1.05 Statement of Work.pdf
PDF 99 KB Posted
- Attached to
- Office Furniture- Supply Federal contract opportunity
- Solicitation number
- N0018924Q0324
About this file
This document is a Statement of Work (SOW) for a federal contract opportunity to provide office furniture and related services to the U.S. Fleet Forces Command, N7. The SOW details the requirements for the procurement, delivery, installation, and disposal of existing furnishings across seven office spaces in two buildings.
The base requirement includes 67 cubicle workstations, 8 private offices, furnishings for 4 existing offices, a conference room, and other related furniture and equipment. The contractor shall coordinate all removal, disposal, procurement, delivery, installation, and electrical work. The base year has a delivery date of December 1, 2024. There is also an Option 1 requirement for an additional 40 cubicle workstations, 6 private offices, furnishings for 2 executive offices, a conference table, and other items, with a delivery date of December 1, 2025. The contract opportunity is being issued by the Department of the Navy, Naval Supply Systems Command.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment I List of Clauses and Provisions REV 3.pdf | ||
| QA_N7_Response REV 3.docx | DOCX document | |
| QA_N7_Response REV 2.docx | DOCX document | |
| Combined Synopsis and Soliciation REV 3.pdf | ||
| QA_N7_Response REV 1.docx | DOCX document | |
| 1.05 Statement of Work Rev 2.pdf | ||
| Attachment IV Sample of Carpet Color.jpg | JPG image | |
| Combined Soliciation and Synopsis REV 2.pdf | ||
| Attachment 1 List of Clauses and Provisions REV 2.pdf | ||
| QA_N7_Response.docx | DOCX document | |
| Attachment I List of Clauses and Provisions REV 1.pdf | ||
| FFC MAP of Vendor Site Visit.pdf | ||
| Combined Soliciation and Synopsis REV 1.pdf | ||
| 1.05 Statement of Work REV 1.pdf | ||
| Attachment 1 List of Clauses and Provisions.pdf | ||
| Combined Synopsis and Solicitation pdf.pdf |
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
U.S. Fleet Forces Command, N7
1.0 Introduction
U.S. Fleet Forces Command, N7, has a requirement to support authorized billets and workforce to ensure mission accomplishment. This requirement includes the procurement, delivery, removal of the existing workstations/furniture/carpet and disposal of all trash, installation of the new workstations, and all required electrical work. The contractor shall provide all necessary personnel, management, material, equipment, and facilities to satisfy the requirement for the seven (7) office spaces in NH4S and NH20.
1.1 Sixty-seven (67) cubicle workstations (similar in size) with standing privacy walls, one (1) L-shaped desk, one
(1) three drawer filing cabinet, one (1) overhead cabinet, one (1) wardrobe, one (1) pencil drawer and one (1) mesh armchair with casters.
1.2 Eight (8) floor to ceiling private offices (that allow light penetration) with furnishings to include one (1) L-shaped desk, one (1) hutch, one (1) three drawer filing cabinet, one (1) wardrobe, one (1) pencil drawer, one (1) executive mesh armchair with casters and two (2) office chairs.
1.3 Office furnishings for two (2) existing hard walled private offices to include one (1) L-shaped desk, one (1) hutch, one (1) three drawer filing cabinet, one (1) wardrobe, one (1) pencil drawer, one (1) executive mesh armchair with casters and two (2) office chairs.
1.4 Office furnishings for two (2) existing executive offices to include one (1) executive desk, one (1) hutch, one
(1) three drawer filing cabinet, one (1) wardrobe, one (1) pencil drawer, one (1) executive leather armchair with casters and two (2) office chairs.
1.5 One (1) six-person executive conference table with ten (10) matching chairs with casters.
1.6 One (1) floor to ceiling enclosed conference room and ten (10) matching chairs with casters for use with existing table.
1.7 Two (2) four-person conference tables with four (4) matching chairs with casters.
1.8 One (1) floor to ceiling enclosed supply closet with locking door.
1.9 Seven (7) centrally located utility spaces for existing safe, printer, copier, shredder, microwave and office supplies.
2.0 Requirement/Deliverables:
The contractor shall remove all existing furnishings/carpet and provide/install twenty-seven (27) cubicle workstations, two (2) floor to ceiling private offices with furnishings, office furnishings for (2) offices, one (1) floor to ceiling enclosed conference room and ten (10) matching chairs with casters to complement existing conference table, two (2) small conference tables with four (4) matching chairs with casters, four (4) centrally located utility spaces and mesh arm chairs with casters for all new cubicle workstations.
2.1 NH-20 Room 100: The contractor shall remove all existing furnishings/carpet to provide/install eight (8) cubicle workstations, one (1) floor-to-ceiling private office with furnishings, one (1) small conference table with four (4) matching chairs with casters and one (1) centrally located utility space.
2.2 NH-20 Room 201: The contractor shall remove all existing furnishings/carpet to provide/install two (2) cubicle workstations and one (1) centrally located utility space.
2.3 NH4S Room 236: The contractor shall remove all existing furnishings/carpet to provide/install twelve (12) cubicle workstations, one (1) floor-to-ceiling private office with furnishings, one (1) floor-to-ceiling private conference room with ten (10) matching chairs with casters that complement existing conference table, and one
(1) centrally located utility space.
2.4 NH4S Room 241: The contractor shall remove all existing furnishings/carpet to provide/install five (5) cubicle workstations, office furnishings for (2) existing hard-walled floor-to-ceiling offices, one (1) small conference table with four (4) chairs and one (1) centrally located utility space.
2.5 The contractor shall:
2.5.1 Coordinate the removal and disposal of existing workstations/office furniture/carpet/trash, procurement, receipt, delivery, installation, required electrical work/connections and scheduling to satisfy the total requirement.
2.5.2 Provide necessary grommets and cable management needed to conceal all data/electrical cords.
2.5.3 Present each workstation in a neat and professional manner.
2.6 Delivery Address
1562 Mitscher Ave, Suite 250 Norfolk, VA. 23551
2.7 Delivery Date
Delivery and installation shall be completed by 1 December 2024.
3.0 Option 1 Requirement/Deliverables:
The contractor shall remove all existing furnishing/carpet and provide/install forty (40) cubicle workstations, six (6) floor to ceiling private offices with furnishings, office furnishings for two (2) executive offices, one (1) conference table with ten (10) chairs for executive office space, one (1) floor to ceiling supply closet with locking door, three
(3) centrally located utility spaces and mesh arm chairs with casters for all new workstations.
3.1 NH4S Room 145: The contractor shall remove all existing furnishings/carpet and provide/install twenty (20) cubicle workstations, three (3) floor-to-ceiling private offices with furnishings, and configuration of one (1) centrally located utility space.
3.2 NH4S Room 233: The contractor shall remove all existing furnishings/carpet and provide/install fourteen (14) cubicle workstations, one (1) floor-to-ceiling private office with furnishings, and one (1) centrally located utility space.
3.3 NH4S Room 136: The contractor shall remove all existing furnishings/carpet to provide/install four (4) cubicle workstations, (2) floor-to-ceiling private offices with furnishings, one (1) floor to ceiling supply closet with locking door, and one (1) centrally located utility space.
3.4 NH4S Room 138: The contractor shall remove all existing furnishings/carpet to provide/install two (2) cubicle workstations (one of the two cubicle workstations will have low wall with a counter), office furnishings for two (2) existing floor-to-ceiling executive offices, and one (1) six-person conference table with ten (10) matching chairs for executive office space.
3.4.1 The contractor shall remove existing wall between offices 136 and 138.
3.5 The contractor shall:
3.5.1 Coordinate the removal and disposal of existing workstations/office furniture/carpet/trash, procurement, receipt, delivery, installation, required electrical work/connections and scheduling to satisfy the total requirement.
3.5.2 Provide necessary grommets and cable management needed to conceal all data/electrical cords.
3.5.3 Present each workstation in a neat and professional manner.
3.6 Delivery Address
1562 Mitscher Ave, Suite 250 Norfolk, VA. 23551
3.7 Delivery Date
Delivery and installation shall be completed by 1 December 2025.
File details come from the government source that posted it. Updated .