1-WWTP Influent Pump Improvements Project Manual 4603.017.pdf
PDF 9 MB Posted
- Attached to
- WWTP Influent Pump Improvements
- Solicitation number
- Not on record
- Issued by
- Schuylkill County, Pennsylvania
About this file
This is a project manual and bidding document for the WWTP Influent Pump Improvements project issued by the Porter-Tower Joint Municipal Authority in Tower City, Pennsylvania. The project consists of the addition of a new influent wet well jockey pump with variable frequency drive in the operations building, including piping, panel modifications, process instrumentation, and SCADA integration. The work is divided into two separate contracts: Contract No. 01 for General/Process Mechanical work and Contract No. 02 for Electrical work. Bids will be received electronically via the PennBid Program until Monday, February 9, 2026 at 1:00 PM local time. A pre-bid conference is scheduled for Monday, January 26, 2026 at 11:00 AM at the Porter-Tower WWTP facility located at 860 W. Grand Avenue, Tower City, PA 17980. Attendance at the conference is encouraged but not mandatory. The contract times specify that work shall be substantially complete within 120 days after the contract times commence and fully completed within 150 days. Liquidated damages are assessed at $1,000 per day for failure to achieve substantial completion and $1,000 per day for failure to complete remaining work after substantial completion.
The project was partially financed by a grant from the Commonwealth of Pennsylvania through the Commonwealth Financing Authority. Bidders must submit bid security equal to 10 percent of the maximum bid price in the form of a bid bond. The contract requires performance and payment bonds, each in an amount equal to the contract price. All work must comply with Pennsylvania Prevailing Wage Act requirements, and prevailing minimum wage rates are specified in the project manual. Contractor's Commercial General Liability insurance must maintain minimum limits of $2,000,000 for general aggregate and products-completed operations aggregate, with $1,000,000 per occurrence. Additional insureds must include the Commonwealth Financing Authority, Porter-Tower Joint Municipal Authority, and Martz Technologies, Inc. Contractor must use only American-made steel products in accordance with the Steel Products Procurement Act. Bid documents are available at no cost through the PennBid Program at https://pennbid.bonfirehub.com. The project is designed by Entech Engineering, Inc., with contact information provided for the project manager.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2-WWTP Influent Pump Improvements Project Drawings 4603.017.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT MANUAL
PORTER-TOWER JOINT MUNICIPAL AUTHORITY
860 West Grand Avenue
Tower City, Pennsylvania 17980
WWTP INFLUENT PUMP IMPROVEMENTS
CONTRACT NO. 01 - GENERAL/PROCESS MECHANICAL
CONTRACT NO. 02 - ELECTRICAL
Porter Township
Schuylkill County, Pennsylvania
This Project was financed, in part, by a grant from the Commonwealth of Pennsylvania, Commonwealth Financing Authority prepared by
Entech Engineering, Inc.
201 Penn Street
PO Box 32 Reading, Pennsylvania 19603
610-373-6667
Issued for Bidding:
January 16, 2026
Entech No. 4603.017
Entech Engineering, Inc. Entech No. 4603.017
TABLE OF CONTENTS 1
WWTP INFLUENT PUMP IMPROVEMENTS
CONTRACT NO. 02 - ELECTRICAL
TABLE OF CONTENTS
BIDDING FORMS, CONTRACT FORMS, AND CONDITIONS OF THE CONTRACT
SECTION DESCRIPTION NO. PAGES
Cover Page Table of Contents
PROJECT INFORMATION
EJCDC C-111 Advertisement for Bids Document 00040 Project Information EJCDC C-200 Instructions to Bidders
BID FORM
EJCDC C-410 Bid Form – Contract No. 01 – General/ Process Mechanical EJCDC C-410 Bid Form – Contract No.02 - Electrical Appendix A List of Subcontractors Appendix B List of Equipment and Materials Appendix C EJCDC C-451 – Qualification Statement Appendix D Public Works Employment Verification Form - Contract No.01 Appendix D Public Works Employment Verification Form - Contract No.02 Appendix E Non-Discrimination/Sexual Harassment Certification
REFERENCE DOCUMENTS
EJCDC C-430 Bid Bond - Contract No.01 EJCDC C-430 Bid Bond - Contract No.02 EJCDC C-510 Notice of Award EJCDC C-520 Agreement Between Owner and Contractor for Construction Contract EJCDC C-550 Notice to Proceed EJCDC C-610 Performance Bond EJCDC C-615 Payment Bond EJCDC C-620 Contractor’s Application for Payment EJCDC C-625 Certificate of Substantial Completion EJCDC C-626 Notice of Acceptability of Work Document 00650 Construction Schedule EJCDC C-700 General Conditions of the Construction Contract EJCDC C-800 Supplementary Conditions Document 00830 Prevailing Minimum Wage Determination EJCDC C-940 Work Change Directive EJCDC C-941 Change Order EJCDC C-942 Field Order Document 00943 Contractor's Certification of Completion
TABLE OF CONTENTS 2
WWTP INFLUENT PUMP IMPROVEMENTS
SECTION DESCRIPTION NO. PAGES
TECHNICAL SPECIFICATIONS
DIVISION 01 — GENERAL REQUIREMENTS
