This is a Bid Terms document issued by the City of St. George, Utah for the Vernon Worthen Park Playground Tile Replacement project (Reference No. 26-312). The project involves preparing Vernon Worthen Park Playground for new safety surfacing installation. Bidders must submit proposals in strict accordance with the Contract Documents, Drawings, Specifications, and all related project documents. All work, labor, materials, equipment, permits, fees, and services necessary to complete the specified work must be furnished by the bidder. The bidder certifies that the bid has been developed independently without consultation or agreement with other bidders or competitors. All work is subject to City approval, with the City maintaining authority over quality, suitability, acceptability of materials, interpretation of drawings and specifications, and determination of acceptable contract fulfillment.
Contract performance must be completed within the specified contract time. Liquidated damages are assessed at $250.00 per calendar day for failure to complete work within the contract time or approved extensions, and an additional $250.00 per day for failure to repair deficiencies within ten days of notification. These rates are cumulative. Each bid must be accompanied by a bid bond in the amount of 5% of the total bid, issued by a surety company licensed to do business in the State of Utah on a bond form acceptable to the City. The City of St. George reserves the right to reject any or all proposals or to waive any formality or technicality in any proposal in its interest.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BID TERMS
Project Name: _______Vernon Worthen Park Playground Tile Replacement__________
Reference No: _______26-312______________________________________________________
Proposal of (“BIDDER"), organized and existing under the laws of the State of doing business as a corporation, partnership, or an individual (circle applicable status), to the City of St. George ("CITY"). Pursuant to and in compliance with the Public Notice, BIDDER hereby proposes to perform all Work for the above named Project in strict accordance with the Contract Documents, BIDDER'S Instructions, Drawings, Specifications, and other documents related thereto, the undersigned, having familiarized themselves with the existing conditions on the site and the conditions under which the work on the Drawings and in the Specifications is to be done, hereby proposes to furnish all labor, materials, equipment, incidental items, permits, fees, and services to perform all specified work on the above named project.
By submission of this BID, each BIDDER certifies, and in the case of a joint BID each party thereto certifies as to his own organization, that this BID has been arrived at independently, without consultation, communication, or agreement as to any matter relating to this BID with any other BIDDER or with any competitor.
All Work shall be in strict accordance with the Contract Documents and documents issued thereto and shall be installed at the price/prices set forth in the Contract Documents.
Bidder acknowledges that all Work shall be done subject to CITY’S approval. Decisions and questions as to the quality, suitability, and acceptability of the materials, interpretation of drawings and specifications, and acceptable fulfillment of the Contract by the BIDDER shall be made by CITY.
Of particular importance to be considered in the BID are the following:
CONTRACT TIME AND LIQUIDATED DAMAGES
The WORK is to be performed within the specified CONTRACT TIME. If the CONTRACTOR shall fail to complete the WORK within the CONTRACT TIME, or extension of time granted by the CITY, then the CONTRACTOR will pay the CITY LIQUIDATED DAMAGES assessed at the rates established as follows:
a. $250.00 (dollars) per day for each calendar day that the CONTRACTOR shall be in default after the CONTRACT TIME.
b. $250.00 (dollars) per day for failure to make repairs to deficiencies in the work within 10 days of notification to repair.
The rates specified in ‘b.’ above are cumulative and are in addition to LIQUIDATED DAMAGES assessed in association with the overall Contract Time as listed in ‘a.’ above.
Additional information on LIQUIDATED DAMAGES is provided in the GENERAL