This is a Performance Work Statement for the design, fabrication, and installation of two fall arrest systems for the Vehicle Maintenance Building 3 at Quonset Air National Guard Base in North Kingstown, Rhode Island. The contract number is W50S9426QSY19.

The project requires two independent fall protection rail systems: a Fuel Bay system approximately 42 feet in length and a Main Bay system approximately 65 feet in length with a break to accommodate a fixed crane system. Each rail must support two concurrent users with trolleys, lanyards, and associated components. The system design must comply with multiple ANSI/ASSP standards (Z359.2, Z359.3, Z359.6, Z359.7, Z359.11, Z359.12, Z359.13, Z359.14, Z359.15, and Z359.18) as well as 29 CFR 1910 occupational safety standards. The design engineer must be a Professional Engineer licensed in Rhode Island and experienced in fall protection system design, and must perform dynamic and dead load analysis, calculate fall clearance requirements, and coordinate with building mechanical and electrical systems. The system must be designed for a maximum arresting force of 900 pounds per worker with a safety factor of two against failure. Deliverables include sealed shop drawings, product data, physical samples (harness, carabiner, lifeline, trolley), engineering analysis, manufacturer certificates, operational test certification, and comprehensive operation and maintenance documentation. The contractor must provide operator and maintenance training (minimum four hours) at the installation site, conduct static proof testing, and provide a one-year extended warranty beyond the manufacturer's standard warranty. All welding must comply with AWS D14.1/D14.1M and AWS D1.1/D1.1M standards, and the manufacturer must demonstrate at least five years of continuous fall protection system production with successful installations free of litigation, injuries, or fatalities.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PERFORMANCE WORK STATEMENT

W50S9426QSY19 – 143LRS FALL PROTECTION SYSTEMS

PART 1 - GENERAL

1.1 REFERENCES

A. The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only. Unless otherwise indicated, the issue of referenced publications is the issue listed in the solicitation and is current as of the date of the solicitation.

1. AMERICAN SOCIETY OF SAFETY PROFESSIONALS (ANSI/ASSP)

a. ANSI/ASSP Z359.11: (2021) Safety Requirements for Full Body Harnesses

b. ANSI/ASSP Z359.12: (2019) Connecting Components for Personal Fall Arrest Systems

c. ANSI/ASSP Z359.13: (2022) Personal Energy Absorbers and Energy Absorbing Lanyards

d. ANSI/ASSP Z359.14: (2021) Safety Requirements for Self-Retracting Devices for Personal Fall Arrest and Rescue Systems

e. ANSI/ASSP Z359.15: (2022) Safety Requirements for Single Anchor Lifelines and Fall Arresters for Personal Fall Arrest Systems

f. ANSI/ASSP Z359.2: (2023) Minimum Requirements for a Comprehensive Managed Fall Protection Program

g. ANSI/ASSP Z359.3: (2019) Safety Requirements for Lanyards and Positioning Lanyards

h. ANSI/ASSP Z359.6: (2016) Specifications and Design Requirements for Active Fall Protection Systems

i. ANSI/ASSP Z359.7: (2011) Qualification and Verification Testing of Fall Protection Products

2. ASTM INTERNATIONAL (ASTM)

a. ASTM A 36/A 36M: (2019) Standard Specification for Carbon Structural Steel

b. ASTM A 992/A 992M: (2020) Standard Specification for Structural Steel Shapes

3. AMERICAN WELDING SOCIETY (AWS)

a. AWS D1.1/D1.1M: (2020) Structural Welding Code - Steel

b. AWS D14.1/D14.1M: (2022) Specification for Welding of Industrial and Mill Cranes and Other Material Handling Equipment

4. U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

a. 29 CFR 1910: Occupational Safety and Health Standards

1.2 SYSTEM DESCRIPTION

A. This project has two fall arrest systems. The systems consist of two (2) or three (3) rails total:

1. Fuel Bay: approximately 42 feet in length

2. Main Bay: approximately 65 feet in length, total, with a break to accommodate the fixed crane system.

Systems will be installed in the Vehicle Maintenance Building 3 (Attachment 3) located at Quonset Air National Guard Base (QANGB), North Kingstown, RI 02852.

