1-01 Contract Documents Material Handlers.pdf
PDF 3 MB Posted
- Solicitation number
- Not on record
- Issued by
- York County, Pennsylvania
About this file
Summary of Bid Documents for Stationary Electric Material Handlers
These are bid documents for the York County Solid Waste and Refuse Authority (YCSWA) for the procurement and installation of two (2) stationary electric material handlers at the Blackbridge Road Transfer Station in York, Pennsylvania. The project encompasses the complete supply, installation, testing, startup, commissioning, and training for fully operational stationary electric material handler systems within the facility. Bids will be received online via PennBid until 10:00 AM on Tuesday, March 10, 2026, with public opening and reading of bids at the YCSWA Management Center located at 2700 Blackbridge Road, York, PA 17406. Bidding documents are available at no cost through the PennBid program beginning February 16, 2026. A non-mandatory pre-bid conference will be held on February 24, 2026, at 10:00 AM at the same location, with a virtual attendance option available. The contract requires substantial completion within 406 calendar days of the final notice to proceed and final completion within 435 calendar days, with liquidated damages of $1,000 per day for failure to achieve substantial completion and $2,500 per day for failure to complete remaining work after substantial completion.
All bids must be submitted as a lump sum and must include bid security in the form of a certified check or bid bond in an amount not less than 10% of the bid price. Bidders must comply with Pennsylvania prevailing wage requirements and provide evidence of compliance with public works employment verification procedures through the federal E-Verify program. The successful bidder must furnish performance and payment bonds each equal to 100% of the contract price, as well as comprehensive insurance coverage including workers' compensation, commercial general liability with minimum limits of $2,000,000 general aggregate, automobile liability of $1,000,000, and pollution liability of $2,000,000. All bids shall remain irrevocable for 60 days after the bid opening date, with potential extension to 120 days if award is delayed by required government agency approvals or grant awards. Pennsylvania prevailing wage rates apply to all labor, and all work must comply with state steel products procurement requirements and trade practices regarding materials sourcing. Contractor shall be responsible for all mobilization and demobilization costs, permits, site coordination with ongoing facility operations, and maintaining the work site in a clean and hazard-free condition throughout construction.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
YORK COUNTY
SOLID WASTE AND REFUSE AUTHORITY
BLACKBRIDGE ROAD TRANSFER STATION
BID DOCUMENTS – STATIONARY ELECTRIC MATERIAL HANDLERS
Prepared for:
York County
Solid Waste and Refuse Authority
2700 Blackbridge Rd
York, PA 17406
Prepared by:
ARM Group LLC
1129 West Governor Road
P.O. Box 797
Hershey, PA 17033-0797
February 2026
ARM Project 23011135
York County Solid Waste and Refuse Authority
Blackbridge Road Transfer Station
Stationary Electric Material Handlers
Table of Contents
1.0 - CONTRACT DOCUMENTS (DIVISION 0)
Subject Page
Advertisement for Bids……………………………………………………………AFB-1 – AFB-2
Project Statement….…………………………………………………………………………...PS-1
Instructions to Bidders……………………………………………………….……..ITB-1 – ITB-16
Bid Form - Stationary Electric Material Handler………………...…………………...BF-1 – BF-7
Contractor Statement of Qualifications………………………….…………………………..CSQ-1
Subcontractor and Supplier Listing Form.……………………………………….…….….…….1-5
Bid Bond……………………………………………………………………………...BB-1 – BB-3
Consent of Surety……………….…………………………………………………..................CS-1
Non-Collusion Affidavit………………………………………………………….NCA-1 – NCA-3
Self-Certification of No Disbarment………...……………….........………………………...SEC-1
Pennsylvania Prevailing Wage Requirements……….………………...……….........PW-1 – PW-3
Commonwealth of Pennsylvania Public Works Employment Verification Form…..PWV1-PWV2
Memorandum of Understanding…………………………………………………..…...…...MOU-1
Hold Harmless Agreement……………...…………………………………..………..HH-1 – HH-2
Agreement – Stationary Electric Material Handler.....……………………..……...…….A-1 – A-8
Asbestos-Free and Lead-Free Certification.....……….……………………...….……...….ALFC-1
Performance Bond……………………...………………………………………..…PEB-1 – PEB-4
Payment Bond…………………………..………………………………………....PAB-1 – PAB-4
Certificate of Release……………………..………………………………………..…CR-1 – CR-3
Application for Payment…………………..……………………………………….AFP-1 – AFP-4
General Conditions…………………………..…………………………………..….GC-1 – GC-80
YCSWA – Blackbridge Road Transfer Station ii February 2026
Table of Contents ARM Group LLC
2.0 TECHNICAL SPECIFICATIONS
Prepared by Providence Engineering Corporation
Sections Identified Within Volume
3.0 DRAWING LIST
Prepared by Providence Engineering Corporation
Sheet SMH01 - Stationary Material Handlers (SMH)
4.0 TRANSFER STATION TECHNICAL SPECIFICATIONS AND DRAWINGS
Refer to Section 4 of the Bidding Documents for the complete Transfer Station scope of work, including all technical specifications and full drawing sets for the entire facility. Section 4 is provided for coordination purposes only with other on-site contractors.
ADVERTISEMENT FOR BIDS
York County Solid Waste and Refuse Authority
Blackbridge Road Transfer Station Construction Project
Procurement and Installation of Stationary Electric Material Handlers
Bids for the procurement and installation of two (2) Stationary Electric Material Handlers for the
Blackbridge Road Transfer Station Construction Project will be received by the York County Solid
Waste and Refuse Authority (YCSWA) online via PennBid, until 10:00AM local time on Tuesday, March 10, 2026, at which time the Bids received will be publicly opened and read aloud at the
YCSWA Management Center (2700 Blackbridge Road, York, PA 17406). Bids shall be submitted online via the PennBid Program (https://pennbid.bonfirehub.com) by the date and time indicated in the Instruction to Bidders along with the Bid security and the other documents required to be submitted as identified herein. Bidding documents will only be distributed online at PennBid.
Bidding documents will be made available at no cost via the PennBid Program
(https://pennbid.bonfirehub.com) on or after Monday, February 16, 2026.
Bid security in the form of a Certified Check or Bid Bond shall be furnished with the bid in an amount not less than 10%.
All questions about the meaning or intent of the Bidding Documents are to be submitted via the
PennBid Program in accordance with the Instructions to Bidders. Telephone inquiries are unacceptable. No questions will be answered after the Request for Information (RFI) deadline provided on PennBid.
A Non-Mandatory Pre-Bid Conference will be held at the YCSWA Management Center (2700
Blackbridge Road, York, PA 17406) on Tuesday, February 24, 2026, at 10:00 a.m.
Representatives of YCSWA will be present to discuss the Project. Bidders may attend and are encouraged to participate in the Conference. A virtual attendance option will also be available.
Bidders interested in attending the Conference virtually must email Terry Simpson directly at tsimpson@armgroup.net. A meeting link will be provided to those requesting virtual participation.
YCSWA will transmit to all Plan Holders of record such Addenda as it considers necessary in response to questions arising at the Conference.
All bids shall be irrevocable for sixty (60) days after the bid opening date unless award is delayed by a required approval of another government agency, the sale of bonds, or the award of a grant or grants, in which case this Bid shall remain subject to acceptance for 120 days after the bid opening date as provided by the Public Works Contract Regulation Law Act of November 26, 1978 (P.L.
1309, No. 317), as amended by the Act of December 12, 1994 (P.L. 1042, No. 142).
YCSWA reserves the right to reject any and all Bids and to waive any omissions, errors, mistakes, defects, or irregularities in any Bid at its sole discretion.
York County Solid Waste and Refuse Authority
Felicia Dell
Chairperson
YCSWA – Blackbridge Road Transfer Station February 2026
Project Statement PS-1 ARM Group LLC
PROJECT STATEMENT
All Work and related activities are to occur at the York County Solid Waste and Refuse
Authority’s Resource Recovery Center, located in York County, PA. The Contractor shall include the furnishing of all labor, required materials (not specifically listed as owner supplied), equipment, services, and the performance of all operations required to complete the Work as indicated on the Contract Drawings and in accordance with the Contract Documents. Work covered under the Contract for the Stationary Electric Material Handlers generally includes, but is not limited to, the following:
a) All work associated with the stationary electric material handlers for the Blackbridge
Road Transfer Station Project, as indicated on the Contract Drawings and specified in the
Technical Specifications and other Contract Documents.
b) The Stationary Electric Material Handlers Contractor shall be responsible for furnishing all materials, labor, equipment, coordination, and installation required to provide fully installed, tested, and operational stationary electric material handler systems within the building.
The Contractor(s) shall perform all work and provide all materials necessary for the complete and satisfactory performance of the project as depicted, described, or derived from the Bidding Documents and Contract Drawings, regardless of whether specific items or details are explicitly mentioned above.
Instructions to Bidders ITB-1 ARM Group LLC
EJCDC® C-200, Instructions to Bidders for Construction Contract.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
Guidelines Page 1 of 17
INSTRUCTIONS TO BIDDERS
TABLE OF CONTENTS
Page
Article 1— Defined Terms
Article 2— Bidding Documents
Article 3— Conditions of Work
Article 4— Qualifications of Bidders
Article 5— Collusive Bids
Article 6— Examination of Contract Documents and Site
Article 7— Bidder’s Representations and Certifications
Article 8— Interpretations and Addenda
Article 9— Bid Security
Article 10— Contract Times
Article 11— Damages
Article 12— Substitute and “Or Equal” Items
Article 13— Subcontractors, Suppliers, and Others
Article 14— Pennsylvania Steel Products Procurement Act (No. 1978-3)
Article 15— Trade Practices Act
Article 16— Employment Guidelines
Article 17— Preparation of Bid
Article 18— Basis of Bid
Article 19— Submittal of Bid
Article 20— Modification and Withdrawal of Bid
Article 21— Opening of Bids
Article 22— Bids to Remain Subject to Acceptance
Article 23— Evaluation of Bids and Award of Contract
Article 24— Pre-Bid Conference
Article 25— Sales and Tax
Article 26— Prevailing Wage
Article 27— Execution of Agreement, Bond, Insurance and Issuance of Notice to Proceed
Article 28— Payments
Instructions to Bidders ITB-2 ARM Group LLC
EJCDC® C-200, Instructions to Bidders for Construction Contract.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, Guidelines Page 2 of 17
Article 29— Notice to Successful Bidder
Article 30— Inspections
Article 31— Assignments
Article 32— Insurance
Article 33— Working Hours
Article 34— Site Conditions During Construction
Instructions to Bidders ITB-3 ARM Group LLC
EJCDC® C-200, Instructions to Bidders for Construction Contract.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, Guidelines Page 3 of 15
ARTICLE 1—DEFINED TERMS
1.01 Terms used in these Instructions to Bidders have the meanings indicated in the General
Conditions. Additional terms used in these Instructions to Bidders have the meanings indicated below:
A. “Bidder" means one who submits a Bid directly to Owner, as distinct from a sub-
Bidder, who submits a bid to a Bidder.
B. “Successful Bidder" means the lowest, responsible Bidder to whom Owner (on the basis of Owner's evaluation as hereinafter provided) makes an award.
C. “Bidding Documents" includes the Advertisement and Invitation to Bid, Instructions to Bidders, Bid Form and the Contract Documents (including all Addenda issued prior to receipt of Bids).
1.02 Other terms used in the Bidding Documents and not defined elsewhere have the following meanings, which are applicable to both the singular and plural thereof:
A. “Day” means a calendar day of twenty-four (24) hours measured from midnight to the next midnight shall constitute a day, unless otherwise specified.
B. “Contract Drawings” - shall mean "Drawings" as defined in the General Conditions of the Contract Documents.
ARTICLE 2—BIDDING DOCUMENTS
2.01 Bidding documents are available at no cost via the PennBid Program
(https://pennbid.bonfirehub.com).
2.02 Bidding Documents are made available for the sole purpose of obtaining Bids for completion of the Project and permission to download or distribution of the Bidding
Documents does not confer a license or grant permission or authorization for any other use. Authorization to download documents, or other distribution, includes the right for plan holders to print documents solely for their use, and the use of their prospective
Subcontractors and Suppliers, provided the plan holder pays all costs associated with printing or reproduction. Printed documents may not be re-sold under any circumstances.
2.03 Complete sets of Bidding Documents shall be used in preparing Bids; the Owner assumes no responsibility for errors or misinterpretations resulting from the use of incomplete sets of Bidding Documents.
2.04 The Owner, in making Bidding Documents available on the above terms, does so only for the purpose of obtaining Bids on the Work and does not confer a license or grant for any other use.
ARTICLE 3—CONDITIONS OF WORK
3.01 Bidders must inform themselves fully of all conditions relating to the work in question.
Bidders shall assume all risks, whether or not patent, latent, known, hidden, or foreseeable.
Failure to do so will not relieve the Successful Bidder of his obligation to furnish and
Instructions to Bidders ITB-4 ARM Group LLC
EJCDC® C-200, Instructions to Bidders for Construction Contract.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, Guidelines Page 4 of 15 perform the work which forms the basis of this bid, or to carry out the provisions of the contract with respect to performance of the contemplated work set forth in this bid. The
Bidder is presumed to have investigated and examined all bidding documents and the
Owner assumes the Bidder's bid is made with full knowledge and understanding of the conditions of the Contract.
3.02 It is likewise understood and required that the Successful Bidder shall employ such methods, in the performance of this contract, as will comply with any applicable statutes of the Commonwealth of Pennsylvania and regulations or ordinances of the Township and/or other local municipality.
ARTICLE 4—QUALIFICATIONS OF BIDDERS
4.01 Bidder is to submit the following information with its Bid to demonstrate Bidder’s qualifications to perform the Work:
A. Contractor shall submit the completed and signed Contractor Statement of
Qualifications Form included in this Bid Package with all required supporting documentation attached.
B. Contractor shall submit the completed Subcontractor and Supplier Listing Form included in this Bid Package.
4.02 A Bidder’s failure to submit required qualification information within the times indicated may disqualify Bidder from receiving an award of the Contract.
4.03 No requirement in this Article 4 to submit information will prejudice the right of Owner to seek additional pertinent information regarding Bidder’s qualifications.
4.04 The Bidder, including any individual, corporation, or partnership affiliated in any way with the Bidder, including any of Bidder’s subcontractors, shall not appear on the current
Pennsylvania Department of Labor and Industry Debarment List.
4.05 A bid may be rejected at Owner’s sole discretion if the Bidder does not submit evidence that it meets or exceeds the above minimum qualifications.
4.06 The Bidder, including any individual, corporation, or partnership affiliated in any way with the Bidder, shall not have been held in default by Owner on any contract of Owner within 36 months prior to the day of the Bid Opening.
ARTICLE 5—COLLUSIVE BIDS
5.01 More than one (1) Bid from an individual, a firm or partnership, corporation, or an association under the same name or different names will not be considered. Reasonable grounds for believing that the Bidder is interested in more than one (1) Bid for the same work may cause the rejection of all Bids in which such Bidder is interested. Any or all
Bids may be rejected if there is any reason for believing that collusion exists among any
Instructions to Bidders ITB-5 ARM Group LLC
EJCDC® C-200, Instructions to Bidders for Construction Contract.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, Guidelines Page 5 of 15 of the Bidders; participants in such collusion will not be considered in future Bids. All
Bids submitted must include an executed Non-Collusive Affidavit.
ARTICLE 6—EXAMINATION OF CONTRACT DOCUMENTS AND SITE
6.01 Before submitting a Bid, each Bidder shall:
A. Examine the Contract Documents thoroughly, B. Visit the site to familiarize himself with local conditions that may in any manner affect cost, progress, performance or furnishing of the Work, C. Familiarize himself with Federal, State, and local laws, ordinances, rules and regulations that may in any manner affect cost, progress, performance or furnishing of the Work, D. Study and carefully correlate Bidder's observations with the Contract Documents, E. Notify the Owner of all conflicts, errors, or discrepancies in the Contract Documents.
6.02 Reference is made to the General Conditions for the identification of those reports of investigations, tests of subsurface and latent physical conditions and drawings of physical conditions in, or relating to, existing surface and subsurface conditions (except
Underground Facilities) at the site or otherwise affecting cost, progress, performance or furnishing of the Work which have been relied upon by the Owner in preparing the
Drawings and Specifications. Bidder may rely upon the accuracy of the technical data contained in such reports and drawings, but not upon non-technical data, interpretations or opinions contained therein or for the completeness, accuracy and continuity of such condition thereof for the purposes of bidding or construction. Such technical data has been identified and set forth in the General Conditions. These reports and drawings are not part of the Contract Documents. Copies of such reports and drawings will be made available by the Owner to any Bidder on request. Before submitting his Bid each Bidder will, at his own expense, make such additional investigations and tests as the Bidder may deem necessary to determine his Bid for performance and furnishing of the Work in accordance with the time, price, and other terms and conditions of the Contract Documents.
6.03 Information and data reflected in the Contract Documents with respect to Underground
Facilities at or contiguous to the site is based upon information and data furnished to
Owner by owners of such Underground Facilities or others, and Owner does not assume responsibility for the accuracy or completeness thereof unless it is expressly provided otherwise in the General Conditions.
6.04 By prior arrangement, in advance, Owner will provide each Bidder reasonable access to the site to conduct such investigations and tests, as each Bidder deems necessary for submission of his Bid. Bidder shall fill all holes, and clean up and restore the site to its former condition upon completion of such investigations and tests.
6.05 The lands upon which the Work is to be performed, rights-of-way for access thereto, and other lands designated for use by Successful Bidder in performing the Work are identified in the Contract Documents.
Instructions to Bidders ITB-6 ARM Group LLC
EJCDC® C-200, Instructions to Bidders for Construction Contract.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, Guidelines Page 6 of 15
6.06 The submission of a Bid will constitute an incontrovertible representation by the Bidder that he has complied with every requirement of this Article 6, and that the Contract
Documents are sufficient in scope and detail to indicate and convey understanding of all terms and conditions for performance of the Work. Later claims for labor, equipment or materials required, or for other difficulties encountered which could have been foreseen had Bidder complied with the requirements of this Article 6, will not be recognized.
ARTICLE 7—BIDDER’S REPRESENTATIONS AND CERTIFICATIONS
7.01 Express Representations and Certifications in Bid Form, Agreement
A. The Bid Form that each Bidder will submit contains express representations regarding the Bidder’s examination of Project documentation, Site visit, and preparation of the
Bid, and certifications regarding lack of collusion or fraud in connection with the Bid.
Bidder should review these representations and certifications and assure that Bidder can make the representations and certifications in good faith, before executing and submitting its Bid.
B. If Bidder is awarded the Contract, Bidder (as Contractor) will make similar express representations and certifications when it executes the Agreement.
ARTICLE 8—INTERPRETATIONS AND ADDENDA
8.01 Owner on its own initiative may issue Addenda to clarify, correct, supplement, or change the Bidding Documents.
8.02 Bidder shall submit all questions about the meaning or intent of the Bidding Documents via the “Messages/Vendor Discussions” feature in PennBid no later than nine (9) days prior to the date for receipt of bids.
8.03 Interpretations or clarifications considered necessary by Engineer in response to such questions will be issued by Addenda delivered to all registered plan holders. Questions received after Monday, March 2, 2026 at 10:00AM may not be answered.
8.04 Only responses set forth in an Addendum will be binding. Oral and other interpretations or clarifications will be without legal effect. Responses to questions are not part of the
Contract Documents unless set forth in an Addendum that expressly modifies or supplements the Contract Documents.
8.05 "Pre-Bid Minutes", which may be issued as a record of the Pre-Bid Conference, are not a part of the Contract Documents.
ARTICLE 9—BID SECURITY
9.01 A Bid security shall be made payable to Owner, in an amount of ten percent (10%) of the
Bidder's maximum Bid price, and in the form of a certified or bank cashier's check or a
Bid Bond. If a Bid Bond is used, it must be on the form furnished with the Contract
Documents, be executed by the Bidder, and must have corporate surety satisfactory to the
Owner and authorized to conduct business in Pennsylvania.
Instructions to Bidders ITB-7 ARM Group LLC
EJCDC® C-200, Instructions to Bidders for Construction Contract.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, Guidelines Page 7 of 15
9.02 The Bid security of the Successful Bidder will be retained until such Bidder has executed and delivered the Contract and furnished the required contract security, whereupon it will be returned. If the Successful Bidder fails to execute and deliver the required contract security within ten (10) days of the Notice of Intent to Award, Owner may annul the Notice of Intent to Award, and the Bid security of that Bidder will be forfeited to Owner as liquidated damages or on account of Owner's actual damages as Owner may elect. The Bid security of any Bidder whom Owner believes to have a reasonable chance of receiving the award may be retained by Owner until the earlier of the seventh day after the "Effective
Date of the Agreement" (which term is defined in the General Conditions) or the sixty-first day after the Bid opening, whereupon Bid security furnished by such Bidders will be returned. Bid security with Bids which are not competitive may be returned within seven
(7) days after the Bid opening.
ARTICLE 10—CONTRACT TIMES
10.01 The date by which, the Work and identified portions thereof (Milestones) are to be substantially complete and available for Owner’s use, and also completed and ready for final payment (the Contract Time), are set forth in the Agreement. Such Contract Times are of the essence.
The Milestones are as follows:
Milestone 1 – The Transfer Station Stationary Electric Material Handlers and all related work shall be Substantially Complete and available for the Owner’s use within 406 calendar days from receipt of the Final Notice to Proceed.
Achievement of this milestone is contingent upon the progress of work performed by others at the site. Installation of the material handlers and associated equipment cannot commence until the work by others has advanced to a stage sufficient to support such installation.
Milestone 2 – Final Completion shall be achieved within 435 calendar days from receipt of the Final Notice to Proceed.
The Contract Times associated with this milestone are similarly dependent upon the timely progress and completion of work performed by others that directly impacts installation and commissioning activities.
10.02 The phrase “available for Owner’s Use” does not mean physically capable of being utilized by Owner. The phrase “available for Owner’s Use” means that the Owner is able to commence and carry out its operations in accordance with the design intent of the Plans and Specifications and not alter its normal operating procedure as a result of any failure by Contractor to complete any aspect of that portion of the Work.
Instructions to Bidders ITB-8 ARM Group LLC
EJCDC® C-200, Instructions to Bidders for Construction Contract.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, Guidelines Page 8 of 15
ARTICLE 11—DAMAGES
11.01 Provisions for damages are set forth in the Agreement.
ARTICLE 12—SUBSTITUTE AND “OR EQUAL” ITEMS
12.01 The Contract, if awarded, will be on the basis of material and equipment described or specified in the Contract Documents without consideration of possible substitute "or equal" items. Whenever it is indicated in the Drawings or specified in the Specifications that a substitute or "or equal" item of material or equipment may be furnished or used by the Successful Bidder if acceptable to Owner, application for such acceptance will not be considered by Owner until after the "Effective Date of the Agreement". The procedure for submittal of any such application by Successful Bidder and consideration by Owner is set forth in Paragraphs 7.05 and 7.06 of the General Conditions.
ARTICLE 13—SUBCONTRACTORS, SUPPLIERS, AND OTHERS
13.01 Unless otherwise specified, the name of each Subcontractor, person, or organization proposed for the Work, all submittals required in the Contract Documents pertaining thereto, and Subcontractor's respective work to be performed shall be submitted by
Contractor to Owner not later than thirty (30) days before Subcontractor begins work on the Project.
13.02 No Successful Bidder shall be required to employ any Subcontractor, other person, or organization against whom he has reasonable objection.
13.03 After submission of the list described in Section 13.01 above, the Successful Bidder may change subcontractors, persons, or organizations proposed for the Work only with
Owner's written consent.
ARTICLE 14—PENNSYLVANIA STEEL PRODUCTS PROCUREMENT ACT (NO.
1978-3)
14.01 The Successful Bidder acknowledged familiarity with the requirements of the
Pennsylvania Steel Products Procurement Act (the “Steel Act”).
14.02 At the time of delivery of all products to which the Steel Act applies, the Successful Bidder will provide documentation, including but not limited to invoices, bills of lading invoices, and mill certification, and all other documentation or information required by the Owner to evidence compliance with the Steel Act.
14.03 The Successful Bidder acknowledges that failure of the Successful Bidder, or any
Subcontractors to provide documentation satisfying compliance with the Steel Act is a material breach of the Successful Bidder’s contractual obligation to the Owner.
14.04 The Successful Bidder acknowledges that determinations regarding compliance with these provisions and sufficiency of related documentation shall be at the sole discretion of the
Owner.
Instructions to Bidders ITB-9 ARM Group LLC
EJCDC® C-200, Instructions to Bidders for Construction Contract.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, Guidelines Page 9 of 15
14.05 This provision shall not apply in any case where the head of the public agency in writing, determines that the type of steel products necessary for the performance of the contract are not produced in the United States in sufficient quantities to meet the requirements of the contract.
ARTICLE 15—TRADE PRACTICES ACT
15.01 The Successful Bidder acknowledged familiarity with the requirements of the Trade
Practices Act (the “Trade Act”).
15.02 In accordance with the Trade Practices Act of July 23, 1968, P.L. 686 (71 P.S. § 773.101 et seq.), the Successful Bidder cannot and shall not use or permit to be used in the work any aluminum or steel products made in a foreign country which is listed below as a foreign country which discriminates against aluminum or steel products manufactured in
Pennsylvania. The countries of Argentina, Brazil, South Korea, and Spain have been found to discriminate against certain products manufactured in Pennsylvania. Therefore, the purchase or use of those countries' products, as listed below, is not permitted.
Therefore, the purchase or use of those countries' products, as listed below, is not permitted:
o Argentina: carbon steel wire rod and cold-rolled carbon steel sheet.
o Brazil: welded carbon steel pipes and tubes; carbon steel wire rod; tool steel; certain stainless steel products, including hot-rolled stainless steel bar; stainless steel wire rod and cold-formed stainless steel bar; prestressed concrete steel wire strand; hot-rolled carbon steel plate in coil; hot-rolled carbon steel sheet; carbon steel plate in coil; hot-rolled carbon steel sheet; and cold-rolled carbon steel sheet.
o South Korea: welded carbon steel pipes and tubes; hot-rolled carbon steel plate; hot-rolled carbon steel sheet; and galvanized steel sheet.
o Spain: certain stainless steel products, including stainless steel wire rod, hot- rolled stainless steel bars; and cold-formed stainless steel bars; prestressed concrete steel wire strand; and certain steel products, including hot-rolled steel plate, cold-rolled carbon steel plate, carbon steel structural shapes; galvanized carbon steel sheet, hot-rolled carbon steel bars, and cold-formed carbon steel bars.
15.03 At the time of delivery of all products to which the Trade Act applies, the Successful
Bidder will provide documentation, including but not limited to invoices, bills of lading invoices, and mill certification, and all other documentation or information required by the Owner to evidence compliance with the Trade Act.
15.04 The Successful Bidder acknowledges that failure of the Successful Bidder, or any
Subcontractors to provide documentation satisfying compliance with the Trade Act is a material breach of the Successful Bidder’s contractual obligation to the Owner.
15.05 The Successful Bidder acknowledges that determinations regarding compliance with these provisions and sufficiency of related documentation shall be at the sole discretion of the
Owner.
Instructions to Bidders ITB-10 ARM Group LLC
EJCDC® C-200, Instructions to Bidders for Construction Contract.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, Guidelines Page 10 of 15
ARTICLE 16—EMPLOYMENT GUIDELINES
16.01 Attention of Bidders is particularly called to the requirement for ensuring that employees and applicants for employment are not discriminated against because of their race, color, religion, sex, age, ancestry, national origin, or handicap. Responsibility under the
Immigration Reform and Control Act of 1986, for verifications of identity and employment eligibility in connection with Bidder’s own agents/servants, workers, and employees, is assumed and continues to be assumed and complied with by the Bidder.