Section 010005 Administrative Provisions Section 010010 Summary of Work Section 010040 Allowances Section 010045 Coordination Section 010047 Cutting and Patching Section 010050 Field Engineering Section 010150 Measurements and Payments Section 010200 Project Meetings Section 010300 Submittals Section 010322 Photographic Documentation Section 010400 Quality Control Section 010500 Construction Facilities and Temporary Controls Section 010600 Materials and Equipment Section 010700 Mobilization and Project Closeout Section 010732 Selective Demolition Section 010735 Sludge and Grit Removal and Disposal Section 010810 Operation and Maintenance Manuals Section 010815 Project Record Drawings Section 010820 Demonstration and Training
DIVISION 03 – CONCRETE
Section 033000 Cast in Place Concrete
DIVISION 11 – EQUIPMENT
Section 110060 Process Hangers and Supports Section 110075 Process Mechanical Identification Section 110100 Self Priming Wastewater Pumps Section 110850 Above Grade Ductile Iron Cement Lined Section 110852 Above Grade Valves and Specialties Section 110970 Gauges and Accessories Section 110987 PolyVinyl Chloride (PVC) Piping Section 110990 Process Field Instrumentation Section 112320 Temporary Bypass Pumping Section 119130 Pipe Painting
TABLE OF CONTENTS 3
WWTP INFLUENT PUMP IMPROVEMENTS
SECTION DESCRIPTION NO. PAGES
TECHNICAL SPECIFICATIONS
DIVISION 26 – ELECTRICAL
Section 260500 Basic Electrical Requirements Section 260519 Low-Voltage Electrical Power Conductors and Cables Section 260526 Grounding and Bonding for Electrical Systems Section 260529 Hangers and Supports for Electrical Systems Section 260533 Raceways and Boxes for Electrical Systems Section 260553 Identification for Electrical Systems Section 262816 Enclosed Switches and Circuit Breakers Section 262923 Variable-Frequency Drives
ATTACHMENTS
Attachment A Submittal List Attachment B Steel Products Procurement Act Certification
DRAWINGS
Refer to Drawing No. G-001 for a complete list of Drawings.
END OF TABLE OF CONTENTS
PROJECT INFORMATION
EJCDC® C-111, Advertisement for Bids for Construction Contract.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
ADVERTISEMENT FOR BIDS
PORTER-TOWER JOINT MUNICIPAL AUTHORITY
WWTP INFLUENT PUMP IMPROVEMENTS
General Notice
Porter-Tower Joint Municipal Authority (Owner) is requesting Bids for the construction of the following Project:
Porter-Tower Joint Municipal Authority WWTP Influent Pump Improvements
Contract No. 01 - General/Process Mechanical Contract No. 02 - Electrical
4603.017
Bids for the construction of the Project will be received electronically via the PennBid Program by the Porter-Tower Joint Municipal Authority until Monday, February 9, 2026 at 1:00 pm local time. After bid opening, a public notice will be issued via PennBid containing any available bid results. It should be noted that bid results are subject to further review and should not be construed as issuance of an award.
The Project includes the following Work:
The project generally consists of the addition of a new influent wet well Jockey pump with Variable Frequency Drive in the Operations building. Work includes piping, panel modification, process instrumentation and SCADA integration, as specified herein and as shown on the Drawings consisting of demolition, structural, process mechanical, electrical demolition and electrical.
Obtaining the Bidding Documents
All project documents are available at no cost via the PennBid Program (https://pennbid.bonfirehub.com).
Pre-bid Conference
A pre-bid conference for the Project will be held on Monday, January 26, 2026 at 11:00 am at Porter- Tower WWTP, 860 W. Grand Ave, Tower City, PA 17980. Attendance at the pre-bid conference is encouraged but not required.
Instructions to Bidders.
For all further requirements regarding bid submittal, bid security, qualifications, procedures, and contract award, refer to the Instructions to Bidders that are included in the Bidding Documents.
Attention is called to the fact that prevailing minimum wage rates as determined by the Secretary of the Department of Labor and Industry must be paid by the Contractors on this project and that employees and applicants for employment shall not be discriminated against because of their race, age, color, religion, sex, national origin, or handicap. Each Bidder is required to meet the requirements of Public Works Employment Verification Act, Act 127 of 2012.
Any and all steel products used or supplied in the performance of the contract or any subcontracts shall be from steel made in the United States.
https://pennbid.bonfirehub.com/
EJCDC® C-111, Advertisement for Bids for Construction Contract.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
The Porter-Tower Joint Municipal Authority hereby reserves the right, which is understood and agreed to by all bidders, to refuse and reject any or all bids submitted, and also reserves the right to waive any informality in bids received.
Except as otherwise provided by law, no bidder may withdraw its bid for sixty (60) days after the Bid Due Date, unless the contract award is delayed by a required approval of another government agency, the sale of bonds, or the award of a grant or grants, in which case the Bids shall remain open to acceptance and shall be irrevocable for a period of one hundred twenty (120) days after the Bid Due Date.
This Advertisement is issued by:
Owner: Porter-Tower Joint Municipal Authority By: Tyler Romberger Title: Superintendent Date: January 16, 2026