Each rail must have 2 trolleys, lanyards, and other components for support of 2 people. Personnel may be located on work stands or on the vehicle.

Refer to additional information and photographs provided in Attachment 1.

B. Engineering Analysis Design Requirements

1. Fall protection systems must be designed by a Professional Engineer experienced in the design of fall protection systems, registered and licensed in the State of Rhode Island.

2. Fall protection systems must be designed for use above vehicles with 2 concurrent users;

users must be able to walk uninterrupted the entire length of each system without having to unhitch from the system to pass through intermediate support points.

3. The overall system and all components must comply with ANSI/ASSP Z359.2, ANSI/ASSP Z359.3, ANSI/ASSP Z359.6, ANSI/ASSP Z359.7, ANSI/ASSP Z359.11, ANSI/ASSP Z359.12, ANSI/ASSP Z359.13, ANSI/ASSP Z359.14, ANSI/ASSP Z359.15, and ANSI/ASSP Z359.18.

4. Dynamic and dead load reactions must be generated for all intermediate and end supports of the fall protection system.

5. Design fall protection systems to safely resist the dynamically applied loads while maintaining a safety factor of two against failure.

6. Design of fall protection systems must be based on the understanding that the underlying structural steel supports are provided as part of the bay and are adequate to support the imposed loads. Fall Protection loads must be furnished to the hangar structural designer.

7. The Design Engineer must prepare a fall clearance analysis verifying adequate fall distance to safely stop the worker in the event of a fall.

8. Rails must be designed for 2 workers falling at a time with full body harnesses and shock-absorbing lifelines, with a maximum arresting force of 900 pounds per worker.

9. The Design Engineer must coordinate the Fall Protection System with the mechanical and electrical systems, lighting, piping, and structural supports of the hangar.

1.3 SUBMITTALS

A. The following Submittals will be required:

1. Shop Drawings

a. Fall Protection System: Sealed and signed by a licensed Professional Engineer (licensed in the State of Rhode Island) responsible for the preparation of the engineering analysis, who thereby certifies preparing or supervising the preparation of data to comply with specified requirements and recognized engineering principles and practices.

2. Product Data

a. Track System

b. Deceleration Devices

c. Harnesses

1. Include capacities, sizes, performances, test certifications, operations, safety features, finishes, and similar manufacturer information.

3. Samples

a. Full Body Harness

b. Self-Closing Carabiner

c. Self-Retracting Lifeline

d. Fall Arrest Trolley

4. Design Data

a. Engineering Analysis: Sealed and signed by a registered Professional Engineer (licensed in the State of Rhode Island) who thereby certifies preparing or supervising the preparation of data to comply with specified requirements and recognized engineering principles and practices.

5. Certificates

a. Fall Protection System:

1. Letter signed by the manufacturer certifying that system components comply with requirements and compliance with contract documents.

2. Compliance with 29 CFR 1910 and with approved drawings and calculations.

6. Manufacturer's Field Reports

a. Attendee List: Submit list of attendees at the training class in the use, care, and maintenance of all protection equipment.

b. Operational Test: Provide a Letter of Certification from the licensed Design Engineer indicating the completion of operational proof testing on installed systems.

7. Operation and Maintenance Data

a. Fall Protection System:

1. Include emergency, operation, and maintenance manuals; a complete parts list;

operation and maintenance procedures for proper use and safe operation of equipment; as-built or record drawings of equipment as tested and approved.

1.4 QUALITY ASSURANCE

A. Provide a list of qualifications to design the system specified, listing experience including similar projects.

B. The manufacturer must have produced fall protection systems similar to those required for this Project full-time for no less than 5 years and must demonstrate successful installations in the last 5 years, free of litigation, injuries, or fatalities resulting from their products or design.

C. The system manufacturer or manufacturer's authorized representative who is trained and approved for installation of units required for this project must perform work full-time for no less than 5 years and demonstrate successful installations in the last 5 years, free of litigation, injuries, or fatalities resulting from their products or design.

D. The Professional Engineer must be registered and licensed as a Professional Engineer in the State of Rhode Island, and be employed by the fall protection manufacturer as a full-time fall arrest systems designer.

