1-Technical Specifications Fenimore Woods Parking Accessibility Site Improvements.pdf
PDF 545 KB Posted
- Solicitation number
- US.255103
- Issued by
- Delaware County, Pennsylvania
About this file
This is a technical specifications document for the Fenimore Woods Parking, Accessibility, and Site Improvements project being solicited by Radnor Township, Pennsylvania. The project, identified as Contract #B-26-003, involves comprehensive site improvements at 1194 Eagle Road in Radnor Township, including repaving of existing asphalt and gravel parking lots, construction of new pedestrian trails, installation of utilities, signage and site furnishings, and completion of grading, topsoil placement, and site restoration. The work is organized into multiple divisions covering general requirements, site demolition, concrete work, earthwork, exterior improvements, utilities, and site furnishings. Specific bid items include mobilization and demobilization, site layout, erosion and sedimentation controls, milling and removal of existing pavement and gravel, removal of existing concrete and asphalt curbs, removal of concrete wheel stops and picnic table pads, disposal of spoils, and installation of new Superpave asphalt mixtures, with measurements in square yards, linear feet, or lump sum amounts as applicable.
The specifications establish that this is a single prime contract with work restricted to 7:00 a.m. to 5:00 p.m., Monday through Friday, unless otherwise approved by the Owner and authorities having jurisdiction. The Owner will occupy the premises during the entire construction period with the exception of areas under construction, requiring contractors to provide a minimum of 72 hours' notice for activities affecting Owner operations and to maintain existing exits and access to walkways and adjacent facilities. Payment for work is based on actual measurements and quantities multiplied by unit prices, with unit prices covering all required labor, supervision, products, tools, equipment, transportation, services, and incidentals necessary to complete each item. The document does not specify contract award dates, response deadlines, site visit requirements, bidder's meetings, pricing terms, set-asides, or funding sources.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Fenimore Woods Parking, Accessibility, and Site Improvements
Technical Specifications
Table of Contents:
DIVISION 01 – GENERAL REQUIREMENTS
01 1100 Summary of Work 01 2973 Measurement and Payment 01 3100 Project Management and Coordination 01 3300 Submittal Procedures 01 4100 Regulatory Requirements 01 5000 Temporary Facilities and Controls 01 5526 Traffic Control 01 6000 Product Requirements 01 7700 Closeout Procedures
DIVISION 02 – EXISTING CONDITIONS
02-4100 Site Demolition
DIVISION 03 – CONCRETE
03-3000 Cast-in-Place Concrete
DIVISION 07 – SITE FURNISHINGS
07-6200 Aluminum Gutters, Downspouts, and Accessories
DIVISION 22 - PLUMBING
22-4713 Drinking Fountains
DIVISION 31 – EARTHWORK
31-1000 Site Clearing 31-2000 Earth Moving 31-2500 Erosion & Sedimentation Control
DIVISION 32 – EXTERIOR IMPROVEMENTS
32-1200 Flexible Bituminous Pavement 32-1243 Porous Asphalt Paing 32-1713 Precast Concrete Parking Bumpers 32-1723 Hot Thermoplastic Pavement Markings 32-1723.13 Detectable Warning Surface
32-3129 Wood Fences and Gates 32-9200 Lawns and Grasses
DIVISION 33 – UTILITIES
33-4000 Site Drainage Utilities 33-7113 Direct-Bury PVC Conduit and Pull Tape
SECTION 011100 - SUMMARY
PART 1 – GENERAL
1.01 RELATED DOCUMENTS
Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.02SUMMARY
A. Section Includes:
1.01. Related Documents
1.02. Summary
1.03. Project Information
1.04. Work Covered by the Contract Documents
1.05. Type of Contract
1.06. Coordination with Occupants
1.07. Work Restrictions
1.08. Specification and Drawing Conventions
1.03 PROJECT INFORMATION
Project Identification: Fenimore Woods Parking, Accessibility, and Site Improvements.
Project Location: 1194 Eagle Rd, St Davids, PA 19087
Owner: Radnor Township, 301 Iven Ave, Wayne, PA 19087
Engineer: Radnor Township, 301 Iven Ave, Wayne, PA 19087
1.04 WORK COVERED BY THE CONTRACT DOCUMENTS
A. The Work for this Project is defined by the Contract Documents, and includes, but is not limited to, all labor, materials, equipment, tools, transportation, facilities, and appurtenances thereto, which are indicated, to install the necessary parking, accessibility, and site improvements at Fenimore Woods located at 1194 Eagle Road in Radnor Township, PA.
1.05 TYPE OF CONTRACT
A. The project will be constructed under a single prime contract.
1.06 COORDINATION WITH OCCUPANTS
Partial Owner Occupancy: Owner will occupy the premises during entire construction period, with the exception of areas under construction. Cooperate with Owner during construction operations to minimize conflicts and facilitate Owner usage. Perform the Work so as not to interfere with Owner’s operations. Maintain existing exits unless otherwise indicated.
Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Owner and authorities having jurisdiction.
Provide not less than 72 hours’ notice to Owner of activities that will affect Owner’s operations.
1.07 WORK RESTRICTIONS
Comply with restrictions on construction operations.
Comply with limitations on use of public streets, work on public streets, rights of way, and other requirements of authorities having jurisdiction.
On-Site Work Hours: Limit work to between 7:00 a.m. to 5:00 p.m., Monday through Friday, unless otherwise indicated. Work hours may be modified to meet Project requirements if approved by Owner and authorities having jurisdiction.
Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after arranging for temporary utility services according to requirements indicated:
Notify Owner and Engineer not less than two days in advance of proposed utility interruptions.
Obtain Owner’s written permission before proceeding with utility interruptions.
Noise, Vibration, Dust, and Odors: Coordinate operations that may result in high levels of noise and vibration, dust, odors, or other disruption to Owner occupancy with Owner.