+ + END OF ADVERTISEMENT FOR BIDS + +
PROJECT INFORMATION 00040 - 1
DOCUMENT 00040 – PROJECT INFORMATION
PART 1 – PROJECT IDENTIFICATION
1.1 PROJECT NAME
A. WWTP Influent Pump Improvements Contract No. 01 - General/Process Mechanical Contract No. 02 - Electrical
1.2 LOCATION
A. Porter Township, Schuylkill County, Pennsylvania
1.3 OWNER
A. Porter-Tower Joint Municipal Authority 860 West Grand Avenue Tower City, Pennsylvania 17980
Contact: Tyler Romberger Phone: 717-647-9213
1.4 ENGINEER
A. Entech Engineering, Inc.
201 Penn Street PO Box 32 Reading, PA 19603
Contact: Clint Davis, Project Manager Phone: 610-373-6667
Email: cdavis@entecheng.com
PART 2 – PRODUCTS (NOT USED)
PART 3 – EXECUTION (NOT USED)
END OF SECTION 00040
EJCDC® C-200, Instructions to Bidders for Construction Contract.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
TOC Page1 of 1
INSTRUCTIONS TO BIDDERS FOR CONSTRUCTION CONTRACT
TABLE OF CONTENTS
Page
Article 1— Defined Terms
Article 2— Bidding Documents
Article 3— Qualifications of Bidders
Article 4— Pre-Bid Conference
Article 5— Site and Other Areas; Existing Site Conditions; Examination of Site; Owner’s Safety Program;
Other Work at the Site
Article 6— Bidder’s Representations and Certifications
Article 7— Interpretations and Addenda
Article 8— Bid Security
Article 9— Contract Times
Article 10— Substitute and “Or Equal” Items
Article 11— Subcontractors, Suppliers, and Others
Article 12— Preparation of Bid
Article 13— Basis of Bid
Article 14— Submittal of Bid
Article 15— Modification and Withdrawal of Bid
Article 16— Opening of Bids
Article 17— Bids to Remain Subject to Acceptance
Article 18— Evaluation of Bids and Award of Contract
Article 19— Bonds and Insurance
Article 20— Signing of Agreement
Article 21— Sales and Use Taxes
Article 22— Steel Products Procurement Act
Article 23— Labor Requirements
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
ARTICLE 1—DEFINED TERMS
1.01 Terms used in these Instructions to Bidders have the meanings indicated in the General Conditions and Supplementary Conditions. Additional terms used in these Instructions to Bidders have the meanings indicated below:
A. Issuing Office—The office from which the Bidding Documents are to be issued.
ARTICLE 2—BIDDING DOCUMENTS
2.01 Bidder shall obtain a complete set of Bidding Requirements and proposed Contract Documents (together, the Bidding Documents). See the Agreement for a list of the Contract Documents. It is Bidder’s responsibility to determine that it is using a complete set of documents in the preparation of a Bid. Bidder assumes sole responsibility for errors or misinterpretations resulting from the use of incomplete documents, by Bidder itself or by its prospective Subcontractors and Suppliers.
2.02 Bidding Documents are made available for the sole purpose of obtaining Bids for completion of the Project and permission to download or distribution of the Bidding Documents does not confer a license or grant permission or authorization for any other use. Authorization to download documents, or other distribution, includes the right for plan holders to print documents solely for their use, and the use of their prospective Subcontractors and Suppliers, provided the plan holder pays all costs associated with printing or reproduction. Printed documents may not be re-sold under any circumstances.
2.03 Bidding Documents are available at no cost via the PennBid Program (https://pennbid.bonfirehub.com).
2.04 Electronic Documents
A. When the Bidding Requirements indicate that electronic (digital) copies of the Bidding Documents are available, such documents will be made available to the Bidders as Electronic Documents in the manner specified.
1. Bidding Documents will be provided in Adobe PDF (Portable Document Format) (.pdf) that is readable by Adobe Acrobat Reader. It is the intent of the Engineer and Owner that such Electronic Documents are to be exactly representative of the paper copies of the documents. However, because the Owner and Engineer cannot totally control the transmission and receipt of Electronic Documents nor the Contractor’s means of reproduction of such documents, the Owner and Engineer cannot and do not guarantee that Electronic Documents and reproductions prepared from those versions are identical in every manner to the paper copies.
B. Unless otherwise stated in the Bidding Documents, the Bidder may use and rely upon complete sets of Electronic Documents of the Bidding Documents, described in Paragraph 2.04.A above. However, Bidder assumes all risks associated with differences arising from transmission/receipt of Electronic Documents versions of Bidding Documents and reproductions prepared from those versions and, further, assumes all risks, costs, and responsibility associated with use of the Electronic Documents versions to derive information that is not explicitly contained in printed paper versions of the documents, and for Bidder’s reliance upon such derived information.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
ARTICLE 3—QUALIFICATIONS OF BIDDERS
3.01 Bidder is to submit the following information with its Bid to demonstrate Bidder’s qualifications to perform the Work:
A. EJCDC C-451 Statement of Qualifications.
B. A written statement that Bidder is authorized to do business in the state where the Project is located, or a written certification that Bidder will obtain such authority prior to the Effective Date of the Contract.
C. Bidder’s state or other contractor license number, if applicable.
3.02 A Bidder’s failure to submit required qualification information within the times indicated may disqualify Bidder from receiving an award of the Contract.
3.03 No requirement in this Article 3 to submit information will prejudice the right of Owner to seek additional pertinent information regarding Bidder’s qualifications.
ARTICLE 4—PRE-BID CONFERENCE
4.01 A mandatory pre-bid conference will be held at the time and location indicated in the Advertisement or invitation to bid. Representatives of Owner and Engineer will be present to discuss the Project. Proposals will not be accepted from Bidders who do not attend the conference. It is each Bidder’s responsibility to sign in at the pre-bid conference to verify its participation. Bidders must sign in using the name of the organization that will be submitting a Bid.
4.02 Information presented at the pre-Bid conference does not alter the Contract Documents. Owner will issue Addenda to make any changes to the Contract Documents that result from discussions at the pre-Bid conference. Information presented, and statements made at the pre-bid conference will not be binding or legally effective unless incorporated in an Addendum.
