1__SOW.docx
DOCX document 19 KB Posted
- Attached to
- NHTIC PARKING LOT REPAIR 2023
- Solicitation number
- 140L6226Q0004
About this file
This is a Statement of Work (SOW) for parking lot repairs at the National Historic Trails Interpretive Center (NHTIC) in Casper, Wyoming. The contractor must furnish all labor, materials, equipment, tools, supervision, and incidentals necessary to crack seal, install 12-inch-wide pavement reinforcing fabric, seal coat, and re-stripe the existing asphalt parking lot and associated access road. The work is designed to preserve existing pavement, improve safety and accessibility, and maintain a safe parking area for approximately 30,000-40,000 annual visitors to the facility located at 1501 N. Poplar Street, Casper, WY 82601.
All on-site construction work must occur between April 1 and September 29 during favorable weather conditions (dry, above freezing temperatures, and in accordance with manufacturer requirements), with on-site work limited to 31 calendar days from initial mobilization. The facility operates Tuesday through Saturday, 9:30 a.m. to 5:00 p.m., and no work shall occur on Saturdays when the parking lot must remain fully open to the public. The contractor is required to develop and implement comprehensive plans including first aid and safety plans, work schedules, staging and sequencing, quality control, pesticide plan, Spill Prevention Control and Countermeasure Plan (SPCC), and a traffic control plan compliant with MUTCD and local requirements while maintaining safe access for the public, staff, and ADA users. The Government reserves the right to require full facility and parking lot opening on Fridays and Saturdays for special events, which the contractor must accommodate without additional cost.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attch_8_UPDATED_Full_Spec_0001.docx | DOCX document | |
| Attch_9_Q_A_Amd_1_(2)_0001.docx | DOCX document | |
| Sol_140L6226Q0004_Amd_0001.pdf | ||
| 5__MAP.pdf | ||
| 7__INSTRUCTIONS_1442.pdf | ||
| 3__FULL_SPEC.pdf | ||
| Sol_140L6226Q0004.pdf | ||
| 2__BID_SCHEDULE.xlsx | XLSX spreadsheet | |
| 4__MAP-PARKING.pdf | ||
| 6__Wage_Determination.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NHTIC Parking Lot Repairs 2026 Statement of Work (Section C)
1. Project Overview and Scope of Work
The Contractor shall furnish all labor, materials, equipment, tools, supervision, and incidentals necessary to crack seal, install pavement reinforcing fabric (12” wide), seal coat, and re-stripe the existing asphalt parking lot and associated access road complete in place at the National Historic Trails Interpretive Center (NHTIC), Casper, Wyoming. The work preserves the existing pavement, improves safety and accessibility, and maintains a safe parking area for approximately 30,000–40,000 annual visitors to the Center.
The facility address is 1501 N. Poplar Street, Casper, WY 82601; work limits and layout are shown on the project drawings and exhibits identified in this solicitation.
The Contractor shall perform, at a minimum, all work items in accordance with the plans, specifications, exhibits, and drawings. Specific attention:
2. Plans, Safety and Protection
Develop and implement all plans and work associated with the administration and implementation of this contract including but not limited to first aid and safety plans, work plans, schedules, staging and sequencing, quality control, pesticide plan, Spill Prevention Control and Countermeasure Plan (SPCC), and a traffic control plan that complies with the MUTCD and local requirements, maintaining safe access to the facility for the public, staff, and ADA users at all times.
3. Period of Performance, Schedule, and Access
All on-site construction work shall occur between April 1, and September 29, within favorable weather conditions (dry, above freezing temperatures and in accordance with product manufacturer requirements).
Contractor shall complete all contract work as specified in the contract and on-site work is limited to 31 calendar days from initial mobilization.
The facility is open to the public Tuesday through Saturday, 9:30 a.m. to 5:00 p.m.; no work shall occur on Saturday, and the parking lot shall be fully open on Saturdays.
The Government reserves the right to require the facility and parking lot to be fully open on Fridays and Saturdays for special events; the Contractor shall accommodate these events without additional cost to the Government.
PLEASE SEE ATTACHMENT 3 (FULL SPEC) FOR FURTHER DETAILS.
File details come from the government source that posted it. Updated .