E. Welding must be in accordance with all requirements of AWS D14.1/D14.1M. Welders and welding operators must be qualified in accordance with AWS D1.1/D1.1M.

1.5 PROJECT CONDITIONS

A. The Contractor is responsible for the coordination and proper relation of their work to the building structure and to the work of all trades. Verify all dimensions of the building that relate to the fabrication of the crane/fall system and notify the Contracting Officer of any discrepancy before finalizing fabrication or order placements.

1.6 DELIVERY, STORAGE, AND HANDLING

A. Deliver, store, and handle materials, components, and equipment in the manufacturer's original unopened protective packaging. Store materials, components, and equipment off of the ground, under cover, and in a dry location. Handle according to the manufacturer's written recommendations to prevent damage, deterioration, or soiling.

1.7 WARRANTY

A. Provide a manufacturer's warranty to correct any defective work, materials, or components for a period of one year after the date of Substantial Completion, in addition to the manufacturer's standard warranty.

PART 2 - PRODUCTS

2.1 SYSTEM DESIGN

A. Track System

1. Single track fall arrest system and connections to the bay of the structure.

2. Constructed of ASTM A 36/A 36M or ASTM A 992/A 992M steel.

3. Components must be painted safety yellow.

B. Trolleys

1. All-steel body.

2. Compatible with the rail system.

3. 360-degree rotating eye.

C. Deceleration Devices: Provide 1 self-retracting lifeline/lanyard (SRL) for each user for which the system is designed. Meet or exceed applicable standards of ANSI/ASSP Z359.13, ANSI/ASSP Z359.14, and 29 CFR 1910, meeting the following requirements:

1. Maximum Load: 310 pounds.

2. Weight: 20 pounds maximum.

3. Construction: Heavy-duty self-contained, portable, sealed aluminum or stainless steel casing with 3/16 inch minimum stainless steel wire rope, with swiveling safety snap hooks, and a centrifugal braking system.

4. Cable Length: As required to permit personnel to access the SRL safely from the ground level.

5. Fall Arrest Forces: Less than 900 pounds.

D. Provide one harness for each user for which the system is designed. Meet or exceed applicable standards of ANSI/ASSP Z359.11 and 29 CFR 1910. Full body harness, lightweight nylon, Class III, approved for fall arrest with back and front "Dee" rings.

E. Accessories: Meet or exceed standards of ANSI/ASSP Z359.12, ANSI/ASSP Z359.15, and 29 CFR 1910.

2.2 MATERIALS

A. Fasteners must be designed and provided by the fall protection system manufacturer. All equipment must be provided by a single source. All materials must be new and undamaged.

Fasteners must be designed to support a load on the system of two times the maximum design load without failure.

PART 3 - EXECUTION

3.1 INSTALLATION

A. Install according to the approved shop drawings and manufacturer’s instructions. Install anchorage and fasteners in accordance with the manufacturer’s recommendations to obtain the allowable working loads published in the product literature and in accordance with this Section. Do not load or stress the fall arrest system until all materials and fasteners are properly installed and ready for service. Deform threads of all bolted connections after nuts have been installed and torqued to the proper tension, or provide prevailing torque lock nuts.

3.2 FIELD QUALITY CONTROL

A. After erection, the Contractor and the Contracting Office shall jointly inspect the installed system and components to determine compliance with specifications and approved submittals.

Systems must remain out of service until the inspection is complete and a Letter of Certification has been received and signed by the Contracting Officer.

B. After erection and joint inspection, statically test the fall protection system in service to determine that each component of the system operates as specified, is properly installed and adjusted, and is free from defects in material, manufacture, installation, and workmanship. Rectify deficiencies disclosed by testing and retest the system or component to prove that the system is fully operational. Any weights required for static proof testing must be provided by the Contractor.

C. Provide a minimum of 1 class (4 hours minimum) of operator and maintenance training after the system has been installed and proof-tested. Training is to be conducted at the installation site for the users and maintainers of the system. The Contractor must submit the final attendee list.

3.3 CLEANING

Remove all loose materials, crating, and packaging materials from the premises.