Notify Owner and Engineer not less than two days in advance of proposed disruptive operations.
1.08 SPECIFICATION AND DRAWING CONVENTIONS
Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows:
Imperative mood and streamlined language are generally used in the Specifications. The words “shall,” “shall be,” or “shall comply with,” depending on the context, are implied where a colon is used within a sentence or phrase.
Specification requirements are to be performed by Contractor unless specifically stated otherwise.
Division 00 Contracting Requirements: General provisions of the Contract, including General and Supplementary Conditions, apply to all Sections of the Specifications.
Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications.
Drawing Coordination: Requirements for materials and products identified on Drawings are described in detail in the Specifications. One or more of the following are used on Drawings to identify materials and products:
Terminology: Materials and products are identified by the typical generic terms used in the individual Specifications Sections.
PART 2 – PRODUCTS (Not Used)
PART 3 – EXECUTION (Not Used)
END OF SECTION
SECTION 01 2973
MEASUREMENT AND PAYMENT
PART 1 – GENERAL
1.01 DESCRIPTION
The work of this section includes the description of the various pay items found on the Bid Form and the method of measurement of each pay item.
1.02 QUALITY ASSURANCE
A. Work completed under the Contract shall be measured by the ENGINEER according to the standards of weights and measures recognized by the U.S. Bureau of Standards.
B. The method of measurement and computations to be used in determination of quantities of material furnished and of work performed under the Contract will be those methods generally recognized as conforming to good engineering practice.
C. Measurement for area computations will be made on the surface. Pay measurements for area computations will not exceed the neat dimensions indicated on the Drawings, unless otherwise ordered in writing by the ENGINEER.
D. Structures will be measured according to neat lines indicated on the Drawings, or as altered to fit field conditions. No payment will be made for length, width, or depth, in excess of that indicated on the Drawings or specified for any construction, unless otherwise approved by the ENGINEER in writing.
E. Items which are measured by the linear foot, such as pipe, will be measured parallel to the base or foundation upon which such items are placed.
F. In computing volumes of excavation, the average end area method, based on horizontal measurements, or other acceptable methods, will be used.
G. The term “each”, when used as an item of payment, will mean complete payment for the work described in the Contract Documents.
H. The term “lump sum”, when used as an item of payment, will mean complete payment for the work described in the Contract Documents, including all necessary fittings and accessories, and required testing completed.
I. In cases where the payment clause in the specifications relating to any unit or lump sum price stated in the Contract requires that the said unit or lump sum price cover and be considered compensation for certain work or materials essential to the item, this same item shall not be measured or paid for under any other pay item which may appear elsewhere in the specifications.
J. Where specific items are listed under each construction measurement and payment item, it shall be understood that the price and payment shall constitute full compensation for furnishing all labor, materials and equipment required to acceptably complete the work as described, and all other related work necessary to complete the construction as more fully defined in the specifications and/or shown on the drawings.
1.03 PAYMENT
A. Payment Includes: Full compensation for all required labor, supervision, products, tools, equipment, plant, transportation, services, and incidentals; erection, application or installation of an item of the Work; overhead and profit.
1. “Incidentals” are to be considered as an additional obligation to the other work required for the item(s). Incidental work is not payable directly but is to be considered included in the contract price for the item(s) of work.
2. All work not specifically identified as a separate bid item on the bid form is “Incidental”.
B. Final payment for Work governed by unit prices will be made based on the actual measurements and quantities, subject to the established pay limits, accepted by the ENGINEER multiplied by the unit price for Work which is incorporated in or made necessary by the Work.
1.04 DEFECT ASSESSMENT
A. Replace the Work, or portions of the Work, not conforming to specified requirements.
B. If, in the opinion of the ENGINEER, it is not practical to remove and replace the Work, the ENGINEER will direct one of the following remedies:
1. The defective work may remain, but the unit sum/price will be adjusted to a new sum/price at the discretion of the ENGINEER and OWNER.
2. The defective work will be partially repaired to the instructions of the ENGINEER, and the unit sum/price will be adjusted to a new sum/price at the discretion of the
ENGINEER.
C. The individual specification sections may modify these options or may identify a specific formula or percentage sum/price reduction.
D. The authority of the ENGINEER and OWNER to assess the defect and identify payment adjustments is final.
PART 2 – PRODUCTS (Not Used)
PART 3 – EXECUTION
3.01 MOBILIZATION/DEMOBILIZATION (Bid Item 1)
Description: This work is the assembly and set-up required to comply with the contract and with local and State laws and regulations, including Contractor’s offices, shops, plants, storage areas, sanitary or other facilities. This work includes obtaining the required permits, insurance, bonds, and any other initial items required for the start of the work.
Measurement and Payment: Lump sum.
3.02 LAYOUT (Bid Item 2)
Description: Layout of the proposed improvements at the project site.
Measurement and Payment: Lump sum.
3.03 EROSION AND SEDIMENTATIOIN CONTROLS (Bid Item 3)
Description: Install and maintain erosion and sedimentation controls per the contract documents.
Measurement and Payment: Lump sum.
3.04 MILLING OF ASPHALT PAVEMENT SURFACE, 2” DEPTH, MILLED MATERIAL
RETAINED BY CONTRACTOR (Bid Item 4)
Description: Mill existing asphalt pavement surface to a 2” depth in areas specified on the plans. Refer to PennDOT Pub 408.
Measurement and Payment: Square Yards.
3.05 REMOVE EXISTING PAVEMENT STRUCTURE TO 6” DEPTH (Bid Item 5)
Description: Remove existing pavement structure to 6” depth in areas specified on the plans.
Measurement and Payment: Square Yards
3.06 SCARIFY EXISTING GRAVEL TO 4” DEPTH (Bid Item 6)
Description: Scarify existing gravel to 4” depth in areas specified on the plans.
