This is a Statement of Work for a construction project under the Indian Health Service's Portland Area jurisdiction. The project involves the installation of a replacement individual septic system for a private home owned by a Cowlitz Tribe member located at 2423 S. Silver Lake Rd, Castle Rock, WA 98611 (Cowlitz County). The system will include a 1,050-gallon two-compartment concrete septic tank with effluent filter, 4" solid sewer pipe, one underground two-way cleanout, a distribution box with speed levelers, 4" PVC feeder lines, and 180 linear feet of gravity chamber drainfield laterals. The contractor must pump, decommission, and abandon the existing septic tank in compliance with applicable federal, state, and local regulations. Upon completion, all facilities will be transferred to and operated by the homeowner.
The contractor is responsible for mobilization and demobilization, utility location verification, and site protection. Key execution requirements include completing pre-construction and post-construction submittals (manufacturer product information and swing-tie measurements), obtaining approval from the Contracting Officer's Representative before deviating from design specifications, attending a mandatory pre-construction meeting, and ensuring a minimum of five days of continuous dry weather before commencing work. The contractor must provide 24-hour notice to the Designer and COR prior to final backfill and obtain Health Department approval before final backfill installation. Work must comply with Washington Administrative Code, Cowlitz County Public Health Standards, and the attached design specifications. The period of performance is 45 days from the issuance of notice to proceed. Project contact is Jennifer Toth at (360) 536-6351 or jennifer.toth@ihs.gov.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
PL 86-121 CONSTRUCTION PROJECT
INDIAN HEALTH SERVICE
PORTLAND AREA
| Statement of Work, Project PO-21-C87L | Page 3 of 3 |
| Solicitation No: | TBD |
| Project Name: | J. Jenkins On-Site Septic System Replacement |
| Project Location: | 2423 S. Silver Lake Rd |
| Castle Rock, WA 98611 |
Cowlitz County
Project No: PO-21-C87L
A. Project Description
This project is for the installation of a replacement individual septic system for an existing home on fee land in Cowlitz County.
The individual on-site septic system shall include 4” solid sewer pipe; one underground two-way cleanout; one 1,050-gallon two-compartment concrete septic tank with effluent filter, a distribution box with speed levelers, and 4” PVC feeder lines connected to gravity trench chamber drainfield laterals. The existing septic tank shall be pumped, decommissioned, and abandoned in accordance with all applicable federal, state, and local regulations.
B. Ownership
This project will provide sanitation facilities for a private home owned by a member of the Cowlitz Tribe. Upon completion, the facilities will be transferred to the homeowner. The system will be operated by the homeowner.
C. TERO & Other Fees
TERO fees do not apply.
D. Scope of Work
D.1 Summary: Work is to be completed at a private home, under the jurisdiction of Cowlitz County. The Contractor must review site conditions, and report any concerns or discrepancies to the Contracting Officer’s Representative (COR) in writing prior to beginning construction. In accordance with the Design, the Contractor must complete the following:
D.2 Work Requirements include:
D.2.1. Mobilize and demobilize D.2.2. Install solid sewer pipe D.2.3. Install one underground two-way cleanout D.2.4. Install one 1,050 gallon, two-compartment septic tank D.2.5. Install PVC Transport Pipe from Septic Tank to Distribution Box
D.2.6. Install distribution box with speed levelers D.2.7. Install feeder lines to laterals D.2.8. Install 180 LF of gravity chamber drainfield per design D.2.9. Abandon existing septic tank
E. Technical Requirements
E.1 Codes, References, and Standards Work under this contract shall be performed in compliance with the codes, references, and standards listed below. If conflicts exist between these references, consult the COR for direction.
i. Washington Administrative Code
ii. Cowlitz County Public Health Standards
iii. Attached Septic Design
iv. Attached Technical Provisions
E.2 Submittals The Contractor must provide electronic copies of the below listed items to the COR in the manner specified.
i. Pre-Construction Manufacturer’s product information for system components, including septic tank and distribution box with speed levelers.
Any equipment or material variations from those specified in the Design.
ii. Post–Construction (submit with payment invoice)
a) Swing-tie measurements for the tank riser lid centers and drainfield distal ends in accordance with Washington Administrative Code (WAC 246-272A-0265 - Record drawings).
b) Equipment or material variations from those specified in the Bid Schedule.
E.3 Material Specifications
i. The Contractor must install materials as specified on the Design.
ii. Materials specified may be substituted with equals with written approval from the COR in accordance with submittal procedure E.2 i.b) above.
E.4 Work Execution Requirements
i. The Contractor is responsible for determining the exact location of all utilities before construction. The Contractor is responsible for protecting utilities from damage during construction.
ii. The Contractor must attend a pre-construction meeting before beginning work under this contract, unless otherwise explicitly authorized by the Contracting Officer.
iii. A minimum of five days of continuous dry weather conditions is required prior to commencing work, unless explicitly waived by the COR.
iv. All debris generated during construction must be removed from site.
v. All areas disturbed by construction activities must be finish-graded.
vi. The Contractor must not damage or disturb soils when clearing drainfield.
vii. The Contractor must notify and obtain approval from the COR before deviating from the Design.
viii. The Contractor must obtain approval from the Contracting Officer via the COR prior to installing material quantities in excess of those specified on the Bid Schedule.
ix. The Contractor must notify and advise the COR on all work to be done or in progress sufficiently in advance so that proper inspection can be performed.
x. The Contractor must provide the Designer and COR 24-hours’ notice for inspection prior to final backfill.
xi. The Contractor must obtain approval for final backfill from the Health Department via the Designer or COR.
Project Manager and Recommended COR:
Jennifer Toth
(360) 536-6351 jennifer.toth@ihs.gov
Project Completion Time:
The period of performance (POP) is 45 days from issuance of notice to proceed (NTP).