ARTICLE 5—SITE AND OTHER AREAS; EXISTING SITE CONDITIONS; EXAMINATION OF SITE; OWNER’S
SAFETY PROGRAM; OTHER WORK AT THE SITE
5.01 Site and Other Areas
A. The Site is identified in the Bidding Documents. By definition, the Site includes rights-of-way, easements, and other lands furnished by Owner for the use of the Contractor. Any additional lands required for temporary construction facilities, construction equipment, or storage of materials and equipment, and any access needed for such additional lands, are to be obtained and paid for by Contractor.
5.02 Existing Site Conditions
A. Subsurface and Physical Conditions; Hazardous Environmental Conditions
1. The Supplementary Conditions identify the following regarding existing conditions at or adjacent to the Site:
a. Those reports of explorations and tests of subsurface conditions at or adjacent to the Site that contain Technical Data.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
b. Those drawings known to Owner of existing physical conditions at or adjacent to the Site, including those drawings depicting existing surface or subsurface structures at or adjacent to the Site (except Underground Facilities), that contain Technical Data.
c. Reports and drawings known to Owner relating to Hazardous Environmental Conditions that have been identified at or adjacent to the Site.
d. Technical Data contained in such reports and drawings.
2. Owner will make copies of reports and drawings referenced above available to any Bidder on request. These reports and drawings are not part of the Contract Documents, but the Technical Data contained therein upon whose accuracy Bidder is entitled to rely, as provided in the General Conditions, has been identified and established in the Supplementary Conditions. Bidder is responsible for any interpretation or conclusion Bidder draws from any Technical Data or any other data, interpretations, opinions, or information contained in such reports or shown or indicated in such drawings.
3. If the Supplementary Conditions do not identify Technical Data, the default definition of Technical Data set forth in Article 1 of the General Conditions will apply.
B. Underground Facilities: Underground Facilities are shown or indicated on the Drawings, pursuant to Paragraph 5.05 of the General Conditions, and not in the drawings referred to in Paragraph 5.02.A of these Instructions to Bidders. Information and data regarding the presence or location of Underground Facilities are not intended to be categorized, identified, or defined as Technical Data.
5.03 Other Site-related Documents
A. No other Site-related documents are available.
5.04 Site Visit and Testing by Bidders
A. Bidder is required to visit the Site and conduct a thorough visual examination of the Site and adjacent areas. During the visit the Bidder must not disturb any ongoing operations at the Site.
B. On request, and to the extent Owner has control over the Site, and schedule permitting, the Owner will provide Bidder general access to the Site to conduct such additional examinations, investigations, explorations, tests, and studies as Bidder deems necessary for preparing and submitting a successful Bid. Owner will not have any obligation to grant such access if doing so is not practical because of existing operations, security or safety concerns, or restraints on Owner’s authority regarding the Site. Bidder is responsible for establishing access needed to reach specific selected test sites.
C. Bidder must comply with all applicable Laws and Regulations regarding excavation and location of utilities, obtain all permits, and comply with all terms and conditions established by Owner or by property owners or other entities controlling the Site with respect to schedule, access, existing operations, security, liability insurance, and applicable safety programs.
D. Bidder must fill all holes and clean up and restore the Site to its former condition upon completion of such explorations, investigations, tests, and studies.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
5.05 Owner’s Safety Program
A. Site visits and work at the Site may be governed by an Owner safety program. If an Owner safety program exists, it will be noted in the Supplementary Conditions.
5.06 Other Work at the Site
A. Reference is made to Article 8 of the Supplementary Conditions for the identification of the general nature of other work of which Owner is aware (if any) that is to be performed at the Site by Owner or others (such as utilities and other prime contractors) and relates to the Work contemplated by these Bidding Documents. If Owner is party to a written contract for such other work, then on request, Owner will provide to each Bidder access to examine such contracts (other than portions thereof related to price and other confidential matters), if any.
ARTICLE 6—BIDDER’S REPRESENTATIONS AND CERTIFICATIONS
6.01 Express Representations and Certifications in Bid Form, Agreement
A. The Bid Form that each Bidder will submit contains express representations regarding the Bidder’s examination of Project documentation, Site visit, and preparation of the Bid, and certifications regarding lack of collusion or fraud in connection with the Bid. Bidder should review these representations and certifications, and assure that Bidder can make the representations and certifications in good faith, before executing and submitting its Bid.
B. If Bidder is awarded the Contract, Bidder (as Contractor) will make similar express representations and certifications when it executes the Agreement.
ARTICLE 7—INTERPRETATIONS AND ADDENDA
7.01 Owner on its own initiative may issue Addenda to clarify, correct, supplement, or change the Bidding Documents.
7.02 Bidder shall submit all questions about the meaning or intent of the Bidding Documents via the “Messages/Vendor Discussions” feature in PennBid no later than seven (7) days prior to the date for receipt of bids.
7.03 Interpretations or clarifications considered necessary by Engineer in response to such questions will be issued by Addenda delivered to all registered plan holders. Questions received less than seven days prior to the date for opening of Bids may not be answered.
7.04 Only responses set forth in an Addendum will be binding. Oral and other interpretations or clarifications will be without legal effect. Responses to questions are not part of the Contract Documents unless set forth in an Addendum that expressly modifies or supplements the Contract Documents.