Measurement and Payment: Square Yards
3.07 REMOVE EXISTING GRAVEL TO 4” DEPTH (Bid Item 7)
Description: Remove existing gravel to 4” depth in areas specified on the plans.
Measurement and Payment: Square Yards
3.08 REMOVE EXISTING CONCRETE CURB (Bid Item 8)
Description: Remove existing concrete curb per the plans
Measurement and payment: Linear Feet
3.09 REMOVE EXISTING ASPHALT CURB (Bid Item 9)
Description: Remove existing asphalt curb per the plans.
Measurement and payment: Linear Feet
3.10 REMOVE EXISTING CONCRETE WHEEL STOPS FROM SITE (Bid Item 10)
Description: Remove existing concrete wheel stops from site per the plans.
Measurement and payment: Each
3.11 REMOVE EXISTING 7’x5’x6” CONCRETE PADS WITH CONCRETE PICNIC TABLES (Bid Item 11)
Description: remove existing 7’x5’x6” concrete pads with concrete picnic tables per the plans
Measurement and payment: Each
3.12 LEGALLY DISPOSE OF SPOILS OFF SITE (Bid Item 12)
Description: Contractor to retain and legally dispose of all demolished construction materials off site.
Measurement and Payment: Lump Sum
3.13 SUPERPAVE VOLUMETRIC ASPHALT MIXTURE DESIGN, LEVELING COURSE, PG
64-S, 0.3 <3.0 MILLION ESALS, 9.5MM MIX (Bid Item 13)
Description: Install and compact 9.5mm wearing course where necessary. Refer to PennDOT Pub 408.
Measurement and Payment: Square Yards
3.14 SUPERPAVE VOLUMETRIC ASPHALT MIXTURE DESIGN, WEARING COURSE, PG
64-S, 0.3 <3.0 MILLION ESALS, 9.5MM MIX, 2" DEPTH (Bid Item 14)
Description: Install and compact 2” depth 9.5mm wearing course in areas specified on the plans. Refer to PennDOT Pub 408.
3.15 SUPERPAVE VOLUMETRIC ASPHALT MIXTURE DESIGN, BASE COURSE, PG 64-S,
0.3 <3.0 MILLION ESALS, 25MM MIX, 3" DEPTH (Bid Item 15)
Description: Install and compact 3” depth 25mm base course. Refer to PennDOT Pub 408
Measurement and Payment: Square Yards
3.16 INSTALL 6” COMPACTED 2A MATERIAL (Bid Item 16)
Description: Install and compact 6” 2A material. Refer to PennDOT Pub 408
Measurement and Payment: Square Yards
3.17 INSTALL 4” COMPACTED 2A MATERIAL (Bid Item 17)
Description: Install and compact 6” 2A material. Refer to PennDOT Pub 408
Measurement and Payment: Square Yards
3.18 INSTALL 4” COMPACTED POROUS PAVEMENT ON 22” UNIFORMLY GRADED
COURSE AGGREGATE, AASHTO No. 3 (Bid Item 18)
Description: Install and compact 4” of porous pavement on 22” uniformly graded course aggregate, AASHTO No. 3. Refer to PennDOT Pub 408.
Measurement and Payment: Square Yards
3.19 INSTALL SWALE LINED WITH LARGE RIVER ROCK (3”-8”) TO AN 18” DEPTH (Bid Item 19)
Description: Install swale lined with heavy-duty, non-woven class 2 geotextile fabric.
Measurement and Payment: Square Yards
3.20 INSTALL 4,000 PSI CONCRETE CURB WITH 18” DEPTH, 7” TOP WIDTH, 8”
BOTTOM WIDTH, ON 4” AASHTO #57 CLEAN CRUSHED GRAVEL (Bid Item 20)
Description: Install 4,000 PSI Concrete Curb with 18" Depth, 6" Top Width, 8" Bottom Width, on 4" AASHTO #57 Clean Crushed Gravel, at areas identified on the plan.
Measurement and Payment: Linear Feet
3.21 INSTALL 4,000 PSI CONCRETE SIDEWALK TO A DEPTH OF 4” ON 6” AASHTO #57
CRUSHED GRAVEL (Bid Item 21)
Description: Install 4,000 psi concrete sidewalk to a depth of 4” on 6” AASHTO #57 crushed gravel.
3.22 INSTALL RED BRICK DETECTABLE WARNING STRIPS (Bid Item 22)
Description: Install red brick detectable warning strips on ADA ramps. Refer to PennDOT Pub 408.
Measurement and Payment: Each
3.23 INSTALL 2-2” PVC CONDUIT WITH METAL WARNING TAPE AND PULL WIRE (Bid Item 23)
Description: Install 2-2” PVC conduit to depths specified on plans with metal warning tape and pull wire.
Measurement and payment: Linear Feet
3.24 INSTALL THERMOPLASTIC PAVEMENT MARKINGS FOR ADA PARKING SPACES
(Bid Item 24)
Description: Install thermoplastic pavement markings for ADA Parking Spaces, including 4” white lines and handicap space symbol. Refer to PennDOT Pub 408.
Measurement and payment: Each.
3.25 INSTALL R7-8 AND R7-8P HANDICAP PARKING SIGNS (Bid Item 25)
Description: Install R7-8 No Parking sign and R7-8P Van Accessible sign and mount a minimum of 60” above grade. Refer to PennDOT Pub 408.
Measurement and Payment: Each
3.26 INSTALL NEW CONCRETE WHEEL STOPS (Bid Item 26)
Description: Install new concrete wheel stops per the plans.
Measurement and Payment: Each
3.27 INSTALL TWO (2) SLOPED ALUMINUM GUTTERS ALONG PAVILION ROOF WITH
DEBRIS GUARDS, DOWNSPOUTS, AND DOWNSPOUT EXTENSIONS (Bid Item 27)
Description: Install Two (2) sloped aluminum gutters along pavilion roof with debris guards, downspouts, and downspout extensions.
