1-2601-073 RICHFIELD CITY 2026 CHIP SEAL Specs.pdf

PDF 5 MB Posted

Attached to
Richfield City- 2026 Chip Seal
Solicitation number
RA26-107
Issued by
Tooele County, Utah

About this file

This is a Project Manual for a public works construction contract issued by Richfield City, Utah, for the 2026 Chip Seal project (Project #2601-073). The project involves chip sealing of Richfield City roadways across two schedules, with Schedule 1 encompassing northeast chip seal work anticipated at approximately $140,000 and Schedule 2 covering southwest chip seal work anticipated at approximately $190,000. The work includes surface preparation, emulsified asphalt application, chip seal coat placement, flush coat application, and pavement marking installation. Bids were due March 23 at 11:00 AM local time at the Richfield City Office, 75 East Center Street, Richfield, Utah 84701. No pre-bid conference was held, but questions were accepted through March 18 at 5:00 PM directed to Micklane Farmer at Jones & DeMille Engineering. Both schedules are to be completed within 30 days of contract commencement, with final completion and readiness for payment within 45 days. The Contract utilizes EJCDC standard forms including performance bonds, payment bonds, and general conditions for a stipulated price contract.

The project is awarded as a single contract to the lowest responsive and responsible bidder with unit price work being the basis of compensation. Bid security of 5 percent of the maximum bid price is required in the form of a bid bond. Progress payments are made monthly at 95 percent of completed work value with retainage, and final payment occurs upon completion and acceptance. Liquidated damages of $1,200 per day apply for failure to achieve substantial completion within 30 days and $600 per day for failure to complete remaining work within 45 days. The contractor must furnish performance and payment bonds equal to the contract price, maintain comprehensive general liability insurance with minimum limits of $2,000,000 aggregate and $1,000,000 per occurrence, and obtain builder's risk insurance. Work must be performed between June 1 and August 31, with application temperatures between 70 and 136 degrees Fahrenheit for chip seal placement. The contractor is responsible for all traffic control, surface preparation, material testing, and compliance with applicable AASHTO and UDOT standards for asphalt emulsions, aggregates, and pavement markings.

View the file

Other files

File Type Posted
2-2601-073 RICHFIELD CITY 2026 CHIP SEAL Plans.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RICHFIELD CITY

2026 CHIP SEAL

PROJECT MANUAL

PUBLISH DATE

FOR BIDDING ONLY

Project #: (2601-073)

Richfield City 00 01 10 Table of Contents 2026 Chip Seal (2601-073) Page 1 of 2

DOCUMENT 00 01 10

TABLE OF CONTENTS

NUMBER TITLE

PROCUREMENT AND CONTRACTING REQUIREMENTS GROUP

Division 00 � Procurement and Contracting Requirements

Introductory Information 00 01 10 Table of Contents

Procurement Requirements 00 11 13 Advertisement for Bids 00 21 13 Instructions to Bidders 00 41 11 Bid Form for Construction Contract 00 43 13.11 Bid Bond (Penal Sum Form)

Contracting Requirements 00 51 00 Notice of Award 00 52 13.11 Agreement between Owner and Contractor for Construction Contract (Stipulated

Price) 00 55 00 Notice to Proceed 00 61 13.13 Performance Bond Form 00 61 13.16 Payment Bond Form 00 62 76.11 Contractor�s Application for Payment Form 00 63 36 Field Order Form 00 65 16 Certificate of Substantial Completion Form 00 65 19.21 Notice of Acceptability of Work 00 72 11 Standard General Conditions of the Construction Contract 00 73 11 Supplementary Conditions of the Construction Contract

SPECIFICATIONS GROUP

GENERAL REQUIREMENTS SUBGROUP (Division 01)

Division 01 � General Requirements 01 10 00 Summary 01 20 00 Price and Payment Procedures 01 30 00 Administrative Requirements 01 33 00 Submittal Procedures 01 40 00 Quality Requirements 01 50 00 Temporary Facilities and Controls 01 55 26 Traffic Control 01 70 00 Execution and Closeout Requirements 01 71 13 Mobilization

FACILITY CONSTRUCTION SUBGROUP (Division 02 to 19)

Division 02 to 19 � Not Used

FACILITY SERVICES SUBGROUP (Division 20 to 29)

Richfield City 00 01 10 Table of Contents

(2601-073) Page 2 of 2

Division 20 to 29 – Not Used

SITE AND INFRASTRUCTURE SUBGROUP (Division 30 to 39)

Division 30 to 31 – Not Used

Division 32 – Exterior Improvements 32 01 13.51 Flush Coat 32 01 13.64 Chip Seal 32 17 23.13 Painted Pavement Markings

Division 33 to 39 – Not Used

PROCESS EQUIPMENT SUBGROUP (Division 40 to 49)

Division 40 to 49 – Not Used

DRAWINGS

SHEET

NUMBER TITLE

G-001 TITLE

G-002 LEGEND

G-003 PLAN SHEET INDEX

SM-01 SUMMARIES

PL-01 SCHEDULE 1 – ROAD PLAN

PL-02 SCHEDULE 2 – ROAD PLAN

Richfield City 00 11 13 Advertisement for Bids

(2601-073) Page 1 of 1

DOCUMENT 00 11 13

ADVERTISEMENT FOR BIDS

Richfield City, Utah, 75 East Center Street, Richfield, UT 84701

General Notice:

Richfield City (Owner) is requesting Bids for the construction of the following Project: 2026 Chip Seal.

Bids for the construction of the Project will be received at the Richfield City Office located at 75 E Center

Street, Richfield, Utah 84701 until March 23 at 11:00 A.M. local time. At that time the Bids received will be publicly opened and read.

The Project includes the following Work: Chip seal of Richfield City roadways. Bids will be received for single contract.

Owner anticipates that the total bid price for Schedule 1 northeast chip seal will be approximately

$140,000. Owner anticipates that the total bid price for Schedule 2 southwest chip seal will be approximately $190,000. It is anticipated that both schedules will be completed in 30 days.

Obtaining Bidding Documents:

Information and Bidding Documents for the Project can be found at the following designated website:

https://utah.bonfirehub.com/portal/?tab=openOpportunities.

The Issuing Office for the Bidding Documents is: Jones & DeMille Engineering, Inc., 1535 South 100

West, Richfield, UT 84701

Prospective Bidders may examine the Bidding Documents at the Issuing Office Monday through Friday between the hours of 8:00 a.m. to 5:00 p.m., except holidays or may obtain copies of the Bidding

Documents from the Issuing Office as described below. Partial sets of Bidding Documents will not be available from the Issuing Office.

Neither Owner nor Engineer will be responsible for full or partial sets of Bidding Documents, including addenda, if any, obtained from sources other than the designated websites and the Issuing Office.

Questions are due in writing to Micklane Farmer, PM, at micklane.f@jonesanddemille.com on or before

Wednesday March 18 @ 5 P.M. local time.

Pre-bid Conference:

A pre-bid conference will not be held.

Instructions to Bidders:

For further requirements regarding bid submittal, qualifications, procedures, and contract award, refer to the Instructions to Bidders that are included in the Bidding Documents. The Owner may reject any or all bids submitted.

Issued by:

Owner: Richfield City

By: Michele Jolley

Title: City Manager

Date: 3/5/2026

EJCDC® C-200, Instructions to Bidders for Construction Contract.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

TOC Page1 of 1

DOCUMENT 00 21 13

INSTRUCTIONS TO BIDDERS FOR CONSTRUCTION CONTRACT

TABLE OF CONTENTS

Page

Article 1� Defined Terms

Article 2� Bidding Documents

Article 3� Qualifications of Bidders

Article 4� Pre-Bid Conference

Article 5� Site and Other Areas; Existing Site Conditions; Examination of Site; Owner�s Safety Program;

Other Work at the Site

Article 6� Bidder�s Representations and Certifications

Article 7� Interpretations and Addenda

Article 8� Bid Security

Article 9� Contract Times

Article 10� Substitute and �Or Equal� Items

Article 11� Subcontractors, Suppliers, and Others

Article 12� Preparation of Bid

Article 13� Basis of Bid

Article 14� Submittal of Bid

Article 15� Modification and Withdrawal of Bid

Article 16� Opening of Bids

Article 17� Bids to Remain Subject to Acceptance

Article 18� Evaluation of Bids and Award of Contract

Article 19� Bonds and Insurance

Article 20� Signing of Agreement

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

ARTICLE 1�DEFINED TERMS

1.01 Terms used in these Instructions to Bidders have the meanings indicated in the General Conditions and Supplementary Conditions. Additional terms used in these Instructions to Bidders have the meanings indicated below:

A. Issuing Office�The office from which the Bidding Documents are to be issued, and which registers plan holders.

ARTICLE 2�BIDDING DOCUMENTS

2.01 Bidder shall obtain a complete set of Bidding Requirements and proposed Contract Documents

(together, the Bidding Documents). See the Agreement for a list of the Contract Documents. It is

Bidder�s responsibility to determine that it is using a complete set of documents in the preparation of a Bid. Bidder assumes sole responsibility for errors or misinterpretations resulting from the use of incomplete documents, by Bidder itself or by its prospective Subcontractors and Suppliers.

2.02 Bidding Documents are made available for the sole purpose of obtaining Bids for completion of the Project and permission to download or distribution of the Bidding Documents does not confer a license or grant permission or authorization for any other use. Authorization to download documents, or other distribution, includes the right for plan holders to print documents solely for their use, and the use of their prospective Subcontractors and Suppliers, provided the plan holder pays all costs associated with printing or reproduction. Printed documents may not be re-sold under any circumstances.

2.03 Owner has established a Bidding Documents Website as indicated in the Advertisement or invitation to bid. Owner recommends that Bidder register as a plan holder with the Issuing Office at such website and obtain a complete set of the Bidding Documents from such website. Bidders may rely that sets of Bidding Documents obtained from the Bidding Documents Website are complete, unless an omission is blatant. Registered plan holders will receive Addenda issued by

Owner.

2.04 Plan rooms (including construction information subscription services, and electronic and virtual plan rooms) may distribute the Bidding Documents or make them available for examination.

Those prospective bidders that obtain an electronic (digital) copy of the Bidding Documents from a plan room are encouraged to register as plan holders from the Bidding Documents Website or

Issuing Office. Owner is not responsible for omissions in Bidding Documents or other documents obtained from plan rooms, or for a Bidder�s failure to obtain Addenda from a plan room.

2.05 Electronic Documents

A. When the Bidding Requirements indicate that electronic (digital) copies of the Bidding

Documents are available, such documents will be made available to the Bidders as Electronic

Documents in the manner specified.

1. Bidding Documents will be provided in Adobe PDF (Portable Document Format) (.pdf) that is readable by a current version of Adobe Acrobat or equivalent program. It is the intent of the Engineer and Owner that such Electronic Documents are to be exactly representative of the paper copies of the documents. However, because the Owner and

Engineer cannot totally control the transmission and receipt of Electronic Documents nor the Contractor�s means of reproduction of such documents, the Owner and

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Engineer cannot and do not guarantee that Electronic Documents and reproductions prepared from those versions are identical in every manner to the paper copies.

B. Unless otherwise stated in the Bidding Documents, the Bidder may use and rely upon complete sets of Electronic Documents of the Bidding Documents, described in

Paragraph 2.06.A above. However, Bidder assumes all risks associated with differences arising from transmission/receipt of Electronic Documents versions of Bidding Documents and reproductions prepared from those versions and, further, assumes all risks, costs, and responsibility associated with use of the Electronic Documents versions to derive information that is not explicitly contained in printed paper versions of the documents, and for Bidder�s reliance upon such derived information.

ARTICLE 3�QUALIFICATIONS OF BIDDERS

3.01 To demonstrate Bidder�s qualifications to perform the Work, after submitting its Bid and within

14 days of Owner�s request, Bidder must submit the following information:

A. Written evidence establishing its qualifications such as financial data, previous experience, and present commitments.

B. Subcontractor and Supplier qualification information.

C. Information regarding three projects similar in size and scope as proposed Project that Bidder has completed within the last five years. Include name and phone number of person Owner or Engineer may contact regarding each referenced project.

D. Other required information regarding qualifications.

3.02 A Bidder�s failure to submit required qualification information within the times indicated may disqualify Bidder from receiving an award of the Contract.

3.03 No requirement in this Article 3 to submit information will prejudice the right of Owner to seek additional pertinent information regarding Bidder�s qualifications.

ARTICLE 4�PRE-BID CONFERENCE

4.01 A pre-bid conference will not be conducted for this Project.

ARTICLE 5�SITE AND OTHER AREAS; EXISTING SITE CONDITIONS; EXAMINATION OF SITE; OWNER�S

SAFETY PROGRAM; OTHER WORK AT THE SITE

5.01 Site and Other Areas

A. The Site is identified in the Bidding Documents. By definition, the Site includes rights-of-way, easements, and other lands furnished by Owner for the use of the Contractor. Any additional lands required for temporary construction facilities, construction equipment, or storage of materials and equipment, and any access needed for such additional lands, are to be obtained and paid for by Contractor.

5.02 Existing Site Conditions

A. Subsurface and Physical Conditions; Hazardous Environmental Conditions

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

1. The Supplementary Conditions identify the following regarding existing conditions at or adjacent to the Site:

a. Those reports of explorations and tests of subsurface conditions at or adjacent to the Site that contain Technical Data.

b. Those drawings known to Owner of existing physical conditions at or adjacent to the Site, including those drawings depicting existing surface or subsurface structures at or adjacent to the Site (except Underground Facilities), that contain

Technical Data.

c. Reports and drawings known to Owner relating to Hazardous Environmental

Conditions that have been identified at or adjacent to the Site.

d. Technical Data contained in such reports and drawings.

2. Owner will make copies of reports and drawings referenced above available to any

Bidder on request. These reports and drawings are not part of the Contract Documents, but the Technical Data contained therein upon whose accuracy Bidder is entitled to rely, as provided in the General Conditions, has been identified and established in the

Supplementary Conditions. Bidder is responsible for any interpretation or conclusion

Bidder draws from any Technical Data or any other data, interpretations, opinions, or information contained in such reports or shown or indicated in such drawings.

3. If the Supplementary Conditions do not identify Technical Data, the default definition of

Technical Data set forth in Article 1 of the General Conditions will apply.

B. Underground Facilities: Underground Facilities are shown or indicated on the Drawings, pursuant to Paragraph 5.05 of the General Conditions, and not in the drawings referred to in

Paragraph 5.02.A of these Instructions to Bidders. Information and data regarding the presence or location of Underground Facilities are not intended to be categorized, identified, or defined as Technical Data.

5.03 Other Site-related Documents

A. No other Site-related documents are available.

5.04 Site Visit and Testing by Bidders

A. Bidder is required to visit the Site and conduct a thorough visual examination of the Site and adjacent areas. During the visit the Bidder must not disturb any ongoing operations at the

Site.

B. Bidders visiting the Site are required to arrange their own transportation to the Site.

C. Bidder is not required to conduct any subsurface testing, or exhaustive investigations of Site conditions.

5.05 Owner�s Safety Program

A. Site visits and work at the Site may be governed by an Owner safety program. If an Owner safety program exists, it will be noted in the Supplementary Conditions.

5.06 Other Work at the Site

A. Reference is made to Article 8 of the Supplementary Conditions for the identification of the general nature of other work of which Owner is aware (if any) that is to be performed at the

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Site by Owner or others (such as utilities and other prime contractors) and relates to the

Work contemplated by these Bidding Documents. If Owner is party to a written contract for such other work, then on request, Owner will provide to each Bidder access to examine such contracts (other than portions thereof related to price and other confidential matters), if any.

ARTICLE 6�BIDDER�S REPRESENTATIONS AND CERTIFICATIONS

6.01 Express Representations and Certifications in Bid Form, Agreement

A. The Bid Form that each Bidder will submit contains express representations regarding the

Bidder�s examination of Project documentation, Site visit, and preparation of the Bid, and certifications regarding lack of collusion or fraud in connection with the Bid. Bidder should review these representations and certifications and assure that Bidder can make the representations and certifications in good faith, before executing and submitting its Bid.

B. If Bidder is awarded the Contract, Bidder (as Contractor) will make similar express representations and certifications when it executes the Agreement.

ARTICLE 7�INTERPRETATIONS AND ADDENDA

7.01 Owner on its own initiative may issue Addenda to clarify, correct, supplement, or change the

Bidding Documents.

7.02 Bidder shall submit all questions about the meaning or intent of the Bidding Documents to

Engineer in writing. Contact information and submittal procedures for such questions are as follows:

A. Micklane Farmer at m.farmer@jonesanddemille.com

7.03 Interpretations or clarifications considered necessary by Engineer in response to such questions will be issued by Addenda delivered to all registered plan holders. Questions received less than seven days prior to the date for opening of Bids may not be answered.

7.04 Only responses set forth in an Addendum will be binding. Oral and other interpretations or clarifications will be without legal effect. Responses to questions are not part of the Contract

Documents unless set forth in an Addendum that expressly modifies or supplements the Contract

Documents.

ARTICLE 8�BID SECURITY

8.01 A Bid must be accompanied by Bid security made payable to Owner in an amount of 5 percent of

Bidder�s maximum Bid price (determined by adding the base bid and all alternates) and in the form of a Bid bond issued by a surety meeting the requirements of Paragraph 6.01 of the General

Conditions. Such Bid bond will be issued in the form included in the Bidding Documents.

8.02 The Bid security of the apparent Successful Bidder will be retained until Owner awards the contract to such Bidder, and such Bidder has executed the Contract, furnished the required

Contract security, and met the other conditions of the Notice of Award, whereupon the Bid security will be released. If the Successful Bidder fails to execute and deliver the Contract and furnish the required Contract security within 15 14 days after the Notice of Award, Owner may consider Bidder to be in default, annul the Notice of Award, and the Bid security of that Bidder will be forfeited, in whole in the case of a penal sum bid bond, and to the extent of Owner�s

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

damages in the case of a damages-form bond. Such forfeiture will be Owner�s exclusive remedy if

Bidder defaults.

8.03 The Bid security of other Bidders that Owner believes to have a reasonable chance of receiving the award may be retained by Owner until the earlier of 7 days after the Effective Date of the

Contract or 61 days after the Bid opening, whereupon Bid security furnished by such Bidders will be released.

8.04 Bid security of other Bidders that Owner believes do not have a reasonable chance of receiving the award will be released within 7 days after the Bid opening.

ARTICLE 9�CONTRACT TIMES

9.01 The number of days within which, or the dates by which, the Work is to be (a) substantially completed and (b) ready for final payment, and (c) Milestones (if any) are to be achieved, are set forth in the Agreement.

9.02 Deleted.

9.03 Provisions for liquidated damages, if any, for failure to timely attain a Milestone, Substantial

Completion, or completion of the Work in readiness for final payment, are set forth in the

Agreement.

ARTICLE 10�SUBSTITUTE AND �OR EQUAL� ITEMS

10.01 Deleted.

10.02 The Contract for the Work, as awarded, will be on the basis of materials and equipment specified or described in the Bidding Documents, and those �or-equal� or substitute or materials and equipment subsequently approved by Engineer prior to the submittal of Bids and identified by

Addendum. No item of material or equipment will be considered by Engineer as an �or-equal� or substitute unless written request for approval has been submitted by Bidder and has been received by Engineer within 10 days of the issuance of the Advertisement for Bids or invitation to

Bidders. Each such request must comply with the requirements of Paragraphs 7.05 and 7.06 of the General Conditions, and the review of the request will be governed by the principles in those paragraphs. The burden of proof of the merit of the proposed item is upon Bidder. Engineer�s decision of approval or disapproval of a proposed item will be final. If Engineer approves any such proposed item, such approval will be set forth in an Addendum issued to all registered Bidders.

Bidders cannot rely upon approvals made in any other manner.

10.03 All prices that Bidder sets forth in its Bid will be based on the presumption that the Contractor will furnish the materials and equipment specified or described in the Bidding Documents, as

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

supplemented by Addenda. Any assumptions regarding the possibility of post-Bid approvals of

�or-equal� or substitution requests are made at Bidder�s sole risk.

ARTICLE 11�SUBCONTRACTORS, SUPPLIERS, AND OTHERS

11.01 Deleted.

11.02 The apparent Successful Bidder, and any other Bidder so requested, must submit to Owner a list of the Subcontractors or Suppliers proposed for the following portions of the Work within five days after Bid opening:

A. Major categories of the Work which exceed 5 percent of the bid amount

11.03 If requested by Owner, such list must be accompanied by an experience statement with pertinent information regarding similar projects and other evidence of qualification for each such

Subcontractor or Supplier. If Owner or Engineer, after due investigation, has reasonable objection to any proposed Subcontractor or Supplier, Owner may, before the Notice of Award is given, request apparent Successful Bidder to submit an acceptable substitute, in which case apparent

Successful Bidder will submit a substitute, Bidder�s Bid price will be increased (or decreased) by the difference in cost occasioned by such substitution, and Owner may consider such price adjustment in evaluating Bids and making the Contract award.

11.04 If apparent Successful Bidder declines to make any such substitution, Owner may award the

Contract to the next lowest Bidder that proposes to use acceptable Subcontractors and Suppliers.

Declining to make requested substitutions will constitute grounds for forfeiture of the Bid security of any Bidder. Any Subcontractor or Supplier, so listed and against which Owner or Engineer makes no written objection prior to the giving of the Notice of Award will be deemed acceptable to Owner and Engineer subject to subsequent revocation of such acceptance as provided in

Paragraph 7.07 of the General Conditions.

11.05 The Contractor shall not award work to Subcontractors in excess of the limits stated in the

Supplementary Conditions.

ARTICLE 12�PREPARATION OF BID

12.01 The Bid Form is included with the Bidding Documents.

A. All blanks on the Bid Form must be completed in ink and the Bid Form signed in ink. Erasures or alterations must be initialed in ink by the person signing the Bid Form. A Bid price must be indicated for each section, bid item, alternate, adjustment unit price item, and unit price item listed therein.

B. If the Bid Form expressly indicates that submitting pricing on a specific alternate item is optional, and Bidder elects to not furnish pricing for such optional alternate item, then Bidder may enter the words �No Bid� or �Not Applicable.�

12.02 If Bidder has obtained the Bidding Documents as Electronic Documents, then Bidder shall prepare its Bid on a paper copy of the Bid Form printed from the Electronic Documents version of the

Bidding Documents. The printed copy of the Bid Form must be clearly legible, printed on 8½ inch by 11-inch paper and as closely identical in appearance to the Electronic Document version of the

Bid Form as may be practical. The Owner reserves the right to accept Bid Forms which nominally vary in appearance from the original paper version of the Bid Form, providing that all required information and submittals are included with the Bid.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

12.03 A Bid by a corporation must be executed in the corporate name by a corporate officer (whose title must appear under the signature), accompanied by evidence of authority to sign. The corporate address and state of incorporation must be shown.

12.04 A Bid by a partnership must be executed in the partnership name and signed by a partner (whose title must appear under the signature), accompanied by evidence of authority to sign. The official address of the partnership must be shown.

12.05 A Bid by a limited liability company must be executed in the name of the firm by a member or other authorized person and accompanied by evidence of authority to sign. The state of formation of the firm and the official address of the firm must be shown.

12.06 A Bid by an individual must show the Bidder�s name and official address.

12.07 A Bid by a joint venture must be executed by an authorized representative of each joint ventures in the manner indicated on the Bid Form. The joint venture must have been formally established prior to submittal of a Bid, and the official address of the joint venture must be shown.

12.08 All names must be printed in ink below the signatures.

12.09 The Bid must contain an acknowledgment of receipt of all Addenda, the numbers of which must be filled in on the Bid Form.

12.10 Postal and e-mail addresses and telephone number for communications regarding the Bid must be shown.

12.11 The Bid must contain evidence of Bidder�s authority to do business in the state where the Project is located, or Bidder must certify in writing that it will obtain such authority within the time for acceptance of Bids and attach such certification to the Bid.

12.12 If Bidder is required to be licensed to submit a Bid or perform the Work in the state where the

Project is located, the Bid must contain evidence of Bidder�s licensure, or Bidder must certify in writing that it will obtain such licensure within the time for acceptance of Bids and attach such certification to the Bid. Bidder�s state contractor license number, if any, must also be shown on the Bid Form.

ARTICLE 13�BASIS OF BID

13.01 Lump Sum � Deleted.

13.02 Base Bid with Alternates

A. Bidders must submit a Bid on a lump sum basis for the base Bid and include a separate price for each alternate described in the Bidding Documents and as provided for in the Bid Form.

The price for each alternate will be the amount added to or deleted from the base Bid if

Owner selects the alternate.

B. In the comparison of Bids, alternates will be applied in the same order of priority as listed in the Bid Form.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

13.03 Sectional Bids - Deleted

13.04 Cost-Plus-Fee Bids - Deleted

13.05 Unit Price

A. Bidders must submit a Bid on a unit price basis for each item of Work listed in the unit price section of the Bid Form.

B. The �Bid Price� (sometimes referred to as the extended price) for each unit price Bid item will be the product of the �Estimated Quantity�, which Owner or its representative has set forth in the Bid Form, for the item and the corresponding �Bid Unit Price� offered by the

Bidder. The total of all unit price Bid items will be the sum of these �Bid Prices�; such total will be used by Owner for Bid comparison purposes. The final quantities and Contract Price will be determined in accordance with Paragraph 13.03 of the General Conditions.

C. Discrepancies between the multiplication of units of Work and unit prices will be resolved in favor of the unit prices. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum.

D. The project has been divided into separate schedules for convenience of keeping track of the

Work items. Only one contract will be awarded.

13.06 Allowances

A. For cash allowances the Bid price must include such amounts as the Bidder deems proper for

Contractor's overhead, costs, profit, and other expenses on account of cash allowances, if any, named in the Contract Documents, in accordance with Paragraph 13.02.B of the General

Conditions.

13.07 Price-Plus-Time Bids - Deleted

ARTICLE 14�SUBMITTAL OF BID

14.01 The Bidding Documents include one separate unbound copy of the Bid Form, and, if required, the

Bid Bond Form. The An unbound copy of the Bid Form is to be completed and submitted with the

Bid security and the other documents required to be submitted under the terms of Article 2 of the Bid Form.

14.02 A Bid must be received no later than the date and time prescribed and at the place indicated in the Advertisement or invitation to bid and must be enclosed in a plainly marked package with the

Project title, and, if applicable, the designated portion of the Project for which the Bid is submitted, the name and address of Bidder, and must be accompanied by the Bid security and other required documents.

A. If a Bid is sent by mail or other delivery system, the sealed envelope containing the Bid must be enclosed in a separate package plainly marked on the outside with the notation �BID

ENCLOSED.� A mailed Bid must be addressed to the location designated in the

Advertisement.

B. If a Bid is sent by email or other electronic delivery system, the electronic Bid shall be received, not just sent, before the date and time prescribed in the advertisement or invitation to bid. An emailed Bid shall be sent to Micklane Farmer at micklane.f@jonesanddemille.com

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

14.03 Bids received after the date and time prescribed for the opening of bids, or not submitted at the correct location or in the designated manner, will not be accepted and will be returned to the

Bidder unopened.

ARTICLE 15�MODIFICATION AND WITHDRAWAL OF BID

15.01 An unopened Bid may be withdrawn by an appropriate document duly executed in the same manner that a Bid must be executed and delivered to the place where Bids are to be submitted prior to the date and time for the opening of Bids. Upon receipt of such notice, the unopened Bid will be returned to the Bidder.

15.02 If a Bidder wishes to modify its Bid prior to Bid opening, Bidder must withdraw its initial Bid in the manner specified in Paragraph 15.01 and submit a new Bid prior to the date and time for the opening of Bids.

15.03 If within 24 hours after Bids are opened any Bidder files a duly signed written notice with Owner and promptly thereafter demonstrates to the reasonable satisfaction of Owner that there was a material and substantial mistake in the preparation of its Bid, the Bidder may withdraw its Bid, and the Bid security will be returned. Thereafter, if the Work is rebid, the Bidder will be disqualified from further bidding on the Work.

ARTICLE 16�OPENING OF BIDS

16.01 Bids will be opened at the time and place indicated in the advertisement or invitation to bid and, unless obviously non-responsive, read aloud publicly. An abstract of the amounts of the base Bids and major alternates, if any, will be made available to Bidders after the opening of Bids.

ARTICLE 17�BIDS TO REMAIN SUBJECT TO ACCEPTANCE

17.01 All Bids will remain subject to acceptance for the period of time stated in the Bid Form, but Owner may, in its sole discretion, release any Bid and return the Bid security prior to the end of this period.

ARTICLE 18�EVALUATION OF BIDS AND AWARD OF CONTRACT

18.01 Owner reserves the right to reject any or all Bids, including without limitation, nonconforming, nonresponsive, unbalanced, or conditional Bids. Owner also reserves the right to waive all minor

Bid informalities not involving price, time, or changes in the Work.

18.02 Owner will reject the Bid of any Bidder that Owner finds, after reasonable inquiry and evaluation, to not be responsible.

18.03 If Bidder purports to add terms or conditions to its Bid, takes exception to any provision of the

Bidding Documents, or attempts to alter the contents of the Contract Documents for purposes of

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

the Bid, whether in the Bid itself or in a separate communication to Owner or Engineer, then

Owner will reject the Bid as nonresponsive.

18.04 If Owner awards the contract for the Work, such award will be to the responsible Bidder submitting the lowest responsive Bid.

18.05 Evaluation of Bids

A. In evaluating Bids, Owner will consider whether the Bids comply with the prescribed requirements, and such alternates, unit prices, and other data, as may be requested in the

Bid Form or prior to the Notice of Award.

B. Deleted

C. Deleted.

D. For the determination of the apparent low Bidder when unit price bids are submitted, Bids will be compared on the basis of the total of the products of the estimated quantity of each item and unit price Bid for that item, together with any lump sum items.

E. Deleted.

F. Deleted.

G. Deleted.

H. If the lowest acceptable Bid exceeds the amount of funds available to finance the Contract including reasonable contingencies, the Owner may reject the Bids or may award portions of project as the budget allows. Bids will be evaluated based on the Work that is awarded.

18.06 In evaluating whether a Bidder is responsible, Owner will consider the qualifications of the Bidder and may consider the qualifications and experience of Subcontractors and Suppliers proposed for those portions of the Work for which the identity of Subcontractors and Suppliers must be submitted as provided in the Bidding Documents.

A. In order to be considered qualified for the Project, the Bidder shall have successfully constructed at least two similar sized chip seal projects. Use Document 00 45 14 �

Qualifications Statement to document similar past project experience and submit with Bid.

18.07 Owner may conduct such investigations as Owner deems necessary to establish the responsibility, qualifications, and financial ability of Bidders and any proposed Subcontractors or Suppliers.

ARTICLE 19�BONDS AND INSURANCE

19.01 Article 6 of the General Conditions, as may be modified by the Supplementary Conditions, sets forth Owner�s requirements as to performance and payment bonds, other required bonds (if any), and insurance. When the Successful Bidder delivers the executed Agreement to Owner, it must be accompanied by required bonds and insurance documentation.

19.02 Article 8, Bid Security, of these Instructions, addresses any requirements for providing bid bonds as part of the bidding process.

ARTICLE 20�SIGNING OF AGREEMENT

20.01 When Owner issues a Notice of Award to the Successful Bidder, it will be accompanied by the unexecuted counterparts of the Agreement along with the other Contract Documents as

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

identified in the Agreement. Within 15 14 days thereafter, Successful Bidder must execute and deliver the required number of counterparts of the Agreement and any bonds and insurance documentation required to be delivered by the Contract Documents to Owner. Within 10 days thereafter, Owner will deliver one fully executed counterpart of the Agreement to Successful

Bidder, together with printed and electronic copies of the Contract Documents as stated in

Paragraph 2.02 of the General Conditions.

EJCDC® C-410, Bid Form for Construction Contract.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

DOCUMENT 00 41 11

BID FORM FOR CONSTRUCTION CONTRACT

PROJECT: RICHFIELD CITY 2026 CHIP SEAL

The terms used in this Bid with initial capital letters have the meanings stated in the Instructions to

Bidders, the General Conditions, and the Supplementary Conditions.

ARTICLE 1�OWNER AND BIDDER

1.01 This Bid is submitted to: Richfield City, c/o Jones & DeMille Engineering, 1535 South 100 West, Richfield, UT 84701

1.02 The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement with Owner in the form included in the Bidding Documents to perform all Work as specified or indicated in the Bidding Documents for the prices and within the times indicated in this Bid and in accordance with the other terms and conditions of the Bidding Documents.

ARTICLE 2�ATTACHMENTS TO THIS BID

2.01 The following documents are submitted with and made a condition of this Bid:

A. Required Bid security.

B. Evidence of authority to do business in the state of the Project; or a written covenant to obtain such authority within the time for acceptance of Bids.

C. Contractor�s license number as evidence of Bidder�s State Contractor�s License or a covenant by Bidder to obtain said license within the time for acceptance of Bids.

D. Required Bidder qualification information as indicated in Article 3 of the Instructions to

Bidders.

ARTICLE 3�BASIS OF BID�LUMP SUM BID AND UNIT PRICES

3.01 Deleted.

3.02 Unit Price Bids

A. Bidder will perform the following Work at the indicated unit prices:

(Remainder of Page Left Intentionally Blank)

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

SCHEDULE 1

Item Item Description Unit

Estimated Bid Unit Bid Price

No. Quantity Price

1-1 Mobilization L.S. 1

1-2 Traffic Control L.S. 1

1-3 Chip Seal Coat Type II S.Y. 47,689

1-4 Emulsified Asphalt, PMRE Ton 90

1-5 Emulsified Asphalt, Flush Coat Ton 24

1-6 Pavement Marking Paint Gal. 38

Schedule 1 Subtotal

SCHEDULE 2

2-1 Mobilization L.S. 1

2-2 Traffic Control L.S. 1

2-3 Chip Seal Coat Type II S.Y. 19,495

2-4 Emulsified Asphalt, PMRE Ton 37

2-5 Emulsified Asphalt, Flush Coat Ton 10

Schedule 2 Subtotal

Total Bid Price

B. Bidder acknowledges that:

1. each Bid Unit Price includes an amount considered by Bidder to be adequate to cover Contractor’s overhead and profit for each separately identified item, and

2. estimated quantities are not guaranteed and are solely for the purpose of comparison of Bids, and final payment for all Unit Price Work will be based on actual quantities, determined as provided in the Contract Documents.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

3.03 Deleted.

ARTICLE 4�BASIS OF BID�COST-PLUS FEE - DELETED

ARTICLE 5�PRICE-PLUS-TIME BID - DELETED

ARTICLE 6�TIME OF COMPLETION

6.01 Bidder agrees that the Work will be substantially complete and will be completed and ready for final payment in accordance with Paragraph 15.06 of the General Conditions on or before the dates or within the number of calendar days indicated in the Agreement.

6.02 Deleted.

6.03 Deleted.

6.04 Bidder accepts the provisions of the Agreement as to liquidated damages.

ARTICLE 7�BIDDER�S ACKNOWLEDGEMENTS: ACCEPTANCE PERIOD, INSTRUCTIONS, AND RECEIPT OF

ADDENDA

7.01 Bid Acceptance Period

A. This Bid will remain subject to acceptance for 60 days after the Bid opening, or for such longer period of time that Bidder may agree to in writing upon request of Owner.

7.02 Instructions to Bidders

A. Bidder accepts all of the terms and conditions of the Instructions to Bidders, including without limitation those dealing with the disposition of Bid security.

7.03 Receipt of Addenda

A. Bidder hereby acknowledges receipt of the following Addenda:

Addendum Number Addendum Date

ARTICLE 8�BIDDER�S REPRESENTATIONS AND CERTIFICATIONS

8.01 Bidder�s Representations

A. In submitting this Bid, Bidder represents the following:

1. Bidder has examined and carefully studied the Bidding Documents, including Addenda.

2. Bidder has visited the Site, conducted a thorough visual examination of the Site and adjacent areas, and become familiar with the general, local, and Site conditions that may affect cost, progress, and performance of the Work.

3. Bidder is familiar with all Laws and Regulations that may affect cost, progress, and performance of the Work.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

4. Bidder has carefully studied the reports of explorations and tests of subsurface conditions at or adjacent to the Site and the drawings of physical conditions relating to existing surface or subsurface structures at the Site that have been identified in the

Supplementary Conditions, with respect to the Technical Data in such reports and drawings.

5. Bidder has carefully studied the reports and drawings relating to Hazardous

Environmental Conditions, if any, at or adjacent to the Site that have been identified in the Supplementary Conditions, with respect to Technical Data in such reports and drawings.

6. Bidder has considered the information known to Bidder itself; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Bidding Documents; and the Technical

Data identified in the Supplementary Conditions or by definition, with respect to the effect of such information, observations, and Technical Data on (a) the cost, progress, and performance of the Work; (b) the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder, if selected as Contractor; and

(c) Bidder�s (Contractor�s) safety precautions and programs.

7. Based on the information and observations referred to in the preceding paragraph, Bidder agrees that no further examinations, investigations, explorations, tests, studies, or data are necessary for the performance of the Work at the Contract Price, within the Contract

Times, and in accordance with the other terms and conditions of the Contract.

8. Bidder is aware of the general nature of work to be performed by Owner and others at the Site that relates to the Work as indicated in the Bidding Documents.

9. Bidder has given Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder has discovered in the Bidding Documents, and of discrepancies between Site conditions and the Contract Documents, and the written resolution thereof by Engineer is acceptable to Contractor.

10. The Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performance and furnishing of the Work.

11. The submission of this Bid constitutes an incontrovertible representation by Bidder that without exception the Bid and all prices in the Bid are premised upon performing and furnishing the Work required by the Bidding Documents.

8.02 Bidder�s Certifications

A. The Bidder certifies the following:

1. This Bid is genuine and not made in the interest of or on behalf of any undisclosed individual or entity and is not submitted in conformity with any collusive agreement or rules of any group, association, organization, or corporation.

2. Bidder has not directly or indirectly induced or solicited any other Bidder to submit a false or sham Bid.

3. Bidder has not solicited or induced any individual or entity to refrain from bidding.

4. Bidder has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing for the Contract. For the purposes of this Paragraph 8.02.A:

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

a. Corrupt practice means the offering, giving, receiving, or soliciting of anything of value likely to influence the action of a public official in the bidding process.

b. Fraudulent practice means an intentional misrepresentation of facts made (a) to influence the bidding process to the detriment of Owner, (b) to establish bid prices at artificial non-competitive levels, or (c) to deprive Owner of the benefits of free and open competition.

c. Collusive practice means a scheme or arrangement between two or more Bidders, with or without the knowledge of Owner, a purpose of which is to establish bid prices at artificial, non-competitive levels.

d. Coercive practice means harming or threatening to harm, directly or indirectly, persons or their property to influence their participation in the bidding process or affect the execution of the Contract.

(Remainder of page intentionally left blank.)

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

BIDDER hereby submits this Bid as set forth above:

Bidder:

(typed or printed name of organization)

By:

(individual�s signature)

Name:

(typed or printed)

Title:

(typed or printed)

Date:

(typed or printed)

If Bidder is a corporation, a partnership, or a joint venture, attach evidence of authority to sign.

Attest:

(individual�s signature)

Name:

(typed or printed)

Title:

(typed or printed)

Date:

(typed or printed)

Address for giving notices:

Bidder�s Contact:

Name:

(typed or printed)

Title:

(typed or printed)

Phone:

Email:

Address:

Bidder�s Contractor License No.: (if applicable)

EJCDC® C-430, Bid Bond (Penal Sum Form).

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

DOCUMENT 00 43 13.11

BID BOND (PENAL SUM FORM)

Bidder Surety

Name: Name:

Address (principal place of business): Address (principal place of business):

Owner Bid

Name: Richfield City Project (name and location):

Address (principal place of business): 2026 Chip Seal

75 East Center Street, Richfield, Utah 84701

Bid Due Date: [Date]

Bond

Penal Sum:

Date of Bond:

Surety and Bidder, intending to be legally bound hereby, subject to the terms set forth in this Bid Bond, do each cause this Bid Bond to be duly executed by an authorized officer, agent, or representative.

Bidder Surety

(Full formal name of Bidder) (Full formal name of Surety) (corporate seal)

By: By:

(Signature) (Signature) (Attach Power of Attorney)

Name: Name:

(Printed or typed) (Printed or typed)

Title: Title:

Attest: Attest:

(Signature) (Signature)

Name: Name:

Title:

(Printed or typed)

Title:

(Printed or typed)

Notes: (1) Note: Addresses are to be used for giving any required notice. (2) Provide execution by any additional parties, such as joint venturers, if necessary.

EJCDC® C-430, Bid Bond (Penal Sum Form).

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

1. Bidder and Surety, jointly and severally, bind themselves, their heirs, executors, administrators, successors, and assigns to pay to Owner upon default of Bidder the penal sum set forth on the face of this Bond.

Payment of the penal sum is the extent of Bidder�s and Surety�s liability. Recovery of such penal sum under the terms of this Bond will be Owner�s sole and exclusive remedy upon default of Bidder.

2. Default of Bidder occurs upon the failure of Bidder to deliver within the time required by the Bidding

Documents (or any extension thereof agreed to in writing by Owner) the executed Agreement required by the Bidding Documents and any performance and payment bonds required by the Bidding Documents.

3. This obligation will be null and void if:

3.1. Owner accepts Bidder�s Bid and Bidder delivers within the time required by the Bidding Documents

(or any extension thereof agreed to in writing by Owner) the executed Agreement required by the

Bidding Documents and any performance and payment bonds required by the Bidding Documents, or

3.2. All Bids are rejected by Owner, or

3.3. Owner fails to issue a Notice of Award to Bidder within the time specified in the Bidding Documents

(or any extension thereof agreed to in writing by Bidder and, if applicable, consented to by Surety when required by Paragraph 5 hereof).

4. Payment under this Bond will be due and payable upon default of Bidder and within 30 calendar days after receipt by Bidder and Surety of written notice of default from Owner, which notice will be given with reasonable promptness, identifying this Bond and the Project and including a statement of the amount due.

5. Surety waives notice of any and all defenses based on or arising out of any time extension to issue Notice of Award agreed to in writing by Owner and Bidder, provided that the total time for issuing Notice of Award including extensions does not in the aggregate exceed 120 days from the Bid due date without Surety�s written consent.

6. No suit or action will be commenced under this Bond prior to 30 calendar days after the notice of default required in Paragraph 4 above is received by Bidder and Surety, and in no case later than one year after the Bid due date.

7. Any suit or action under this Bond will be commenced only in a court of competent jurisdiction located in the state in which the Project is located.

8. Notices required hereunder must be in writing and sent to Bidder and Surety at their respective addresses shown on the face of this Bond. Such notices may be sent by personal delivery, commercial courier, or by

United States Postal Service registered or certified mail, return receipt requested, postage pre-paid, and will be deemed to be effective upon receipt by the party concerned.

9. Surety shall cause to be attached to this Bond a current and effective Power of Attorney evidencing the authority of the officer, agent, or representative who executed this Bond on behalf of Surety to execute, seal, and deliver such Bond and bind the Surety thereby.

10. This Bond is intended to conform to all applicable statutory requirements. Any applicable requirement of any applicable statute that has been omitted from this Bond will be deemed to be included herein as if set forth at length.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .