1-CS27008-27056210-Solicitation.pdf

PDF 1 MB Posted

Attached to
DFCM Construction - Invitational - Bridgerland Technical College - Main Campus West Facade and Door Improvements - Project #27056210
Solicitation number
CS27008
Issued by
Utah

About this file

This is an Invitational Low Bid Solicitation document issued by the Utah Division of Facilities Construction and Management (DFCM) for construction services at Bridgerland Technical College in Logan, Utah. The project involves painting the west facade of the BTECH Main Campus, including walls, trim, overhead doors and trim, with the addition of a numbering system to all overhead doors. An additive alternate includes painting the northwest wall as shown in project photos. Only four invited contractors are eligible to bid: Accent Painting, Brush Brothers Painting, Nicholls Brothers Painting, and Pecks Painting. A mandatory meeting is scheduled for July 28, 2026, at 3:00 PM at the project site, with attendance required for all prime contractors wishing to bid. The questions deadline is July 30, 2026, at 3:00 PM, the addendum deadline is August 3, 2026, at 3:00 PM, and bid submissions are due August 11, 2026, at 3:00 PM via the U3P website. Subcontractor lists must be submitted by August 12, 2026, at 3:00 PM. The substantial completion date is December 31, 2026, with liquidated damages of $100 per day for delays.

The construction budget is $149,999.00, with a bid bond requirement of 5% of the bid amount submitted on the AIA Document A310-2010 form or equivalent. The project is tax-exempt. DFCM intends to award a Short Form Construction Contract to the contractor submitting the lowest responsive and responsible bid. All contractors must comply with Utah state licensure requirements and must submit a DFCM Subcontractors List Form with their bid. Contractors and their principals must certify they have not been debarred or suspended and are not restricted foreign entities. Bid tabulation will be available within 24 hours of the bid deadline, with contract award immediately following evaluation. The project references DFCM Approved Fabricator List, DFCM Design Management Documents, DFCM Roofing Design Requirements, and State of Utah High Performance Building Standard requirements.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Division of FaciliƟes ConstrucƟon and Management Taylorsville State Office Building 4315 South 2700 West, 3rd Floor

Taylorsville, Utah 84129 dfcm.utah.gov | 801.957.7270

Invitational Low Bid Procurement for Construction Services

Project budgets up to $150,000

July 16, 2026

Main Campus West Facade and Door Improvements Bridgerland Technical College

Logan, Utah

DFCM Project #27056210 U3P Reference # CS27008

DFCM Invitational Low Bid for ConstrucƟon Services, 5.15.2026 2

SolicitaƟon Summary The State of Utah Division of FaciliƟes ConstrucƟon and Management (DFCM) is requesƟng bids for ConstrucƟon services for the project below. Only the Contractors listed below are invited to bid on this project. Bids submiƩed by Contractors not listed below will not be considered for award.

- Accent Painting - Eric Castillo - eric@accentpainting.com

- Brush Brothers Painting - Blake Isaacson - blake@brushbrotherspaint.com

- Nicholls Brothers Painting - Brady Henderson - rentacrew@msn.com

- Pecks Painting - Michelle MacKenzie - michelle@peckspainting.com

Main Campus West Facade and Doors Improvements Bridgerland Technical College 1301 N 600 W Logan, Utah DFCM Project #27056210 | U3P Reference # CS27008

CommunicaƟon during the selecƟon process shall be directed to the DFCM RepresentaƟves below only.

DFCM Project Manager: Carl Francis jcfrancis@utah.gov 435-230-2086 Brief Project DescripƟon: Paint the west facade of the BTECH Main Campus.

SubstanƟal CompleƟon Date: December 31, 2026 Liquidated Damages: $100.00 per day ConstrucƟon Budget: $149,999.00 Tax Exempt: Yes ☐ No ☒ Energy IncenƟves: Yes ☐ No ☒

SolicitaƟon Schedule Event Date Time LocaƟon

SolicitaƟon PosƟng Thursday, July 16, 2026 3:00 PM U3P

Mandatory MeeƟng Tuesday, July 28, 2026 3:00 PM

☒In person: BTech – 1301 N 600 W, Logan, Utah - Meet in the main building entrance lobby, located on the east side.