Measurement and Payment: Each
3.28 INSTALL WATER BOTTLE FILLING STATION AND DRINKING FOUNTAIN ON 4'X4'
CONCRETE PAD. VERIFY LOCATION OF EXISTING WATER SERVICE LINE AND CONNECT
TO ASSEMBLY (Bid Item 28)
Description: Install Water Bottle Filling Station and Drinking Foundation on 4'x4'x6" Concrete Pad. Verify Location of Existing Water Service Line and Connect to Assembly.
Measurement and Payment: Lump Sump
3.29 INSTALL DOUBLE-LEAF SWING POST AND RAIL GATE WITH MOUNTED R7-1 "NO
PARKING ANY TIME'' SIGN (Bid Item 29)
Description: Install ADA Accessible Double-Leaf Swing Post and Rail Gate with Mounted R7-1 "No Parking Any Time" Sign
Measurement and Payment: Each
3.30 RAKE/LOOSEN SOIL AND INSTALL 4" TOPSOIL W/HYDROSEED IN ALL
DISTURBED AREAS (Bid Item 30)
Description: Rake/loosen soil and install 4" topsoil w/hydroseed in all disturbed areas identified on the plans.
Measurement and Payment: Square Yard
SECTION 01 3100
PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.01 PROJECT COORDINATION
A. CONTRACTOR is responsible for coordinating his work and the work of any subcontractors in order to produce the finished product as intended by the Contract Documents. Claims for extra work resulting from failure to properly coordinate the work of all trades will not be honored.
B. CONTRACTOR shall coordinate scheduling, submittals, and work of the various sections of Specifications to assure efficient and orderly sequence of installation of construction elements, with provisions for accommodating items to be installed later.
1.02 COORDINATION MEETINGS
CONTRACTOR shall schedule and hold coordination meetings and preinstallation conferences with OWNER, ENGINEER, and any subcontractors to assure coordination of the work.
1.03 COORDINATION OF SUBMITTALS
A. Schedule and coordinate submittals as specified in Section 01 3300.
B. Coordinate requests for substitutions to assure compatibility of space, of operating elements, and effect on work of other sections.
1.04 COORDINATION WITH OWNER AND ENGINEER
A. Notify OWNER five (5) business days in advance of beginning work in a work area.
B. Operate existing equipment and valves only with permission of OWNER and in presence of OWNER's designated representative.
C. Cooperate with OWNER to keep existing facilities in service during construction.
1.05 COORDINATION OF PROJECT CLOSEOUT
A. Coordinate completion and cleanup of portions of work designated for partial usage by the OWNER in preparation for Substantial Completion.
B. After OWNER's occupation of premises, coordinate access to site for correction of defective work and work not in accordance with Contract Documents, to minimize disruption of OWNER's activities.
C. Assemble and coordinate closeout submittals specified in Section 01 7700.
1.06 COORDINATION OF UTILITIES AND OTHER OWNERS
A. Prior to beginning construction, inform all public service companies, individuals, and others owning or controlling any facilities or structures within the project, which may be affected by the work, that it will commence on a certain date.
B. CONTRACTOR's attention is directed to the Provisions of Pennsylvania General Assembly Act No. 287 as they apply to the work under this Contract.
PART 2 – PRODUCTS (Not Used)
SECTION 01 3300
SUBMITTAL PROCEDURES
PART 1 – GENERAL
1.01 CONSTRUCTION SCHEDULE
A. Construction Schedule shall be horizontal bar-chart type with a separation time bar for each significant construction activity. No activity on the schedule shall have a duration longer than fifteen (15) days, with the exception of fabrication, procurement and punch list activities. Activity duration shall be the total number of actual days required to perform that activity including consideration of weather impact on completion of that activity.
B. Prepare the schedule on a sheet, or series of sheets, of reproducible media and sufficient width to show data for the entire construction period. Provide a continuous vertical line to identify the first working day of each week. Within each time bar, indicate estimated completion percentage in 10 percent increments. As work progresses, place a contrasting mark in each bar to indicate actual completion.
C. Secure time commitments for performing critical elements of the work from all parties involved. Coordinate each element on the schedule with other construction activities.
Show each activity in proper sequence. Graphically indicate the sequences necessary for completion of related portions of the work.
D. Coordinate the Construction Schedule with the Schedule of Values, list of subcontractor, list of suppliers, and anticipated submittal schedule for shop drawings, product data and samples.
E. Indicate completion in advance of the date established for Substantial Completion.
Indicate Substantial Completion on the schedule to allow time for the ENGINEER's procedures necessary to issue a Certificate of Substantial Completion.
F. Following favorable response to the submittal by the ENGINEER, print and distribute copies to each subcontractor and other parties required to comply with scheduled dates.
Post copies in the temporary field office(s). When revisions are made, distribute to the same parties and post in the same locations. Delete parties from distribution when they have completed their assigned portion of the work and are no longer involved in construction activities.
G. In general, revise the schedule every month. All Change Orders to the Contracts or other activity, where revisions have been recognized or made, must be incorporated into the schedule.
1.02 APPLICATION FOR PAYMENT
The procedure for submittal, review and payment of monthly applications for progress payments shall be established at the preconstruction conference. Submit one (1) executed original and four (4) copies of each application for payment to the OWNER in a format similar to EJCDC C-620. Complete every entry on the form, including notarization and execution by person authorized to sign legal documents on behalf of the CONTRACTOR.
Incomplete applications will be returned without action. Entries shall match data on the Schedule of Values and Construction Schedule. Use updated schedules if revisions have been made. Include amounts of Change Orders issued prior to the last day of the construction period covered by the application.