ARTICLE 8—BID SECURITY
8.01 A Bid must be accompanied by Bid security made payable to Owner in an amount of 10 percent of Bidder’s maximum Bid price (determined by adding the base bid and all alternates) and in the form of a Bid bond issued by a surety meeting the requirements of Paragraph 6.01 of the General Conditions. Such Bid bond will be issued in the form included in the Bidding Documents.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
8.02 The Bid security of the apparent Successful Bidder will be retained until Owner awards the contract to such Bidder, and such Bidder has executed the Contract, furnished the required Contract security, and met the other conditions of the Notice of Award, whereupon the Bid security will be released. If the Successful Bidder fails to execute and deliver the Contract and furnish the required Contract security within 15 days after the Notice of Award, Owner may consider Bidder to be in default, annul the Notice of Award, and the Bid security of that Bidder will be forfeited, in whole in the case of a penal sum bid bond, and to the extent of Owner’s damages in the case of a damages-form bond. Such forfeiture will be Owner’s exclusive remedy if Bidder defaults.
8.03 The Bid security of other Bidders that Owner believes to have a reasonable chance of receiving the award may be retained by Owner until the earlier of 7 days after the Effective Date of the Contract or 61 days after the Bid opening, whereupon Bid security furnished by such Bidders will be released.
8.04 Bid security of other Bidders that Owner believes do not have a reasonable chance of receiving the award will be released within 7 days after the Bid opening.
ARTICLE 9—CONTRACT TIMES
9.01 The number of days within which, or the dates by which, the Work is to be (a) substantially completed and (b) ready for final payment, and (c) Milestones (if any) are to be achieved, are set forth in the Agreement.
9.02 Provisions for liquidated damages, if any, for failure to timely attain a Milestone, Substantial Completion, or completion of the Work in readiness for final payment, are set forth in the Agreement.
ARTICLE 10—SUBSTITUTE AND “OR EQUAL” ITEMS
10.01 The Contract for the Work, as awarded, will be on the basis of materials and equipment specified or described in the Bidding Documents, and those “or-equal” or substitute or materials and equipment subsequently approved by Engineer prior to the submittal of Bids and identified by Addendum. No item of material or equipment will be considered by Engineer as an “or-equal” or substitute unless written request for approval has been submitted by Bidder and has been received by Engineer within 10 days of the issuance of the Advertisement for Bids or invitation to Bidders. Each such request must comply with the requirements of Paragraphs 7.05 and 7.06 of the General Conditions, and the review of the request will be governed by the principles in those paragraphs. The burden of proof of the merit of the proposed item is upon Bidder. Engineer’s decision of approval or disapproval of a proposed item will be final. If Engineer approves any such proposed item, such approval will be set forth in an Addendum issued to all registered Bidders.
Bidders cannot rely upon approvals made in any other manner.
10.02 All prices that Bidder sets forth in its Bid will be based on the presumption that the Contractor will furnish the materials and equipment specified or described in the Bidding Documents, as supplemented by Addenda. Any assumptions regarding the possibility of post-Bid approvals of “or-equal” or substitution requests are made at Bidder’s sole risk.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
ARTICLE 11—SUBCONTRACTORS, SUPPLIERS, AND OTHERS
11.01 The apparent Successful Bidder, and any other Bidder so requested, must submit to Owner a list of the Subcontractors or Suppliers proposed for the following portions of the Work with the Bid submittal on the Bid Forms provided.
11.02 If requested by Owner, such list must be accompanied by an experience statement with pertinent information regarding similar projects and other evidence of qualification for each such Subcontractor or Supplier. If Owner or Engineer, after due investigation, has reasonable objection to any proposed Subcontractor or Supplier, Owner may, before the Notice of Award is given, request apparent Successful Bidder to submit an acceptable substitute, in which case apparent Successful Bidder will submit a substitute without an increase in Bid Price.
11.03 If apparent Successful Bidder declines to make any such substitution, Owner may award the Contract to the next lowest Bidder that proposes to use acceptable Subcontractors and Suppliers.
Declining to make requested substitutions will constitute grounds for forfeiture of the Bid security of any Bidder. Any Subcontractor or Supplier, so listed and against which Owner or Engineer makes no written objection prior to the giving of the Notice of Award will be deemed acceptable to Owner and Engineer subject to subsequent revocation of such acceptance as provided in Paragraph 7.07 of the General Conditions.
ARTICLE 12—PREPARATION OF BID
12.01 The Bid Form is included with the Bidding Documents for Reference. Bidders shall complete the electronic bid form within PennBid (“Prepare Your Submission” tab), inclusive of all pricing items and required supporting documents as identified.
12.02 All blanks on supplemental forms shall be completed legibly.
12.03 Bids, inclusive of bid security, and all documents required to be submitted with bids, shall be submitted electronically via the PennBid Program (“Prepare Your Submission” tab).
12.04 A Bid by a corporation must be executed in the corporate name by a corporate officer (whose title must appear under the signature), accompanied by evidence of authority to sign. The corporate address and state of incorporation must be shown.
12.05 A Bid by a partnership must be executed in the partnership name and signed by a partner (whose title must appear under the signature), accompanied by evidence of authority to sign. The official address of the partnership must be shown.
12.06 A Bid by a limited liability company must be executed in the name of the firm by a member or other authorized person and accompanied by evidence of authority to sign. The state of formation of the firm and the official address of the firm must be shown.
12.07 A Bid by an individual must show the Bidder’s name and official address.
12.08 A Bid by a joint venture must be executed by an authorized representative of each joint venturer in the manner indicated on the Bid Form. The joint venture must have been formally established prior to submittal of a Bid, and the official address of the joint venture must be shown.
12.09 The Bid must contain an acknowledgment of receipt of all Addenda, the numbers of which must be filled in on the Bid Form.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
12.10 Postal and e-mail addresses and telephone number for communications regarding the Bid must be shown.
12.11 The Bid must contain evidence of Bidder’s authority to do business in the state where the Project is located, or Bidder must certify in writing that it will obtain such authority within the time for acceptance of Bids and attach such certification to the Bid.
12.12 If Bidder is required to be licensed to submit a Bid or perform the Work in the state where the Project is located, the Bid must contain evidence of Bidder’s licensure, or Bidder must certify in writing that it will obtain such licensure within the time for acceptance of Bids and attach such certification to the Bid. Bidder’s state contractor license number, if any, must also be shown on the Bid Form.
ARTICLE 13—BASIS OF BID
13.01 Unit Price
A. Bidders must submit a Bid on a unit price basis for each item of Work listed in the unit price section of the Bid Form.
B. The “Bid Price” (sometimes referred to as the extended price) for each unit price Bid item will be the product of the “Estimated Quantity”, which Owner or its representative has set forth in the Bid Form, for the item and the corresponding “Bid Unit Price” offered by the Bidder. The total of all unit price Bid items will be the sum of these “Bid Prices”; such total will be used by Owner for Bid comparison purposes. The final quantities and Contract Price will be determined in accordance with Paragraph 13.03 of the General Conditions.
C. Discrepancies between the multiplication of units of Work and unit prices will be resolved in favor of the unit prices. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum.
13.02 Allowances
A. For cash allowances that Bid price must include such amounts as the Bidder deems proper for Contractor’s overhead, costs, profit, and other expenses on account of cash allowances, if any named in the Contract Documents, in accordance with paragraph 13. 02. B of the General Condition.
ARTICLE 14—SUBMITTAL OF BID
14.01 Bids shall be submitted online via the PennBid Program (https://pennbid.bonfirehub.com) by the date and time indicated in the Advertisement for Bids along with the Bid security and the other documents required to be submitted as identified herein.
ARTICLE 15—MODIFICATION AND WITHDRAWAL OF BID
15.01 Bids may be modified or withdrawn within PennBid at any time prior to the due date and time listed in the Advertisement for Bids.
15.02 If within 24 hours after Bids are opened any Bidder files a duly signed written notice with Owner and promptly thereafter demonstrates to the reasonable satisfaction of Owner that there was a material and substantial mistake in the preparation of its Bid in accordance with all Commonwealth of Pennsylvania laws and statutes (including but not limited to Pennsylvania Act
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
of January 23, 1974 as may be amended), the Bidder may withdraw its Bid, and the Bid security will be returned. Thereafter, if the Work is rebid, the Bidder will be disqualified from further bidding on the Work.
ARTICLE 16—OPENING OF BIDS
16.01 After bid opening, the time of which is listed in the Advertisement for Bids, a public notice will be issued via PennBid containing any available bid results. It should be noted that bid results are subject to further review and should not be construed as issuance of an award.
ARTICLE 17—BIDS TO REMAIN SUBJECT TO ACCEPTANCE
17.01 All Bids will remain subject to acceptance for the period of time stated in the Bid Form, but Owner may, in its sole discretion, release any Bid and return the Bid security prior to the end of this period.
ARTICLE 18—EVALUATION OF BIDS AND AWARD OF CONTRACT
18.01 Owner reserves the right to reject any or all Bids, including without limitation, nonconforming, nonresponsive, unbalanced, or conditional Bids. Owner also reserves the right to waive all minor Bid informalities not involving price, time, or changes in the Work.
18.02 Owner will reject the Bid of any Bidder that Owner finds, after reasonable inquiry and evaluation, to not be responsible.
18.03 If Bidder purports to add terms or conditions to its Bid, takes exception to any provision of the Bidding Documents, or attempts to alter the contents of the Contract Documents for purposes of the Bid, whether in the Bid itself or in a separate communication to Owner or Engineer, then Owner will reject the Bid as nonresponsive.
18.04 If Owner awards the contract for the Work, such award will be to the responsible Bidder submitting the lowest responsive Bid.
18.05 Evaluation of Bids
A. For the determination of the apparent low Bidder when unit price bids are submitted, Bids will be compared on the basis of the total of the products of the estimated quantity of each item and unit price Bid for that item, together with any lump sum items.
18.06 In evaluating whether a Bidder is responsible, Owner will consider the qualifications of the Bidder and may consider the qualifications and experience of Subcontractors and Suppliers proposed for those portions of the Work for which the identity of Subcontractors and Suppliers must be submitted as provided in the Bidding Documents.
18.07 Owner may conduct such investigations as Owner deems necessary to establish the responsibility, qualifications, and financial ability of Bidders and any proposed Subcontractors or Suppliers.
ARTICLE 19—BONDS AND INSURANCE
19.01 Article 6 of the General Conditions, as may be modified by the Supplementary Conditions, sets forth Owner’s requirements as to performance and payment bonds, other required bonds (if any), Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
and insurance. When the Successful Bidder delivers the executed Agreement to Owner, it must be accompanied by required bonds and insurance documentation.
19.02 Article 8, Bid Security, of these Instructions, addresses any requirements for providing bid bonds as part of the bidding process.
ARTICLE 20—SIGNING OF AGREEMENT
20.01 When Owner issues a Notice of Award to the Successful Bidder, it will be accompanied by the unexecuted counterparts of the Agreement along with the other Contract Documents as identified in the Agreement. Within 15 days thereafter, Successful Bidder must execute and deliver the required number of counterparts of the Agreement and any bonds and insurance documentation required to be delivered by the Contract Documents to Owner. Within 10 days thereafter, Owner will deliver one fully executed counterpart of the Agreement to Successful Bidder, together with printed and electronic copies of the Contract Documents as stated in Paragraph 2.02 of the General Conditions.
