Grady Littlejohn Park Improvements - Technical Specifications Summary

This technical specifications document pertains to the City of McKinney, Texas' Grady Littlejohn Park Improvements project, a comprehensive site renovation and building construction initiative. The project encompasses extensive site work including demolition, grading, erosion control, utility installation (water lines, sanitary sewers, electrical service), landscaping with irrigation systems, hardscape construction (concrete paving, sidewalks), structural steel framing, metal fabrications, roofing, and building systems. The scope includes Division 1 General Requirements through Division 16 Electrical work, with detailed specifications for materials, installation methods, quality assurance standards, and testing requirements. The specifications reference numerous ASTM standards, ACI requirements, NFPA codes, and manufacturer-specific guidelines for compliance. Key site elements include site furnishings, tree preservation and pruning, new plantings with warranty provisions, LED lighting fixtures, standing seam metal roofing, hollow metal doors and frames, and a complete electrical distribution system with panelboards and controls.

The specifications establish rigorous quality assurance requirements including manufacturer qualifications, third-party testing and inspection services, pre-installation conferences, mock-ups for approval, and comprehensive field quality control testing. Materials must be new, first-grade quality delivered in original packaging with certifications of compliance. Installation work requires experienced contractors with minimum five to ten years of documented experience in their respective trades, many requiring manufacturer certification. The document mandates compliance with local building codes, the National Electrical Code, OSHA requirements, and governs provisions for thermal movement, water infiltration prevention, and fire-resistance ratings. Contractor responsibilities include utility coordination, traffic control, temporary facilities, environmental protection, and extensive documentation through project record drawings and operation and maintenance manuals. Warranty periods range from one to twenty years depending on product type, with plant material guarantees extending twenty-four months after final acceptance.

View the file

Other files

File Type Posted
5-02 Plan Set.pdf PDF
7-01 CSP Specifications.pdf PDF
6-04 Competitive Sealed Proposal.pdf PDF
2-05 Required Forms.pdf PDF
8-08 Geotechnical Report.pdf PDF
4-07 Construction Agreement and Bonds.pdf PDF
3-06 Bid Bond.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GRADY LITTLEJOHN

TABLE OF CONTENTS

City of McKinney Bid Specifications Section I……………………………………………….……… 16 pages City of McKinney Bid Specifications Section II .……………………………………….………….... 50 pages

SITE RENOVATION SPECIFICATIONS.……………………………………….…………... 195 pages

DIVISIONS

DIVISION NO. 1 - GENERAL CONDITIONS

Section 01010 - Summary of Work……………………………………………………………………. 3 pages Section 01050 - Field Engineering …………………………………………………………….……… 2 pages Section 01090 - References......................................................................................................... 2 pages Section 01230 - Alternates......................................................................................................... 1 page Section 01310 - Construction Schedules .................................................................................... 2 pages Section 01340 - Shop Drawings, Product Data and Samples...................................................... 3 pages Section 01370 - Schedule of Values ........................................................................................... 1 page Section 01410 - Testing Laboratory Services ............................................................................. 8 pages Section 01510 - Temporary Facilities........................................................................................... 2 pages Section 01570 - Traffic Regulations ............................................................................................ 1 page Section 01630 - Substitutions and Project Options...................................................................... 2 pages Section 01700 - Contract Closeout ............................................................................................. 1 page Section 01710 - Cleaning ............................................................................................................ 2 pages Section 01730 - Operating and Maintenance Date ..................................................................... 3 pages Section 01780 - Project Record Documents ............................................................................... 3 pages

DIVISION NO. 2 - SITE WORK

Section 02050 - Demolition ......................................................................................................... 2 pages Section 02101 - Site Clearing & Preparation ...............................................................................2 pages Section 02112 - Existing Tree Pruning .........................................................................................5 pages Section 02140 - Site Underdrains …….........................................................................................2 pages Section 02200 - Earthwork……….................................................................................................3 pages Section 02210 - Earthwork for Landscape Areas .........................................................................3 pages Section 02221 - Trenching, Backfilling, & Compaction................................................................ 6 pages Section 02245 - Finish Grading for Landscape Areas ................................................................. 2 pages Section 02372 - Drilled Piers…………….………………………………………………………………5 pages Section 02514 - Non-Vehicular Concrete Paving and Sidewalks................................................. 3 pages Section 02550 - Site Utilities………………………. ..................................................................... 10 pages Section 02810 - Landscape Irrigation System................................................................................9 pages Section 02832 - Ornamental Fencing.............................................................................................5 pages Section 02870 - Site Furnishing .....................................................................................................2 pages Section 02900 - Landscaping…………………………..………………………………….……….…. 14 pages Section 02920 - Sodding .............................................................................................................. ..5 pages Section 02940 – Landscape Maintenance (Alternate)……..………………………………….……… 9 pages

DIVISION NO. 3 - CONCRETE

Section 03100 - Concrete Formwork .......................................................................................... 3 pages Section 03200 - Concrete Reinforcement ................................................................................... 3 pages Section 03300 - Cast-in-Place Concrete....................................................................................... 6 pages

DIVISION NO. 4 - MASONRY

Section 04300 – Stone Masonry ................................................................................................. 2 pages

DIVISION NO. 5 – METALS

Section 05120 – Structural Steel ................................................................................................ 4 pages Section 05500 – Metal Fabrications ..............................................................................................5 pages

DIVISION NO. 6 (not used)

DIVISION NO. 7 - THERMAL AND MOISTURE PROTECTION

Section 07920 - Sealants ............................................................................................................. 7 pages