1.03 SHOP DRAWINGS, PRODUCT DATA, SAMPLES AND CERTIFICATIONS
A. Fabricated materials or equipment to be incorporated in the work shall be subject to review by the ENGINEER. The CONTRACTOR shall obtain and check prints of manufacturers certified shop drawings and other pertinent data. When the CONTRACTOR has reviewed the shop drawings and is satisfied they are correct, he shall number each submittal (shop drawing, certificate, and manual) and submit them to the ENGINEER for review. Submittal numbering system shall be the section number referenced by these Specifications followed by the submittal number (i.e., 32 1200-1, 33 1216-1 and 33 1216-2).
B. Shop drawings are intended to mean fabrication and installation drawings. These drawings and pertinent data shall be complete and in such detail as the ENGINEER may require for providing information regarding the design, installation, testing, and operation for products and/or equipment.
C. All costs necessary for compliance with the requirements of this section of the Specifications shall be included in the bid.
D. Detailed shop drawings, data, and literature for fabricated materials or equipment to be incorporated in the work shall be submitted to the ENGINEER for review at least two weeks before fabrication. The CONTRACTOR shall obtain and check manufacturer's shop drawings, certified prints, and other pertinent data for conformance with all requirements of the Drawings and Specifications in ample time to permit satisfactory progress of the work.
E. After completion of such checking and verification by the CONTRACTOR, the CONTRACTOR shall include a full completed copy of Attachment 1 as a cover sheet for the shop drawing. In addition, the submittal number shall be written or typed in the lower right hand corner of all copies of each shop drawing. The submittal numbering system should be the specification section number followed by the submittal number (i.e. 33 3113-1 - Ductile
Iron Pipe, 33 3113-2 -PVC Pipe). Failure to include a cover sheet or not numbering submittals shall be grounds for rejection of the submittal by the ENGINEER. (See Attachment 1 at the end of this section).
F. All data, drawings, and correspondence from subcontractors, material men, or suppliers shall be routed through the CONTRACTOR. This procedure is required so that the CONTRACTOR's superintendent can familiarize himself with all information which the CONTRACTOR sends to the ENGINEER and also to prevent the ENGINEER from taking action upon something other than that which is desired by the CONTRACTOR. The ENGINEER shall consider for review only such data and details as are verified and transmitted to him directly by the CONTRACTOR.
G. All correspondence between the ENGINEER and the CONTRACTOR, all shop drawings, and all data for review of drawings or materials will be handled by the ENGINEER. All such data shall be delivered directly to him at the ENGINEER's office. The replies pertaining to these matters will be delivered to the CONTRACTOR or the CONTRACTOR's representative at the job site.
H. A sufficient number of shop drawings and review data shall be submitted to the ENGINEER, who will retain four (4) copies of each submittal. All additional copies, up to a maximum of four (4), received by ENGINEER will be returned to the CONTRACTOR or CONTRACTOR’s representative at the job site. The ENGINEER's notations of the action which the ENGINEER has taken will be noted on all the returned copies. Sufficient time for the review of all shop drawing submittals shall be allowed in the CONTRACTOR's schedule.
A minimum of two weeks shall be allotted for each shop drawing review.
I. Drawings of minor or incidental fabricated materials and/or equipment may not be required by the ENGINEER. The CONTRACTOR shall furnish the ENGINEER with tabulated lists of such fabrications, showing the names of the manufacturers and catalog numbers, together with samples of general data as may be required to permit intelligent determination as to their acceptability for incorporation in the work.
J. Upon successful review by the ENGINEER of the shop drawings, data sheets, samples, other data, the fabrications furnished shall be in conformity with the same. The acceptance of the shop drawings, data sheets, samples or other data shall in no way release the CONTRACTOR from CONTRACTOR’s responsibility for the proper fulfillment, by any fabrication, of the requirements of the Agreement.
K. All reviews of shop drawings, data sheets or literature are subject to the products fulfilling the specific requirements of the Drawings and Specifications. Review of items that do not conform in detail to the specified product shall place upon the CONTRACTOR the responsibility for suc- cessful operation of the proposed product. Should the item subsequently prove to be defective or otherwise unsatisfactory for the service for which it was intended, the CONTRACTOR shall, without cost to the OWNER and without obligation on the part of the ENGINEER, replace the item with the material originally specified. The ENGINEER's review of shop drawings or layout for any material, apparatus, or device shall not relieve the CONTRACTOR from the responsibility of furnishing the same of proper dimension, size, quantity, quality, and all performance characteristics to efficiently perform the requirements and intent of the Contract Documents. Such review shall not relieve the CONTRACTOR from responsibility for errors of any sort on the shop drawings. If the shop drawings deviate from the Contract Documents, the CONTRACTOR shall advise the ENGINEER of the deviations, in writing accompanying the shop drawings, including the reasons for the deviations, and shall request a deviation from the Contract Documents as hereinafter described.
L. The shop drawings are intended to be utilized by the CONTRACTOR for additional fabrication, assembly, and erection data. The shop drawings do not change or supersede the Drawings and Specifications except in specific cases when the CONTRACTOR requests, in writing, a deviation from the Drawings and Specifications. The CONTRACTOR's request for a change shall give, in detail, the specific change requested and shall state the reason for the change. Changes requested by the CONTRACTOR and reviewed by the ENGINEER shall not be construed to include acceptance of any change except the changed details specifically requested and accepted.
M. It shall be the responsibility of the CONTRACTOR to make all the necessary changes in other items, which result from deviations or changes requested by the CONTRACTOR and reviewed by the ENGINEER, so that all items perform the requirements and intent of the Contract Documents.
N. The CONTRACTOR shall furnish the number of samples required by individual sections of the Specifications. Submit samples under separate transmittal letter with appropriate section and article number of the Specifications as identification. A separate transmittal letter is required for each sample submitted.
O. The CONTRACTOR shall furnish all certifications including Statements of Compliance, Installation Certificates, and certified test results as required by individual sections of the Specifications. Submit certificates under separate transmittal letter using the same numbering system as specified for shop drawings and product data. The number of certifications submitted shall be the same as used for shop drawing and review data submittals.
