This document is a scope of work and technical specifications for a cement plaster (stucco) repair project for the Renwick Courthouse Bell Tower in the City of Fredericksburg, Virginia. The project includes miscellaneous repairs to the bell tower, such as repairing delaminated and/or unbonded stucco, repairing cracks in stucco, and installing new control joints in the stucco veneer. The project includes allowances for up to 100 square feet of stucco patch repair, 200 linear feet of crack repair, and 20 linear feet of control joint installation. Mockups are required, and the completed work must have a uniform appearance. The project is subject to ASTM C926 requirements for cement plastering.
The contract documents include a unit pricing schedule for any quantities that exceed the allowances. Contractors must maintain accurate records and submit updated documentation with each payment application. The project is funded by the City of Fredericksburg, and the contract term is not specified.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Renwick Courthouse Bell Tower, Bid Set (Rev – Addendum 3) August 20, 2024 City of Fredericksburg STRUCTURAL REPAIRS
092400 - CEMENT PLASTERING Page 1 of 6
SECTION 092400 - CEMENT PLASTER (STUCCO) REPAIR
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
1. Miscellaneous repairs at bell tower.
B. Related Sections:
1. §012100 “Allowances”.
2. §012200 “Unit Prices”.
3. §024119 “Selective Demolition”.
1.3 ACTION SUBMITTALS
A. Product Data: For each type of product.
B. Mock-ups: Install site-prepared base and finish coats to match adjacent. Finish must be acceptable to Review Board.
1.4 QUALITY ASSURANCE
A. Mockups: Build mockups to verify selections made under Sample submittals, to demonstrate aesthetic effects, and to set quality standards for materials and execution.
1. Build mockups for each substrate and finish texture indicated for cement plastering, including accessories.
a. Size: 2 square feet in surface area.
2. Approval of mockups does not constitute approval of deviations from the Contract Documents contained in mockups unless Architect specifically approves such deviations in writing.
3. Subject to compliance with requirements, approved mockups may become part of the completed Work if undisturbed at time of Substantial Completion.
092400 - CEMENT PLASTERING Page 2 of 6
1.5 PRECONSTRUCTION TESTING
A. Preconstruction Testing Service: Engage a qualified testing agency to perform preconstruction testing on stucco as follows:
1. Provide test specimens as indicated below and representative of proposed materials and existing construction.
2. Existing Stucco: Test and match according to ASTM C1324, modified as agreed by testing service and Engineer for Project requirements, to determine proportional composition of original ingredients, sizes and colors of aggregates, and approximate strength of the following:
a. Base-Coat Cement Plaster
b. Cement Plaster Finish Coat
3. Temporary Patch: As directed by Engineer, provide temporary materials followed by permanent repairs at locations from which existing samples were taken.
1.6 DELIVERY, STORAGE, AND HANDLING
A. Store materials inside under cover, and keep them dry and protected against damage from weather, moisture, direct sunlight, surface contamination, corrosion, construction traffic, and other causes.
1.7 FIELD CONDITIONS
A. Comply with ASTM C 926 requirements.
B. Exterior Plasterwork:
1. Apply and cure plaster to prevent plaster drying out during curing period. Use procedures required by climatic conditions, including moist curing, providing coverings, and providing barriers to deflect sunlight and wind.
2. Apply plaster when ambient temperature is greater than 40 deg F, and will remain above 40 deg F for at least three (3) days after application.
3. Protect plaster coats from freezing for not less than 48 hours after set of plaster coat has occurred.
C. Factory-Prepared Finishes: Comply with manufacturer's written recommendations for environmental conditions for applying finishes.
PART 2 - PRODUCTS
2.1 METAL LATH
A. Expanded-Metal Lath: ASTM C 847, cold-rolled carbon-steel sheet with ASTM A 653/A 653M, G60, hot-dip galvanized-zinc coating.
092400 - CEMENT PLASTERING Page 3 of 6
2.2 MISCELLANEOUS MATERIALS
A. Water for Mixing and Finishing Plaster: Potable and free of substances capable of affecting plaster set or of damaging plaster, lath, or accessories.
B. Fiber for Base Coat: Alkaline-resistant glass or polypropylene fibers, 1/2 inch long, free of contaminants, manufactured for use in cement plaster.
C. Fasteners for Attaching Metal Lath to Substrates: ASTM C 1063.
D. Wire: ASTM A 641, Class 1 zinc coating, soft temper, not less than 0.0475-inch diameter unless otherwise indicated.
2.3 PLASTER MATERIALS
A. Portland Cement: ASTM C 150, Type II.
1. Color for Finish Coats: Match existing.
B. Colorants for Job-Mixed Finish Coats: Colorfast mineral pigments that produce finish plaster color to match existing color.
