1-482-11090 NOI.pdf
PDF 199 KB Posted
- Attached to
- Arkansas River East Bank Restoration - REBID
- Solicitation number
- 260102
- Issued by
- Sedgwick County, Kansas
About this file
This is a Notice of Intent (NOI) for stormwater discharge authorization submitted to the Kansas Department of Health and Environment (KDHE) by the City of Wichita for the Arkansas River East Bank Restoration project. The project involves excavation, filling, regrading, and installation of a retaining wall to stabilize soil and promote vegetative growth, removal of an existing temporary sidewalk, and installation of a new 10-foot-wide sidewalk to facilitate pedestrian flow. The project site is located south of Central Avenue and North Nims Avenue in Wichita, Kansas, with a total site area of 1.16 acres and an estimated disturbance area of 1.00 acre. Construction is anticipated to begin June 1, 2025, and be completed by June 1, 2027. The project will discharge stormwater runoff to the Little Arkansas River.
Authorization was granted by KDHE on July 7, 2025, with Kansas permit number S-LA20-0119 and federal permit number KSR123344, valid through July 31, 2027. The stormwater pollution prevention plan includes installation of silt fence, inlet protection, construction entrance, temporary seeding, and erosion control measures throughout the construction phases. The plan was developed by Jeffrey Alan Best, a licensed landscape architect (License No. 679). An annual permit fee of $60.00 is required and must be paid before processing. No conditions or considerations were noted for approval, and no contaminated soils, endangered species habitat impacts, or jurisdictional wetland disturbances were identified at the site.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2-482-11090-Attachment A.pdf | ||
| 3-BP 482-11090.pdf | ||
| 4-260102 Bid Table.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Effective: August 1, 2022 Notice of Intent (NOI) for Discharge of Stormwater Runoff from Construction Activites Page 1 of 4
NOTICE OF INTENT (NOI)
For Authorization to Discharge Stormwater Runoff from Construction Activities In accordance with the Kansas Water Pollution Control General Permit Under the National Pollutant Discharge Elimination System (NPDES)
Submission of this Notice of Intent constitutes notice that the party identified in Section I of this form requests authorization for coverage under the Kansas Water Pollution Control general permit, or KDHE issued successor permits, issued for stormwater runoff from construction activities in the State of Kansas. Becoming a permittee obligates the discharger to comply with the terms and conditions of the general permit. A complete request for Authorization for coverage under the general permit must be submitted or the request will not be processed. KDHE will notify owners or operators whose Notice of Intent (NOI) and supporting documentation for Authorization of stormwater runoff associated with construction activities are incomplete, deficient, or denied.
I. OWNER OR OPERATOR ADDRESS, BILLING, CONTACT & RECORDS LOCATION INFORMATION
Owner/Operator Tim Kellams Mailing Address: 455 N MAIN ST., FL 7 Company Name: City of Wichita City, State Zip: WICHITA, KS 67202 Phone: (316) 268-4678 Email: tkellams@wichita.gov
Contact Name: Tim Kellams Mailing Address: 455 N MAIN ST., FL 7 Company Name: City of Wichita City, State Zip: WICHITA, KS 67202-1620 Phone: (316) 268-4678 E-mail: tkellams@wichita.gov
PERMIT FEE BILLING INFORMATION
Billing Contact: Tim Kellams Billing Address: 455 N MAIN ST., FL 7
WICHITA, KS 67202-1620
Phone: (316) 268-4678 E-mail: tkellams@wichita.gov
II. SITE INFORMATION
Project Name: City of Wichita Arkansas River East Bank Restoration Street Address: South of Central Ave & N Nims Ave
Wichita, KS 67202 County: Sedgwick
Legal Site Description:
Qtr: Qtr: Qtr: Section: 17 Township: 27S Range: 01E
Decimal Degrees Latitude: 37.692805 Decimal Degrees Longitude: -97.350211
AUTHORIZED:Submission Received: 6/4/2025 Submission Number:
HQC-X8CV-87FGR YES X NO
Reviewer: Is Authorization Conditional
YES NO X
(if yes, see Section V for conditions)
Larry Hook Are there any Considerations
YES NO X
(if yes, see Section V for considerationsAuthorized By:
Secretary, Kansas Department of Health and Environment KS Permit No.: S-LA20-0119
Issued: July 07,2025 Federal Permit No.: KSR123344
KEIMS Watermark KSR123344 v1.0
Approved Issued On:07/07/2025
Expires On:07/31/2027
Project Name: City of Wichita Park Plaza Riverbank Improvements Notice of Intent (NOI)
Effective: August 1, 2022 Notice of Intent (NOI) for Discharge of Stormwater Runoff from Construction Activites Page 2 of 4
B. Existing Conditions/Uses
1) Is any part of the project located on Indian Country Land?
No
2) If stormwater runoff drains to or through a Municipal Separate Storm sewer System (MS4): MS4 Name:
3) Name of the first receiving water, stream, or lake Little Arkansas River, River Basin LA - LITTLE
ARKANSAS
4) Are contaminated soils present on the site or is there groundwater contamination located within the site boundary?
No
5) Are there any contaminated soils that will be disturbed or any contaminated groundwater that will be pumped by the proposed construction activity?
No
6) Are there any surface water intakes for public drinking water supplies located within ½ mile of the site discharge points?
No
7) Are there any known historical or archeological sites present within the site boundary or any historic structures located within 1000 feet of the project site?
No
Note: Include documentation of project-specific coordination with the Kansas Historical Society in making this determination
8) Is any threatened or endangered species habitat located within the site boundary or in the receiving water body?
No
Note: Include documentation of project-specific coordination with the Kansas Department of Wildlife, Parks & Tourism in making this determination.
9) Will the project impact the line or grade of a stream or does it include dredge or fill of a potential jurisdictional water body or wetlands?
No
10) Are any Critical Water Quality Management Areas, Special Aquatic Life Use Waters, or Outstanding National Resource Waters located within ½ mile of the facility boundary?
No
C. Project Description
1) Project Description:
Excavate, fill and regrade the site. Install retaining wall to help stabilize the soil and promote vegetative growth throughout the site. Remove old temporary sidewalk and install new 10' wide sidewalk to help pedestrian flow.
Does this NOI include all proposed soil disturbing activities associated with the entire common plan of development? Yes
2) Anticipated project Start Date: June 1, 2025 and Completion Date: June 1, 2027
3) Estimated total area to be disturbed: 1.00 Acres
4) Total area of the site: 1.16 Acres
5) Do you plan to disturb ten or more acres that are within a common drainage area? No
KEIMS Watermark KSR123344 v1.0
Approved
Project Name: City of Wichita Park Plaza Riverbank Improvements Notice of Intent (NOI)
Effective: August 1, 2022 Notice of Intent (NOI) for Discharge of Stormwater Runoff from Construction Activites Page 3 of 4
D. Maps
Include an area map showing the outline of the construction site and the topographic features of the area at least one mile beyond the project site.
E. Erosion Control Plan and Best Management Practices
1) Provide a summary of the sequence of major soil disturbing activities including installation of the corresponding stormwater management and pollution control features.
1. Install site boundary erosion control devices including silt fence along property lines downstream from areas to be disturbed and inlet protection around existing inlets on-site and adjacent. A construction entrance will also be installed at this point.
2. Clear and grub for site grading.
3. Strip existing topsoil and stockpile, commence mass grading of site.
4. Construct water line, sanitary sewer, and storm sewer improvements while other utilities, parking lot staging and building foundations work is completed.
5. Staging and maintenance of BMPs to be accomplished to ensure effective sediment and erosion control.
6. Spread topsoil over future site finish grades and install temporary seeding and erosion control measures.
7. Install localized permanent seeding/sod and landscape when possible and maintain temporary BMPs until permanent landscape and sediment control devices are established.
8. PPD As-builts are to be completed and approved.
9. Upon establishment of 95% permanent sediment and erosion control measures are complete, contractor to coordinate and turn-over permanent erosion control inspection and maintenance manual responsibility to the owner/operator.
10.When all construction activity is completed, the site is stabilized, all temporary structural BMPs removed and permanent water quality measures are operating, the contractor may delegate the post construction and maintenance duties to the owner/operator.
2) Provide one or more site plans covering the anticipated soil disturbing activities showing the limits of disturbance, the existing and proposed elevation contours, the types and locations of erosion/sediment control measures and stormwater management/pollution control features during each phase of construction and the locations where stormwater runoff leaves the construction site.
3) Provide a description of the best management practices to be utilized to control erosion and the discharge of sediment and other pollutants in stormwater runoff throughout construction and the design calculations for each sediment basin including total drainage area and storage capacity below the elevation of the mass volume flow outlet device.
4) Provide the name and License or Certification Number of the engineer, geologist, architect, landscape architect, or Certified Professional in Erosion and Sediment Control (CPESC) under which the construction stormwater pollution prevention plan has been developed.
Jeffrey Alan Best 679 Landscape Architect Name License or Certification Number Profession or Field
III. ANNUAL FEES
The first year of the annual permit fee specified in K.A.R 28-16-56 et seq. as amended is currently $60.00 and can be paid through the KEIMS system at time of submittal. The fee must be paid before this NOI will be processed. An invoice for the annual permit fee will be sent to the contact person requesting a permit until such time as the permittee submits a Notice of Termination (NOT).
Failure to pay the annual fee timely may result in termination of the construction stormwater discharge Authorization.
KEIMS Watermark KSR123344 v1.0
Approved
Project Name: City of Wichita Park Plaza Riverbank Improvements Notice of Intent (NOI)
Effective: August 1, 2022 Notice of Intent (NOI) for Discharge of Stormwater Runoff from Construction Activites Page 4 of 4
IV. OWNER OR OPERATOR CERTIFICATIONS
I, the undersigned, certify that a Stormwater Pollution Prevention Plan (SWP2 Plan) will be or has been developed for the construction site described in this NOI and supporting documentation. I further certify that the plan will be implemented at the time construction begins, and, as required by the NPDES general permit for Stormwater Runoff from Construction Activity, will revise the SWP2 plan if necessary.
I understand that continued coverage under the NPDES general permit for Stormwater Runoff from Construction Activities is contingent upon maintaining eligibility as provided for in the requirements and conditions of the general permit, and paying the annual fee.
I certify under penalty of law that this document and all attachments were prepared under my direction or supervision in accordance with a system designed to assure that qualified personnel properly gather and evaluate the information submitted.
Based on my inquiry of the person or persons who manage the system, or those persons directly responsible for gathering the information, the information submitted is, to the best of my knowledge and belief, true, accurate, and complete. I am aware that there are significant penalties for submitting false information, including the possibility of fine and imprisonment.
Tim Kellams 6/4/2025 4:33:04 PM Signature (owner or operator) Date
Official Title
V. CONDITIONS AND/OR CONSIDERATIONS OF APPROVAL
Conditions of Authorization - For Official Use Only:
When indicated, Conditions of Authorization are as follows:
NONE
Notes on Consideration – For Official Use Only:
NONE
KEIMS Watermark KSR123344 v1.0
Approved