P. CONTRACTOR shall make resubmittals under procedures specified for initial submittals and shall identify changes made since previous submittals. ENGINEER will review the first submittal and the first resubmittal at no cost to the CONTRACTOR. Additional submittals will be reviewed by the ENGINEER and the costs for these reviews will be borne by the CONTRACTOR. These costs when incurred by the CONTRACTOR will be deducted from CONTRACTOR's progress payments. Each resubmittal shall contain the original submittal number with a suffix letter after the original number such as "A" for the first resubmittal, "B" for the second resubmittal, "C" for the third, and so forth.
1.04 WARRANTIES
A. CONTRACTOR shall obtain warranties, executed by responsible subcontractors, suppliers, and manufacturers, within ten (10) days after completion of the applicable item of work. Except for items put into use with the OWNER’s permission, lave date of beginning of time warranty until the date of Substantial Completion is determined.
B. Warranties shall be bound in a commercial quality 8 1/2" x 11" three-ring side binders, with hardback, cleanable, plastic covers. Label cover of each binder with type or printed title "WARRANTIES", with title of project; name, address and telephone number of CONTRACTOR; and name of responsible principle. Provide each binder with a Table of Contents, neatly typed, with each item identified with the number and title of the specification section in which it is specified, and the name of the product or work item.
Separate each warranty with index tab sheets keyed to the Table of Contents listing.
Provide full information, using separate typed sheets as necessary. List subcontractor, supplier, and manufacturer, with name, address, and telephone number of responsible principle.
C. Verify that documents are in proper form, contain full information, and are notarized.
Co-execute submittals when required. Retain warranties until time specified for submittal.
D. For equipment or component parts of equipment put into service during construction with the OWNER's permission, submit documents within ten (10) days after acceptance.
Make other submittals within ten (10) days after date of Substantial Completion, prior to final Application for Payment. For items of work accepted after the date of Substantial Completion, submit within ten (10) days after acceptance, listing the date of acceptance as the beginning of the warranty period.
1.05 PROJECT RECORD DOCUMENTS
A. Record Documents shall consist of the following:
1. Contract Drawings
TS-1: Title Sheet
EF-1: Existing Features and Demolition Plan
SP-1: Site Improvements Plan
GP-1: Grading Plan 1
GP-2: Grading Plan 2
CD-1: Construction Details 1
CD-2: Construction Details 2
ES-1: Erosion and Sedimentation Control Plan
2. Specifications
3. Addenda
4. Change Orders and other modifications to the Contract(s)
5. Reviewed shop drawings, product data, and samples
6. Manufacturer’s Certificates and Statements of Compliance
7. Installation Certificates
B. Record Drawings: Maintain a clean, undamaged set of blue or black line white prints of Contract Drawings and shop drawings. Mark the set to show the actual installation where the installation varies substantially from the work as originally shown. Mark whichever drawing is most capable of showing conditions fully and accurately. Where shop drawings are used, record a cross- reference at the corresponding location in the Contract Drawings.
Give particular attention to concealed elements that would be difficult to measure and record at a later date.
C. Mark Record Documents with red erasable pencil. Use other colors to distinguish between variations in separate categories of the work. Mark new information that is important to the OWNER, but was not shown on the Contract Drawings or shop drawings.
Measure and record the horizontal and vertical locations of all underground utilities and appurtenances referenced to permanent surface improvements. Note related Change Order numbers where applicable.
E. At project closeout, CONTRACTOR shall submit Record Drawings to the ENGINEER certified by a principal officer of the CONTRACTOR. In general, the certification statement shall read as follows:
"These Record Drawings have been completed and certified by (Name of CONTRACTOR) as reflecting as-constructed conditions. Responsibility for accuracy of the Record Drawings rests with (Name of CONTRACTOR)."
BY: (Principal Officer of CONTRACTOR)
TITLE: __________________________________________
DATE: __________________________________________
ATTACHMENT 1
Project: Fenimore Woods Improvement Project
Title: _______________________________________
(Submittal Number - Name)
Checked By: _______________________________________
(CONTRACTOR's Name)
Signed By: _______________________________________
(Checker's Name)
Date: _______________________________________
This submittal has been reviewed and approved by the CONTRACTOR with respect to the means, methods, techniques, sequences and procedures of construction, and safety precautions and programs incidental thereto. The CONTRACTOR also warrants that this submittal complies with the Contract Documents and comprises no variation thereto.
Notes:
1. The CONTRACTOR is responsible for putting the submittal number in the lower right-hand corner of all copies of each submittal.
2. The CONTRACTOR is responsible for binding or stapling all copies of each submittal individually.
SECTION 01 4100
REGULATORY REQUIREMENTS
PART 1 – GENERAL
1.01 REQUIREMENTS INCLUDE
A. Comply with requirements of permits obtained by the OWNER, when these permits are specifically noted in this section of the specifications.
D. The work described in the technical specifications is governed by the rules, regulations, and standard specifications of:
1. Radnor Township
2. The Pennsylvania Municipal Authorities Act, Last Amendment
3. Where noted, PennDOT Specifications, Publication 408, Latest Edition, PennDOT Publication #72 – Standards for Roadway Construction, and PennDOT Bulletin 15 – Approved Construction Materials, with all supplements current at the time of construction. When particular Articles or Sections are referred to, all paragraphs other than those relating to Measurement and Payment shall apply. Measurement and Payment shall be defined in these specifications.
4. Pennsylvania Bureau of Labor Law Compliance Prevailing Wage Rates
Where a discrepancy exists between any of the Sections of these Technical Specifications, and the rules, regulations, and ordinances of the governing municipality, the rules of the governing municipality shall prevail.
SECTION 01 5000
TEMPORARY FACILITIES AND CONTROLS
PART 1 - GENERAL
FIELD OFFICE FACILITIES FOR THE ENGINEER
The CONTRACTOR is not required to provide field facilities for the ENGINEER. The CONTRACTOR is required to maintain one (1) set of Plans and Specifications at the project site at all times.
ELECTRIC POWER AND TELEPHONE
The cost of electric current used for the construction of the work, testing of all electrical and mechanical equipment, and other related work shall be borne by the CONTRACTOR up to and including the date of acceptance of work.
The CONTRACTOR shall provide the ENGINEER with telephone service on this project. A cell phone for the construction foreman will satisfy this requirement.
BARRIERS
Provide barriers to prevent unauthorized entry to construction areas, and to protect adjacent properties from damage from construction operations and demolition.
Provide protection for plant life designated to remain. Replace damaged plant life.
Protect non-owned vehicular traffic, stored materials, site and structures from damage.
TEMPORARY WATER SUPPLY AND SANITARY ARRANGEMENTS
Water supply: Provide adequate capacity at each stage of construction. Provide trucked in service as required.
Sanitary facilities including temporary toilets and wash facilities: Comply with regulations and health codes for the type, number, location, and maintenance of facilities.
PARKING
CONTRACTOR shall provide and maintain suitable parking areas for the use of all construction workers and others performing Work or furnishing services in connection with the Project, as required, to avoid any need for parking personal vehicles where they may interfere with public traffic, the OWNER's operations, or construction activities.
SAFETY FENCE
CONTRACTOR shall furnish and erect all necessary temporary construction safety fence where indicated on Plans to provide adequate warning of hazardous work areas. The fence shall be polyethylene and colored “OSHA Orange”.
PROGRESS CLEANING
Maintain areas free of waste materials, debris and rubbish. Maintain site in a clean and orderly condition.
Remove waste materials, debris, and rubbish from site periodically and dispose of away from site.
PART 2 – PRODUCTS (Not Used)
PART 3 – EXECUTION
INSTALLATION
Use qualified personnel for installation of temporary facilities. Locate facilities where they will serve the Project adequately and result in minimum interference with performance of the Work. Relocate and modify facilities as required.
Provide each facility ready for use when needed to avoid delay. Maintain and modify as required. Do not remove until facilities are no longer needed.
COLLECTION AND DISPOSAL OF WASTE
Collect waste from construction areas and elsewhere daily. Comply with requirements of NFPA 241 for removal of combustible waste material and debris. Enforce requirements strictly. Do not hold materials more than 7 days during normal weather or 3 days when temperature is expected to rise above 80°F. Handle hazardous, dangerous or unsanitary waste materials separately from other waste by containerizing properly. Dispose of materials in a lawful manner.
SECTION 01 5526
TRAFFIC CONTROL
PART 1 - GENERAL
GENERAL SAFETY
A. CONTRACTOR shall furnish, install and maintain such barricades, fences, railings, signs, warning lights, safety helmets and other devices as are necessary for the general safety of both the public and workmen on and around the work sites.
B. CONTRACTOR shall immediately remove any spillage caused by CONTRACTOR’s operations on any street, sidewalk or pedestrian way.
GENERAL CONVENIENCE
A. CONTRACTOR shall conduct CONTRACTOR’s operations to minimize inconvenience to and obstruction of the public. CONTRACTOR shall not have under construction more work than CONTRACTOR can reasonably and effectively prosecute at any one time, in the judgement of the ENGINEER.
B. CONTRACTOR shall minimize the adverse effects of CONTRACTOR’s work on abutting property owners. Unless otherwise noted or approved by the ENGINEER in each instance, the CONTRACTOR shall maintain intersections, roadways and driveways open to traffic.
C. Where the CONTRACTOR is permitted to close a roadway and detour traffic, the CONTRACTOR shall always maintain access to homes and businesses within the work zone. The CONTRACTOR shall always maintain, access through the work zone to all school, police, fire and emergency vehicles.
MAINTENANCE OF TRAFFIC
A. Unless otherwise noted, all public vehicle and pedestrian traffic shall be allowed to pass through or around the CONTRACTOR's work sites with a minimum of delay. The CONTRACTOR, in performing work under this Contract, shall conform to the requirements of PennDOT Publications 213 and shall adapt the traffic control details shown on the Drawings and the typical drawings shown in Publications 213 to the specific requirements of the work sites, subject to the approval of the ENGINEER.
B. CONTRACTOR shall furnish, install and maintain such flaggers, barricades, traffic cones, non- metallic channelizing drums, lights, signs, flashers, signals, fences and other devices for the control of vehicle and pedestrian traffic in the work site as are necessary to insure the safety of and facilitate the convenience of the public, to restrict the movement of traffic within the approved limits, and to clearly indicate in advance the restrictions whether or not said signs and devices are specifically described on the Drawings or the Specifications.
C. CONTRACTOR shall not store materials or equipment in locations that will interfere with the safe movement of either vehicle or pedestrian traffic. At the end of each working day and at the other times when the work is suspended for any reason, the CONTRACTOR shall remove from all roadways and pedestrian ways open to traffic all debris, equipment, materials and other obstructions unless otherwise permitted by the ENGINEER.
D. When assigned to flagging traffic, the sole responsibility of flaggers shall be to direct public traffic through and around the work. Such flaggers shall have no other duties.
E. CONTRACTOR will be required to notify the OWNER, ENGINEER, PennDOT, and the Township Police Department ten (10) days prior to the date CONTRACTOR desires to restrict traffic in the streets and shall provide one (1) working day notice prior to the completion of the work.
F. During working hours, CONTRACTOR shall maintain a minimum of ten (10) feet of the existing paving width to provide maintenance of traffic in two directions at all locations.
G. Access must be maintained at all times to all properties, driveways and entrances, by the construction and maintenance of bridges across the trenches so that interference with the normal use of properties will be minimized.
H. CONTRACTOR shall make provisions for safe and expeditious movement of pedestrians in the construction area, with particular attention to intersections, mailboxes, and bus stops.
I. All signs and devices used to fulfill the requirements of this section shall be kept clean and maintained in first class operating condition and shall be moved and relocated as required to conform with construction operations and to keep traffic flowing with minimum restrictions. The CONTRACTOR shall run temporary overhead wires for traffic signals as required. Underground wire and conduit, signal detector loops and traffic signal interconnect wires, where damaged or removed, shall be restored to pre-existing conditions. All signal relocations and temporary wiring shall meet the approval of the ENGINEER, the Township, PennDOT and the utility company.
J. Temporary impact attenuating devices shall be selected, designed and installed by the CONTRACTOR as required by the Drawings and according to PennDOT Publication 408, PennDOT Publication 72 (Drawing RC-57), and the manufacturer's specifications. Provide 18 inches x 36 inches clearance markers to delineate impact attenuating devices. White, reflectorized, barrier mount delineators shall delineate temporary concrete median barriers. Submit a shop drawing (minimum scale: 1 inch = 20 feet) of the impact attenuating device at each location in accordance with Section 01 3300. Shop drawings must be sealed by a Professional Engineer licensed in Pennsylvania and contain a statement certifying that the impact attenuating device is specifically applicable to each location.
K. In order to maintain traffic within approved limits, trenches shall be safely decked by the use and maintenance of steel plates or other decking, which shall have sufficient strength to safely support all street traffic including all types of truck loads.
L. Particular attention is called to the fact that when steel plates are used for decking over trenches, the CONTRACTOR, for the purpose of identification and in order to assist the Police Department when an emergency occurs, shall have the CONTRACTOR's name and telephone number with area code painted on both sides of every plate used. The lettering shall be 4 inches in height. The lettering and letter spacing shall conform to Highway Alphabet Series D as defined in publication "Standard Alphabets for Highway Signs," published by the Federal Highway Administration. The CONTRACTOR's name shall be placed in the center of the plate. The paint to be used shall be white and of good quality and durability relative to painting on steel. Should the lettering on the plates become obliterated during the Contract period, the CONTRACTOR will be required to repaint the letters. The lettering shall always be clean and legible. In lieu of painting, embossed lettering of the same design may be used
M. When construction work, including repaving, has been completed, all temporary safeguards shall be removed, clean-up shall be completed, and the travelways restored to their original conditions.
N. CONTRACTOR shall be responsible for the installation of any and all temporary pavement markings required for proper channelization of traffic during construction, and for the removal of these pavement markings when they are no longer applicable. The CONTRACTOR shall also be responsible for the restoration of the original pavement markings, in kind, within ten (10) days after placement of permanent paving.
O. CONTRACTOR shall coordinate activities, including traffic control activities with all other contractors operating in the area, whether under contract with the OWNER, the Township, PennDOT, or others.
P. CONTRACTOR shall designate an individual, or individuals, as CONTRACTOR’s Maintenance or Traffic Coordinator who is responsible for maintaining the traffic control devices. The name, address and phone number where he may be reached at all times shall be supplied to the ENGINEER and the Township Police Department.
PART 2 – PRODUCTS (Not Used)
SECTION 01 6000
PRODUCT REQUIREMENTS
PART 1 – GENERAL
1.01 SUMMARY
A. Section Includes:
Description of Requirements
Submittals
Quality Assurance
Delivery, Storage and Handling
Project Conditions
Installation and Assistance
Related Sections:
1.02 DEFINITIONS
A. Products: Means new material, machinery, components, equipment, fixtures, and systems forming the Work. Does not include machinery and equipment used for preparation, fabrication, conveying and erection of the Work. Products may also include existing materials or components required for reuse.
B. Installation: Means all supervision, labor, materials, tools, equipment, and services as required for installation and test operation of equipment.
1.03 DESCRIPTION OF REQUIREMENTS
A. CONTRACTOR is responsible for changes in design when necessitated by an equipment manufacturer’s requirements where it differs from the Drawings and Specifications.
B. Conform to ANSI, ASME, IEEE, NEMA, AGMA, and other accepted applicable standards.
Provide equipment of high quality construction design to withstand all stresses which may occur during fabrication, testing, transportation, installation, and all operating conditions.
C. Where a manufacturer’s name is given in the Specifications, it is the responsibility of CONTRACTOR to meet the specific mechanical and performance requirements given for the particular unit of Work as described in the respective technical section.
D. Provide interchangeable components of the same manufacturer, for similar components.
E. Do not use materials and equipment removed from existing premises, except as specifically permitted by the Contract Documents.
F. Product Options:
1. Reference Standard Specification:
Products Specified by Reference Standards or by Description Only: Any product meeting those standards or description.
2. Open Proprietary Specification:
Products Specified by Naming One or More Manufacturers: Products of manufacturers names and meeting specifications. Substitutions may be requested in accordance with paragraph 1.03(G) and 1.04(E) below and Document 00700 – General Conditions, EJCDC 1910-8, 1996 Edition, Article 6.05.
3. Closed Proprietary Specification:
Products Specified by Naming One or More Manufacturers followed by words indicating that no substitution is permitted: Products of manufacturers named and meeting specifications, no substitutions allowed.
G. Substitutions: Substitution requests will only be considered under one or more of the following conditions:
1. The substitution will result in significant cost savings or, in the opinion of ENGINEER, other important benefits to OWNER.
2. The specified product is unavailable through no fault of CONTRACTOR.
3. The substitution is essential in order to comply with final interpretations of code or insurance requirements.
4. Subsequent information discloses the inability of specified products to perform property or to fit in the designated space.
5. ENGINEER will consider requests for Substitutions only within 15 days after date established in Notice to Proceed.
6. Substitutions at time periods other than the above may be considered when a product becomes unavailable through no fault of CONTRACTOR.
7. Document each request with complete data substantiating compliance of proposed Substitution with Contract Documents and set forth in Paragraph…
This is the start of the file's text. The full file is on GovTribe.