This is a Request for Qualifications (RFQ) issued by the California Department of Transportation (Caltrans), Division of Design, District 7, for on-call land surveying services throughout Ventura County. The consultant will provide land surveying services on an as-needed basis to support Caltrans Division of Design, District 7, including control surveys, design and topographic surveys, construction staking, cadastral land net surveys, as-built surveys, utilities surveys, monumentation surveys, Records of Survey, laser scanning, 3D/4D modeling, subsurface utility mapping, and GIS data collection. Work will be performed within Ventura County and may extend up to 30 miles beyond district/county boundary lines. The contract is expected to commence after contract 07A5326 authority is exhausted, anticipated by July 1, 2026. Interviews will be conducted via WebEx on February 3, 2026, with the most highly qualified firm required to submit financial documents within four days of selection notification. Negotiations with the top-ranked firm are scheduled for the week of March 13, 2026, with a deadline to complete cost negotiations and submit the final cost proposal by March 23, 2026.
The estimated contract value is $2,400,000 to $3,900,000 with a three-year term. The fee for profit is fixed at 10.1 percent, with escalation rates of 1.81 percent for the initial partial year (January 16, 2026 through January 31, 2027) and 3.62 percent annually for the subsequent three full-year periods. A 0 percent Disadvantaged Business Enterprise (DBE) participation goal is required. Statements of Qualifications must be submitted electronically as a single unprotected PDF file by 10:00 a.m. on January 16, 2026, through a Novell Filr account. Questions concerning the RFQ must be submitted in writing to Adam Matheny at Adam.Matheny@dot.ca.gov no later than seven business days after the RFQ advertisement. The consultant contract manager must be a Professional Land Surveyor or pre-January 1, 1982 Registered Civil Engineer licensed in California with a minimum of five years of responsible experience managing similar land surveying services contracts and five years of demonstrated experience delivering land surveying services work. Caltrans does not guarantee that any work or services will be required under any contract issued as a result of this RFQ.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Addendum_1_-_DBE_CM_GenAI_SOQ__10-24-2025_version_2.pdf | ||
| SOQ-Responsiveness-Checklist.pdf | ||
| 02-SOQ_Submittal_Instructions.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
December 15, 2025 RFQ Number 07A6288
STATE OF CALIFORNIA DEPARTMENT OF TRANSPORTATION
REQUEST FOR QUALIFICATIONS NOTICE
NUMBER 07A6288
Read carefully as the following revisions have been made to this document:
• On September 30, 2025, the U.S. Department of Transportation (U.S.
DOT) issued an interim final rule (IFR) which, among other things, implemented changes to the Disadvantaged Business Enterprise (DBE) Program via modifications to 49 Code of Federal Regulations Part
26. (Docket Number DOT-OST-2025-0897.) The IFR was published in the Federal Register on October 3, 2025, and took immediate effect. (90 FR 47969 (Oct. 3, 2025).)
• On 03/07/25, GENERAL, Executive Order N-12-23 replaces Executive Order N-12-12. GenAI Reporting and Factsheet Form STD1000 is retired.
• On 01/31/25, GENERAL the Fee & Escalation table has been revised.
• On 07/25/24, GENERAL, Executive Order N-12-12 – Generative
Artificial Intelligence (GenAI) Technology Use and Reporting added.
Note: Questions concerning this Request for Qualifications (RFQ) must be submitted in writing to the attention of Adam Matheny at Adam.Matheny@dot.ca.gov. Questions must be received no later than seven (7) business days after the RFQ advertisement. Consultants contacting the District or Division directly seeking information about this RFQ will be disqualified from consideration in the selection process.
I. GENERAL INFORMATION
A. Caltrans is soliciting Statements of Qualifications (SOQs) from qualified firms that may lead to the award of a contract for On-Call Land Surveying Services. In submitting your SOQ, you shall comply with the instructions found herein. In addition to those programs that are specified in this solicitation, prospective consultants are encouraged to consider programs that are available, such as those for the use of small businesses, disadvantaged businesses, disabled veteran businesses, new emerging firms, and other businesses covered by State and Federal programs.