ARTICLE 21—SALES AND USE TAXES
21.01 Owner is exempt from Pennsylvania state sales and use taxes on materials and equipment to be incorporated in the Work. Said taxes must not be included in the Bid. Refer to Paragraph SC-7.10 of the Supplementary Conditions for additional information.
ARTICLE 22—STEEL PRODUCTS PROCUREMENT ACT
22.01 The Contractor shall comply with Act No. 3 of 1978, known as the “Steel Products Procurement Act”. Except as provided in this Act, the Contractor shall only supply steel products to be used in the performance of the Contract, or any subcontract thereunder, which are produced in the United States. Certificates of compliance with regard to this Act shall be supplied by the Contractor to the Engineer.
ARTICLE 23—LABOR REQUIREMENTS
23.01 By submitting a Bid Proposal, the Bidder agrees to comply with the "Pennsylvania Prevailing Wage Act" (Act of August 15, 1961, P.L. 987 as Amended).
23.02 During the performance of this Contract, the Contractor agrees as follows:
A. The Contractor will not discriminate against any employees or applicant for employment because of race, color, religion, sex, national origin, or handicap.
B. The Contractor will take affirmative action to ensure that applicants are employed, and that employees are treated during employment, without regard to race, color, religion, sex, national origin, or handicap. Such action shall include, but not be limited to, the following:
employment, upgrading, demotion, or transfer; recruitment or recruitment advertising;
layoff or termination; rates of pay or other forms of compensation; and selection for training, including apprenticeship.
C. The Contractor agrees to post in conspicuous places, available to employees and applicants for employment, notices which may be provided by the Authority setting forth the provisions of this nondiscrimination clause.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
D. The Contractor will, in all solicitations or advertisements for employees placed by or on behalf of the Contractor, state that all qualified applicants will receive consideration for employment without regard to race, color, religion, sex, national origin, or handicap.
E. The Contractor will send to each labor union or representative of workers with which the Contractor has a collective bargaining agreement or other contract or understanding, a notice, to be provided, advising the labor union or workers' representatives of the Contractor's commitments under this Section and shall post copies of the notice in conspicuous places available to employees and applicants for employment.
F. In the event of the Contractor's noncompliance with the nondiscrimination clauses of this Contract or with any of the said rules, regulations, or orders, this Contract may be canceled, terminated, or suspended in whole or in part and the Contractor may be declared ineligible for further Authority contracts.
G. The Contractor will include the provisions of these paragraphs in every subcontract or purchase order unless exempted.
23.03 No person who, at the time, is serving sentence in a penal or correctional institution shall be employed on the work covered by this Contract.
23.04 This project must be performed under prevailing wage guidelines. Prevailing wage documents are contained in the reference section of this Project Manual.
BID FORM
EJCDC® C-410, Bid Form for Construction Contract.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
BID FORM FOR CONSTRUCTION CONTRACT
PORTER-TOWER JOINT MUNICIPAL AUTHORITY
The terms used in this Bid with initial capital letters have the meanings stated in the Instructions to Bidders, the General Conditions, and the Supplementary Conditions.
ARTICLE 1—OWNER AND BIDDER
1.01 This Bid is submitted to: Electronic bids, inclusive of all requested supporting documents, shall be submitted via the PennBid Program (https://pennbid.bonfirehub.com).
1.02 The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement with Owner in the form included in the Bidding Documents to perform all Work as specified or indicated in the Bidding Documents for the prices and within the times indicated in this Bid and in accordance with the other terms and conditions of the Bidding Documents.
ARTICLE 2—ATTACHMENTS TO THIS BID
2.01 The following documents are submitted with and made a condition of this Bid:
A. Required Bid security;
B. List of Proposed Subcontractors;
C. List of Equipment and Materials;
D. Required Bidder Qualification Statement with supporting data; and
E. Appendix D – Public Works Employment Verification Form – Act 127
F. Appendix E – Non-Discrimination/Sexual Harassment Certification
ARTICLE 3—BASIS OF BID—LUMP SUM BID AND UNIT PRICES
3.01 Lump Sum Bids
A. Bidder will complete the Work in accordance with the Contract Documents for the following lump sum (stipulated) price(s), together with any Unit Prices indicated in Paragraph 3.02:
Item No.
Description
Lump Sum Bid Price
1 Bonds and Insurances $
2 Submittals $
3 Mobilization $
4 Selective Demolition $
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
5 Influent Jockey Pump Installation $
6 Piping, Valves and Appurtenances $
7 Process Field instrumentation $
8 Utilities $
9 Start Up and Commissioning $
10 Training and O/M Manuals $
11 Project Closeout $
Total Lump Sum Bid Price $
3.02 Unit Price Bids
A. Bidder will perform the following Work at the indicated Unit Prices:
Item No.
Description Unit Estimated Quantity
Bid Unit Price Bid Amount
12 Miscellaneous Cast-in-Place Concrete
CY 1 $ $
13 Liquid Sludge Disposal GAL 140 $ $
14 Grit Removal TON 0.4 $ $
Total of All Unit Price Bid Items $
B. Bidder acknowledges that:
1. each Bid Unit Price includes an amount considered by Bidder to be adequate to cover Contractor’s overhead and profit for each separately identified item, and
2. estimated quantities are not guaranteed, and are solely for the purpose of comparison of Bids, and final payment for all Unit Price Work will be based on actual quantities, determined as provided in the Contract Documents.
3.03 Total Bid Price (Lump Sum and Unit Prices)
Total Bid Price (Total of all Lump Sum and Unit Price Bids)
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
3.04 Allowances
1.1 SCADA Integration and Panel Modifications $57,000.00
ARTICLE 4—TIME OF COMPLETION
4.01 Bidder agrees that the Work will be substantially complete and will be completed and ready for final payment in accordance with Paragraph 15.06 of the General Conditions on or before the dates or within the number of calendar days indicated in the Agreement.