DIVISION NO. 8 (not used)

DIVISION NO. 9 – FINISHES

Section 09900 - Painting and Staining.......................................................................................... 3 pages

DIVISION NO. 10 THROUGH 16 (not used)

Seal Date:

11/14/25

SITE RENOVATIONS - ELECTRICAL SPECIFICATIONS ……………………….… 39 pages

DIVISIONS

DIVISION NO. 1 THROUGH 15 (not used)

DIVISION NO. 16 - ELECTRICAL

Section 16010 – General Requirements ...................................................................................... 9 pages Section 16111 – Raceways and Fittings ........................................................................................ 3 pages Section 16112 – Surface Raceways ............................................................................................. 2 pages Section 16120 - Wire and Cable ……............................................................................................ 3 pages Section 16130 - Boxes ………………............................................................................................. 1 pages Section 16141 – Wiring Devices ……........................................................................................... .. 3 pages Section 16160 - Cabinet and Enclosures ....................................................................................... 2 pages Section 16195 – Electrical Identification.......................................................................................... 2 pages Section 16450 – Grounding and Bonding ....................................................................................... 2 pages Section 16461 – Transformers ……….......................................................................................... .. 4 pages Section 16471 – Panel Boards ………........................................................................................... 4 pages Section 16485 - Contractors ………….......................................................................................... .. 2 pages Section 16491 - Disconnect Switches............................................................................................. 2 pages

10/29/2025

BUILDING - ARCHITECTURAL SPECIFICATIONS.……………………….…………... 100 pages

DIVISIONS

DIVISION NO. 1 AND 2 (not used)

DIVISION NO. 3 - CONCRETE

Section 03350 - Sealed Concrete................................................................................................... 2 pages

DIVISION NO. 4

04720-Cast Stone …………………………………………………………………………………………...7 pages

DIVISION NO. 5 (not used)

DIVISION NO. 6 - WOOD, PLASTICS AND COMPOSITES

Section 06100 - Rough Carpentry.................................................................................................... 6 pages Section 06201 - Tongue & Groove.................................................................................................... 3 pages

DIVISION NO. 7 - THERMAL AND MOISTURE PROTECTION

Section 07210 - Thermal Insulation................................................................................................. 3 pages Section 07214 - Spray Foam Insulation ....................................................................................... 4 pages Section 07256 - Fluid Applied Vapor Barrier .................................................................................. 8 pages Section 07474 - Fiber-Cement Panels………………………………………………………………… 7 pages Section 07610 - Standing Seam Metal Roofing…………………………………………………………. 5 pages Section 07620 - Sheet Metal Flashing and Trim………………………………………………………….9 pages

DIVISION NO. 8

Section 08113 - Hollow Metal Doors and Frames ……………………………………………………… 9 pages Section 08331 - Overhead Insulating Rolling Doors…………………………………………………… 5 pages Section 08332 - Overhead Rolling Counter Doors………………………………………………………4 pages Section 08710 - Door Hardware…………………………………………………………………………. 6 pages Section 09770 - Fiberglass Reinforced Panels (FRP)………………………………………………… 6 pages

DIVISION NO. 9 (not used)

DIVISION NO. 10 - SPECIALTIES

Section 10211 - Toilet Partitions …………………………………………………………………………. 5 pages Section 10430 - Exterior Signage………………………………………………………………………… 3 pages Section 10440 - Interior Signage …………………………………………………………………………. 3 pages Section 10800 - Toilet Accessories………………………………………………………………………. 5 pages

DIVISION NO. 11 THROUGH 16 (not used)

AT

T S

XETE FO

SA

K .R

EG

IS

TE

RED ARCHITECTKO

BEY SEAL

E

21 1 0 0

September 9, 2025

BUILDING - STRUCTURAL SPECIFICATIONS.……………………….…………………… 65 pages

DIVISIONS

DIVISION NO. 1 - GENERAL CONDITIONS

Section 01400 – Quality Requirements ......................................................................................... 7 pages

DIVISION NO. 2 (not used)

DIVISION NO. 3 - CONCRETE

Section 03300 – Cast-In-Place Concrete ....................................................................................... 24 pages

DIVISION NO. 4 - MASONRY

Section 04200 – Concrete Masonry Units .................................................................................... 17 pages

DIVISION NO. 5 - METALS

Section 05120 – Structural Steel Framing .................................................................................. 10 pages Section 05310 – Steel Decking .................................................................................................. 6 pages

DIVISION NO. 6 THROUGH 16 (not used)

SEPTEMBER 9, 2025

SUMMARY OF WORK (01010)

DIVISION NO. 1

SECTION 01010

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and General Provisions of Contract, including General and Special Conditions and all applicable specification sections, apply to this section.

1.2 DESCRIPTION OF WORK INCLUDED:

A. General: The Scope of Work for this Project shall consist of providing all supplies, support services, data, labor, tools, materials, equipment, supervision, construction, and all else required to complete the improvements at the existing Towne Lake Park, with the City of McKinney, Texas.

B. Project Scope: The Base Bid Work shall include, but not be limited to, the following major items, to the extent specified and indicated:

1. Provide administration and construction support services to complete the work including construction staking and surveying.

2. Apply for and procure all applicable permits from the applicable governing agencies.

This project falls within the City of McKinney, Collin County, Texas.

3. Procure necessary permits for personnel, equipment, and construction operations.

4. Coordinate and schedule work provided by others.

5. Register all vendors, subcontractors who will be on the job.

6. Video tape existing site conditions.

7. Establish traffic control on or near project site.

8. Establish temporary utilities (water); Note – contractor pays for water.

9. Utilities line locate and staking (coordinate with Engineering staff).

10. Coordinate with testing services (paid by City of McKinney). City will contract with labs.

11. Removal/Preservation of existing site elements

12. Construction of new vehicular and pedestrian paving

13. New Up, down, and specialty lighting through the limit of work.

14 New Signage

15. Installation of Site Furnishings

16. New landscaping.

17. New electrical services.

18. New irrigation system.

19. Provide and install utilities and drainage systems as per drawings,

20. Provide grading repair and grassing to all areas damaged by construction operations.

21. Clean-up.

22. Punch list to Substantial Completion.

23. Final walk-through.

24. Punch list and close-out to Final Acceptance.

25. Coordination with local municipality and other governing agencies as required.

26. Coordination with other contractors as required.

27. Coordination as required regarding electrical service to controllers.

SITE RENOVATIONS SPECIFICATIONS

1.3 DRAWINGS

A. Refer to Index of Drawings within the set.

1.4 PROJECT MANUAL

A. Bidding and Contract Requirements; General Requirements - Division 1 and Technical

Specifications, Divisions 2 through 16 as listed in Table of Contents, dated April, 2016.

1.5 UNIT PRICES

A. Refer to Bid Form in Section I for Unit Prices.

1.6 QUALITY ASSURANCE

A. The work shall comply with the requirements of the Contract Documents including cited national specifications and standards; state and local government authority codes and standards.

B. In case of conflicts between cited national and local standards, local requirements shall govern unless otherwise directed in writing. All conflicts shall be brought to the attention of Owner's Representative in writing.

1.7 OTHER REQUIREMENTS

A. Any affected utility owners shall be notified not less than 7 days prior to starting work in an area in which a utility may be located. Notices shall be in writing. Any affected utility owner and Owner's Representative shall be notified 72 hours prior to commencing construction operations.

B. The Contractor shall prosecute the Work as indicated, in accordance with the Contract

Documents, and in a timely manner so as to ensure coordination of all parts of the work with work of other parties under adjoining and interfacing contracts, including governmental bodies and utility companies.

C. Proposals for scheduling work at times other than the normal work period of a calendar day shall be submitted to Owner's Representative not less than 48 hours in advance of those times. Such proposals shall outline all special precautions to be taken to control the hazards presented by prosecuting the work at times other than the normal work period of a calendar day. The proposal shall include supplementary lighting of work areas, availability of medical facilities, security precautions and all other precautions necessary.

D. Construction equipment and vehicles which exceed the weight, size and noise limitation of the authorities having jurisdiction shall not be operated outside the construction limits of the site.

1.8 INTERPRETATION

A. Overlapping and Conflicting Requirements: Where compliance with two or more industry standards or sets of requirements is specified or indicated, and overlapping of those different standards or requirements establishes different or conflicting minimums or levels of quality, the most stringent requirement is intended and will be enforced by Owner's Representative and Owner, unless specific language in the Contract Documents clearly indicates that a less stringent requirement is to be fulfilled. Refer apparently-equal-but-different requirements, and uncertainties as to which level of quality is more stringent, to Owner's Representative and Owner for a written decision before proceeding with the work in question.

B. Minimum Quality/Quantity: In every instance, the quality level or quantity indicated or specified is intended to be the minimum for the work to be performed or provided. Except as otherwise indicated, the actual work may either comply exactly with that minimum (within specified tolerances), or may exceed that minimum within reasonable limits. In complying with these requirements, indicated numeric values are either minimums or maximums as noted, or as appropriate for context of the requirements. Refer instances of uncertainty to Owner's Representative and Owner for a written decision before proceeding with the work in question.

END OF SECTION

FIELD ENGINEERING (01050)

SECTION 01050

1.1 REQUIREMENTS INCLUDED

A. Field and construction staking (provided by Contractor).

B. Coordinate and schedule field and construction staking. Communicate to surveyor needed reference points, control points, etc.

C. Civil, structural or other professional engineering services specified, or required to execute Contractor's construction methods.

1.2 RELATED REQUIREMENTS

A. Conditions of the Contract.

1.3 QUALIFICATIONS OF SURVEYOR OR ENGINEER (if required)

A. Qualified surveyor or engineer acceptable to City of McKinney. Provided and paid for by

Contractor.

1.4 SURVEY REFERENCE POINTS

A. Existing basic horizontal and vertical control points for the Project are those designated on the Drawings.

B. Locate and protect control points prior to starting site work, and preserve all permanent reference points during construction.

1. Make no changes or relocations without prior written notice to the Landscape

Architect.

2. Report to the Landscape Architect when any reference point is lost or destroyed, or requires relocation because of necessary changes in grades or locations.

3. Require surveyor to replace Project control points which may be lost or destroyed.

1.5 PROJECT SURVEY REQUIREMENTS

A. Establish a minimum of two permanent bench marks on site, referenced to data established by survey control points.

1. Record locations, with horizontal and vertical data, on Project Record

Documents.

B. Establish lines and levels, locate and lay out, by instrumentation and similar appropriate means:

1. Stakes for grading, fill and topsoil placement.

C. From time to time, verify layouts by same methods.

FIELD ENGINEERING (01050)

1.6 RECORDS (provided by Contractor)

A. Maintain a complete, accurate log of all control and survey work as it progresses.

REFERENCES (01090)

SECTION 01090

1.1 SUMMARY

A. This Section identifies abbreviations and acronyms and includes definitions of words and phrases used in Contract Documents, definitions of standard Specification language, and explanation of Specification format and content.

