08 FTQW 21-1004 Submittal Register 18 FEB 21.xls
XLS spreadsheet 82 KB Posted
- Attached to
- Airfield Regulators Repair Federal contract opportunity
- Solicitation number
- FA500421B0003
About this file
This submittal register outlines 111 line items of documents required to be submitted by the contractor in response to solicitation number FTQW 21-1004 for the repair of airfield regulators at Eielson Air Force Base in Alaska. Key submittals include the contractor's schedule of prices, baseline construction schedule and monthly updates, accident prevention and environmental protection plans, shop drawings for electrical equipment, product data sheets, test reports from equipment inspections and grounding system tests, operation and maintenance manuals, and as-built drawings and records. The due dates for initial submittals range from 1 to 30 days after award. The register also requires submittal of training documentation and waste disposal records upon project completion.
A separate federal contract opportunity posting seeks bids for the removal and replacement of constant current regulators and an airfield lighting control system at Eielson AFB, with a project value between $1,000,000 and $5,000,000. A pre-bid site visit will take place on May 26, 2021 and final bids are due by June 11, 2021. Questions must be submitted by June 2, 2021. The selected contractor must register in the System for Award Management and follow all COVID-19 safety protocols during the site visit and project duration.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Solicitation Amendment - FA500421B00030001.pdf | ||
| Question and Answer.pdf | ||
| JA Brand Name_Redacted.pdf | ||
| 08 FTQW 21-1004 Project Specifications 18 FEB 21.pdf | ||
| Wage Determination AK20210001.pdf | ||
| 03 FTQW 21-1004 SOW Repair Airfield Regulators 29 MAR 21.pdf | ||
| Solicitation - FA500421B0003.pdf | ||
| 03 FTQW 21-1004 SOW Atch A.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Submittal Register
| TITLE: | CONSTRUCTION DOCUMENT | SUBMITTAL REGISTER | ||||||||||||||||||
| JOB NAME: | REPAIR AIRFIELD REGULATORS | |||||||||||||||||||
| LOCATION: | EIELSON AFB, ALASKA | |||||||||||||||||||
| CONTRACT NO: | FTQW 21-1004 | |||||||||||||||||||
| CONTRACTOR: | ||||||||||||||||||||
| CONTRACTOR SCHEDULE DATES | CONTRACTOR ACTION | APPROVING AUTHORITY | ||||||||||||||||||
| (a) | (b) | (c) | (d) | (e) | (f) | (g) | (h) | (i) | (j) | (k) | (l) | (m) | (n) | (o) | (p) | (q) | (r) | |||
| Line | Activity # | Trans-mittal # | Specification Section | SD # | Submittal Description | Item Submitted | Paragraph # | Classification: GOVT or A/E Revwr | Submit | Approval Needed By | Material Needed By | Action Code | Date Of Action | Date FWD to APPR / Auth Date RCD From CONTR | Date FWD To Other Revwr | Date RCD From Other Revwr | Action Code | Date Of Action | Mailed To CONTR/ Date RCD From APPR Authority | Remarks |
| 01 20 00 | 01 | Preconstruction Submittals | Schedule of Prices | 1.3 | G | |||||||||||||||
| 1 | 01 30 00 | 01 | Preconstruction Submittals | View Location Map | 1.4 | |||||||||||||||
| 2 | 01 30 00 | 01 | Preconstruction Submittals | Progress and Completion Pictures | 1.5 | |||||||||||||||
| 3 | 01 30 00 | 04 | Samples | Color Boards | 1.3 | |||||||||||||||
| 4 | 01 32 16.00 20 | 01 | Preconstruction Submittals | Baseline Construction Schedule | 1.2 | G | ||||||||||||||
| 5 | 01 32 16.00 20 | 07 | Certificates | Monthly Updates | 1.4 | G | ||||||||||||||