☐Virtual:

QuesƟons Deadline Thursday, July 30, 2026 3:00 PM U3P

Addendum Deadline Monday, August 3, 2026 3:00 PM U3P

Bid and Bid Bond Deadline Tuesday, August 11, 2026 3:00 PM U3P

Subcontractor Lists Deadline Wednesday, August 12, 2026 3:00 PM Email to:

dfcmcontracts@utah.gov

DFCM Invitational Low Bid for ConstrucƟon Services, 5.15.2026 3

Project Details

Detailed Project DescripƟon/Base Bid:

Paint the west façade of the BTECH Main Campus. PainƟng shall include walls, trim, overhead doors and trim, and adding a numbering system to all of the overhead doors.

AddiƟve Alternates:

AddiƟve Alternate 1: Paint the northwest wall as shown in the project photos.

Project Requirements:

- DFCM Approved Fabricator List

- DFCM Design Management Documents

- DFCM Roofing Design Requirements

- State of Utah High Performance Building Standard and all appendixes

DFCM Invitational Low Bid for ConstrucƟon Services, 5.15.2026 4

Solicitation Documents The solicitation documents consist of all documents listed below and referenced within this solicitation.

Solicitation Documents and Forms The following project specific documents and forms can be accessed in the U3P project for this solicitation.

Project specific documents:

- Invitational Low Bid Solicitation

- Approved Plans

Standard documents and forms:

- DFCM Subcontractor List Form & Instructions

DFCM Construction Management Standard Reference Documents All DFCM standard documents referenced in this solicitation can be accessed by visiting the DFCM Construction Management – Standard Documents page of the DFCM website.

DFCM Invitational Low Bid for ConstrucƟon Services, 5.15.2026 5

Procurement Process

1. Mandatory Meeting A mandatory meeting will be held on the date and time and at the location specified on the Solicitation Schedule. All prime Contractors wishing to bid on this project must attend and sign in. Contractors not in attendance at this meeting are ineligible to bid on this project. Subcontractors and suppliers are invited to attend this meeting, but it is not mandatory.

During the mandatory meeting, a presentation will be made describing the overall scope of work and intended project schedule. Interested Contractors may ask questions and request clarification about the project and the procurement process.

2. Requests for Information, Questions and Addendum All project related requests for information, clarifications, and questions must be submitted to DFCM via the U3P website no later than the time and date specified on the Solicitation Schedule. An addendum in response will be posted on the U3P website no later than the time and date specified on the Solicitation Schedule. All addenda issued shall become part of the solicitation, and any changes or additional requirements shall be incorporated into the Contractor’s proposal and/or bid.

a) Interpretation of Drawings and Specifications If any person or entity contemplating submitting a proposal or bid is in doubt as to the meaning of any part of the drawings, specifications or other contract documents, such person shall submit a request for an interpretation to DFCM via the U3P website no later than the time and date specified on the Solicitation Schedule. Any interpretation of the proposed documents will be made only by addenda posted on the U3P website. Neither DFCM nor A/E will be responsible for any other explanations or interpretations of the proposed documents. The A/E is deemed to be the architect or engineer hired by DFCM as the A/E or Consultant for the project.

b) Product Approvals Where reference is made to one or more proprietary products in the contract documents, but restrictive descriptive materials of one or more manufacturer(s) is referred to in the contract documents, the products of other manufacturers will be accepted, provided they equal or exceed the standards set forth in the drawings and specifications and are compatible with the intent and purpose of the design, subject to the written approval of the A/E. Such written approval must occur prior to the time and date specified on the Solicitation Schedule for the final addendum. The A/E’s written approval will be issued in an addendum. If the descriptive material is not restrictive, the products of other manufacturers specified will be accepted without prior approval provided they are compatible with the intent and purpose of the design as determined by the A/E.

3. Bidding, Bid Deadline, and Bid Bonds Bids must be submitted via the U3P website no later than the time and date specified on the Solicitation Schedule.

Contractors attempting to submit a bid through U3P website after the bid deadline has passed will not be successful and therefore disqualified from consideration of award of this project. It is the sole responsibility of the Contractor to confirm their bid is successfully submitted into U3P prior to the bid deadline.

Technical questions related to bidding in U3P should be directed to u3padmin@utah.gov.

After the bid deadline listed on the Solicitation Schedule has passed, the bid tabulation will be available within the following 24 hours in U3P and the Contract award will go to the Contractor submitting the lowest responsive and responsible bid.

Before submitting a bid, the Contractor shall carefully examine the solicitation; shall visit the site of the Work; shall fully inform themselves as to all existing conditions and limitations; and shall include in their bid the cost of all items required by the solicitation. If the Contractor observes that portions of the Contract Documents are at variance with applicable laws, building codes, rules, regulations or contain obvious erroneous or uncoordinated information, the Contractor shall promptly notify the DFCM Project Manager, and the necessary changes shall be accomplished by addendum.

DFCM Invitational Low Bid for ConstrucƟon Services, 5.15.2026 6

By submitting a bid, in any format, the Bidder / Offeror / Vendor certifies that: (1) no product to be supplied by the Bidder / Offeror / Vendor in connection with this Solicitation is a “forced labor product” as that term is defined in Utah Code 63G-6a-121; and (2) to the extent, if any, that this Solicitation involves technology, or technology services, networks or systems, the Bidder / Offeror / Vendor is not a “restricted foreign entity” as that term is defined in Utah Code 63G-6a-121.

a) Bid Bonds A bid bond properly signed by the Contractor and a qualified surety and submitted on the AIA Document A310 – 2010 Bid Bond form, or equivalent, in the amount of 5% of the bid, must accompany the bid submitted within U3P. If the bid bond is not provided with the bid, the bid is nonresponsive, and the Contractor may be disqualified from the selection process.

The bid bond must be submitted on the AIA document A310 – 2010 Bid Bond Form, or equivalent, to be accepted unless only one bid is received by DFCM, or the failure to comply with the bid bond requirements is determined by the Director of DFCM to be immaterial based on the following:

1. the bid bond is submitted on a form other than the AIA Document A310 – 2010 Bid Bond form, or equivalent, and the bid bond meets all other requirements including being issued by a surety firm authorized to do business in the State of Utah and be listed in the U.S. Department of the Treasury Circular 570, Companies Holding Certificates of Authority as Acceptable Securities on Federal Bonds and as Acceptable Reinsuring Companies for an amount not less than the amount of the bond to be issued. A co-surety may be utilized to satisfy this requirement; and

2. the Contractor provides a bid bond properly signed by a qualified surety and on the AIA Document A310 – 2010 Bid Bond form, or equivalent, by the close of business of the next business day after DFCM notifies the Contractor of the defective bid bond.

4. Termination and Debarment By submitting a bid, the Contractor certifies that neither it nor its principals, including project nor site managers, have been, or are under consideration for, debarment or suspension, or any action that would exclude such from participation in a construction Contract by any governmental department or agency. If the Contractor cannot certify this statement, provide a detailed written explanation to dfcmcontracts@utah.gov by the time and date specified as the bid deadline on the Solicitation Schedule. DFCM reserves the right to reject the Contractor’s explanation and disqualify them from the selection process.

5. Listing of Subcontractors All Contractors are required to submit their DFCM Subcontractors List Form to dfcmcontracts@utah.gov by the time and date specified on the Solicitation Schedule. The DFCM Subcontractors List Form & Instructions can be found on the DFCM website – Construction Management - Standard Documents page and is also posted in U3P.

If the DFCM Subcontractors List Form is not provided by the time and date specified on the Solicitation Schedule, the bid is nonresponsive, and the Contractor may be disqualified from the selection process.

DFCM retains the right to audit or take other steps necessary to confirm compliance with requirements for the listing and changing of subcontractors. Any Contractor who is found incompliant with these requirements is subject to a debarment hearing and may be debarred from consideration for award of DFCM contracts for a period not to exceed three years.

6. Withdrawal of Bids Bids may be withdrawn on written request received from bidder prior to the time fixed for opening. Negligence on the part of the bidder in preparing the bid confers no right for the withdrawal of the bid after it has been opened.

7. DFCM Reservation of Rights The Division of Facilities Construction and Management reserves the right to reject any or all proposals or bids or to waive any formality or technicality in any proposal or bid in the best interest of the State.

DFCM Invitational Low Bid for ConstrucƟon Services, 5.15.2026 7

8. Contract and Bonding Requirements DFCM intends to enter into a Short Form ConstrucƟon Contract with the Contractor submitting the lowest responsive and responsible bid. A copy of the Short ConstrucƟon Contract and the corresponding Contract CondiƟons can be found on the DFCM website – ConstrucƟon Management - Standard Documents page.

9. Licensure The Contractor shall comply with and require all subcontractors to comply with the license laws as required by the State of Utah.

10. Financial Responsibility of Contractors, Subcontractors and Sub-subcontractors Contractors shall respond promptly to any inquiry in writing by DFCM to any concern of financial responsibility of the Contractor, Subcontractor or Sub-subcontractor.

File details come from the government source that posted it. Updated .