1.2 QUALITY ASSURANCE

A. Application: When a standard is specified by reference, comply with requirements and recommendations stated in that standard, except when requirements are modified by the Contract Documents, or applicable codes establish stricter standards.

B. Publication Date: The publication in effect on the date of issue of Contract Documents, except when a specific publication date is specified.

1.3 ABBREVIATIONS AND NAMES OF ORGANIZATIONS

A. Obtain copies of referenced standards direct from publication source, when needed for proper performance of Work, or when required for submittal by Contract Documents. For abbreviations not listed, and for addresses and phone numbers, refer to the "Encyclopedia of Associations," published by Gale Research Co., Inc., available in most public libraries.

AA Aluminum Association AABC Associated Air Balance Council AAMA Architectural Aluminum Manufacturers Association AASHTO American Association of State Highway and Transportation Officials ACI American Concrete Institute ADC Air Diffusion Council AGC Associated General Contractors of America AIA American Institute of Architects AISC American Institute of Steel Construction AISI American Iron and Steel Institute AMCA Air Movement and Control Association ANSI American National Standards Institute ARI Air Conditioning and Refrigeration Institute

ASHRAE American Society of Heating, Refrigerating and Air Conditioning Engineers

ASLA American Society of Landscape Architects ASME American Society of Mechanical Engineers ASPA American Sod Producers Association ASTM American Society for Testing and Materials AWI Architectural Woodwork Institute AWPA American Wood-Preservers' Association AWS American Welding Society AWWA American Water Works Association CDA Copper Development Association CRSI Concrete Reinforcing Steel Institute CSI Construction Specifications Institute

REFERENCES (01090)

EJMA Expansion Joint Manufacturer's Association FGMA Flat Glass Marketing Association FM Factory Mutual System FS Federal Specification GA Gypsum Association IEEE Institute of Electrical and Electronics Engineers IMIAC International Masonry Industry-All Weather Council ISA International Society of Arboriculture MFMA Maple Flooring Manufacturers Association MIL Military Specification ML/SFA Metal Lath/Steel Framing Association NAAMM National Association of Architectural Metal Manufacturers NCMA National Concrete Masonry Association NCTCOG North Central Texas Council of Governments NEBB National Environmental Balancing Bureau NEMA National Electrical Manufacturers Association NFPA National Fire Protection Association NRCA National Roofing Contractors Association NSWMA National Solid Waste Management Association NTMA National Terrazzo and Mosaic Association NWMA National Woodwork Manufacturers Association PCA Portland Cement Association PCI Prestressed Concrete Institute PS Product Standard SCPI Structural Clay Products Institute SDI Steel Deck Institute SDI Steel Door Institute SIGMA Sealed Insulating Glass Manufacturers Association SJI Steel Joint Institute SMACNA Sheet Metal and Air Conditioning Contractors' National Association SPRI Single Ply Roofing Institute SSPC Steel Structures Painting Council TAS Technical Aid Series TCA Tile Council of America, Inc.

UL Underwriters' Laboratories, Inc.

WCLIB West Coast Lumber Inspection Bureau

1.4 DEFINITIONS

A. Indicated: The work "indicated" refers to graphic representations, notes or schedules on

Drawings, Paragraphs or schedules in Specifications, and similar requirements in Contract Documents. Terms such as "shown," "noted," "scheduled," and "specified" are used to help locate a reference. No limitation on location is intended except as specifically noted.

B. Directed: Terms such as "directed," "requested," "authorized," "selected," "approved,"

"required," and "permitted" are hereby defined as "directed by Landscape Architect," "requested by Landscape Architect," "authorized by Landscape Architect," etc. No implied meaning shall be interpreted to extend the Landscape Architect's responsibility into the Contractor's area of construction supervision.

ALTERNATES (01230)

SECTION 01230

1.1 SCOPE

A. Quote as additions or deductions to the Base Bid, Alternates to the various Sections of the Work which may be included in the Contract Price.

B. Price all Alternates complete, furnished and installed including taxes, insurances, overhead and profit.

C. Include in the price quoted for each Alternate any changes required in other Sections as a result of the Alternate.

D. Refer to the respective Section for complete Specifications of each Alternate.

1.2 ALTERNATES

A. Alternate No. 1: Limestone Block Bench Type A as noted on L1.00.

B. Alternate No. 2: Limestone Block Bench Type B as noted on L1.00.

CONSTRUCTION SCHEDULES (01310)

SECTION 01310

A. Promptly after award of the Contract, prepare and submit to the Owner’s Project Manager estimated construction progress schedules for the Work, such subschedules of related activities which are essential to its progress.

B. Submit revised progress schedules monthly to Owner’s Project Manager and Landscape

Architect.

1.2 RELATED REQUIREMENTS

A. Conditions of the Contract.

B. Section 01340: Shop Drawings, Product Data and Samples.

1.3 FORM OF SCHEDULES

A. Prepare schedules in the form of a PERT chart.

1. Provide separate horizontal bar for each trade or operation.

2. Horizontal Time Scale: Identify the first work day of each week.

3. Scale and Spacing: To allow space for notations and future revisions.

B. Format of Listings: The chronological order of the start of each item of work.

C. Identification of Listings: By major specification section numbers.

1.4 CONTENT OF SCHEDULES

A. Construction Progress Schedule:

1. Show the complete sequence of construction by activity.

2. Show the dates for the beginning, and completion of, each major element of construction, including permits, fees, & inspections.

3. Show projected percentage of completion for each item, as of the first day of each month.

B. Submittals Schedule for Shop Drawings, Product Data and Samples. Show:

1. The dates for Contractor's submittals.

2. The dates approved submittals will be required from the Landscape Architect.

Allow a minimum of 12 working days in the Landscape Architect's office.

C. Provide subschedules to define critical portions of prime schedules.

1.5 PROGRESS REVISIONS

A. Indicate progress of each activity to date of submission.

CONSTRUCTION SCHEDULES (01310)

B. Show changes occurring since previous submission of schedule:

1. Major changes in scope.

2. Activities modified since previous submission.

3. Revised projections of progress and completion.

4. Other identifiable changes.

C. Provide a narrative report as needed to define:

1. Problem areas, anticipate delays, and the impact on the schedule.

2. Corrective action recommended, and its effect.

3. The effect of changes on schedules of other prime contractors.

1.6 SUBMISSIONS

A. Submit initial schedules within 15 days after award of Contract.

1. Landscape Architect will review schedules and return review copy within 10 days after receipt.

2. If required, resubmit within 7 days after return of review copy.

B. Submit revised progress schedules with each application for payment.

C. Submit the number of opaque reproductions which the Contractor requires, plus one copy which will be retained by the Landscape Architect.

1.7 DISTRIBUTION

A. Distribute copies of the reviewed schedules to:

1. Job site file.

2. Subcontractors.

3. Other concerned parties.

B. Instruct recipients to report promptly to the Contractor, in writing, any problems anticipated by the projections shown in the schedules.

SHOP DRAWINGS, PRODUCT DATA AND SAMPLES (01340)

SECTION 01340

A. Submit Shop Drawings, Product Data and Samples required by Contract Documents.

Included are (Reference Plans):

• Electrical & Fixtures (Cut Sheets)

• Site Furnishings (Shop Drawings & Cut Sheets)

• Signage (Shop Drawings)

• Specialty Concrete (Cut Sheets & Mock Up)

• Irrigation (Cut Sheets)

1.2 RELATED REQUIREMENTS

A. Conditions of the Contract: Definitions, and additional responsibilities of parties.

B. Designate in the construction schedule, or in a separate coordinated schedule, the dates for submission and the dates that reviewed Shop Drawings, Product Data and Samples will be needed.

1.3 SHOP DRAWINGS

A. Present drawings in a clear and thorough manner.

1. Identify details by reference to sheet, detail, or schedule shown on Contract

Drawings.

1.4 PRODUCT DATA

A. Preparation:

1. Clearly mark each copy to identify pertinent products or models.

2. Show performance characteristics and capacities.

3. Show dimensions and clearances required.

4. Show wiring diagrams and controls.

B. Manufacturer's Standard Schematic Drawings and Diagrams:

1. Modify drawings and diagrams to delete information which is not applicable to the work.

2. Supplement standard information to provide information specifically applicable to the work.

1.5 SAMPLES

A. Provide office samples of sufficient size and quantity to clearly illustrate:

1. Functional characteristics of the product, with integrally related parts and attachment devices.

2. Full range of color, texture and pattern.

B. Field Samples and Mock-ups:

1. Erect, at the Project site, at a location acceptable to the Owner’s Representative.

2. Size or Area: That specified in the respective specification section.

3. Fabricate each sample and mock-up complete and finished.

4. Remove mock-ups at conclusion of work or when acceptable to the Owner’s

Representative.

1.6 SUBMISSION REQUIREMENTS

A. Make submittals promptly in accordance with approved schedule, and in such sequence as to cause no delay in the work or in the work of any other contractor.

B. Submit Shop Drawings, Product Data and Samples for structural, mechanical and electrical items to the Owner’s Representative with a copy of the transmittal sent to the Landscape Architect.

C. Number of Submittals Required:

1. Shop Drawings: Submit two prints of each drawing.

2. Product Data: Submit six copies of product data.

3. Samples: Submit the number stated in each specification section, minimum of two samples for each item.

D. Submittals Shall Contain:

1. The date of submission and the dates of any previous submissions.

2. The Project title and number.

3. Contract identification.

4. The Names of:

a. Contractor

b. Supplier

c. Manufacturer

5. Identification of the product, with the specification section number.

6. Field dimensions, clearly identified as such.

7. Relation to adjacent or critical features of the work or materials.

8. Applicable standards, such as ASTM or Federal Specification numbers.

9. Identification of deviations from Contract Documents.

10. Identification of revisions on resubmittals.

11. A 3" x 3" blank space for Landscape Architect's stamp and signature.

12. Contractor's stamp, initialed or signed, certifying to review of submittal, verification of products, field measurements and field construction criteria, and coordination of the information within the submittal with requirements of the work and of Contract Documents.

1.7 RESUBMISSION REQUIREMENTS

A. Make any corrections or changes in the submittals required by the Landscape Architect and resubmit until approved.

B. Shop Drawings and Product Data:

1. Revise initial drawings or data, and resubmit as specified for the initial submittal.

2. Indicate any changes which have been made other than those requested by the

Landscape Architect.

C. Samples: Submit new samples as required for initial submittal.

1.8 DISTRIBUTION

A. Distribute reproductions of Shop Drawings and copies of Product Data which have been reviewed by the Landscape Architect and do not require revisions.

1. Owner

2. Job site file.

2. Record Documents file.

3. Other affected contractors.

4. Subcontractors.

5. Supplier or fabricator.

B. Distribute samples which have been approved by the Landscape Architect as directed by the Landscape Architect.

1.9 LANDSCAPE ARCHITECT DUTIES

A. Review submittals with reasonable promptness and in accordance with schedule.

B. Affix stamp and initials or signature, and indicate requirements for revisions and resubmittal, if any.

C. Return submittals to the Contractor for distribution, or for resubmission.

SCHEDULE OF VALUES (01370)

SECTION 01370

A. Submit to the Owner’s Project Manager a Schedule of Values at least 20 days prior to submitting the first Application for Payment.

1.2 RELATED REQUIREMENTS

A. Conditions of the Contract.

1.3 FORM AND CONTENT OF SCHEDULE OF VALUES

A. Schedule shall list the installed value of the component parts of the Work in sufficient detail to serve as a basis for computing values for progress payments during construction. Contractor to submit Schedule of Values within two weeks after execution of contract for Owner and Landscape Architect review and approval.

B. Identify schedule with:

1. Title of Project and location.

2. City of McKinney project number.

3. Landscape Architect

4. Name and address of Contractor.

5. Date of submission.

C. The sum of all values listed in the schedule shall equal the total Contract Sum.

D. Provide additional breakdown of values as requested by the Owner’s Project Manager.

E. Note: City of McKinney does not pay for stored materials.

TESTING LABORATORY SERVICES (01410)

SECTION 01410

1.1 SCOPE

A. An independent testing laboratory, engaged and paid for by the Owner, will perform the professional testing and laboratory services.

B. Make all inspections and perform all tests in accordance with the rules and regulations of the building code, local authorities, the specifications of the ASTM and other applicable technical societies or organizations.

C. Materials and workmanship not meeting the required standards or performance obligations are to be removed and replaced, including subsequent testing, at the expense of the Contractor.

D. Where the terms "Inspector" and "Testing Laboratory" are used, they mean and refer respectively to an officially designated and accredited inspector of the testing laboratory engaged by the Owner.

E. Testing, inspection, and certifications specified in other sections of these Specifications shall be paid by the Owner, unless otherwise indicated, and shall be by agencies approved by the Owner and the Landscape Architect.

F. Inspection by the laboratory shall not relieve the Contractor or Fabricator of his responsibility to furnish materials and workmanship in accordance with the Contract Documents.

G. Testing agencies shall meet the requirements of ASTM E 329, "Recommended Practice for Inspection and Testing Agencies for Concrete, Steel and Bituminous Materials as Used in Construction."

H. The inspection and testing services of the testing agencies shall be under the direction of a registered engineer licensed in the State of Texas, charged with engineering managerial responsibility, and having at least five (5) years engineering experience in inspection and testing of construction materials.

1.2 RESPONSIBILITY OF CONTRACTOR

A. Deliver to the laboratory, without cost to the Owner, adequate quantities of representative samples of materials proposed for use which are required to be tested.

B. Advise laboratory and Owner 48 hours in advance of construction operations to allow laboratory to complete any required checks or tests and to assign personnel for field inspection and testing as specified.

C. Provide adequate facilities for safe storage and proper curing of concrete test samples on project site for the first twenty-four (24) hours and also for subsequent field curing as required by ASTM Specifications C 31.

D. Furnish such nominal labor as is required to assist laboratory personnel in obtaining and handling samples at the site.

E. Furnish Concrete Mix Designs, in accordance with ACI 318-83, made by an independent testing laboratory approved by the Owner and paid for by the Contractor.

1.3 AUTHORITY AND DUTIES OF LABORATORY PERSONNEL

A. Laboratory personnel shall inspect and/or test materials, assemblies, specimens, and work performed, including design mixes, methods and techniques as specified and report to the Landscape Architect the progress thereof.

B. If the material furnished and/or work performed fails to meet requirements of Contract

Documents, laboratory inspector shall promptly notify both the Contractor and the Landscape Architect of such failure.

C. Laboratory technicians do not act as foreman, or perform other duties for Contractor. Work will be checked as it progresses, but failure to detect any defective work or materials shall not, in any way, prevent rejection when such defect is discovered.

D. The laboratory inspector is not authorized to revoke, alter, relax, enlarge, or release any requirement of the Contract Documents or to approve or accept any portion of the work.

1.4 SUBMITTALS

A. Submit copies or in PDF format, to the Owner, Contractor and to the Landscape Architect, of reports of each and every inspection and test required to be made as part of the work in this Section, or ordered by the Landscape Architect or the Contractor to be made either in addition to or supplementary to inspecting and testing specified herein or in other Sections of the Specifications.

B. State in report all details of each inspection and test. Indicate satisfactory compliance with requirements of the Contract Documents. Also state in report and and all unsatisfactory conditions or failure to comply with requirements of the Contract Documents. This requirement is in addition to reporting immediately to the Contractor and the Architect all items of unsatisfactory conditions and failures to comply with the requirements of the Contract Documents.

C. At completion of each trade or branch of work requiring inspecting and testing, submit a final certificate attesting to satisfactory completion of work inspected and full compliance with requirements, for all work and materials tested.

1.5 REFERENCED STANDARDS

A. The latest edition of all standards referenced in this section shall apply, unless noted otherwise.

PART 2 - PRODUCTS (NOT APPLICABLE)

PART 3 - EXECUTION

3.1 FILLING AND BACKFILLING

A. The Contractor shall make available to the testing agency, free of charge, adequate samples of each fill and backfill material from the proposed sources of supply.

B. A fifty (50) pound sample of each type of off-site and site-excavated material proposed for use shall be given to the testing agency by the Contractor not less than 10 calendar days prior to the start of the specified work. Analyze samples as required to provide a soil description and to determine compliance with gradation and quality requirements, and test as follows:

1. Tests for liquid limit of soils in accordance with ASTM D423.

2. Tests for plastic limit of soils and plasticity index of soils in accordance with ASTM

D424.

3. Tests of moisture/density relations of soil in accordance with ASTM D1557, Method D.

C. Furnish a report for each individual test, describing variances from specified requirements, and state whether material is acceptable for the intended use.

D. Inspect underslab drainage material and placement for compliance with specified gradation, quality, and compaction.

E. Make in-place compaction test for moisture content, moisture density relations, and density of materials-in-place, to determine that backfill and fill materials have been compacted to the specified density. Tests shall be made at the following frequencies:

1. One test for each five thousand (5,000) square feet of area of each lift placed under pavement. Stagger test locations in each lift from those in the previous lift. A minimum of three (3) tests will be required of each lift.

2. One test for each one hundred (100) linear feet, or portion thereof, of each lift on each face of strip footings and walls, with locations staggered as above.

3. One test of each lift placed at any free-standing footing, pier, or similar support, with locations taken on a different side in, each case from, the lift below.

F. Reports may be combined on a daily basis, if so desired, provided that the location of each test and applicable lift are clearly identified and any problems are detailed.

3.2 FOOTING EXCAVATIONS

A. Soils testing laboratory shall inspect each concrete footing excavation to determine that proper bearing stratum is obtained and utilized for bearing and that excavations are properly clean and dry before concrete is placed.

3.3 CONCRETE REINFORCING STEEL

A. Inspect all concrete reinforcing steel prior to placing of concrete for compliance with Contract

Documents and approved Shop Drawings. All cases of non-compliance with Contract Documents and approved Shop Drawings shall be immediately called to the attention of the Contractor and reported to the Owner and the Landscape Architect.

B. Observe and report on the following:

1. Number and size of bars.

2. Bending and length of bars.

3. Splicing.

4. Clearance to forms including chair heights.

5. Clearance between bars or spacing.

6. Rust, form oil, and other contamination.

7. Grade of steel.

8. Securing, typing, and chairing of bars.

9. Excessive congestion of reinforcing steel.

C. Inspector shall have a minimum of three (3) years experience inspecting reinforcing steel in similar size projects.

3.4 CONCRETE CONTROL AND TESTING

A. Receive and evaluate all proposed concrete mix designs submitted by the Contractor. If the mix designs comply with Drawings and Specifications, the laboratory shall submit a letter to Owner and the Architect certifying compliance. Mix designs not complying with the Drawings and Specifications shall be returned by the laboratory as unacceptable.

B. Secure composite samples of concrete at the jobsite in accordance with ASTM C172, "Sampling Fresh Concrete."

C. Mold and cure three (3) specimens from each sample in accordance with ASTM C31, "Making and Curing Concrete Test Specimens in the Field." Supervise the curing protection provided (by others) for test specimens in the field, and the transportation from the field to the laboratory. The test cylinders shall be stored in the field 24 hours and then be carefully transported to the laboratory and cured in accordance with ASTM C31.

D. Test specimens in accordance with ASTM C39, "Test for Compressive Strength of

Cylindrical Concrete Specimen." Two (2) specimens shall be tested at twenty-eight (28) days for acceptance and one (1) shall be tested at seven (7) days for information.

E. Make one (1) strength test (three [3] cylinders) for each 100 cubic yards of fraction thereof, of each mix design of concrete placed in any one (1) day.

F. Make slump tests from each truck load of concrete or more often at the option of the Architect, following the procedural requirements of ASTM C143 and C172. Slump tests shall always be made from the same batch from which strength tests are made.

G. Determine total air content of air entrained normal-weight concrete sample for each strength test in accordance with ASTM C231, "Test for Air Content of Freshly Mixed Concrete by the Pressure Method."

H. Determine air content and unit weight of light-weight concrete sample for each strength test in accordance with ASTM C172 and ASTM C567.

I. Determine temperature of concrete sample for each strength test.

J. The testing agency shall furnish and maintain a competent inspector at the mixing plant (at the start of each day's mixing). The inspector shall examine concrete materials for compliance with specifications and approved mix design, weighing and measuring devices, proportioning and mixing of materials, and water and cement content of each batch, the general operation of the plant and the transportation of concrete to the job site. The inspector shall make the necessary tests to determine the amount of free surface moisture contained in the fine and coarse aggregate, and shall determine by calculations the amount of water to be added to each batch to obtain concrete of proper consistency and water cement ratio as determined from data obtained in the preliminary test.

K. The testing laboratory shall control the addition of water to the concrete at the jobsite and the length of time the concrete is allowed to remain in the truck during the placement. The inspector shall compare the mixture with the criteria on the approved mix design and report any significant deviation to the Architect, Contractor and design laboratory. Corresponding adjustments shall be made before the concrete is discharged.

L. The testing laboratory shall certify each delivery ticket indicating class of concrete delivered

(or poured), amount of water added and the time at which the cement and aggregate was discharged into the truck, and the time at which the concrete was discharged from the truck.

M. Evaluation and Acceptance:

1. If the measured slump, or air content of air entrained concrete falls outside the specified limits, a check test shall be made immediately on another portion of the same sample. In the event of a second failure, the concrete shall be considered to have failed to meet the requirements of the specifications, and shall not be used in concrete operations in the work.

2. The strength level of the concrete will be considered satisfactory if 90% of the strength test results and the averages of all sets of three (3) consecutive strength tests results are equal to, or exceed specified strength and no individual test result is below specified strength by more than 500 psi.

3. Completed concrete work will be accepted when the requirements of "Specifications for Structural Concrete for Buildings" ACI 301-72, Chapter 18, have been complied with.

4. In any case where the average strength of the laboratory control cylinders, as shown by the tests for any portion of the structure, falls below the minimum ultimate compressive strength hereinbefore specified, the Architects shall have the right to require the Contractor to provide improved curing conditions of temperature and moisture to secure the required strength. Also, if the average strength of the laboratory control cylinders should fall so low as to cause the portions of the structure to which the respective unsatisfactory test reports apply to be in question by the Architect, the Contractor shall follow the core procedure set forth in the current edition of ASTM Designation C 42. If the results of the core tests indicate, in the opinion of the Architects, that the strength of the structure is inadequate, such replacement, load testing, or strengthening, as may be ordered by the Architect, shall be provided by the Contractor without cost to the Owner. If core tests are so ordered, and the results of such tests disclose that the strength of the structure is as required by the provisions of the Specifications and Drawings, the cost of the tests will be borne by the Owner.

N. Concrete Test Reports:

1. Reports shall be made and distributed immediately after the respective tests or inspections are made.

2. Where reports indicate deviations from the Contract Documents, they shall also include a determination of the probable cause of the deviation and, where applicable, a recommendation for corrective action.

3. Whenever the testing laboratory recognizes a trend of decreasing quality in the concrete due to changing seasons, conditions of curing, or other cause; this shall be brought to the attention of the Architect, along with a recommendation for corrective action to be taken before the materials fall below the requirements of these Specifications.

O. Comply with ACI 311-75, "Guide for Concrete Inspection."

3.5 STRUCTURAL STEEL

A. Inspect all structural steel during fabrication and during and after erection for conformance with Contract Documents and Shop Drawings. Any cases of insufficient bracing or guying, or other unsafe conditions shall be immediately called to attention of Contractor and reported to Architect. Architect will review stage steel during construction. Notify Landscape Architect when stage support steel work commences.

B. Shop Inspection:

1. Examination of all steel for straightness and alignment.

2. Examination of all fabricated pieces and checking of same with erection plans and detail drawings.

3. Visual examination of all shop welding.

4. Ultrasonic testing of all full penetration welds.

5. Examination of galvanizing.

6. Examination of installation of shop welded shear studs.

7. Examination of shop painting.

C. Field Inspection:

1. Proper erection of all pieces.

2. Proper installation of high-strength bolts, including the checking of calibration of impact wrenches.

3. Plumbness of structure and proper bracing.

4. Proper field painting.

5. Visual examination of all field welding.

6. Ultrasonic testing of all penetration welds in moment connections, column splices, and column bases.

7. Installation of field welded shear studs.

8. Inspect all shop fabricated members, upon their arrival at the jobsite, for defects incurred during transit and handling.

D. Qualifications of Welders:

Fabricator and erector shall provide the testing laboratory with names of welders to be employed on work, together with certification that each of these welders has passed qualification tests within the last year using procedures covered in the American Welding Society Standard D1.1, latest edition.

E. Inspection of shop and field welding shall be in accordance with Section 6, of the AWS

Structural Welding Code and as follows:

1. Visually inspect the welding of all shop fabricated members and note the location of all cover plates, connectors, bearing stiffeners, splicing ends, and fillet welds for proper return around ends of cover plates and check for seams, folds, and laminations.

2. Warped or out-of-plumb connectors shall be reported prior to any further welding.

3. Ultrasonically test all penetration welds in accordance with ASTM E 164.

4. Joints in which materials is 2" or more in thickness shall not have the weld interrupted after operations has started, unless at least 2/3 of its length, for its full depth, has been completed without an interruption of more than one hour. Welding may be interrupted for longer periods, provided the preheat temperature is maintained for the full length of joint for the entire time welding is interrupted.

5. Surfaces to be welded and all filler metal shall be carefully inspected. Surface preparations, fit-up and cleanliness of surface shall be noted. Electrodes shall be checked for size, type and condition.

6. Welds shall be sound, clean metal, free of slab inclusions and porosity. Filler metal shall be completely fused with base metal and shall have complete penetration of the joint. Root passes shall be checked for penetration from the back side of joint.

Welds showing inclusions, porosity, lack of fusion, penetration and uneven contour (sagging or overlaps) shall be ordered gouged out and rewelded. Welds showing any undercut shall have a small stringer bead ordered to be run in along the toe of undercut using a smaller diameter electrode than that which made the original weld.

No craters shall be left in welds. Any welding defects, including porosity, fusion, and undercuts in excess of that allowed shall be cause for rejection. Where craters occur, the inspector shall order them to be filled out with weld metal.

7. The welding inspector shall be present during alignment and fit-up of members being welded, and shall check for correct surface preparation of root openings, sound weld metal, and proper penetration in the root pass. Where weld has not penetrated completely, the inspector shall order the joint to be chipped down to sound metal, or gouged out, and rewelded. Root passes shall be thoroughly inspected for cracks. All cracks shall be gouged out and rewelded (2" beyond each end of crack).

8. The…