This document appears to be a Condition Table for the three-year asbestos re-inspection of Buildings 14 and 17 at the Waco VA Medical Center. It provides detailed information on the condition and removal priority of asbestos-containing materials (ACM) found throughout the buildings, including pipe insulation, boiler stacks, floor tiles, and miscellaneous materials. The table includes a qualitative ranking and quantitative rating system for assessing the current condition, potential for disturbance, and removal priority of the ACM.
The related federal contract opportunity is a solicitation (Solicitation Number: 36C25724B0015) for the abatement and clean-up of Buildings 14 and 17 at the Doris Miller VA Medical Center in Waco, Texas. The Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 17 is the agency responsible for this requirement.
View the file
Other files
Show all 27
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
HMA
| Homogeneous Area No. | Bldg | Floor | Material Description | Friable Yes/No | Accessibility Yes/No Restricted | Current Condition 1 | Potential for Disturbance 2 | Removal Priority 3 | |||
| Rating | Based On | Rating | Based On | ||||||||
| Building 14 - First Floor | |||||||||||
| HMA-02 | 14 | Lower Level | Pipe Insulation and Fittings | Yes | No | 7 | Damage | 2 | Access | 6 | |
| HMA-02 | 14 | Upper Level/ Mezzanine | Pipe Insulation and Fittings | Yes | No | 7 | Damage | 2 | Access | 6 | |
| HMA-02 | 14 | Generator Rm & Corridor | Pipe Insulation and Fittings | Yes | No | 7 | Damage | 2 | Access | 6 | |
| HMA-02 | 14 | North Wall Detail A-A' | Pipe Insulation and Fittings | Yes | No | 7 | Damage | 2 | Access | 6 | |
| HMA-02 | 14 | North Wall Detail B-B' | Pipe Insulation and Fittings | Yes | No | 7 | Damage | 2 | Access | 6 | |
| HMA-02 | 14 | East Wall | |||||||||
| Detail C-C' | Pipe Insulation and Fittings | Yes | No | 7 | Damage | 2 | Access | 6 | |||
| HMA-02 | 14 | Under Condensate Tank Detail | |||||||||
| D-D' | Pipe Insulation and Fittings | Yes | No | 7 | Damage | 2 | Access | 6 | |||
| HMA-02 | 14 | Under Deaerator Tank Detail E-E' | Pipe Insulation and Fittings | Yes | No | 7 | Damage | 2 | Access | 6 | |
| HMA-02 | 14 | Heater Piping Detail F-F' | Pipe Insulation and Fittings | Yes | No | 7 | Damage | 2 | Access | 6 | |
| HMA-04 | 14 | Boiler Stack Detail G | White Cloth Material | Yes | Yes | 8 | Intact | 2 | Access | 9 | |
| HMA-05 | 14 | Boiler Stack Detail G | Gasket Material | No | No | 9 | Intact | 1 | Maintenance | 9 | |
| HMA-04 | 14 | Boiler Stack Detail H | White Cloth Material | Yes | Yes | 8 | Intact | 2 | Access | 9 | |
| HMA-05 | 14 | Boiler Stack Detail H | Gasket Material | No | No | 9 | Intact | 1 | Maintenance | 9 | |
| Building 14 - Second Floor | |||||||||||
| HMA-01 | 14 | 2 | 12x12 Floor Tile and Mastic | No | Yes | 10 | Intact | 2 | Floor Maintenance | 7 | |
| HMA-02 | 14 | 2 | Pipe Insulation and Fittings | Yes | No | 7 | Damage | 2 | Access | 6 | |
| HMA-03 | 14 | 2 | Black Sink Undercoating | No | No | 10 | Intact | 1 | Maintenance | 10 | |
| Building 14 - Roof | |||||||||||
| No ACM |
&L&"Times New Roman,Regular"&11 &C&"Times New Roman,Bold"&12WACO V. A. MEDICAL CENTER
2016 THREE-YEAR ASBESTOS REINSPECTION
CONDITION AND REMOVAL PRIORITY TABLE&R&"Times New Roman,Regular"&11 &CPage &P of &N
Tables
| 1 Qualitative Rankings and Quantitative (Numerical) Ratings for Current Condition | |||
| Qualitative Ranking | Numerical Rating | Description of Current Condition | |
| Good | 8, 9, 10 | Surfacing material has no visible damage or small amounts of damage; covering on thermal system insulation is intact or has small amounts of damage; miscellaneous materials intact; no visible debris or small amounts of debris. | |
| Fair | 4, 5, 6, 7 | Surfacing material has moderate but not extensive amounts of visible damage; covering on thermal system insulation is cut or torn, exposing moderate but not extensive amounts of insulation; moderate but not extensive damage to miscellaneous materials such as floor tile; moderate but not extensive amounts of visible dust and debris.. | |
| Poor | 1, 2, 3 | Extensive damage to surfacing material; covering on thermal system insulation is cut or torn extensively and insulation itself is damage; miscellaneous materials such as floor tile extensively damaged and underlying mastic exposed; extensive amounts of dust and debris. | |
| 2 Qualitative Rankings and Quantitative (Numerical) Ratings for Potential for Disturbance | |||
| Qualitative Ranking | Numerical Rating | Assessment Factors | |
| Physical Disturbance | Environmental Disturbance | ||
| Low | 1, 2, 3 | Accessibility: accessibility during normal operations |
Activities: activities that people do and how often they do them Vibration: vibration from operating machinery, HVAC equipment, and so forth
Air/Dust: air currents strong enough to dislodge loose ACM; airborne dust that can erode material
Corrosive: corrosive atmosphere or liquids that can erode the covering or matrix
Water Damage: water damage from leaking roof, pipe or other source
| Medium | 4, 5, 6, 7 | |
| High | 8, 9, 10 | |
| 3 Qualitative Rankings and Quantitative (Numerical) Ratings for Removal Priority | ||
| Qualitative Ranking | Numerical Rating | Description of Current Condition |
| High | 1, 2, 3 | Address short-term |
| Medium | 4, 5, 6, 7 | Address with on-going maintenance procedures |
| Low | 8, 9, 10 | Maintain in good condition |