The Bidder/Contractor expressly agrees to comply with the Americans with Disabilities
Act of 1990 (the “ADA”), and all other applicable Federal, State, and/or Local laws, ordinances, rules regulations and orders prohibiting discrimination in hiring or employment opportunities. Compliance is not delegable to any union, training program, or other source of recruitment, which prevents the Successful Bidder from meeting his/her obligations hereunder. The Successful Bidder has the responsibility and obligation to become aware of and comply with all applicable statutes, rules, regulations, etc. which affect this transaction in any regard.
ARTICLE 17—PREPARATION OF BID
17.01 The Bid Form is included with the Bidding Documents for Reference. Bidders shall complete the electronic bid form within PennBid (“Prepare Your Submission” tab).
17.02 A Bid by a corporation must be executed in the corporate name by a corporate officer
(whose title must appear under the signature), accompanied by evidence of authority to sign. The corporate address and state of incorporation must be shown.
17.03 A Bid by a partnership must be executed in the partnership name and signed by a partner
(whose title must appear under the signature), accompanied by evidence of authority to sign. The official address of the partnership must be shown.
17.04 The Bid must contain an acknowledgment of receipt of all Addenda, the numbers of which must be filled in on the Bid Form.
ARTICLE 18—BASIS OF BID
18.01 Lump Sum
o Bidders must submit a Bid on a lump sum basis as set forth in the Bid Form.
ARTICLE 19—SUBMITTAL OF BID
19.01 Bids shall be submitted online via the PennBid Program (https://pennbid.bonfirehub.com) by the date and time indicated in the Advertisement for Bids along with the Bid security and the other documents required to be submitted as identified herein.
19.02 Bids received after the date and time prescribed for the opening of bids, or not submitted at the correct location or in the designated manner, will not be accepted and will be returned to the Bidder unopened.
The following documents are submitted with and made a condition of this Bid:
Instructions to Bidders ITB-11 ARM Group LLC
EJCDC® C-200, Instructions to Bidders for Construction Contract.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, Guidelines Page 11 of 15 o Bid Form (with completed Pay Item Schedule & Acknowledgment of Addenda);
o Contractor Statement of Qualifications (with supporting documentation);
o Subcontractors and Suppliers Listing Form;
o Required Bid Bond;
o Consent of Surety;
o Non-Collusion Affidavit;
o Self-Certification of No Disbarment, Suspension, or Ineligibility;
o Commonwealth of Pennsylvania Public Works Employment Verification Form;
o Memorandum of Understanding;
o Hold Harmless Agreement; and o Asbestos-Free & Lead-Free Certification.
ARTICLE 20—MODIFICATION AND WITHDRAWAL OF BID
20.01 A Bid may be withdrawn or modified at any time within PennBid prior to the due date and time identified in the Invitation for Bids.
20.02 If a Bidder wishes to modify its Bid prior to Bid opening, Bidder must withdraw its initial
Bid in the manner specified in Paragraph 20.01 and submit a new Bid prior to the date and time for the opening of Bids.
20.03 No Bid may be withdrawn after the opening of Bids, except in accordance with
Pennsylvania law relating to the withdrawal of bids, Act 4, approved January 23, 1974, P.L. 9, Section 1 et. seq., as amended.
ARTICLE 21—OPENING OF BIDS
21.01 A summary of bids received will be issued via a Public Notice on PennBid shortly after bid opening, the time of which is listed in the Invitation to Bid. It should be noted that bid results are subject to further review and should not be construed as issuance of an award.
ARTICLE 22—BIDS TO REMAIN SUBJECT TO ACCEPTANCE
22.01 Each Bid shall remain subject to acceptance for sixty (60) days after the day of the Bid
Opening, but Owner may, in his sole discretion, release or reject any Bid and return the
Bid security prior to that date.
ARTICLE 23—EVALUATION OF BIDS AND AWARD OF CONTRACT
23.01 Owner reserves the right to reject any and all Bids, to waive any and all informalities, to negotiate with the Successful Bidder, and to disregard all non-conforming, non-responsive or conditional Bids. Discrepancies between words and figures will be resolved
Instructions to Bidders ITB-12 ARM Group LLC
EJCDC® C-200, Instructions to Bidders for Construction Contract.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, Guidelines Page 12 of 15 in favor of words. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum.
23.02 In evaluating Bids, Owner shall consider whether or not the Bids comply with the prescribed requirements.
23.03 Owner may consider the qualifications and experience of Subcontractors and other persons and organizations (including those who are to furnish the principal items of material or equipment) proposed for the Work. Operating costs, maintenance considerations, performance data and guarantees of materials and equipment may also be considered by Owner.
23.04 Owner may conduct such investigations as he deems necessary to assist in the evaluation of any Bid and to establish the responsibility, qualifications, and financial ability of any
Bidder or proposed Subcontractor to do the Work in accordance with the Contract
Documents to Owner's satisfaction within the prescribed time.
23.05 Owner reserves the right to reject the Bid of any Bidder who does not pass any such evaluation to Owner's satisfaction.
23.06 If the Contract is to be awarded, it will be awarded to the lowest Qualified Bidder whose evaluation by Owner indicates to Owner that the award will be in the best interests of the
Owner and the Project. The lowest Qualified Bidder is defined as the Bidder having submitted the lowest Total Bid Price.
23.07 Except as otherwise provided by law, if the Contract is to be awarded, Owner will give the Successful Bidder a Notice of Intent to Award within sixty (60) days after the day of the Bid Opening.
ARTICLE 24—PRE-BID CONFERENCE
24.01 A Pre-Bid Conference will be held at the time and place indicated in the Advertisement for Bids. Representatives of Owner will be present to discuss the Project. Bidders may attend and are encouraged to participate in the Conference. Owner will transmit to all Plan
Holders of record such Addenda as Owner considers necessary in response to questions arising at the Conference.
ARTICLE 25—SALES AND TAX
25.01 For purposes of Pennsylvania Sales and Use Tax, the Owner is a governmental entity which provides public utility services and all portions of the Work are exempt from
Pennsylvania Sales and Use Taxes, except all materials and equipment incorporated into any portion of the Project which do not become the possession of the Owner (e.g., temporary facilities, office equipment, etc.).
25.02 The Contract Price includes, and the Successful Bidder shall be responsible for, payment of all Sales and Use Taxes on the above portion of the Work which is not exempt, and for
Instructions to Bidders ITB-13 ARM Group LLC
EJCDC® C-200, Instructions to Bidders for Construction Contract.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, Guidelines Page 13 of 15 payment of all excise and other taxes. Additional information is provided in the
Supplementary Conditions regarding Pennsylvania Sales and Use Tax.
ARTICLE 26—PREVAILING WAGE
26.01 The Successful Bidder will be required to comply with the Pennsylvania Prevailing Wage
Act.
ARTICLE 27—EXECUTION OF AGREEMENT, BOND, INSURANCE AND ISSUANCE
OF NOTICE TO PROCEED
27.01 The Successful Bidder will be required, within ten (10) calendar days following Notice of
Intent to Award, to furnish to the Owner in at least three (3) counterparts, the Performance
Bond and Payment Bond, all in the form prescribed for execution of Bids, excepting that all general partners of a partnership shall sign the bonds. Both bonds shall have corporate surety satisfactory to the Owner, and authorized to conduct business in Pennsylvania; shall be paid for by the Successful Bidder and shall be in an amount equal to 100% of the
Contract Price. Within ten (10) calendar days following Notice of Intent to Award, the
Successful Bidder shall sign and deliver to the Owner in at least three (3) counterparts, the Contract and insurance policies, or certificates of insurance required by the Contract
Documents. Such insurance policies or certificates shall state that the insurance cannot be cancelled without approval of or reasonable written notice to the Owner. Within thirty
(30) calendar days upon receipt of the above documentation in the form prescribed by these Contract Documents, the Owner will execute the Contract and issue the Notices to
Proceed for the Project specified in Paragraph 27.02.
27.02 The following is the anticipated time schedule for execution of the Agreement:
o Bids Received: On the date stated in the Invitation to Bid o Notice of Intent to Award: Within Sixty (60) days after Bid receipt o Submit Insurance Certificates, Bonds and executed Agreement: Within ten (10) days from date of Notice of Intent to Award o Limited Notice to Proceed: Within thirty (30) days of receipt of properly executed
Insurance Certificates, Bonds and Contract
• Authorizes the contractor to begin specific activities (e.g., mobilization, design work, procurement of long-lead materials, site preparation, submittals). Contractor is limited to the scope and costs identified in this step.
o Final Notice to Proceed: Onsite construction activities will begin once building permit is obtained by Owner.
• Grants full authorization for construction and contractual obligations after Owner obtains building permits.
o Complete the Work: By the Time indicated in the Contract Documents
Successful Bidders are to expedite the signature of all agreements and the satisfactory provisions of all bonds and insurances to meet this schedule. Time is of the essence for this project.
Instructions to Bidders ITB-14 ARM Group LLC
EJCDC® C-200, Instructions to Bidders for Construction Contract.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, Guidelines Page 14 of 15
ARTICLE 28—PAYMENTS
28.01 The Owner shall pay the Contractor for the Work subject to additions and deductions and retainage, in accordance with the unit prices and/or lump sum prices stipulated in his Bid and as outlined in the Agreement.
28.02 Payments shall be made, in monthly installments, according to the valuation of Work done, in accordance with the Contractor’s applications for payment to the extent the same may be approved for payment by the Owner. Such applications shall be made to the
Owner not later than the twenty-eighth (28th) day of each month, for work done and materials incorporated into the Work up to the date of the application for payment and, within ten (10) days thereafter, the Owner will direct that payment be made to the
Contractor.
28.03 The Owner is hereby authorized to expend so much of the retained percentage as may be required in making repairs and corrections of any defective work, if within seventy-two
(72) hours of delivery of written notice to the Contractor, or his agent, he or they shall neglect to make needed repairs and corrections as directed by the Owner.
ARTICLE 29— NOTICE TO SUCCESSFUL BIDDER
29.01 The residence or place of business designated in the bid or proposal is hereby designated as the place to which all notices, letters or other communications shall be served, and to which all notices, letters and other communications shall be mailed or delivered. All notices specifically mentioned herein, and all other communications of any kind which may be hereafter dispatched, may be sent by regular mail and the Successful Bidder shall be deemed to receive said notice. If the communications in question have been addressed to the Successful Bidder at the aforesaid address and have been deposited in the United
States Postal Service, the date of the service of the notice or other communications upon the Successful Bidder personally will be date of postmark.
ARTICLE 30—INSPECTIONS
30.01 The Owner, or its authorized representative, may inspect the services being provided pursuant to this contract; and may require the correction of any improper performance or any deficient performance herein through the designated supervisor of the Contractor.
ARTICLE 31—ASSIGNMENTS
31.01 Neither the contract, nor any portion thereof, may be assigned, sub-let, or transferred to any person, firm, or corporation, except upon the written consent and approval of the
Owner.