| 6 | 01 35 13 | 01 | Preconstruction Submittals | Construction Operation Plan | 3.1 | G | ||||||||||||||
| 7 | 01 35 26 | 01 | Preconstruction Submittals | Accident Prevention Plan (APP) | 1.6 | G | ||||||||||||||
| 8 | 01 35 26 | 06 | Test Reports | Notifications and Reports | 1.11 | |||||||||||||||
| 9 | 01 35 26 | 06 | Test Reports | Accident Reports | 1.11.2 | G | ||||||||||||||
| 10 | 01 35 26 | 06 | Test Reports | LHE Inspection Reports | 1.11.3 | |||||||||||||||
| 11 | 01 35 26 | 07 | Certificates | Crane Operators/Riggers | 1.5.1.4 | |||||||||||||||
| 12 | 01 35 26 | 07 | Certificates | Standard Lift Plan | 1.6.2.2 | |||||||||||||||
| 13 | 01 35 26 | 07 | Certificates | Critical Lift Plan | 1.6.2.3 | G | ||||||||||||||
| 14 | 01 35 26 | 07 | Certificates | Activity Hazard Analysis (AHA) | 1.7 | |||||||||||||||
| 15 | 01 35 26 | 07 | Certificates | Confined Space Entry Permit | 1.8.1 | |||||||||||||||
| 16 | 01 35 26 | 07 | Certificates | Hot Work Permit | 1.8.1 | G | ||||||||||||||
| 17 | 01 35 26 | 07 | Certificates | Certificate of Compliance | 1.11.4 | |||||||||||||||
| 18 | 01 35 26 | 07 | Certificates | License Certificates | 1.13 | |||||||||||||||
| 19 | 01 45 00.00 10 | 01 | Preconstruction Submittals | Contractor Quality Control (CQC) Plan | 3.2 | G | ||||||||||||||
| 20 | 01 45 00.00 10 | 06 | Test Reports | Verification Statement | 3.5.2 | |||||||||||||||
| 21 | 01 57 19 | 01 | Preconstruction Submittals | Preconstruction Survey | 1.6.1 | |||||||||||||||
| 22 | 01 57 19 | 01 | Preconstruction Submittals | Regulatory Notifications | 1.6.2 | |||||||||||||||
| 23 | 01 57 19 | 01 | Preconstruction Submittals | Environmental Protection Plan (EPP) | 0 | |||||||||||||||
| 24 | 01 57 19 | 01 | Preconstruction Submittals | Stormwater Notice of Intent and copy of ADEC approval | 0 | |||||||||||||||
| 25 | 01 57 19 | 01 | Preconstruction Submittals | Dirt and Dust Control Plan | 1.7.11.1 | |||||||||||||||
| 26 | 01 57 19 | 01 | Preconstruction Submittals | Employee Training Records | 1.6.5 | |||||||||||||||
| 27 | 01 57 19 | 01 | Preconstruction Submittals | Environmental Manager Qualifications | 1.6.4 | |||||||||||||||
| 28 | 01 57 19 | 01 | Preconstruction Submittals | Completed Checklist For Spruce Lake Disposal | 0 | |||||||||||||||
| 29 | 01 57 19 | 01 | Preconstruction Submittals | Notice of Intent For Asbestos Abatement | 0 | |||||||||||||||
| 30 | 01 57 19 | 01 | Preconstruction Submittals | Notice Of Building Demolition | 0 | |||||||||||||||
| 31 | 01 57 19 | 01 | Preconstruction Submittals | Stormwater Pollution Prevention Plan (SWPPP) | 0 | |||||||||||||||
| 32 | 01 57 19 | 01 | Preconstruction Submittals | Evidence Of Delivery Of SWPPP to ADEC | 0 | |||||||||||||||
| 33 | 01 57 19 | 01 | Preconstruction Submittals | Contaminated Soil Sampling And Analysis Plan (SAP) | 0 | |||||||||||||||
| 34 | 01 57 19 | 01 | Preconstruction Submittals | Contaminated Soil Sampling And Analysis Field Report | 0 | |||||||||||||||
| 35 | 01 57 19 | 01 | Preconstruction Submittals | Initial Contractor Hazardous Material Inventory | 0 | G | ||||||||||||||
| 36 | 01 57 19 | 06 | Test Reports | Laboratory Analysis | 3.7.1.1.2 | |||||||||||||||
| 37 | 01 57 19 | 06 | Test Reports | Inspection Reports | 3.2.1.3 | |||||||||||||||
| 38 | 01 57 19 | 06 | Test Reports | Solid Waste Management Report | 3.7.2.1 | |||||||||||||||
| 39 | 01 57 19 | 07 | Certificates | Employee Training Records | 1.6.5 | |||||||||||||||
| 40 | 01 57 19 | 07 | Certificates | Erosion and Sediment Control Inspector | 1.6.5 | |||||||||||||||
| 41 | 01 57 19 | 07 | Certificates | ADEC Transport, Treatment, & Disposal Approval Form For Contaminated Media (ATT) | 0 | G | ||||||||||||||
| 42 | 01 57 19 | 11 | Closeout Submittals | Stormwater Pollution Prevention Plan Compliance Notebook | 3.2.1.4 | |||||||||||||||
| 43 | 01 57 19 | 11 | Closeout Submittals | Stormwater Notice of Termination to ADEC | 0 | |||||||||||||||
| 44 | 01 57 19 | 11 | Closeout Submittals | Waste Determination Documentation | 3.7.1 | |||||||||||||||
| 45 | 01 57 19 | 11 | Closeout Submittals | Disposal Documentation for Hazardous and Regulated Waste | 3.7.3.6 | G | ||||||||||||||
| 46 | 01 57 19 | 11 | Closeout Submittals | Assembled Employee Training Records | 1.6.5 | |||||||||||||||
| 47 | 01 57 19 | 11 | Closeout Submittals | Solid Waste Management Permit | 0 | G | ||||||||||||||
| 48 | 01 57 19 | 11 | Closeout Submittals | Solid Waste Management Report | 3.7.2.1 | G | ||||||||||||||
| 49 | 01 57 19 | 11 | Closeout Submittals | Hazardous Waste/Debris Management | 3.7.3.1 | G | ||||||||||||||
| 50 | 01 57 19 | 11 | Closeout Submittals | Regulatory Notifications | 1.6.2 | |||||||||||||||
| 51 | 01 57 19 | 11 | Closeout Submittals | Sales Documentation | 3.7.2.1 | |||||||||||||||
| 52 | 01 57 19 | 11 | Closeout Submittals | Contractor Certification | 0 | |||||||||||||||
| 53 | 01 57 19 | 11 | Closeout Submittals | As-Built Topographic Survey | 0 | |||||||||||||||
| 54 | 01 57 19 | 11 | Closeout Submittals | ADEC Approved Disposal Facility Weight and/or Acceptance Ticket for Contaminated Soil | 0 | G | ||||||||||||||
| 55 | 01 57 19 | 11 | Closeout Submittals | ADEC Approved Disposal Facility Certificate of Thermal Incineration or Disposal of Contaminated Soil along with Confirmatory Sample Results | 0 | G | ||||||||||||||
| 56 | 01 74 19 | 01 | Preconstruction Submittals | Waste Management Plan | 1.6 | G | ||||||||||||||
| 57 | 01 78 00 | 03 | Product Data | Manufacturer's Warranties | G | |||||||||||||||
| 58 | 01 78 00 | 03 | Product Data | Warranty Management Plan | 1.6.1 | G | ||||||||||||||
| 59 | 01 78 00 | 03 | Product Data | Warranty Tags | 1.6.3 | G | ||||||||||||||
| 60 | 01 78 00 | 03 | Product Data | Spare Parts Data | 1.4 | G | ||||||||||||||
| 61 | 01 78 00 | 08 | Manufacturer’s Instructions | Posted Instructions | 1.6.1 | G | ||||||||||||||
| 62 | 01 78 00 | 10 | Operation and Maintenance Data | Operation and Maintenance Manuals | 3.6 | G | ||||||||||||||
| 63 | 01 78 00 | 11 | Closeout Submittals | As-Built Drawings | 2.1 | G | ||||||||||||||
| 64 | 01 78 00 | 11 | Closeout Submittals | As-Built Record of Equipment and Materials | 2.1 | G | ||||||||||||||
| 65 | 01 78 00 | 11 | Closeout Submittals | Final Approved Shop Drawings | 2.1 | G | ||||||||||||||
| 66 | 01 78 00 | 11 | Closeout Submittals | Interim DD Form 1354 | 3.8 | G | ||||||||||||||
| 67 | 01 78 00 | 11 | Closeout Submittals | Checklist For DD Form 1354 | 3.8 | G | ||||||||||||||
| 68 | 01 78 23 | 10 | Operation and Maintenance Data | O&M Database | 1.3 | G | ||||||||||||||
| 69 | 01 78 23 | 10 | Operation and Maintenance Data | Training Plan | 3.1.1 | G | ||||||||||||||
| 70 | 01 78 23 | 10 | Operation and Maintenance Data | Training Outline | 3.1.3 | G | ||||||||||||||
| 71 | 01 78 23 | 10 | Operation and Maintenance Data | Training Content | 3.1.2 | G | ||||||||||||||
| 72 | 01 78 23 | 11 | Closeout Submittals | Training Video Recording | 3.1.4 | G | ||||||||||||||
| 73 | 01 78 23 | 11 | Closeout Submittals | Validation of Training Completion | 3.1.6 | G | ||||||||||||||
| 74 | 02 41 00 | 01 | Preconstruction Submittals | Demolition/Deconstruction Plan | 1.2.2 | G | ||||||||||||||
| 75 | 02 41 00 | 01 | Preconstruction Submittals | Existing Conditions | 1.11 | |||||||||||||||
| 76 | 02 41 00 | 07 | Certificates | Notification | 1.7 | G | ||||||||||||||
| 77 | 02 41 00 | 11 | Closeout Submittals | Receipts | 3.3.4 | G | ||||||||||||||
| 78 | 26 20 00 | 02 | Shop Drawings | Panelboards | 2.11 | |||||||||||||||
| 79 | 26 20 00 | 02 | Shop Drawings | Transformers | 2.13 | |||||||||||||||
| 80 | 26 20 00 | 03 | Product Data | Receptacles | 2.10 | |||||||||||||||
| 81 | 26 20 00 | 03 | Product Data | Circuit Breakers | 2.11.3 | |||||||||||||||
| 82 | 26 20 00 | 03 | Product Data | Switches | 2.8 | |||||||||||||||
| 83 | 26 20 00 | 03 | Product Data | Transformers | 2.13 | |||||||||||||||
| 84 | 26 20 00 | 03 | Product Data | Motor Controllers | 2.15 | |||||||||||||||
| 85 | 26 20 00 | 03 | Product Data | Combination motor controlllers | 2.12 | |||||||||||||||
| 86 | 26 20 00 | 03 | Product Data | manual motor starters | 2.16 | |||||||||||||||
| 87 | 26 20 00 | 03 | Product Data | CATV outlets | 2.19 | |||||||||||||||
| 88 | 26 20 00 | 03 | Product Data | Telecommunications Grounding Busbar | 2.19.3 | |||||||||||||||
| 89 | 26 20 00 | 03 | Product Data | Surge protective devices | 2.25 | |||||||||||||||
| 90 | 26 20 00 | 06 | Test Reports | 600-volt wiring test | 3.1.4.5 | |||||||||||||||
| 91 | 26 20 00 | 06 | Test Reports | Grounding system test | 2.19 | |||||||||||||||
| 92 | 26 20 00 | 06 | Test Reports | Transformer tests | 2.13 | |||||||||||||||
| 93 | 26 20 00 | 06 | Test Reports | Ground-fault receptacle test | 2.10.3 | |||||||||||||||
| 94 | 26 20 00 | 07 | Certificates | Fuses | 2.9 | |||||||||||||||
| 95 | 26 20 00 | 09 | Manufacturer’s Instructions | Transformer factory test | 2.27.1 | |||||||||||||||
| 96 | 26 20 00 | 10 | Operation and Maintenance Data | Electrical Systems, Data Package 5 | ||||||||||||||||
| 97 | 26 56 20 | 1 | Preconstruction Submittals | Protection plan | 1.6.5 | G | ||||||||||||||
| 98 | 26 56 20 | 1 | Preconstruction Submittals | Training | 3.18.2 | G | ||||||||||||||
| 99 | 26 56 20 | 3 | Product Data | Airfield Rotating Beacon | 2.17.1 | |||||||||||||||
| 100 | 26 56 20 | 3 | Product Data | Constant current regulators, each size | 2.23 | G | ||||||||||||||
| 101 | 26 56 20 | 3 | Product Data | Airfield Lighting Control and Monitoring System components, complete | 2.2 | G | ||||||||||||||
| 102 | 26 56 20 | 6 | Test Reports | Visual inspection | 3.15.1 | G | ||||||||||||||
| 103 | 26 56 20 | 6 | Test Reports | Operating test | 3.15.2 | G | ||||||||||||||
| 104 | 26 56 20 | 6 | Test Reports | Constant current regulators, each size | 3.11 | G | ||||||||||||||
| 105 | 26 56 20 | 7 | Certificates | Qualifications of contractor | 1.6.3 | G | ||||||||||||||
| 106 | 26 56 20 | 7 | Certificates | Special Tools | 2.26.1 | G | ||||||||||||||
| 107 | 26 56 20 | 7 | Certificates | List of Parts | 3.19.1 | G | ||||||||||||||
| 108 | 26 56 20 | 8 | Manufacturer’s Instructions | Posted Instructions | 3.18.4 | G | ||||||||||||||
| 109 | 26 56 20 | 10 | Operation and Maintenance Data | Constant current regulators, Data Package 5 | 3.16.7 | G | ||||||||||||||
| 110 | 26 56 20 | 10 | Operation and Maintenance Data | Airfield rotating beacon, Data Package 3 | 3.9 | G | ||||||||||||||
| 111 | 26 56 20 | 10 | Operation and Maintenance Data | Maintenance and repair instructions | 3.19.2 | G |