C. Lime: ASTM C 206, Type S; or ASTM C 207, Type S.
D. Sand Aggregate: ASTM C 897.
E. Acrylic-Based Finish Coatings: Factory-mixed acrylic-emulsion coating systems formulated with colorfast mineral pigments and fine aggregates; for use over cement plaster base coats. Include manufacturer's recommended primers and sealing topcoats for acrylic-based finishes.
1. Color: Match existing and ss selected by Engineer/Owner’s Representative from mock-ups.
2.4 BASE-COAT CEMENT PLASTER
A. General: Comply with ASTM C926 for applications indicated.
1. Fiber Content: Add fiber to base-coat mixes after ingredients have mixed at least two minutes.
Comply with fiber manufacturer's written instructions for fiber quantities in mixes, but do not exceed 1 lb of fiber/cu. yd. (0.6 kg of fiber/cu. m) of cementitious materials.
B. Base-Coat Mixes for Use over Low-Absorption Unit Masonry and Concrete: Single base (scratch) coat for two-coat plasterwork on low-absorption plaster bases as follows:
1. Portland Cement Mix: For cementitious material, mix 1 part portland cement and 0 to 3/4 part lime. Use 2-1/2 to 4 parts aggregate per part of cementitious material.
092400 - CEMENT PLASTERING Page 4 of 6
2.5 CEMENT PLASTER FINISH COATS
A. Job-Mixed Finish-Coat Mixes:
1. Portland Cement Mix: For cementitious materials, mix 1 part portland cement and 1-1/2 to 2 parts lime. Use 1-1/2 to 3 parts aggregate per part of cementitious material.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine substrates and conditions, with Installer present, for compliance with requirements for installation tolerances and other conditions affecting performance of the Work.
B. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 PREPARATION
A. Protect adjacent work from soiling, spattering, moisture deterioration, and other harmful effects caused by plastering.
B. Prepare smooth, solid substrates for plaster according to ASTM C 926.
3.3 EXAMINATION
A. Examine substrates, areas, and conditions, with Installer present for compliance with requirements for substrate and environmental conditions, installation tolerances, and other conditions affecting performance of the Work.
1. If existing substrates cannot be prepared to an acceptable condition for stucco repair work, notify Engineer in writing.
2. Notify Engineer of undocumented detrimental conditions including cracks, bulges, loose backup, rotted wood, rusted metal, and other deteriorated items.
B. Begin historic plastering work only after unsatisfactory conditions have been corrected.
3.4 PLASTER APPLICATION - GENERAL
A. Completed work is to have a uniform appearance as viewed by Engineer from building interior at 5 feet away from surface and from building exterior at 12 feet away from surface.
B. General: In treating historic plaster, disturb it as minimally as possible and as follows unless otherwise indicated:
1. Dismantle loose, damaged, or deteriorated plaster, lath and support systems that cannot be repaired.
092400 - CEMENT PLASTERING Page 5 of 6
2. Verify extent of plaster deterioration before commencing work. Consult Engineer on types and extent of required work.
3. Verify that substrate surface conditions are suitable for repairs.
4. Provide lath, furring, and support systems for plater included in the work of this Section.
5. Replace lost details in new, wet applied plaster that replicate existing textures at adjacent sound materials.
6. Do not deviate more than plus or minus 1/4 inch in 10 feet from a true plane in finished plaster surfaces when measured by a 10-foot straightedge placed on surface.
7. Provide plaster surfaces that are ready to receive field-applied finishes indicated.
8. Finish plaster flush with metal frames and other built-in metal items or accessories that act as a plaster ground unless otherwise indicated. Where casing bead does not terminate plaster at metal frame, cut base coat free from metal frame before plaster sets and groove finish coat at junctures with metal.
9. Install temporary protective measures to protect historic surfaces that shall be treated later.
C. Comply with ASTM C 926.
D. Bonding Compound: Apply on unit masonry and concrete substrates for direct application of plaster.
3.5 PATCH STUCCO (Workcode R1ST)
A. Repair delaminated and/or unbonded stucco. In designated areas, gently sound with a hammer all surfaces covered with stucco to locate all unsound or unbonded stucco. Notify Engineer if additional areas are discovered. Work beyond the allowance quantity must be approved prior to performing work.
B. After delaminated stucco is removed, saw cut (at a 45 degree angle) the perimeters of patch areas to provide a keyed bond for the patch. Then, clean (with high pressure water) the areas to receive new stucco to remove any remaining dust or debris and to dampen the surface. Inspect masonry or concrete substrates below and repair deteriorated surfaces prior to placing stucco. Allow substrate repair to cure before covering with stucco. Cover prepared surfaces with the Manufacturer's bonding agent. Apply a tight, thin coat of stucco over the entire surface. Fill entire area with stucco and cure in accordance with the stucco Manufacturer's recommendations and specifications. At a minimum, cure patches by covering with wet burlap and polyethylene sheets for 48 hours.
C. An allowance of 100 square feet of Workcode R1ST shall be included in the base bid (see §004321 “Allowance Form” and §012100 “Allowances”). In the event that total quantity of the workcode exceeds the specified allowances, the additional quantity shall be reimbursed on a unit price basis, per square foot (see §004322 “Unit Prices Form” and §012200 “Unit Prices”).
D. The Contractor must maintain accurate records and shop drawings and submit updated documentation with each payment application.
3.6 REPAIR CRACK IN STUCCO (Workcode R4ST)
A. Repair cracks in stucco where specifically directed by Engineer.
092400 - CEMENT PLASTERING Page 6 of 6
B. Remove previous repair materials to surface of adjacent substrates. Repair hairline cracks (less than 1/16 inch in width) in substrates by filling with a brush coat of coating. Repair cracks greater than 1/16 inch by routing the crack to minimum 1/4 inch deep, installing a bond breaker tape (depth less than 3/8 inch) or backer rod (depth greater than 3/8 inch) and installing sealant. Comply with the sealant joint width-to-depth ratios shown on Drawings. Broadcast sand into the sealant to provide a textured surface matching the existing.
C. When completed and coated, the repaired surface must not be visible and blend in with the adjacent surface. Acceptable repair surface will be established by the mock-up installation.
D. An allowance of 200 lineal feet of Workcode R4ST shall be included in the base bid (see §004321 “Allowance Form” and §012100 “Allowances”). In the event that total quantity of the workcode exceeds the specified allowances, the additional quantity shall be reimbursed on a unit price basis, per lineal foot (see §004322 “Unit Prices Form” and §012200 “Unit Prices”).
E. The Contractor must maintain accurate records and shop drawings and submit updated documentation with each payment application.
3.7 INSTALL CONTROL JOINT IN STUCCO VENEER (Workcode X1ST)
A. Install new control joints in stucco where specifically directed by Engineer.
B. At designated vertical crack locations, neatly saw cut 5/8-inch wide slot in existing stucco to and approximate 1/2-inch depth. Install backer rod and sealant. Comply with the sealant joint width-to-depth ratios as shown on Drawings. Broadcast sand into the sealant to provide a textured surface matching the existing.
C. When completed and coated, the repaired surface must not be visible and blend in with the adjacent surface. Acceptable repair surface will be established by the mock-up installation.
D. An allowance of 20 lineal feet of Workcode X1ST shall be included in the base bid (see §004321 “Allowance Form” and §012100 “Allowances”). In the event that total quantity of the workcode exceeds the specified allowances, the additional quantity shall be reimbursed on a unit price basis, per lineal foot (see §004322 “Unit Prices Form” and §012200 “Unit Prices”).
E. The Contractor must maintain accurate records and shop drawings and submit updated documentation with each payment application.
3.8 CLEANING AND PROTECTION
A. Remove temporary protection and enclosure of other work after plastering is complete. Promptly remove plaster from door frames, windows, and other surfaces not indicated to be plastered. Repair floors, walls, and other surfaces stained, marred, or otherwise damaged during plastering.
END OF SECTION 092400
| PART 1 - GENERAL |
| 1.1 RELATED DOCUMENTS |
| A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section. |
| 1.2 SUMMARY |
| A. Section Includes: |
| 1. Miscellaneous repairs at bell tower. |
| B. Related Sections: |
| 1. §012100 “Allowances”. |
| 1.3 ACTION SUBMITTALS |
| A. Product Data: For each type of product. |
| B. Mock-ups: Install site-prepared base and finish coats to match adjacent. Finish must be acceptable to Review Board. |
| 1.4 QUALITY ASSURANCE |
| A. Mockups: Build mockups to verify selections made under Sample submittals, to demonstrate aesthetic effects, and to set quality standards for materials and execution. |
| 1. Build mockups for each substrate and finish texture indicated for cement plastering, including accessories. |
| 2. Approval of mockups does not constitute approval of deviations from the Contract Documents contained in mockups unless Architect specifically approves such deviations in writing. |
| 3. Subject to compliance with requirements, approved mockups may become part of the completed Work if undisturbed at time of Substantial Completion. |
| 1.5 PRECONSTRUCTION TESTING |
| A. Preconstruction Testing Service: Engage a qualified testing agency to perform preconstruction testing on stucco as follows: |
| 1. Provide test specimens as indicated below and representative of proposed materials and existing construction. |
| a. Base-Coat Cement Plaster |
| b. Cement Plaster Finish Coat |
3. Temporary Patch: As directed by Engineer, provide temporary materials followed by permanent repairs at locations from which existing samples were taken.
| 1.6 DELIVERY, STORAGE, AND HANDLING |
| A. Store materials inside under cover, and keep them dry and protected against damage from weather, moisture, direct sunlight, surface contamination, corrosion, construction traffic, and other causes. |
| 1.7 FIELD CONDITIONS |
| A. Comply with ASTM C 926 requirements. |
| B. Exterior Plasterwork: |
| 1. Apply and cure plaster to prevent plaster drying out during curing period. Use procedures required by climatic conditions, including moist curing, providing coverings, and providing barriers to deflect sunlight and wind. |
| 2. Apply plaster when ambient temperature is greater than 40 deg F, and will remain above 40 deg F for at least three (3) days after application. |
| 3. Protect plaster coats from freezing for not less than 48 hours after set of plaster coat has occurred. |
C. Factory-Prepared Finishes: Comply with manufacturer's written recommendations for environmental conditions for applying finishes.
| PART 2 - PRODUCTS |
| 2.1 METAL LATH |
| A. Expanded-Metal Lath: ASTM C 847, cold-rolled carbon-steel sheet with ASTM A 653/A 653M, G60, hot-dip galvanized-zinc coating. |
| 2.2 MISCELLANEOUS MATERIALS |
| A. Water for Mixing and Finishing Plaster: Potable and free of substances capable of affecting plaster set or of damaging plaster, lath, or accessories. |
| B. Fiber for Base Coat: Alkaline-resistant glass or polypropylene fibers, 1/2 inch long, free of contaminants, manufactured for use in cement plaster. |
| C. Fasteners for Attaching Metal Lath to Substrates: ASTM C 1063. |
| D. Wire: ASTM A 641, Class 1 zinc coating, soft temper, not less than 0.0475-inch diameter unless otherwise indicated. |
| 2.3 PLASTER MATERIALS |
| A. Portland Cement: ASTM C 150, Type II. |
| 1. Color for Finish Coats: Match existing. |
| B. Colorants for Job-Mixed Finish Coats: Colorfast mineral pigments that produce finish plaster color to match existing color. |
| C. Lime: ASTM C 206, Type S; or ASTM C 207, Type S. |
| D. Sand Aggregate: ASTM C 897. |
| E. Acrylic-Based Finish Coatings: Factory-mixed acrylic-emulsion coating systems formulated with colorfast mineral pigments and fine aggregates; for use over cement plaster base coats. Include manufacturer's recommended primers and sealing topcoats fo... |
| 1. Color: Match existing and ss selected by Engineer/Owner’s Representative from mock-ups. |
| 2.4 BASE-COAT CEMENT PLASTER |
| A. General: Comply with ASTM C926 for applications indicated. |
| 1. Fiber Content: Add fiber to base-coat mixes after ingredients have mixed at least two minutes. Comply with fiber manufacturer's written instructions for fiber quantities in mixes, but do not exceed 1 lb of fiber/cu. yd. (0.6 kg of fiber/cu. m) of c... |
| B. Base-Coat Mixes for Use over Low-Absorption Unit Masonry and Concrete: Single base (scratch) coat for two-coat plasterwork on low-absorption plaster bases as follows: |
| 1. Portland Cement Mix: For cementitious material, mix 1 part portland cement and 0 to 3/4 part lime. Use 2-1/2 to 4 parts aggregate per part of cementitious material. |
| 2.5 CEMENT PLASTER FINISH COATS |
| A. Job-Mixed Finish-Coat Mixes: |
| 1. Portland Cement Mix: For cementitious materials, mix 1 part portland cement and 1-1/2 to 2 parts lime. Use 1-1/2 to 3 parts aggregate per part of cementitious material. |
| PART 3 - EXECUTION |
| 3.1 EXAMINATION |
| A. Examine substrates and conditions, with Installer present, for compliance with requirements for installation tolerances and other conditions affecting performance of the Work. |
| B. Proceed with installation only after unsatisfactory conditions have been corrected. |
| 3.2 PREPARATION |
| A. Protect adjacent work from soiling, spattering, moisture deterioration, and other harmful effects caused by plastering. |
| B. Prepare smooth, solid substrates for plaster according to ASTM C 926. |
| 3.3 EXAMINATION |
| A. Examine substrates, areas, and conditions, with Installer present for compliance with requirements for substrate and environmental conditions, installation tolerances, and other conditions affecting performance of the Work. |
| 1. If existing substrates cannot be prepared to an acceptable condition for stucco repair work, notify Engineer in writing. |
| 2. Notify Engineer of undocumented detrimental conditions including cracks, bulges, loose backup, rotted wood, rusted metal, and other deteriorated items. |
B. Begin historic plastering work only after unsatisfactory conditions have been corrected.
| 3.4 PLASTER APPLICATION - GENERAL |
| A. Completed work is to have a uniform appearance as viewed by Engineer from building interior at 5 feet away from surface and from building exterior at 12 feet away from surface. |
| B. General: In treating historic plaster, disturb it as minimally as possible and as follows unless otherwise indicated: |
| 1. Dismantle loose, damaged, or deteriorated plaster, lath and support systems that cannot be repaired. |
| 2. Verify extent of plaster deterioration before commencing work. Consult Engineer on types and extent of required work. |
| 3. Verify that substrate surface conditions are suitable for repairs. |
| 4. Provide lath, furring, and support systems for plater included in the work of this Section. |
| 5. Replace lost details in new, wet applied plaster that replicate existing textures at adjacent sound materials. |
| 7. Provide plaster surfaces that are ready to receive field-applied finishes indicated. |
| 8. Finish plaster flush with metal frames and other built-in metal items or accessories that act as a plaster ground unless otherwise indicated. Where casing bead does not terminate plaster at metal frame, cut base coat free from metal frame before pl... |
| 9. Install temporary protective measures to protect historic surfaces that shall be treated later. |
| C. Comply with ASTM C 926. |
| D. Bonding Compound: Apply on unit masonry and concrete substrates for direct application of plaster. |
| 3.5 PATCH STUCCO (Workcode R1ST) |
| A. Repair delaminated and/or unbonded stucco. In designated areas, gently sound with a hammer all surfaces covered with stucco to locate all unsound or unbonded stucco. Notify Engineer if additional areas are discovered. Work beyond the allowance q... |
| B. After delaminated stucco is removed, saw cut (at a 45 degree angle) the perimeters of patch areas to provide a keyed bond for the patch. Then, clean (with high pressure water) the areas to receive new stucco to remove any remaining dust or debris ... |
| C. An allowance of 100 square feet of Workcode R1ST shall be included in the base bid (see §004321 “Allowance Form” and §012100 “Allowances”). In the event that total quantity of the workcode exceeds the specified allowances, the additional quantity ... |
| D. The Contractor must maintain accurate records and shop drawings and submit updated documentation with each payment application. |
| 3.6 REPAIR CRACK IN STUCCO (Workcode R4ST) |
| A. Repair cracks in stucco where specifically directed by Engineer. |
| B. Remove previous repair materials to surface of adjacent substrates. Repair hairline cracks (less than 1/16 inch in width) in substrates by filling with a brush coat of coating. Repair cracks greater than 1/16 inch by routing the crack to minimum ... |
| C. When completed and coated, the repaired surface must not be visible and blend in with the adjacent surface. Acceptable repair surface will be established by the mock-up installation. |
| D. An allowance of 200 lineal feet of Workcode R4ST shall be included in the base bid (see §004321 “Allowance Form” and §012100 “Allowances”). In the event that total quantity of the workcode exceeds the specified allowances, the additional quantity ... |
| E. The Contractor must maintain accurate records and shop drawings and submit updated documentation with each payment application. |
| 3.7 INSTALL CONTROL JOINT IN STUCCO VENEER (Workcode X1ST) |
| A. Install new control joints in stucco where specifically directed by Engineer. |
| B. At designated vertical crack locations, neatly saw cut 5/8-inch wide slot in existing stucco to and approximate 1/2-inch depth. Install backer rod and sealant. Comply with the sealant joint width-to-depth ratios as shown on Drawings. Broadcast sa... |
| C. When completed and coated, the repaired surface must not be visible and blend in with the adjacent surface. Acceptable repair surface will be established by the mock-up installation. |
| D. An allowance of 20 lineal feet of Workcode X1ST shall be included in the base bid (see §004321 “Allowance Form” and §012100 “Allowances”). In the event that total quantity of the workcode exceeds the specified allowances, the additional quantity s... |
| E. The Contractor must maintain accurate records and shop drawings and submit updated documentation with each payment application. |
| 3.8 CLEANING AND PROTECTION |
| A. Remove temporary protection and enclosure of other work after plastering is complete. Promptly remove plaster from door frames, windows, and other surfaces not indicated to be plastered. Repair floors, walls, and other surfaces stained, marred, or ... |