ARTICLE 32—INSURANCE
32.01 The Bidder shall not commence work under the Contract until he has obtained all insurance required under Contract Documents and such insurance has been approved by
Instructions to Bidders ITB-15 ARM Group LLC
EJCDC® C-200, Instructions to Bidders for Construction Contract.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, Guidelines Page 15 of 15 the Owner nor shall the Bidder allow any subcontractor to commence work on his sub-contract until all insurance requirements have been so met and approved.
32.02 The Bidder shall take out and maintain during the life of this contract, Workers'
Compensation Insurance for all of his employees employed at the site of the project, and in case any work is sublet, the Successful Bidder shall require the subcontractor similarly to provide Workers' Compensation for all the latter's employed unless such employees are covered by the protection afforded by the Bidder.
32.03 The Bidder shall take out and maintain during the life of this Contract such Public Liability and Property Damage Insurance as shall protect his and any subcontractor performing work covered by this contract from claims for damages for personal injury, including accidental death, as well as from claims for property damages, which may arise from operations under this contract, whether such operations be by himself or by any subcontractor or by anyone directly or indirectly with the Owner and the Commonwealth of Pennsylvania identified under such insurance policy as an "additional named insured" with proof (i.e., Certificate of Insurance) of such coverage provided in the amounts noted in Section “SC-6.03 Contractor’s Insurance” of the Supplementary Conditions.
ARTICLE 33—WORKING HOURS
33.01 Allowable working hours shall be Monday through Friday, 7:00 A.M. until 4:30 P.M.
Should the Contractor require and/or prefer working hours that are different from those listed above, Contractor will be required to submit a formal request to modify the allowable working hours for the project. No Contractor personnel shall be on-site during any other time (other than for emergency reasons) without prior approval of the Owner.
If required to prevent any of the work from obstructing, hindering, or stopping normal operations onsite, the Contractor may request approval from the Owner to perform work outside of the allowable working hours.
ARTICLE 34—SITE CONDITIONS DURING CONSTRUCTION
34.01 The Contractor will be required to minimize disruption to utilities, operations, etc.
34.02 The Contractor may not have exclusive occupancy of the site. In his operations for Work under this Contract, he shall cooperate with, and coordinate his operations with, those of the Owner, other contractors, trades, and work forces, if required.
34.03 Additional information regarding other work during construction is provided in General
Conditions.
Bid Form – Stationary Electric Material Handlers BF-1 ARM Group LLC
EJCDC® C-410, Bid Form for Construction Contract.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
BID FORM – STATIONARY ELECTRIC MATERIAL HANDLERS
The terms used in this Bid with initial capital letters have the meanings stated in the Instructions to Bidders, and the General Conditions.
ARTICLE 1—OWNER AND BIDDER
1.01 This Bid is submitted to the York County Solid Waste and Refuse Authority.
1.02 The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement with Owner in the form included in the Bidding Documents to perform all Work as specified or indicated in the Bidding Documents for the prices and within the times indicated in this Bid and in accordance with the other terms and conditions of the Bidding Documents.
ARTICLE 2—ATTACHMENTS TO THIS BID
2.01 The following documents are submitted with and made a condition of this Bid:
A. Bid Form (with completed Pay Item Schedule & Acknowledgment of Addenda);
B. Contractor Statement of Qualifications (with supporting documentation);
C. Subcontractors and Supplier Listing Forms;
D. Required Bid Bond;
E. Consent of Surety;
F. Non-Collusion Affidavit;
G. Self-Certification of No Disbarment, Suspension, or Ineligibility;
H. Commonwealth of Pennsylvania Public Works Employment Verification Form;
I. Memorandum of Understanding;
J. Hold Harmless Agreement; and
K. Asbestos-Free & Lead-Free Certification.
ARTICLE 3—BASIS OF BID—LUMP SUM BID AND UNIT PRICES
3.01 Bidder will complete the Work in accordance with the Contract Documents for the following price(s):
Pay Item 1 (Base Bid) – Contract – Stationary Electric Material Handlers
A. Scope of work includes, but is not limited to, the following:
• All work associated with the Stationary Electric Material Handlers for the Blackbridge Road Transfer Station Project, as indicated on the Contract Drawings and specified in the Technical Specifications and other Contract Documents.
Bid Form – Stationary Electric Material Handlers BF-2 ARM Group LLC
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
• The Stationary Electric Material Handlers Contractor shall be responsible for furnishing all materials, labor, equipment, coordination, and installation required to provide fully installed, tested, and operational stationary electric material handler systems within the building.
B. The lump sum price shall include, but not limited to, and cover the furnishing of all materials, labor, tools, and equipment necessary for the Contractor to mobilize, including the initial movement of personnel and equipment to the project site as herein specified;
application, fee payment and acquisition of all necessary permits; the establishment of Contractor’s shops, plants, storage areas, field office(s) and any other equipment and/or facilities required; and insurance, bonds, and other initial expenses required for the start of work.
C. The lump sum price shall also include, but not limited to, and cover demobilizing all materials, labor, tools, and personnel and equipment from the Project site; dismantling of Contractor’s shops, plants, storage areas, field office(s), and/or any other equipment, facilities, or activities required for project closeout.
D. The lump sum price shall include, but not limited to, and cover the furnishing of all required materials not specifically listed as owner supplied, labor, tools, supplies, transportation;
storage; flagman; signage; and equipment necessary to complete the project activities associated with the Blackbridge Road Transfer Station Construction, as required and/or depicted in the Contract Documents.
E. Unless Engineer and/or Owner has directed in writing that the work vary from that indicated in the contract documents, the payment amount shall not exceed the price in the Pay Item Schedule.
Bid Form – Stationary Electric Material Handlers BF-3 ARM Group LLC
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
SUMMARY OF PAY ITEM SCHEDULE
(TO BE…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .