVIDE FULL HEIGHT CONSTRUCTION BARRIER WHILE RENOVATION IS TAKING PLACE. PER
HARRIS HEALTH, ONLY ONE ELEVATOR BANK (GROUP OF 3 ELEVATORS) WILL BE DONE AT A
TIME FOR RENOVATION. CONSTRUCTION BARRIER TO BE MOVED TO THE NEXT ELEVATOR
BANK ONLY WHEN CONSTRUCTION IS COMPLETE AND APPROVED TO BE MOVED BY THE
HOSPITAL.
2.23 CAB INTERIORS TO BE REMOVED AND PREPARED FOR NEW FINISHES. THIS INCLUDES:
FLOORING, WALL PANELS, RAILS, AND CEILINGS.
8.03 NEW STAINLESS STEEL ELEVATOR DOOR
9.88 NEW ELEVATOR FINISHES. REFER TO SHEET AF701 AND SPECIFICATIONS.
10.30 PROVIDE NEW HALL STATION. REFER TO SPECIFICATIONS.
10.31 PROVIDE NEW ICON RISER. REFER TO SPECIFICATIONS.
10.32 PROVIDE NEW HALL LANTERNS. REFER TO SPECIFICATIONS.
1 Addendum 01
KEY PLAN
GREEN ELEVATORS
9 10
G
H
J
K
ELEV. LOBBY
AE104AE1046 5
9.18.6 9.7 10.2
'-0
'-0
'-0
'-0
36'-10"
8'-11" 1'-6" 16'-0" 5'-6" 4'-11"
ELEV. 7
ELEV. 8
ELEV. 9
ELEV. 10
ELEV. 11
ELEV. 12
9.88
9.88
9.88
9.88
9.88
9.88
10 11 12
2.08
2.05
2.06
2.05
2.05
2.08 2.08
2.09
2.10
2.10 2.10
2.11
2.07
2.08 2.082.08
2.06
2.052.052.05
2.09
2.10 2.102.10
10.3210.32 10.32
8.038.038.03
10.30
2.09
2.10 2.102.10
10 11 12
10.32
8.038.03
10.30
8.03
10.3210.32
2.09
2.10
2.10 2.10
2.11
10.31
GENERAL DEMOLITION NOTES
1. ALL EXISTING WALL DIMENSIONS ARE TO FINISH FACE, UNLESS OTHERWISE NOTED
2. THE CONTRACTOR SHALL VERIFY DIMENSIONS OF AS-BUILT CONDITIONS, AND NOTIFY THE
ARCHITECT IN WRITING OF ANY DISCREPANCIES. ALL INFORMATION SHOWN ON THE
CONSTRUCTION DOCUMENTS IS BASED ON FIELD OBSERVATIONS AND/OR THE ORIGINAL
CONSTRUCTION DOCUMENTS OF THE FACILITY.
3. DEMOLITION AND CONSTRUCTION WORK MUST BE DONE UNDER NEGATIVE PRESSURE UTILIZING
HEPA FILTRATION UNITS. REFER TO HARRIS HEALTH STANDARDS FOR CONTAINMENT.
4. DO NOT REMOVE BARRIERS FROM WORK AREA UNTIL COMPLETED PROJECT OR AREA HAS BEEN
INSPECTED BY THE SAFETY OFFICER AND INFECTION CONTROL COORDINATOR AND
THOROUGHLY CLEANED BY ENVIRONMENTAL MANAGEMENT SERVICES.
5. CONTRACTOR TO COORDINATE ANY SHUT DOWNS WITH THE OWNER PRIOR TO AND WITH
ADVANCE NOTICE.
6. THE CONTRACTOR SHALL PROVIDE PROTECTIVE COVERING FOR EXISTING FLOOR, WALL AND
CEILING FINISHES IN EXISTING AREAS NOT DESIGNATED FOR DEMOLITION OR NEW
CONSTRUCTION. THE CONTRACTOR SHALL BE RESPONSIBLE FOR THE REPAIR OF ANY DAMAGE
CAUSED BY THIER WORK OR ANY SUBCONTRACTOR.
7. CONTRACTOR TO PROTECT ALL EXISTING ITEMS, WHICH INCLUDE BUT NOT LIMITED TO: WALL
FINISHES, WALL PROTECTION, FLOOR BASE, ELEVATOR DOOR FRAME, CEILINGS, ETC.
NEW DOOR, FRAME AND
HARDWARE IN EXISTING
PARTITION
FLOOR PLAN LEGEND
AREA NOT IN CONTRACT
NEW PARTITION
EXISTING PARTITION TO
REMAIN
NOTE: ALL SYMBOLS MAY NOT BE USED.
EXISTING DOOR & FRAME
EXISTING WINDOW
EXISTING MILLWORK
NEW MILLWORK
NEW WINDOW
NEW DOOR, FRAME AND
HARDWARE IN NEW
PARTITION
EXISTING DOOR, FRAME AND
HARDWARE TO BE
DEMOLISHED
DEMOLITION FLOOR PLAN LEGEND
AREA NOT IN CONTRACT
EXISTING PARTITION TO BE
DEMOLISHED
EXISTING PARTITION TO
REMAIN
NOTE: ALL SYMBOLS MAY NOT BE USED.
EXISTING DOOR & FRAME TO
REMAIN
EXISTING WINDOW & FRAME
TO REMAIN
EXISTING WINDOW & FRAME
TO BE DEMOLISHED
EXISTING MILLWORK TO
REMAIN
EXISTING MILLWORK TO BE
DEMOLISHED
GENERAL PLAN NOTES
1. ELEVATOR DOOR, CAB INTERIORS, CALL LANTERNS, AND ELEVATOR EQUIPMENT
REPLACEMENTS.
2. PATCH AND REPAIR ANY ELEVATOR LOBBY WALLS WITH MATCHING FINISHES.
3. CONTRACTOR TO COORDINATE ANY SHUT DOWNS WITH THE OWNER PRIOR TO AND WITH
ADVANCE NOTICE.
9 10
G
H
J
K
9.18.6 9.7 10.2
ELEV. LOBBY
'-0
'-0
'-0
'-0
36'-10"
8'-11" 1'-6" 16'-0" 5'-6" 4'-11"
2.12
ELEV. 7
ELEV. 8
ELEV. 9
ELEV. 10
ELEV. 11
ELEV. 12
2.23
2.23
2.23
2.23
2.23
2.23
12'-0"
M
IN
4' -0
4'
-0
AE1044 3
PARTITION LEGEND
EXISTING WALL TO REMAINEXISTING 2 HOUR FIRE
CONSTRUCTION
CONTAINMENT BARRIER
REVISIONS
ISSUE DATE
DRAWN BY
SHEET NAME NUMBER
PROJECT NUMBER (SPUR)
CHECKED BY
REGISTRATION
THIS DRAWING IS THE PROPERTY OF
SPUR DESIGN, LLC. THIS DRAWING IS
SUBMITTED UNDER A CONFIDENTIAL
RELATIONSHIP FOR A SPECIFIED
PURPOSE & THE RECIPIENT, BY
ACCEPTING THIS DOCUMENT, ASSUMES
CUSTODY & AGREES THAT THIS
DOCUMENT WILL NOT BE COPIED OR
REPRODUCED IN WHOLE OR IN PART, NOR
ITS CONTENTS BE REVEALED IN ANY
MANNER OR TO ANY PERSON EXCEPT TO
MEET THE PURPOSE FOR WHICH IT WAS
DELIVERED WITHOUT EXPRESS WRITTEN
PERMISSION FROM SPUR DESIGN, LLC.
S P U R D E S I G N
W W W . S P U R - D E S I G N . C O M
312 S W 25 T H S T R E E T ( 4 0 5 ) 8 4 2 - 6 1 0 0
Drawing #
(2291.01)
AE104
23-1FC01327
KJW
NR
08/09/2023
B E
N T
A U
B H
O S
P
IT
A L
G R
E E
N E
L E
V A
T O
R M
O D
E R
N
IZ
A T
IO
N
B
E N
T A
U B
L O
O P
H O
U S
T O
N T
X
LEVEL 4
S U
B M
IS
S
IO
N
N
1/8" = 1'-0"
LEVEL 4 - REFERENCE PLAN2
3/8" = 1'-0" 1/ AE104
ELEVATOR LOBBY (4515) - DEMO ELEVATION - #10, #11, & #1233/8" = 1'-0" 1/ AE104
ELEVATOR LOBBY (4515) - DEMO ELEVATION - #7, #8, & #94
3/8" = 1'-0" 2/ AE104
ELEVATOR LOBBY (4515) - NEW ELEVATION - #7, #8, & #96 3/8" = 1'-0" 2/ AE104
ELEVATOR LOBBY (4515) - NEW ELEVATION - #10, #11, & #125
KEYNOTE LEGEND
2.05 REMOVE ELEVATOR DOOR AND REPLACE WITH NEW ELEVATOR DOOR
2.06 EXISTING HALL STATION TO BE REMOVED AND REPLACED.
2.07 EXISTING ICON RISER TO BE REMOVED AND REPLACED.
2.08 EXISTING HALL LANTERNS TO BE REMOVED AND REPLACED.
2.09 EXISTING WAYFINDING MAP TO REMAIN.
2.10 EXISTING ELEVATOR FRAME TO REMAIN.
2.11 EXISTING HAND SANITIZER TO REMAIN.
2.12 PROVIDE FULL HEIGHT CONSTRUCTION BARRIER WHILE RENOVATION IS TAKING PLACE. PER
HARRIS HEALTH, ONLY ONE ELEVATOR BANK (GROUP OF 3 ELEVATORS) WILL BE DONE AT A
TIME FOR RENOVATION. CONSTRUCTION BARRIER TO BE MOVED TO THE NEXT ELEVATOR
BANK ONLY WHEN CONSTRUCTION IS COMPLETE AND APPROVED TO BE MOVED BY THE
HOSPITAL.
2.23 CAB INTERIORS TO BE REMOVED AND PREPARED FOR NEW FINISHES. THIS INCLUDES:
FLOORING, WALL PANELS, RAILS, AND CEILINGS.
8.03 NEW STAINLESS STEEL ELEVATOR DOOR
9.88 NEW ELEVATOR FINISHES. REFER TO SHEET AF701 AND SPECIFICATIONS.
10.30 PROVIDE NEW HALL STATION. REFER TO SPECIFICATIONS.
10.31 PROVIDE NEW ICON RISER. REFER TO SPECIFICATIONS.
10.32 PROVIDE NEW HALL LANTERNS. REFER TO SPECIFICATIONS.
N
1/8" = 1'-0"
LEVEL 4 - DEMOLITION PLAN1
1 Addendum 01
D N U P
D N
U P
D N
U P
D N
U P
D N
U P
FE
FE FE FE
Fire Dept Valve
DN
UP
DN
UP
N
KEY PLAN
GREEN ELEVATORS
9 10
G
H
J
K
ELEV. LOBBY
AE1056 5
9.18.6 9.7 10.2
36'-10"
8'-11" 1'-6" 16'-0" 5'-6" 4'-11"
'-0
'-0
'-0
'-0
ELEV. 7
ELEV. 8
ELEV. 9 ELEV. 12
ELEV. 11
ELEV. 10
9.88
9.88
9.88
9.88
9.88
9.88
10 11 12
2.06 2.062.06
2.07
2.06
2.05
2.05
2.05
2.10
2.10 2.10
2.11
2.08
2.052.05
2.082.08
2.06
2.05
2.10 2.10 2.10
2.09
10.32 10.3210.32
10.30
8.038.03 8.03
2.10 2.10 2.10
2.09
10 11 12
8.038.03
10.32 10.3210.32
10.31
10.30
2.10
2.10 2.10
8.03
2.11
GENERAL DEMOLITION NOTES
1. ALL EXISTING WALL DIMENSIONS ARE TO FINISH FACE, UNLESS OTHERWISE NOTED
2. THE CONTRACTOR SHALL VERIFY DIMENSIONS OF AS-BUILT CONDITIONS, AND NOTIFY THE
ARCHITECT IN WRITING OF ANY DISCREPANCIES. ALL INFORMATION SHOWN ON THE
CONSTRUCTION DOCUMENTS IS BASED ON FIELD OBSERVATIONS AND/OR THE ORIGINAL
CONSTRUCTION DOCUMENTS OF THE FACILITY.
3. DEMOLITION AND CONSTRUCTION WORK MUST BE DONE UNDER NEGATIVE PRESSURE UTILIZING
HEPA FILTRATION UNITS. REFER TO HARRIS HEALTH STANDARDS FOR CONTAINMENT.
4. DO NOT REMOVE BARRIERS FROM WORK AREA UNTIL COMPLETED PROJECT OR AREA HAS BEEN
INSPECTED BY THE SAFETY OFFICER AND INFECTION CONTROL COORDINATOR AND
THOROUGHLY CLEANED BY ENVIRONMENTAL MANAGEMENT SERVICES.
5. CONTRACTOR TO COORDINATE ANY SHUT DOWNS WITH THE OWNER PRIOR TO AND WITH
ADVANCE NOTICE.
6. THE CONTRACTOR SHALL PROVIDE PROTECTIVE COVERING FOR EXISTING FLOOR, WALL AND
CEILING FINISHES IN EXISTING AREAS NOT DESIGNATED FOR DEMOLITION OR NEW
CONSTRUCTION. THE CONTRACTOR SHALL BE RESPONSIBLE FOR THE REPAIR OF ANY DAMAGE
CAUSED BY THIER WORK OR ANY SUBCONTRACTOR.
7. CONTRACTOR TO PROTECT ALL EXISTING ITEMS, WHICH INCLUDE BUT NOT LIMITED TO: WALL
FINISHES, WALL PROTECTION, FLOOR BASE, ELEVATOR DOOR FRAME, CEILINGS, ETC.
NEW DOOR, FRAME AND
HARDWARE IN EXISTING
PARTITION
FLOOR PLAN LEGEND
AREA NOT IN CONTRACT
NEW PARTITION
EXISTING PARTITION TO
REMAIN
NOTE: ALL SYMBOLS MAY NOT BE USED.
EXISTING DOOR & FRAME
EXISTING WINDOW
EXISTING MILLWORK
NEW MILLWORK
NEW WINDOW
NEW DOOR, FRAME AND
HARDWARE IN NEW
PARTITION
EXISTING DOOR, FRAME AND
HARDWARE TO BE
DEMOLISHED
DEMOLITION FLOOR PLAN LEGEND
AREA NOT IN CONTRACT
EXISTING PARTITION TO BE
DEMOLISHED
EXISTING PARTITION TO
REMAIN
NOTE: ALL SYMBOLS MAY NOT BE USED.
EXISTING DOOR & FRAME TO
REMAIN
EXISTING WINDOW & FRAME
TO REMAIN
EXISTING WINDOW & FRAME
TO BE DEMOLISHED
EXISTING MILLWORK TO
REMAIN
EXISTING MILLWORK TO BE
DEMOLISHED
GENERAL PLAN NOTES
1. ELEVATOR DOOR, CAB INTERIORS, CALL LANTERNS, AND ELEVATOR EQUIPMENT
REPLACEMENTS.
2. PATCH AND REPAIR ANY ELEVATOR LOBBY WALLS WITH MATCHING FINISHES.
3. CONTRACTOR TO COORDINATE ANY SHUT DOWNS WITH THE OWNER PRIOR TO AND WITH
ADVANCE NOTICE.
9 10
G
H
J
K
9.18.6 9.7 10.2
ELEV. LOBBY
36'-10"
8'-11" 1'-6" 16'-0" 5'-6" 4'-11"
'-0
'-0
'-0
'-0
2.12
ELEV. 7
ELEV. 8
ELEV. 9 ELEV. 12
ELEV. 11
ELEV. 10
2.23 2.23
2.23
2.23 2.23
2.23
12'-0"
M
IN
4' -0
4'
-0
AE1054 3
PARTITION LEGEND
EXISTING WALL TO REMAINEXISTING 2 HOUR FIRE
CONSTRUCTION
CONTAINMENT BARRIER
REVISIONS
ISSUE DATE
DRAWN BY
SHEET NAME NUMBER
PROJECT NUMBER (SPUR)
CHECKED BY
REGISTRATION
THIS DRAWING IS THE PROPERTY OF
SPUR DESIGN, LLC. THIS DRAWING IS
SUBMITTED UNDER A CONFIDENTIAL
RELATIONSHIP FOR A SPECIFIED
PURPOSE & THE RECIPIENT, BY
ACCEPTING THIS DOCUMENT, ASSUMES
CUSTODY & AGREES THAT THIS
DOCUMENT WILL NOT BE COPIED OR
REPRODUCED IN WHOLE OR IN PART, NOR
ITS CONTENTS BE REVEALED IN ANY
MANNER OR TO ANY PERSON EXCEPT TO
MEET THE PURPOSE FOR WHICH IT WAS
DELIVERED WITHOUT EXPRESS WRITTEN
PERMISSION FROM SPUR DESIGN, LLC.
S P U R D E S I G N
W W W . S P U R - D E S I G N . C O M
312 S W 25 T H S T R E E T ( 4 0 5 ) 8 4 2 - 6 1 0 0
Drawing #
(2291.01)
AE105
23-1FC01327
KJW
NR
08/09/2023
B E
N T
A U
B H
O S
P
IT
A L
G R
E E
N E
L E
V A
T O
R M
O D
E R
N
IZ
A T
IO
N
B
E N
T A
U B
L O
O P
H O
U S
T O
N T
X
LEVEL 5
S U
B M
IS
S
IO
N
N
1/8" = 1'-0"
LEVEL 5 - REFERENCE PLAN2
3/8" = 1'-0" 1/ AE105
ELEVATOR LOBBY (5506) - DEMO ELEVATION - #10, #11, & #1233/8" = 1'-0" 1/ AE105
ELEVATOR LOBBY (5506) - DEMO ELEVATION - #7, #8, & #94
3/8" = 1'-0" 2/ AE105
ELEVATOR LOBBY (5506) - NEW ELEVATION - #7, #8, & #96 3/8" = 1'-0" 2/ AE105
ELEVATOR LOBBY (5506) - NEW ELEVATION - #10, #11, & #125
KEYNOTE LEGEND
2.05 REMOVE ELEVATOR DOOR AND REPLACE WITH NEW ELEVATOR DOOR
2.06 EXISTING HALL STATION TO BE REMOVED AND REPLACED.
2.07 EXISTING ICON RISER TO BE REMOVED AND REPLACED.
2.08 EXISTING HALL LANTERNS TO BE REMOVED AND REPLACED.
2.09 EXISTING WAYFINDING MAP TO REMAIN.
2.10 EXISTING ELEVATOR FRAME TO REMAIN.
2.11 EXISTING HAND SANITIZER TO REMAIN.
2.12 PROVIDE FULL HEIGHT CONSTRUCTION BARRIER WHILE RENOVATION IS TAKING PLACE. PER
HARRIS HEALTH, ONLY ONE ELEVATOR BANK (GROUP OF 3 ELEVATORS) WILL BE DONE AT A
TIME FOR RENOVATION. CONSTRUCTION BARRIER TO BE MOVED TO THE NEXT ELEVATOR
BANK ONLY WHEN CONSTRUCTION IS COMPLETE AND APPROVED TO BE MOVED BY THE
HOSPITAL.
2.23 CAB INTERIORS TO BE REMOVED AND PREPARED FOR NEW FINISHES. THIS INCLUDES:
FLOORING, WALL PANELS, RAILS, AND CEILINGS.
8.03 NEW STAINLESS STEEL ELEVATOR DOOR
9.88 NEW ELEVATOR FINISHES. REFER TO SHEET AF701 AND SPECIFICATIONS.
10.30 PROVIDE NEW HALL STATION. REFER TO SPECIFICATIONS.
10.31 PROVIDE NEW ICON RISER. REFER TO SPECIFICATIONS.
10.32 PROVIDE NEW HALL LANTERNS. REFER TO SPECIFICATIONS.
N
1/8" = 1'-0"
LEVEL 5 - DEMOLITION PLAN1
1 Addendum 01
Tectonic Copyright 2007 Tectonic Copyright 2007
E X
P
AN
S
IO
N J
O
IN
T
FE FE
FE
TV
N
KEY PLAN
GREEN ELEVATORS
9 10
G
H
J
K
ELEV. LOBBY
AE106AE106 56
9.18.6 9.7 10.2
36'-10"
8'-11" 1'-6" 16'-0" 5'-6" 4'-11"
'-0
'-0
'-0
'-0
ELEV. 7
ELEV. 8
ELEV. 9 ELEV. 12
ELEV. 11
ELEV. 10
9.88
9.88
9.88
9.88
9.88
9.88
10 11 12
2.082.08
2.07
2.08
2.06
2.05
2.10
2.10 2.10
2.052.05
2.11
2.08 2.082.08
2.06
2.09
2.10 2.10 2.10
2.05 2.052.05
10 11 12
10.32
10.30
8.038.03
8.03
10.3210.32
10.31
2.09
2.10
2.10 2.10
2.11
8.038.03
10.32 10.3210.32
8.03
10.30
2.09
2.10 2.10 2.10
GENERAL DEMOLITION NOTES
1. ALL EXISTING WALL DIMENSIONS ARE TO FINISH FACE, UNLESS OTHERWISE NOTED
2. THE CONTRACTOR SHALL VERIFY DIMENSIONS OF AS-BUILT CONDITIONS, AND NOTIFY THE
ARCHITECT IN WRITING OF ANY DISCREPANCIES. ALL INFORMATION SHOWN ON THE
CONSTRUCTION DOCUMENTS IS BASED ON FIELD OBSERVATIONS AND/OR THE ORIGINAL
CONSTRUCTION DOCUMENTS OF THE FACILITY.
3. DEMOLITION AND CONSTRUCTION WORK MUST BE DONE UNDER NEGATIVE PRESSURE UTILIZING
HEPA FILTRATION UNITS. REFER TO HARRIS HEALTH STANDARDS FOR CONTAINMENT.
4. DO NOT REMOVE BARRIERS FROM WORK AREA UNTIL COMPLETED PROJECT OR AREA HAS BEEN
INSPECTED BY THE SAFETY OFFICER AND INFECTION CONTROL COORDINATOR AND
THOROUGHLY CLEANED BY ENVIRONMENTAL MANAGEMENT SERVICES.
5. CONTRACTOR TO COORDINATE ANY SHUT DOWNS WITH THE OWNER PRIOR TO AND WITH
ADVANCE NOTICE.
6. THE CONTRACTOR SHALL PROVIDE PROTECTIVE COVERING FOR EXISTING FLOOR, WALL AND
CEILING FINISHES IN EXISTING AREAS NOT DESIGNATED FOR DEMOLITION OR NEW
CONSTRUCTION. THE CONTRACTOR SHALL BE RESPONSIBLE FOR THE REPAIR OF ANY DAMAGE
CAUSED BY THIER WORK OR ANY SUBCONTRACTOR.
7. CONTRACTOR TO PROTECT ALL EXISTING ITEMS, WHICH INCLUDE BUT NOT LIMITED TO: WALL
FINISHES, WALL PROTECTION, FLOOR BASE, ELEVATOR DOOR FRAME, CEILINGS, ETC.
NEW DOOR, FRAME AND
HARDWARE IN EXISTING
PARTITION
FLOOR PLAN LEGEND
AREA NOT IN CONTRACT
NEW PARTITION
EXISTING PARTITION TO
REMAIN
NOTE: ALL SYMBOLS MAY NOT BE USED.
EXISTING DOOR & FRAME
EXISTING WINDOW
EXISTING MILLWORK
NEW MILLWORK
NEW WINDOW
NEW DOOR, FRAME AND
HARDWARE IN NEW
PARTITION
EXISTING DOOR, FRAME AND
HARDWARE TO BE
DEMOLISHED
DEMOLITION FLOOR PLAN LEGEND
AREA NOT IN CONTRACT
EXISTING PARTITION TO BE
DEMOLISHED
EXISTING PARTITION TO
REMAIN
NOTE: ALL SYMBOLS MAY NOT BE USED.
EXISTING DOOR & FRAME TO
REMAIN
EXISTING WINDOW & FRAME
TO REMAIN
EXISTING WINDOW & FRAME
TO BE DEMOLISHED
EXISTING MILLWORK TO
REMAIN
EXISTING MILLWORK TO BE
DEMOLISHED
GENERAL PLAN NOTES
1. ELEVATOR DOOR, CAB INTERIORS, CALL LANTERNS, AND ELEVATOR EQUIPMENT
REPLACEMENTS.
2. PATCH AND REPAIR ANY ELEVATOR LOBBY WALLS WITH MATCHING FINISHES.
3. CONTRACTOR TO COORDINATE ANY SHUT DOWNS WITH THE OWNER PRIOR TO AND WITH
ADVANCE NOTICE.
9 10
G
H
J
K
9.18.6 9.7 10.2
ELEV. LOBBY
36'-10"
8'-11" 1'-6" 16'-0" 5'-6" 4'-11"
'-0
'-0
'-0
'-0
2.12
ELEV. 7
ELEV. 8
ELEV. 9 ELEV. 12
ELEV. 11
ELEV. 10
2.23
2.23
2.23 2.23
2.23
2.23
M
IN
4' -0
4'
-0
12'-0"
AE1064 3
PARTITION LEGEND
EXISTING WALL TO REMAINEXISTING 2 HOUR FIRE
CONSTRUCTION
CONTAINMENT BARRIER
REVISIONS
ISSUE DATE
DRAWN BY
SHEET NAME NUMBER
PROJECT NUMBER (SPUR)
CHECKED BY
REGISTRATION
THIS DRAWING IS THE PROPERTY OF
SPUR DESIGN, LLC. THIS DRAWING IS
SUBMITTED UNDER A CONFIDENTIAL
RELATIONSHIP FOR A SPECIFIED
PURPOSE & THE RECIPIENT, BY
ACCEPTING THIS DOCUMENT, ASSUMES
CUSTODY & AGREES THAT THIS
DOCUMENT WILL NOT BE COPIED OR
REPRODUCED IN WHOLE OR IN PART, NOR
ITS CONTENTS BE REVEALED IN ANY
MANNER OR TO ANY PERSON EXCEPT TO
MEET THE PURPOSE FOR WHICH IT WAS
DELIVERED WITHOUT EXPRESS WRITTEN
PERMISSION FROM SPUR DESIGN, LLC.
S P U R D E S I G N
W W W . S P U R - D E S I G N . C O M
312 S W 25 T H S T R E E T ( 4 0 5 ) 8 4 2 - 6 1 0 0
Drawing #
(2291.01)
AE106
23-1FC01327
KJW
NR
08/09/2023
B E
N T
A U
B H
O S
P
IT
A L
G R
E E
N E
L E
V A
T O
R M
O D
E R
N
IZ
A T
IO
N
B
E N
T A
U B
L O
O P
H O
U S
T O
N T
X
LEVEL 6
S U
B M
IS
S
IO
N
N
1/8" = 1'-0"
LEVEL 6 - REFERENCE PLAN2
3/8" = 1'-0" 1/ AE106
ELEVATOR LOBBY (6527) - DEMO ELEVATION - #10, #11, & #1233/8" = 1'-0" 1/ AE106
ELEVATOR LOBBY (6527) - DEMO ELEVATION - #7, #8, & #94
3/8" = 1'-0" 2/ AE106
ELEVATOR LOBBY (6527) - NEW ELEVATION - #10, #11, & #1253/8" = 1'-0" 2/ AE106
ELEVATOR LOBBY (6527) - NEW ELEVATION - #7, #8, & #96
KEYNOTE LEGEND
2.05 REMOVE ELEVATOR DOOR AND REPLACE WITH NEW ELEVATOR DOOR
2.06 EXISTING HALL STATION TO BE REMOVED AND REPLACED.
2.07 EXISTING ICON RISER TO BE REMOVED AND REPLACED.
2.08 EXISTING HALL LANTERNS TO BE REMOVED AND REPLACED.
2.09 EXISTING WAYFINDING MAP TO REMAIN.
2.10 EXISTING ELEVATOR FRAME TO REMAIN.
2.11 EXISTING HAND SANITIZER TO REMAIN.
2.12 PROVIDE FULL HEIGHT CONSTRUCTION BARRIER WHILE RENOVATION IS TAKING PLACE. PER
HARRIS HEALTH, ONLY ONE ELEVATOR BANK (GROUP OF 3 ELEVATORS) WILL BE DONE AT A
TIME FOR RENOVATION. CONSTRUCTION BARRIER TO BE MOVED TO THE NEXT ELEVATOR
BANK ONLY WHEN CONSTRUCTION IS COMPLETE AND APPROVED TO BE MOVED BY THE
HOSPITAL.
2.23 CAB INTERIORS TO BE REMOVED AND PREPARED FOR NEW FINISHES. THIS INCLUDES:
FLOORING, WALL PANELS, RAILS, AND CEILINGS.
8.03 NEW STAINLESS STEEL ELEVATOR DOOR
9.88 NEW ELEVATOR FINISHES. REFER TO SHEET AF701 AND SPECIFICATIONS.
10.30 PROVIDE NEW HALL STATION. REFER TO SPECIFICATIONS.
10.31 PROVIDE NEW ICON RISER. REFER TO SPECIFICATIONS.
10.32 PROVIDE NEW HALL LANTERNS. REFER TO SPECIFICATIONS.
N
1/8" = 1'-0"
LEVEL 6 - DEMOLITION PLAN1
1 Addendum 01
V
SD
V
FD
V
FD
V
FD
V
FD
V FD V FD V FD V FD V FD
F
N
KEY PLAN
ELEVATOR PENTHOUSE
9 10
G
H
J
K
ELEV.
MACHINE
PH
9.18.6 9.7 10.2
36'-10"
8'-11" 1'-6" 16'-0" 5'-6" 4'-11"
'-0
'-0
'-0
'-0
2.15
2.152.15
2.152.152.152.15
2.15
2.15
2.16
2.16
2.16
2.16
2.16
2.16
2.17
2.182.18…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .