This is a Required Bid Schedule document for the City of Tallahassee's Invitation for Bids (IFB 102-25-RM) for Dog House Pump Station Replacements covering four pump stations (PS-25, PS-49, PS-59, and PS-85). The base bid includes the replacement of two existing Smith & Loveless wet well-mounted pump stations (PS-85 and PS-49) with new stations, while Bid Alternate #1 adds PS-59 and Bid Alternate #2 adds both PS-59 and PS-25 for a total of four stations. The project scope encompasses removal and replacement of gravity inflow sewer mains, bypass pumping assemblies, above-ground pump stations, rehabilitation of existing wet wells, installation of new kingpin manholes, a new generator at PS-59, electrical site work, fencing modifications, concrete and pavement removal and replacement, tree and landscaping work, and site restoration. A mandatory pre-bid meeting was scheduled for February 18, 2026, at 2:00 PM EST via Microsoft Teams. The award will be based on the lowest responsive base bid, with the City reserving the right to award any combination of base bid and alternates in its best interest.
The bid schedule is organized by pay item with specified units and quantities for each station. Key line items include mobilization, temporary traffic control, temporary erosion and sedimentation control, tree removal and protection, concrete work, sod installation, subgrade stabilization, sanitary sewer pump station installation (designated as lump-sum items including all mechanical, electrical, and site improvements), plug valves, flow meters, gravity sewer mains of varying sizes and depths, fall protection equipment, demolition of existing equipment, electrical services, wet well lining, emergency bypass sewer manholes, and utility as-built preparation. Bidders must complete separate pricing schedules for the base bid covering PS-85 and PS-49, Alternate #1 for PS-59, and Alternate #2 for PS-25, with totals calculated for each section and a comprehensive base bid total provided.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
IFB: 102-25-RM Dog House Pump Station Replacments
(PS-25, 49, 59 85)
Bidders Company Name: Date:
Pay Item Number Pay Item Description Units Bid Quantity Unit Cost Total Cost
GENERAL CONTRACT ITEM
GCI-00 Mobilization LS 1 GCI-10 Temporary Traffic Control LS 1 GCI-20 Work Zone Sign DY 90 GCI-30 Temporary Erosion, Sedimentation, and Water Pollution Control LS 1 GCI-40 Tree Removal LS 1 GCI-50 Selective Clearing and Grubbing LS 1 GCI-60 Tree Protection LF 40
Sub-total
MISCELLANEOUS SURFACE RESTORATION
MSC-01 Demo MES's and CMP LS 1 430-175-118 Culvert Pipe 18" Aluminum CMP LF 24 430-984-125 M.E.S. 18" (Cast in place) EA 2 MSC-02 Demo exist concrete drive SY 20 MSR-01 Concrete, 6" Thick (Conc. Drive and wet well pad) SY 35 MSR-11 Solid Sod (Centipede) SY 50 MSR-30 Site Grading LS 1 RSR-00 Subgrade Stabilization (LBR 40), 12" SY 35
Sub-total
SANITARY SEWER PUMP STATION
SPS-02 Sanitary Sewer Pump Station* LS 1 CIC-08 Cut in Connection to Exist. 8" Force Main** EA 1 SPV-10 10" Plug Valve (rubber lined) EA 1 SMS-6 6" Flow Meter EA 1 GSM-02-1006-PVC Gravity Sewer Main, 10”, 0-6.0 Ft. Depth, PVC (DR26) LF 8 SI-1 Miller DuraHoist Fall Protection Sleeve DH-9SS EA 1 SI-2 Demo Existing Pump Station equip (incl. concrete, fence, piping and valves, all other) LS 1 SI-3 Electrical Services and other Electrical Site work LS 1 SI-4 Wet Well Lining per COT Spec's EA 1
Sub-total
PRECAST CONCRETE
SMH-0506 Emergency By-Pass Sewer Manhole 5' Dia., 0-6' depth (PS # 85) EA 1
MSC-03 Utility As-Built Preparation LS 1
PS 85 Total :
Pay Item Number Pay Item Description Units Bid Quantity Unit Cost Total Cost
GENERAL CONTRACT ITEM
GCI-00 Mobilization LS 1 GCI-10 Temporary Traffic Control LS 1 GCI-20 Additional Variable Message Board, Two (2) Boards DY 90 GCI-30 Temporary Erosion, Sedimentation, and Water Pollution Control LS 1
Sub-total
MISCELLANEOUS SURFACE RESTORATION
MSR-01 Concrete, 6" Thick (Conc. Drive and wet well pad, incl wwm) SY 28 MSR-11 Solid Sod (Centipede) SY 8 RSR-00 Subgrade Stabilization (LBR 40), 12" SY 28
Sub-total
SANITARY SEWER PUMP STATION
SPS-01 Sanitary Sewer Pump Station* LS 1 CIC-06 Cut in Connection to Exist. 6" Force Main** EA 1 SPV-08 8" Plug Valve (rubber lined) EA 1 SMS-6 6" Flow Meter EA 1 GSM-02-0808-PVC Gravity Sewer Main, 8”, 6.1-10.0 Ft. Depth, PVC (DR26) LF 4 SI-1 Miller DuraHoist Fall Protection Sleeve DH-9SS EA 1
SI-2 Demo Existing Pump Station equip (incl. concrete, fence & gates, piping and valves, all other) LS 1
SI-3 Electrical Services and other Electrical Site work LS 1 SI-4 Wet Well Lining per COT Spec's EA 1
Pump Station 85
Pump Station 49
Sub-total
MISCELLANEOUS ITEMS
MISC-01 Utility As-Built Preparation LS 1
PS-49 Total:
Base Bid Total (PS-85 & 49):
Pay Item Number Pay Item Description Units Bid Quantity Unit Cost Total Cost
GENERAL CONTRACT ITEM
GCI-00 Mobilization LS 1 GCI-10 Temporary Traffic Control LS 1 GCI-20 Additional Variable Message Board, Two (2) Boards DY 180 GCI-30 Temporary Erosion, Sedimentation, and Water Pollution Control LS 1 GCI-40 Tree Protection (& Arboricultural Mitigation) LS 1 GCI-50 Selective Clearing and Grubbing (one tree removed) LS 1
Sub-total
MISCELLANEOUS SURFACE RESTORATION
MSR-01 Concrete, 6" Thick (Conc. Drive and wet well pad, incl wwm) SY 31 MSR-02 Concrete 12" Thick (Generator Pad) SY 10 MSR-11 Solid Sod (Centipede) SY 8 RSR-00 Subgrade Stabilization (LBR 40), 12" SY 41
Sub-total
SANITARY SEWER PUMP STATION
SPS-02 Sanitary Sewer Pump Station* LS 1 CIC-08 Cut in Connection to Exist. 8" Force Main** EA 1 SPV-10 10" Plug Valve (rubber lined) EA 1 SMS-6 6" Flow Meter EA 1 GSM-02-1010-PVC Gravity Sewer Main, 10”, 10.1-15.0 Ft. Depth, PVC (DR26) LF 3 SI-1 Miller DuraHoist Fall Protection Sleeve DH-9SS EA 1
SI-2 Demo Existing Pump Station equip (incl. concrete, fence & gates, piping and valves, all other) LS 1
SI-3 Electrical Services and other Electrical Site work LS 1 SI-4 60KW Generator (Installed) LS 1
Sub-total
PRECAST CONCRETE
SMH-0506 Emergency By-Pass Sewer Manhole 5' Dia., 10-12' depth EA 1 Sub-total
MISCELLANEOUS ITEMS
MISC-01 Utility As-Built Preparation LS 1
Add Alternate #1 - PS-59 Total:
Pay Item Number Pay Item Description Units Bid Quantity Unit Cost Total Cost
GENERAL CONTRACT ITEM
GCI-00 Mobilization LS 1 GCI-10 Temporary Traffic Control LS 1 GCI-20 Work Zone Sign DY 90 GCI-30 Temporary Erosion, Sedimentation, and Water Pollution Control LS 1
Sub-total
MISCELLANEOUS SURFACE RESTORATION
MSR-01 Concrete, 6" Thick (Conc. Drive and wet well pad, incl wwm) SY 30 MSR-11 Solid Sod (Centipede) SY 32 RSR-00 Subgrade Stabilization (LBR 40), 12" (2 Stations) SY 30
Sub-total
SANITARY SEWER PUMP STATION
SPS-02 Sanitary Sewer Pump Station* LS 1 CIC-06 Cut in Connection to Exist. 6" Force Main** EA 1 SPV-08 8" Plug Valve (ps #25, rubber lined) EA 1 SMS-6 6" Flow Meter EA 1 GSM-02-0808-PVC Gravity Sewer Main, 8”, 6.1-10.0 Ft. Depth, PVC (DR26) LF 2 SI-1 Miller DuraHoist Fall Protection Sleeve DH-9SS EA 1 SI-2 Demo Existing Pump Station equip (incl. concrete, fence, piping and valves, all other) LS 1 SI-3 Electrical Services and other Electrical Site work LS 1
Pump Station 25 - Add Alternate #2
Pump Station 59 - Add Alternate #1
Sub-total
MISCELLANEOUS ITEMS
MSC-03 Utility As-Built Preparation LS 1
Add Alternate #2 Total:
Base Bid (Stations PS-85 & 49) Base Bid Total:
Add Alternate #1 (PS-59) Bid Alternate 1 Total:
Add Alternate #2 (PS-25) Bid Alternate #2 Total:
*The lump sum price for the New Pump Station pay item shall be full compensation for all items required to furnish and install all pump station mechanical, electrical and site improvements including but not limited to the construction of the pump station, all valves and piping, manholes, fittings and appurtenances (unless otherwise listed separately), concrete driveway, fencing and gates, sodding, landscaping, erosion control, water service line extension, rehabilitation and modfications to existing wet well, electrical panel/control shelter, construction layout, maintenance of traffic, removal and disposal of items or equipment, and any other items needed to complete the project, unless otherwise listed as a bid item. See City of Tallahassee Pay Item Manual for Water and Sewer Construction for full descriptions of pay items. The installation of temporary plugs for by-pass pumping shall be included in this cost of the cut-in-connection.
**The installation of temporary plugs & dewatering of the forcemain is included in the cost of the cut-in-connection.
The award will be based on the lowest responsive Base Bid. The City resereves the right to award any combination of Base Bid and Alternate that is in the best interset of the City.