This document is a Statement of Work for a construction contract to drill a new water well and connect it to the existing water distribution system at the San Marcos Fire Station in Santa Barbara County, California. The scope of work includes locating and drilling a new water well to a minimum depth of 800 feet, constructing a well enclosure, connecting the new well to the existing distribution system, disinfecting the entire water system and collecting water samples for testing. The contractor must begin work within 10 days of the Notice to Proceed dated August 28, 2023. Work hours are limited to weekdays from 8:00 am to 6:00 pm, excluding holidays. This contract is solicited under solicitation number 127EAW23R0042 by the US Department of Agriculture Forest Service.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFI Official Responses - 1.pdf | ||
| A00001 - RFIs Round 1.pdf | ||
| 3. Contract Drawings.pdf | ||
| 127EAW23R0042 - San Marcos Well Drilling.pdf | ||
| 2. Schedule.docx | DOCX document | |
| 5. Davis-Bacon Act WD # CA20230001.pdf | ||
| 4. Specifications.pdf | ||
| 7. RFI Form.docx | DOCX document | |
| 6. Fire Plan.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Section C – Construction
SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
Scope of Contract
This contract is for the locating, drilling, and development of one new water well to support the continuous operation of San Marcos Fire Station. Currently, the existing well casing for the station has deteriorate and is beyond repair.
Contract work is also to include the construction of water well enclosure, to ensure the well is protected from environmental factors. The contractor is also to connect the new water well to the existing distribution system. Once completed, the contractor will need to disinfect the entire system and collect the necessary water samples to submit to the County of Santa Barbara.
Nearby wells around the compound have had success finding water at 200 feet. Contract work pay items will be for Actual Quantities (AQ). A minimum of 800 feet of drilling will be required for this contract in order to promote a well that is not under the influence of surface water.
All work will be completed in accordance with Project Specifications and Drawings. The work includes: all labor, material, and equipment necessary to perform all the operations for the work specified.
Project Location
This project is located within the Los Padres National Forest in Santa Barbara County, California. San
Marcos Fire Station is located along California State Route 154, mile marker 24.447, on the right-hand side of the road if heading northbound. A map of the site can be viewed in the Contract Drawings.
GPS Coordinates: 34°30'42.3"N 119°49'23.7"W
NOTE: Any prospective bidder desiring an explanation or interpretation of the solicitation, drawings, specifications, etc., must request it in writing soon enough to allow a reply to reach all prospective bidders before submission of their bids. Oral explanations or instructions given before the award of a contract will not be binding. In no event shall failure to inspect the site constitute grounds for a claim after contract award. (See Section L, 52.236-27, SITE VISIT.)
Estimated Start Date
August 28th, 2023
Contractor must begin work within 10 days of the effective date of the Notice to Proceed. See Section
F for additional information.
Restrictions on Work
1. Work hours are limited to non-holiday week days, Monday – Friday, 0800 – 1800
2. In accordance with the fire plan, if included in Section J.
3. When the Contracting Officer (or designated representative) determines that adverse weather has made access too dangerous or that continued vehicular travel would cause unacceptable road damage.
Worker's Compensation Insurance
The Contractor shall provide evidence of Worker's Compensation Insurance or a written explanation as to why the Contractor is exempt from the requirement. NOTE: The Contractor working alone is not required to carry the insurance.
Camping and Housing (see also Section H, Camping Permit Compliance)
Camping is not permitted in US Forest Service campgrounds. Contractor [ ] will [X] will not be permitted to camp elsewhere on US Forest Service land. Camping on Forest Service land is not a right; permission may be revoked for failure to comply with the terms of the permit.
Maps
INCLUDED WITH DRAWINGS
Drawings and Specifications
Project Drawings: The following drawings are part of this solicitation:
1. San Marcos Water Well Construction Plans
Specifications:
[X] Construction Standard Institute (CSI) specifications
These specifications are physically incorporated in the solicitation.
[ ] Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects
FP-04 (US Customary Units)
This document is incorporated by reference and is available on the web in either MS Word or Acrobat (https://flh.fhwa.dot.gov/resources/specs/)
It is also available as a wire-bound book that can be purchased from the US Government Printing
Office:
Superintendent of Documents
U.S. Government Printing Office
Internet: bookstore.gpo.gov
Phone: (toll free) 866.512.1800
Fax: 202.512.2250
Mail: Stop SSOP, Washington, DC 20402-0001
Stock Number: 050-001-00341-4 (U.S. Customary)
Special Project Specifications are physically incorporated within this solicitation, beginning on the next page.
The following Standard and Special Project Specifications are applicable to this contract:
# Description Date
1 San Marcos Water Well Construction Specifications 4/1/2021
The requirements contained in these specifications are hereby made a part of this solicitation and any resultant contract.
https://flh.fhwa.dot.gov/resources/specs/ http://bookstore.gpo.gov/
Material Certifications, Testing Reports, & Other Submittals.
Submit the following items to the Contracting Officer for approval.
Title
Referenced by Contract clause or Specification No.
Time of
Government
Approval
After
Submittal Project Schedule Specifications 01 30 00 10 days
Quality Control and Quantity
Measurement: Designation of the
On-The-Job Superintendent
Designation of On-Site Quality
Control Manager
Quality Control Plan
As-Built Drawings
Certificates-of-Compliance
Test Results Bill-of-Ladings
Specifications 01 41 00 10 days
Demolition Schedule Specifications 02 41 19 10 days
Water Supply Well: Contractors
California C57 license
Subcontractor information
Product Data
Shop Drawings
Project Record Documents
Field Quality-Control Report Operation and Maintenance Manual
Specifications 02 52 50 10 days
Valves and Enclosures: Technical data for valves
Technical Data for boxes
Product literature valves
Product literature boxes
Specifications 02 64 00 10 days
Water Distribution System: Product
Data Shop Drawings
Specifications 02 66 00 10 days
Disinfection of Water Distribution
System: Disinfection Agent
Residual test results
Specifications 0267 50 10 days
Concrete Formwork: CO Inspection of Form
Specifications 03 10 00
Concrete Reinforcement: Horizontal and Vertical Reinforcement Plan
Specifications 03 20 10 FIO
Cast-in-Place Concrete: Mix Design, Admixtures, Deliver Tickets
Specifications 03 30 10 FIO
Rough Carpentry: Wood Treatment
Data, Product Data, Maintenance
Instructions, Warranties, Samples
Specifications 06 10 00 FIO
Caulking and Sealants: Product
Data, Maintenance Instructions, Specifications 07 90 00 FIO
Warranties, Samples
Finishes: Product Data, Samples Specifications 09 90 00 FIO
Pressurized Water Storage tanks:
Shop Drawings
Manufacturer’s literature
Manufacturer’s installation instruction Pressure Switch
Specifications 13 57 00 10 days
Low Voltage Electrical Power
Conductors and Cables: Product data, shop drawings
Specifications 26 05 19 10 days
Grounding and Bonding for
Electrical Systems: Product data, shop drawings
Specifications 26 05 26 10 days
Raceways: Product data, shop drawings
Specifications 26 05 33 10 days
Boxes: Product data, shop drawings Specifications 26 05 34 10 days
Identification for Electrical Systems:
Product data, shop drawings
Specifications 26 05 53 10 days
Visual Equipment Inspection
Reports
Specifications 31 31 19 FIO
Trenching and Backfilling:
Certification of place of purchase
Product Data Weigh tickets
Specifications 31 50 00 10 days
Base Courses: Certification of place of purchase
Product Data
Weigh tickets
Specifications 32 11 00 10 days
FIO= “For information only