4.02 Bidder accepts the provisions of the Agreement as to liquidated damages.
ARTICLE 5—BIDDER’S ACKNOWLEDGEMENTS: ACCEPTANCE PERIOD, INSTRUCTIONS, AND RECEIPT OF
ADDENDA
5.01 Bid Acceptance Period
A. This Bid will remain subject to acceptance for 60 days after the Bid opening, unless the contract award is delayed by a required approval of another government agency, the sale of bonds, or the award of a grant or grants, in which case this Bid shall remain open to acceptance and shall be irrevocable for a period of 120 days after the Bid opening.
5.02 Instructions to Bidders
A. Bidder accepts all of the terms and conditions of the Instructions to Bidders, including without limitation those dealing with the disposition of Bid security.
5.03 Receipt of Addenda
A. Bidder hereby acknowledges receipt of the following Addenda:
Addendum Number Addendum Date
ARTICLE 6—BIDDER’S REPRESENTATIONS AND CERTIFICATIONS
6.01 Bidder’s Representations
A. In submitting this Bid, Bidder represents the following:
1. Bidder has examined and carefully studied the Bidding Documents, including Addenda.
2. Bidder has visited the Site, conducted a thorough visual examination of the Site and adjacent areas, and become familiar with the general, local, and Site conditions that may affect cost, progress, and performance of the Work.
3. Bidder is familiar with all Laws and Regulations that may affect cost, progress, and performance of the Work.
4. Bidder has carefully studied the reports of explorations and tests of subsurface conditions at or adjacent to the Site and the drawings of physical conditions relating to existing surface or subsurface structures at the Site that have been identified in the
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
Supplementary Conditions, with respect to the Technical Data in such reports and drawings.
5. Bidder has carefully studied the reports and drawings relating to Hazardous Environmental Conditions, if any, at or adjacent to the Site that have been identified in the Supplementary Conditions, with respect to Technical Data in such reports and drawings.
6. Bidder has considered the information known to Bidder itself; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Bidding Documents; and the Technical Data identified in the Supplementary Conditions or by definition, with respect to the effect of such information, observations, and Technical Data on (a) the cost, progress, and performance of the Work; (b) the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder, if selected as Contractor; and
(c) Bidder’s (Contractor’s) safety precautions and programs.
7. Based on the information and observations referred to in the preceding paragraph, Bidder agrees that no further examinations, investigations, explorations, tests, studies, or data are necessary for the performance of the Work at the Contract Price, within the Contract Times, and in accordance with the other terms and conditions of the Contract.
8. Bidder is aware of the general nature of work to be performed by Owner and others at the Site that relates to the Work as indicated in the Bidding Documents.
9. Bidder has given Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder has discovered in the Bidding Documents, and of discrepancies between Site conditions and the Contract Documents, and the written resolution thereof by Engineer is acceptable to Bidder.
10. The Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performance and furnishing of the Work.
11. The submission of this Bid constitutes an incontrovertible representation by Bidder that without exception the Bid and all prices in the Bid are premised upon performing and furnishing the Work required by the Bidding Documents.
6.02 Bidder’s Certifications
A. The Bidder certifies the following:
1. This Bid is genuine and not made in the interest of or on behalf of any undisclosed individual or entity and is not submitted in conformity with any collusive agreement or rules of any group, association, organization, or corporation.
2. Bidder has not directly or indirectly induced or solicited any other Bidder to submit a false or sham Bid.
3. Bidder has not solicited or induced any individual or entity to refrain from bidding.
4. Bidder has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing for the Contract. For the purposes of this Paragraph 6.02.A:
a. Corrupt practice means the offering, giving, receiving, or soliciting of anything of value likely to influence the action of a public official in the bidding process.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
b. Fraudulent practice means an intentional misrepresentation of facts made (a) to influence the bidding process to the detriment of Owner, (b) to establish bid prices at artificial non-competitive levels, or (c) to deprive Owner of the benefits of free and open competition.
c. Collusive practice means a scheme or arrangement between two or more Bidders, with or without the knowledge of Owner, a purpose of which is to establish bid prices at artificial, non-competitive levels.
d. Coercive practice means harming or threatening to harm, directly or indirectly, persons or their property to influence their participation in the bidding process or affect the execution of the Contract.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
BIDDER hereby submits this Bid as set forth above:
Bidder:
(typed or printed name of organization)
By:
(individual’s signature)
Name:
(typed or printed)
Title:
(typed or printed)
Date:
(typed or printed)
If Bidder is a corporation, a partnership, or a joint venture, attach evidence of authority to sign.
Attest:
(individual’s signature)
Name:
(typed or printed)
Title:
(typed or printed)
Date:
Address for giving notices:
Bidder’s Contact:
Name:
(typed or printed)
Title:
(typed or printed)
Phone:
Email:
Address:
Bidder’s Contractor License No.: (if applicable)
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
BID FORM FOR CONSTRUCTION CONTRACT
PORTER-TOWER JOINT MUNICIPAL AUTHORITY
The terms used in this Bid with initial capital letters have the meanings stated in the Instructions to Bidders, the General Conditions, and the Supplementary Conditions.
ARTICLE 1—OWNER AND BIDDER
1.01 This Bid is submitted to: Electronic bids, inclusive of all requested supporting documents, shall be submitted via the PennBid Program (https://pennbid.bonfirehub.com).
1.02 The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement with Owner in the form…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .