This is a Request for Qualifications (RFQ) issued by Kaysville City Corporation for design and engineering services to support aesthetic and roadside improvements along State Route 177 (SR-177) within the West Davis Corridor segment in Kaysville City, Utah. The City seeks qualified professional engineering and landscape architecture firms to provide design, engineering, permitting, and construction administration services for landscape features, lighting, walls, and aesthetic improvements within state right-of-way. Key services include project management and coordination, site assessment and data collection, concept development, engineering and technical design, permitting and agency coordination with the Utah Department of Transportation (UDOT), preparation of construction documents, and bidding and construction administration support. The project extends along SR-177 between 200 North and Weaver Lane (north limit) and 950 North (south limit). All improvements must comply with UDOT standards and encroachment permit requirements. The RFQ was issued on March 4, 2026, with questions due by March 26, 2026 at 5:00 PM and Statements of Qualifications due by March 31, 2026 at 5:00 PM. Interviews may be conducted at the City's discretion, with advancement limited to the three to five highest-scoring firms. No site visits or bidder conferences are specified in the solicitation.
The total estimated project budget, including construction, is $630,000, with the City making no guarantee as to final construction value. Selection will be based solely on qualifications using a Qualifications-Based Selection (QBS) process, with fee proposals to be negotiated with the highest-ranked firm in accordance with Utah procurement law. Evaluation criteria include Relevant UDOT Corridor Experience (30% weight), Project Team Qualifications (25%), Project Approach & Understanding (25%), Quality Control & Risk Management (10%), and References (10%). Firms must achieve a minimum score of 70% to be considered responsive. The selected consultant must maintain Professional Liability insurance of $1,000,000 per claim for a minimum of three years following substantial completion and procure Commercial General Liability of $1,000,000 per occurrence/$2,000,000 aggregate, Automobile Liability of $1,000,000 combined single limit, Workers' Compensation at statutory limits, and Employer's Liability of $500,000 minimum. Kaysville City will be named as an Additional Insured on applicable policies. Submissions must be in PDF format and directed to Cole R. Stephens at cstephens@kaysville.gov.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR QUALIFICATIONS (RFQ)
Design & Engineering Services
SR-177 Right-of-Way Improvements
(West Davis Corridor Segment – Kaysville City)
Issuing Agency: Kaysville City Corporation RFQ No.: PR-03-04-2026 Issue Date: March 4, 2026 SOQ Due Date: March 31, 2026
1. INTRODUCTION
Kaysville City (“City”) is soliciting Statements of Qualifications (SOQs) from qualified professional engineering and landscape architecture firms to provide design, engineering, permitting, and construction administration services for aesthetic and roadside improvements within state right-of-way along SR-177.
The project limits extend along SR-177 between 200 North and Weaver Lane (north project limit) and 950 North (south project limit) within Kaysville City.
The Utah Department of Transportation (UDOT) will allow City access within state right-of-way solely for the purpose of designing, constructing, and maintaining roadside landscape, lighting, walls, and aesthetic features (“Improvements”). All work must comply with UDOT standards, encroachment permit requirements, and applicable state and federal regulations.
This procurement will follow a Qualifications-Based Selection (QBS) process. Compensation will be negotiated with the highest-ranked firm in accordance with Utah procurement law.
2. PROJECT BACKGROUND
As part of corridor development and community enhancement efforts, the City intends to implement context-sensitive improvements within the SR-177 right-of-way to:
• Enhance visual character and community identity
• Improve corridor aesthetics
• Install and maintain landscape features
• Ensure long-term durability and maintainability
All Improvements are subject to UDOT review, approval, and permitting requirements.
Demonstrated experience working within state highway right-of-way and coordinating directly with UDOT is required.
3. PROJECT OBJECTIVES
The City seeks a consultant team capable of:
1. Designing improvements fully compliant with UDOT standards and encroachment requirements.
2. Delivering durable, low-maintenance landscape and aesthetic features.
3. Ensuring safe integration with highway operations.
4. Preparing complete, construction-ready documents suitable for public bidding.
5. Supporting the City during construction and project closeout.
4. ANTICIPATED SCOPE OF SERVICES
The selected consultant shall provide professional services including, but not limited to:
4.1 Project Management & Coordination
• Project kickoff meeting
• Coordination with City staff and UDOT
• Schedule development and tracking
• Progress reporting
4.2 Site Assessment & Data Collection
• Field reconnaissance
• Survey coordination (as required)
• Utility coordination and mapping
• Identification of right-of-way constraints
4.3 Concept Development
• Landscape themes and planting concepts
• Irrigation concepts (if applicable)
• Decorative lighting concepts (as permitted)
• Entry monument or gateway features
• Preliminary cost estimates
4.4 Engineering & Technical Design
• Final landscape and irrigation design
• Structural design of decorative walls or screening features
• Traffic control considerations (if applicable)
• Compliance with AASHTO and UDOT standards
• Construction cost estimates at design milestones
4.5 Permitting & Agency Coordination
• Preparation of UDOT encroachment permit documentation
• Required technical submittals
• Coordination meetings with UDOT reviewers
• Response to review comments
4.6 Construction Documents
• Plans, specifications, and bid schedule
• Technical specifications consistent with City and UDOT standards
• Final engineer’s estimate
4.7 Bidding & Construction Administration
• Bid support
• Submittal review
• Site visits and observation
• Pay application review
• Project closeout documentation
5. STATEMENT OF QUALIFICATIONS
REQUIREMENTS
SOQs shall include the following in the order listed:
5.1 Cover Letter
Signed by an authorized representative.
5.2 Firm Qualifications
• Legal name and contact information
• Utah professional licensure (PE, PLA, etc.)
• Years in business
• Office location(s)
5.3 Project Team
• Identification of Project Manager
• Key personnel and defined roles
• Subconsultants and responsibilities
• Resumes (maximum two pages per individual)
5.4 Relevant Experience
Provide at least three (3) similar projects within the past ten (10) years, preferably including:
• Projects within UDOT right-of-way
• State highway corridor landscape improvements
• UDOT encroachment permit coordination
Include project description, construction cost, completion date, and client reference.
5.5 Project Approach
• Understanding of UDOT right-of-way constraints
• Regulatory compliance strategy
• Risk identification and mitigation
• Quality control procedures
• Preliminary schedule
5.6 References
Minimum of three (3) references.
5.7 Conflict of Interest Statement
Disclose any actual or potential conflicts of interest, or affirm none exist.
6. EVALUATION CRITERIA
An Evaluation Committee will review all timely received SOQs using the criteria below.
Interviews may be conducted at the City’s discretion.
Firms must achieve a minimum score of seventy percent (70%) to be considered responsive.
Advancement to interviews will be limited to the three (3) to five (5) highest-scoring firms. The City reserves the right to advance fewer firms if deemed appropriate.
Criteria Weight Relevant UDOT Corridor Experience 30% Project Team Qualifications 25% Project Approach & Understanding 25% Quality Control & Risk Management 10% References 10%
Selection will be based solely on qualifications. Fee proposals will not be requested at this stage.
7. PROCUREMENT SCHEDULE
Milestone Date RFQ Issued March 4, 2026 Questions Due March 26, 2026 by 5:00 P.M.
SOQs Due March 31, 2026 by 5:00 P.M.
Interviews (if conducted) TBD Questions submitted to cstephens@kaysville.gov
8. SUBMITTAL INSTRUCTIONS
Electronic SOQs must be submitted in PDF format to:
Cole R. Stephens Kaysville City Corporation cstephens@kaysville.gov
Submittals must be received no later than March 31, 2026 at 5:00 PM. Late submissions will not be accepted.
9. GENERAL CONDITIONS
• The City reserves the right to reject any or all SOQs.
• The City may cancel, suspend, or modify this solicitation at any time.
• The City may request clarification of submitted materials.
• All costs associated with preparing the SOQ are the responsibility of the submitting firm.
• The selected consultant must enter into a Professional Services Agreement with Kaysville
City.
• All work within SR-177 right-of-way is subject to UDOT approval and permitting requirements.
10. PROJECT BUDGET
The total estimated project budget, including construction, is $630,000. The City makes no guarantee as to the final construction value.
11. TERMS AND CONDITIONS
Proposals shall remain valid for sixty (60) days from the submittal deadline.
mailto:cstephens@kaysville.gov mailto:cstephens@kaysville.gov
Services shall be performed in accordance with the professional standard of care ordinarily exercised by design professionals practicing in the State of Utah.
Nothing in this RFQ or any resulting agreement shall be construed as a waiver of Kaysville City’s governmental immunity under the Utah Governmental Immunity Act.
The selected firm will be required to execute the City’s standard Professional Services Agreement, which includes additional terms and conditions.
12. INSURANCE REQUIREMENTS
The selected firm shall procure and maintain insurance meeting or exceeding ULGT-aligned municipal standards, including:
• Commercial General Liability: $1,000,000 per occurrence / $2,000,000 aggregate
• Automobile Liability: $1,000,000 combined single limit
• Workers’ Compensation: Statutory limits
• Employer’s Liability: $500,000 minimum
• Professional Liability (Errors & Omissions): $1,000,000 per claim
Professional Liability coverage shall be maintained for a minimum of three (3) years following substantial completion.
Certificates of insurance shall be provided prior to contract execution. Kaysville City shall be named as an Additional Insured on applicable policies.
EXHIBIT A – SUBMITTAL INFORMATION
Taxpayer ID #: __________________________
Representative Name: __________________________
Title: __________________
Firm Name: _______________________________________________
Address: _________________________________________________
City: __________________ State: ______ Zip: _______________
Phone: __________________
Email: _________________________________________________
I have read and understand the requirements of RFQ PR-03-04-2026 and agree to comply except as noted.
Submitted by: ____________________________
Date: __________
Signature: _______________________________
| REQUEST FOR QUALIFICATIONS (RFQ) |
| Design & Engineering Services |
| SR-177 Right-of-Way Improvements |
| (West Davis Corridor Segment – Kaysville City) |
| 1. INTRODUCTION |
| 2. PROJECT BACKGROUND |
| 3. PROJECT OBJECTIVES |
| 4. ANTICIPATED SCOPE OF SERVICES |
| 4.1 Project Management & Coordination |
| 4.2 Site Assessment & Data Collection |
| 4.3 Concept Development |
| 4.4 Engineering & Technical Design |
| 4.5 Permitting & Agency Coordination |
| 4.6 Construction Documents |
| 4.7 Bidding & Construction Administration |
| 5. STATEMENT OF QUALIFICATIONS REQUIREMENTS |
| 5.1 Cover Letter |
| 5.2 Firm Qualifications |
| 5.3 Project Team |
| 5.4 Relevant Experience |
| 5.5 Project Approach |
| 5.6 References |
| 5.7 Conflict of Interest Statement |
| 6. EVALUATION CRITERIA |
| 7. PROCUREMENT SCHEDULE |
| 8. SUBMITTAL INSTRUCTIONS |
| 9. GENERAL CONDITIONS |
| 10. PROJECT BUDGET |
| 11. TERMS AND CONDITIONS |
| 12. INSURANCE REQUIREMENTS |
| EXHIBIT A – SUBMITTAL INFORMATION |
File details come from the government source that posted it. Updated .