B. The estimated contract amount is $ 2,400,000.00 – 3,900,000.00 C. The estimated contract term is three years.
D. Interviews will be held via WebEx on February 3, 2026.
Confirmation letters will be sent to those firms short-listed.
E. The most highly qualified consulting firm will be required to submit an electronic copy of the financial documents listed on the appropriate Financial Documents Submittal Checklist available on the AE Contract Information website. The most highly qualified consulting firm will be notified of their selection and receive instructions for the electronic submission of the financial documents.
mailto:Adam.Matheny@dot.ca.gov https://dot.ca.gov/programs/procurement-and-contracts/ae-contract-information
The most highly qualified consulting firm must submit a complete financial documents package no later than four (4) days after notification of selection. The prime consultant must submit the complete financial documents package in order for Caltrans to have the information necessary to engage in negotiations. The prime consultant is solely responsible for timely and complete submission of financial documents on behalf of the entire proposed team; financial documents will not be accepted from proposed subconsultant firms. Failure to submit a complete financial documents package by the specified due date may result in termination of negotiations with the most highly qualified consulting firm.
F. Negotiations will be held with the top-ranked firm by teleconference/WebEx during the week of March 13, 2026. The fee for profit shall be (10.1%) ten point one percent, and the escalation shall be as follows:
Year Period Escalation
0 01/16/2026 - 01/31/2027 1.81% 1 02/01/2027 - 01/31/2028 3.62% 2 02/01/2028 - 01/31/2029 3.62% 3 02/01/2029 - 01/31/2030 3.62%
Notes:
1. Partial year will only occur on the last year of the contract term. All other periods are full years.
2. Increases to the loaded billing rates after contract execution is not authorized for any reason per Article IV, Section 17 and Article XVI, Section 6 of the California Constitution.
G. The scheduled date to complete cost negotiations and submit final cost proposal is March 23, 2026.
H. Disadvantaged Business Enterprise Program
1. On September 30, 2025, the U.S. Department of Transportation (U.S.
DOT) issued an interim final rule (IFR) which, among other things, implemented changes to the Disadvantaged Business Enterprise (DBE) Program via modifications to 49 Code of Federal Regulations Part
26. (Docket Number DOT-OST-2025-0897.) The IFR was published in the Federal Register on October 3, 2025, and took immediate effect. (90 FR 47969 (Oct. 3, 2025).) The IFR, as published in the Federal Register, is available at the following url: Docket No. DOT-OST-2025-0897
2. In the event of any ambiguity or discrepancy between the existing law, including the IFR, and this contract, existing law controls.
I. Federal and/or State prevailing wage rates may apply. This requirement, if applicable, will be specified in the draft Agreement. See SOQ Submittal Instructions, Section I.,G. regarding the California Department of Industrial Relations (DIR) Consultant/Contractor Registration Program on the AE Contract Information website.
J. Caltrans does not guarantee, either expressly or by implication, that any work or services will be required under any contract issued as a result of this RFQ.
https://www.federalregister.gov/documents/2025/10/03/2025-19460/disadvantaged-business-enterprise-program-and-disadvantaged-business-enterprise-in-airport
K. A Pre-award or Post-award Audit will be performed on any contract issued as a result of this RFQ.
L. Contract boilerplate can be obtained on the AE Contract Information website.
M. Pursuant to Executive Order (EO) N-6-22 issued March 4, 2022, persons identified in the list established by the US Department of the Treasury are ineligible to bid on, submit a proposal for, enter into, or renew any Agreement with the State for any goods and/or services.
Any person who submits a bid or proposal to Caltrans certifies that it is not identified in the most current lists located https://home.treasury.gov/policy-issues/financial-sanctions/sanctions-programs-and-country-information/ukraine-russia-related-sanctions.
If applicable, any person who submits a bid or proposal to Caltrans certifies that its subcontractors are not identified in the most current lists located https://home.treasury.gov/policy-issues/financial-sanctions/sanctions-programs-and-country-information/ukraine-russia-related-sanctions
N. Pursuant to Executive Order N-12-23 – Generative Artificial Intelligence (GenAI) Technology Use and Reporting, effective February 20, 2025.
1. The State of California seeks to realize the potential benefits of
GenAI, through the development and deployment of GenAI tools, while balancing the risks of these new technologies.
2. Bidder / Offeror must notify the State in writing if it:
A) intends to provide GenAI as a deliverable to the State; or B) intends to utilize GenAI, including GenAI from third parties, to complete all or a portion of any deliverable that materially impacts:
1) functionality of a State system,
2) risk to the State, or
3) Contract performance.
Note: For avoidance of doubt, the term “materially impacts” shall have the meaning set forth in State Administrative Manual (SAM) § 4986.2 Definitions for GenAI.
3. Failure to report GenAI to the State may result in disqualification. The State reserves the right to seek any and all relief to which it may be entitled to as a result of such non-disclosure.
4. Upon notification by a Bidder / Offeror of GenAI as required, the State reserves the right to incorporate GenAI Special Provisions into the final contract or reject bids/offers that present an unacceptable level of risk to the State.
5. Government Code 11549.64 defines “Generative Artificial Intelligence (GenAI)” as an artificial intelligence system that can generate derived synthetic content, including text, images, video, and audio that emulates the structure and characteristics of the system’s training data.
https://dot.ca.gov/programs/procurement-and-contracts/ae-contract-information https://home.treasury.gov/policy-issues/financial-sanctions/sanctions-programs-and-country-information/ukraine-russia-related-sanctions https://home.treasury.gov/policy-issues/financial-sanctions/sanctions-programs-and-country-information/ukraine-russia-related-sanctions https://home.treasury.gov/policy-issues/financial-sanctions/sanctions-programs-and-country-information/ukraine-russia-related-sanctions https://home.treasury.gov/policy-issues/financial-sanctions/sanctions-programs-and-country-information/ukraine-russia-related-sanctions
II. SCOPE OF WORK/DELIVERABLES
The work to be performed for this RFQ is described in the Scope of Work/Deliverables and is hereby incorporated as Attachment 1.
III. CONFLICT OF INTEREST
A. Conflicts of interest may occur due to direct or indirect financial or business interests in the work to be performed or in any real property acquired for such project. Conflicts of interest can include, but are not limited to, past, existing or planned activities or because of relationships with other persons or firms. If there is a conflict of interest, the proposed team, including both the prime consultants and subconsultants, and individual employees of team members would actually or potentially be unable to render impartial assistance or advice to Caltrans. The proposer’s objectivity or availability in performing the contract work may be impaired due to actual or potential conflicts of interest.
B. If the proposed team determines that any actual or potential conflicts of interest exist, it must identity and describe in detail each conflict of interest to Caltrans, using the Disclosure of Potential Conflict of Interest Form, which can be found on the A&E Contract Information website. Along with the description of the actual or potential conflicts of interests, the proposed team shall also offer measures to avoid, neutralize, or mitigate all listed conflicts.
The list of conflicts, including conflicts that apply to individuals as well as firms, and the mitigation measures on the Disclosure of Potential Conflict of Interest Form must be submitted as a separate section in the Statement of Qualifications. Disclosure of information will not disqualify a proposed team from competing for a contract. The existence of actual or potential conflicts of interest will be used as a criterion to evaluate team availability during the evaluation and selection process. Caltrans reserves the right to terminate negotiations wit the first selected firm and begin negotiations with the next selected firm or to cancel the procurement prior to execution if Caltrans learns that the selected firm failed to disclose any actual or potential conflicts, which it knew or should have know about, or if the proposed team provided or omitted information on the disclosure form that results in the information being false or misleading.
C. After award, conflict of interest guidelines and policies shall continue to be monitored and enforced by the Caltrans Contract Manager. Additional information about Conflict-of-Interest issues can be found in the SOQ Submittal Instructions and General Contract Process Information document (Section V. Post Government Employment Restrictions and Section VI.
Conflict of Interest Concerning Consultant(s)) found on the AE Contract Information website (see link below). The State and Federal contract boilerplates on DPAC’s website also contain information on conflict-of-interest issues (Exhibit D) and can be found on the AE Contract Information website (see link below).
D. The prime consultant and subconsultants may be proposed on SOQs for other Caltrans A&E on-call contracts; however, the Caltrans Contract Manager may prohibit work on specific project(s) where Caltrans determines that a conflict of interest exists.
IV. SUBMISSION OF STATEMENTS OF QUALIFICATIONS (SOQs)
A. IMPORTANT: Download “Statement of Qualifications Submittal Instructions and General Contract Process Information” from the AE Contract Information website (Dated Rev. 10/07/2020) . Failure to follow these instructions may result in rejection of your SOQs.
B. SOQ Package Submittal Instructions
Read instructions below carefully. You will be required to submit an electronic SOQ file to Sacramento.
1. The electronic submission of a single unprotected (i.e. not password protected) PDF file of the SOQ is required. The electronic submittal will be accepted until 10:00 a.m. on 1/16/2026. Hard copies of the SOQs are NOT required. Fax copies or copies transmitted by email will not be allowed.
2. You will be required to create a Novell Filr account with Caltrans.
Send an email message to the Contract Analyst, Adam Matheny, at Adam.Matheny@dot.ca.gov containing the information listed below for a link and instructions to complete the self-registration page and submit the SOQ electronically.
Your firm’s name Your email address The solicitation number for which you would like to submit a
SOQ
The file name shall include the contract number, consultant name (max.
25 characters) separated by an underscore (_), ending with the “.pdf” extension.
Example A: 50A0694_JohnDoeConsulting.pdf Example B: 50A0694_aaa1234engineer.pdf
3. SOQ submittals will be considered non-responsive if the electronic submittal is not received by the date and time specified in this RFQ.
C. Request for RFQ Copies Copies of this RFQ may be obtained on the CaleProcure website.
mailto:Adam.Matheny@dot.ca.gov https://www.caleprocure.ca.gov/pages/index.aspx
Attachment 1
Revised 05/06/2021
SCOPE OF WORK/DELIVERABLES
Land Surveying Services for Caltrans, Division of Design, District 7 On-Call Contract
LAND SURVEYING1 SERVICES
A. Purpose of Work
The consultant must perform Land Surveying Services, on an “as-needed” basis to support the California Department of Transportation (Caltrans), Division of Design, District 7. The Caltrans contract manager will assign specific work to the consultant to augment the Caltrans work force through issuing task orders describing the services to be performed. The consultant must only perform work assigned in an authorized task order.
This contract does not guarantee that a task order will be issued. The Consultant may provide services to Caltrans including, but not limited to, control surveys, design and topographic surveys, construction staking, cadastral land net surveys, as-built surveys, utilities surveys, monumentation surveys, Records of Survey, and the preparation, filing, and recordation of survey documents including, but not limited to, survey field notes, monumentation and Records of Survey maps, topographic and design mapping, drawings, and other related survey documents. Other specialty land surveying services provided shall include, but not be limited to, laser scanning including Mobile Terrestrial Laser Scanning (MTLS), 3D/4D Modeling, subsurface utility mapping, surveys utilizing the Global Navigation Satellite System (GNSS), and GIS data collection.
The consultant for this contract must perform the services above after the contract authority for contract 07A5326 is exhausted (expected by 7/1/2026). The consultant must plan accordingly to meet the timing of and the volume of work load needs.
B. Location of Work
The work must be performed on projects to improve the State transportation system throughout the county of Ventura County in California. The specific location within the above-described geographical limits of the work to be performed must be identified in each task order. It may become necessary for Caltrans, Division of Design, District 7, projects to extend into another adjoining District/County line. In such instances, the
1 Defined in section 8726 of the California Business and Professions Code project work must not extend more than a 30-mile radius from the District/County, District 7 geographic boundary.
The following work is excluded from this contract:
1. Headquarters photogrammetry projects.
2. Land surveying office support work performed under the District 7 land surveying contract for right of way engineering services to support the Division of Right of Way.
3. Land surveying office support work (defined by project ID and WBS codes) performed under the District 7 land surveying office support services contract for the Division of Design.
C. Required Services
1. Under an authorized task order, the consultant must provide land surveying services within the geographical jurisdiction of this contract set forth in the “Location of Work” section, including all necessary personnel, material, transportation, lodging, instrumentation, and the specialized facilities and equipment to satisfy all appropriate agencies and required to ensure compliance with all federal, state, and local statutes, laws, codes, regulations, policies, procedures, ordinances, standards, specifications, performance standards, and guidelines, applicable to the consultant's services and work product.
2. Provided in attachment 1A is a list of proposed Caltrans projects; Division of
Design, District 7, however, this list is not exclusive and it constitutes no commitment that the projects will be initiated or completed or work assigned to the consultant. Caltrans reserves the right to add or delete from this list of projects that are within the geographical jurisdiction of this contract set forth in “Location of Work” section within the Division of Design, District 7’s jurisdiction.
3. Caltrans intends to utilize this contract to complete a specific piece of work if it is within the geographical jurisdiction of this contract set forth in the “Location of Work” for each of the projects in this contract utilizing the services described in this Scope Of Work (SOW) and as described in a task order. Caltrans may find it necessary to create a separate contract (or contracts) that involves a specific project in this contract and includes part of the work in this contract. Caltrans reserves the right to procure A&E services involving the listed projects or unlisted projects (within the geographical jurisdiction of this contract set forth in “Location of Work” Section) involving in whole or in part the same work using a project-specific agreement if the schedule to complete performance of the specific project extends beyond the term of this contract or the cost exceeds the dollar balance remaining in the contract after accounting for amounts due to the consultant for work previously performed and for work scheduled to be performed in executed task orders.
Should a project-specific agreement be procured under these provisions, the parties mutually agree that, under Exhibit D, Section III, Termination of this
Contract, Caltrans must terminate for convenience the portion of the contract that includes the common SOW identified in the project specific agreement per Exhibit D, Section III, Termination of this Contract. Such partial termination for convenience must be processed by amendment to this contract. Unless otherwise required by law, regulation, or Caltrans policy or procedure, the consultant may compete for these project specific contracts.
4. At the sole discretion of Caltrans, the consultant may have to provide the required services on safety projects, emergency projects, emergency storm damage projects, excess parcel assessments, or other current/future transportation projects, including minor projects not listed above, except for those specially excluded above, within the geographical jurisdiction of this contract set forth in “Location of Work” Section.
5. The potential projects may vary in scope and size, and may encompass any improvement for the State transportation system including, but not limited to, roadway rehabilitation, widening and/or realignment of existing facilities, relocation of existing facilities, and construction of new facilities. The project location, project limits, purpose, expected results, project deliverables, period of performance, project schedule, and SOW to be performed must be described in each task order.
6. Consultant must be available, on two days’ written notice:
a. To meet with Caltrans; to participate in internal Project Development
Team (PDT) meetings or other Caltrans meetings.
b. To provide technical expertise on an “as-needed” basis.
7. Maintaining a stable work force is essential to the successful completion of Caltrans, Division of Design, District 7, work. The consultant must implement a personnel retention plan.
D. Workplan Standards Guide (WSG) Codes
Task orders are based on the Caltrans WSG. The latest WSG is found in the Guide to Project Delivery WSG, which is available from the Caltrans’ Publication Unit and on the Internet at http://www.dot.ca.gov/hq/projmgmt/guidance.htm.
The WSG references the WBS categories, which are potential and related work http://www.dot.ca.gov/hq/projmgmt/guidance.htm activities applicable to this contract. The WSG references WBS categories which present the potential and related work activities that the consultant may have to perform. All revisions to the current version of the WBS must apply during the life of this contract.
The WBS activities below applicable to this Contract are limited to those set forth below:
160.10.45 Utility Locations Determined for Preliminary Engineering
160.10.65 Right of Way Relinquishment and Vacation Study (See Note 3)
160.20.25 Existing Records (See Note 3)
160.20.30 Land Net Surveys
160.20.35 Land Net Map (See Note 3)
160.20.40 Right of Way Engineering Products (See Note 3)
160.20.50 Control Surveys
160.20.55 Photogrammetric Maps and Products (See Note 1)
160.20.60 Engineering Surveys
160.20.65 As-Built Centerline Surveys
160.20.70 Pavement Surveys
160.30.10 Surveys and Mapping for Environmental Studies
185.10.50 Control Surveys
185.10.55 Photogrammetric Maps and Products (See Note 1)
185.10.60 Engineering Surveys
185.10.65 As-Built Centerline Surveys
185.10.70 Pavement Surveys
185.20.40 Utility Locations Determined for Design
220.05.05 Existing Records (See Note 3)
220.05.10 Land Net Survey
220.05.25 Monumentation Perpetuation Record of Survey
220.10 Land Net Map (See Note 3)
220.15 Right of Way Maps (See Note 3)
220.15.05 Appraisal Maps (See Note 3)
220.15.95 Other Maps (See Note 3)
220.20 Acquisition Documents (See Note 3)
220.20.05 Deeds (See Note 3)
220.20.15 Resolution of Necessity Package (See Note 3)
220.25 Documents to convey property rights (See Note 3)
220.25.05 Director’s deed package (See Note 3)
220.25.95 Other deeds and documents (See Note 3)
220.35.05 Flagged Right of Way (Includes Utilities)
220.35.10 Staked Right of Way
255.35.10 Construction Staking Package
255.35.20 Project Control for Construction
255.70 Right of Way Engineering Products (See Note 3)
270.10.10 Construction Staking Package
270.10.20 Project Control for Construction
270.10.30 Existing Monument Perpetuation (See Note 2)
270.15.15 Slope Stakes
270.15.25 Rough Grade Stakes
270.15.30 Final Grade Stakes
270.15.35 Drainage and Minor Structure Stakes
270.15.50 Miscellaneous Stakes (Includes Utilities)
270.15.55 Photogrammetric Product for Construction (See Note 1)
270.15.60 Ground Stakes for Major Structure
270.15.65 Superstructure Stakes for Major Structure
270.22 Contract Administration
270.66 Technical Support (See Note 3)
285.10.05 Field Surveys for Change Order
285.10.10 Staking for Change Order
285.10.15 Other Functional Support
300.05.05 Right of Way Monumentation Survey
300.05.10 Filed Monumentation Record of Survey
300.10 Trial Exhibits and Testimony (See Note 3)
300.25 Relinquishment and Vacation Maps (See Note 3)
300.30 Deed Package for Excess Land Transactions (See Note 3)
300.35 Right of Way Record Map (See Note 3)
Note 1: The anticipated work for WBS code 160.20.55, 185.10.55 and 270.15.55 must be limited to field surveys and related office processing for aerial mapping control placement and positioning.
Note 2: This WBS code is to be used only for projects with no two (2) phase work.
Note 3: Work performed for the Division of Right of Way must be related to field land surveying services work only.
The consultant must not work on any projects in the planning phase (K-Phase), and the consultant will not be reimbursed for any work performed during this phase of a project.
E. General Personnel Requirements
1. The consultant’s personnel must be capable, competent, and experienced in performing the work in this contract with minimal instruction. Personnel skill level must match the specific job classifications, as set forth or in the consultant’s cost proposal, attachment 2 and task complexity. The consultant’s personnel must be knowledgeable about, and comply with, all federal, state, and local laws and regulations.
2. The consultant must submit a written request and obtain the Caltrans CM’s prior written approval for any substitutions, additions, alterations, or modifications to the consultant’s originally proposed personnel and project organization, as depicted on the proposed consultant’s organization chart or the consultant’s cost proposals. The substitute personnel must have the same job classification, as set forth or in the consultant’s cost proposal, attachment 2, not exceed the billing rate, and meet or exceed the qualifications and experience level of the previously assigned personnel, at no additional cost to Caltrans.
3. In responding to Caltrans’ task order and in consultation with the Caltrans contract manager and the Caltrans task order manager, the Consultant contract manager must identify the specific individuals proposed for the task and their job assignments. The consultant must provide documentation that proposed personnel meet the minimum qualifications as required by this contract.
4. The consultant’s personnel must typically be assigned to and remain on specific Caltrans projects/deliverables until completion and acceptance of the project/deliverables by Caltrans. Personnel assigned by the consultant must be available at the start of a task order and after acceptance of the project/deliverable by Caltrans.
5. After the Caltrans contract manager’s approval of the consultant’s personnel proposal and finalization of a task order, the consultant may not add or substitute personnel without the Caltrans contract manager’s prior written approval.
6. Resumes containing the qualifications and experience of the consultant’s and sub-consultant’s personnel, which include existing, additional, and substitute personnel, and copies of their minimum required certifications, must be submitted to the Caltrans contract manager for review before assignment on a project or task order. The resume and copies of current certification for each candidate must be submitted to the Caltrans contract manager within one week of receiving the request.
7. The Caltrans contract manager or Caltrans task order manager may interview the consultant’s personnel for the qualifications and experience. The Caltrans contract manager’s decision to select the consultant’s personnel will be binding to the consultant and its sub-consultants. The consultant must provide adequate qualified personnel to be interviewed by the Caltrans contract manager or Caltrans task order manager within one week of receiving the request.
8. The Caltrans task order manager will evaluate the adequacy (quality and quantity) of the work performed by the consultant’s personnel, and determining whether the deliverables satisfy the acceptance tests and criteria. The Caltrans contract manager consulting with the Caltrans task order manager may reject any consultant personnel determined by the Caltrans contract manager to lack the minimum qualifications. If the level of performance is below expectations, the Caltrans contract manager may direct the consultant to immediately remove consultant personnel from the project specified in a task order and request another qualified person be assigned as needed. The substitute personnel must meet the qualifications required by this contract for performance of the work as demonstrated by a resume and copies of current certifications submitted by the consultant. Substitute personnel must receive prior written approval from the Caltrans contract manager. Invoices with charges for personnel not pre-approved by the Caltrans contract manager for work on the contract and for each task order must not be reimbursed.
9. The consultant must not remove or replace any existing personnel assigned to task orders without the prior written consent of the Caltrans contract manager. The removal or replacement of personnel without the written approval from the Caltrans contract manager will violate the contract and may cause termination of the contract per Exhibit D, Section III, Termination of the Contract.
10. When assigned consultant personnel is on approved leave and required by the Caltrans contract manager , the consultant contract manager must provide a substitute employee until the assigned employee returns to work from the approved leave. The substitute personnel must have the same job classification, as set forth in the consultant’s cost proposal, attachment 2, not exceed the billing rate, and meet or exceed the qualifications and experience level of the previously assigned personnel, at no additional cost to Caltrans. Substitute personnel must receive prior written approval from the Caltrans contract manager to work on this contract.
11. Other project personnel not identified on the consultant’s cost proposal, must also satisfy minimum qualifications for assigned task orders. Caltrans’ prior written approval is required for all personnel not identified on the consultant’s organization chart or the consultant’s cost proposals before providing services under this contract.
12. The consultant is responsible to provide fully trained personnel to efficiently perform the work. The consultant’s personnel may be asked to attend certain special training if recommended by the Caltrans contract manager. On such occasions, with the approval of the Caltrans contract manager, Caltrans will compensate the consultant for the consultant’s actual cost for time spent in training only. All other costs, fees, and expenses associated with the training, including any transportation costs and training fees, must be the consultant’s responsibility.
13. In location(s) where the consultant personnel is expected to work for extended period(s) of time, the consultant must either relocate the personnel or strive to hire local persons.
14. Independent Contractor Status
For circumstances when Consultant personnel perform work at the Consultant home office or within Caltrans facilities alongside with Caltrans staff, all supervision and instructions shall be transmitted by the Consultant Task Order Manager. Consultant Task Order Manager shall exercise comprehensive control authority over its personnel in the manner and means to fulfill work performed without any involvement of the Caltrans Functional Manager or designee.
a. Consultant Personnel Relationship
i. Consultant is an independent contractor, and nothing contained in the Contract shall be construed as constituting any relationship with Caltrans other than that of project owner and independent contractor. In no event shall the relationship between Consultant personnel and Caltrans be construed as creating any relationship whatsoever between Caltrans and any of Consultant’s employees.
ii. Neither Consultant nor any of its employees is or shall be deemed to be an employee of Caltrans. The Consultant has the sole rights to terminate its personnel at-will without cause and demonstrate its right to control over the personnel.
b. Consultant Personnel - Supervision Control and Instructions
i. Consultant personnel shall operate as independent contractors whereby free to perform jobs in their own ways and means, using their own specific methodologies to achieve the desired task order services and deliverables.
ii. Consultant personnel are not required to follow Caltrans functional office protocols nor Caltrans specific instructions on how to perform its work.
iii. Except as otherwise specified in the Contract, Consultant Contract Manager has sole authority and responsibility to employ, discharge, terminate and otherwise control its employees and has complete and sole responsibility as a principal for its agents, for all subconsultants and for all other persons that Consultant or any subconsultant hires or engages to perform or assist in performing the Scope of Work.
iv. Consultant shall make all of its own business including personnel decisions and bear the risk for its decisions without any burden or liability placed upon Caltrans.
c. Skilled and Qualified Labor
i. The Consultant will provide professional services in an area of its specialization as an essential part of the purpose of the business enterprise, considered as skilled professionals and do not require training.
ii. Consultant shall provide its own training to its employees and subconsultants, and Consultant shall not rely upon Caltrans to provide such training.
d. Consultant agrees that:
i. The Consultant Contract Manager or designee shall manage, instruct, and supervise all Consultant employees and subconsultants, and shall not allow any other party to manage, instruct and supervise such parties.
ii. Unless approved in writing by Caltrans Contract Manager, Consultant shall not hire employees or subconsultants to work on Caltrans matters exclusively and only. Consultant may hire employees and subconsultants for a specific Caltrans matter provided such party has the skills and knowledge to work on other matters and they are assigned to other matters from time to time.
iii. Consultant shall provide its own tools, equipment and supplies, and Consultant shall not rely on Caltrans to provide such tools, equipment, and supplies. Notwithstanding the foregoing, Caltrans may, during the term of the Contract, allow Consultant to access selected items of equipment; provide non-employee User-Ids and related access to Caltrans computer systems to Consultant employees and subconsultants; and provide non-employee access cards and other such forms of identification to Consultant employees and subconsultants.
iv. Consultant shall advise its employees and subconsultants of the foregoing contract terms that apply to them, and Consultant advise such employees and subconsultants to report to Consultant any apparent or actual breaches. Consultant shall relay any such reports to Caltrans Contact Manager.
F. Land Surveying Personnel Requirements
1. The consultant, including the prime consultant and all sub-consultants, must throughout the life of the contract, retain within its firm, a staff of people properly licensed and certified under the laws of the State of California and qualified to perform all aspects of the required work described in this contract and all work specified in a task order with any emergencies that may arise during the life of this contract. The consultant must be prepared to provide additional personnel during the period performance of this contract to accommodate the work.
2. Consultant Contract Manager
The consultant contract manager must coordinate work-related matters and consultant’s operations under this contract with the Caltrans contract manager in coordination with the Caltrans task order manager.
The consultant contract manager must be a Professional Land Surveyor or pre- January 1, 1982 Registered Civil Engineer licensed in the State of California and be in good standing with the California State Board of Professional Engineers, Land Surveyors, and Geologists (BPELSG) during the contract period.
The consultant contract manager must have a minimum of five (5) years of responsible experience performing the duties as a consultant contract manager leading a team of A&E firms for similar Land Surveying Services contracts, and a minimum five (5) years of documented demonstrated experience acceptable to Caltrans in delivering Land Surveying Services work. For each cumulative set of competence, the minimum five (5) years of consultant contract manager experience and 5 years minimum Land Surveying Services experience, each gained from multiple projects at various times, shall be in serial (not in parallel order), with the total time not accounting for double counting or any overlapping within each set of the two types of competence. Specifically for the five years of responsible experience performing the duties as a consultant contract manager, the other Project Manager, Survey Manager, Lead Surveyor, and other lead role position experiences will not qualify for the consultant contract manager experience.
The consultant contract manager must be knowledgeable about all Caltrans policies and procedures. The consultant contract manager must be an employee of the prime consultant.
Besides other specified responsibilities, the consultant contract manager must handle all matters related to the consultant’s personnel, sub-consultants, land surveying services work, and consultant’s and sub-consultants’ operations including, but not limited to:
a. Ensuring that deliverables are acceptance tested and that criteria are specific, measurable, attainable, realistic and time-bound; and that the deliverables satisfy the acceptance tests and criteria.
b. Supervising, reviewing, monitoring, training, and directing the consultant’s and sub-consultants’ personnel.
c. Assigning qualified personnel to complete the required task order work as specified on an “as-needed” basis in coordination with the Caltrans contract manger and Caltrans task order manager.
d. Administering personnel actions for consultant personnel and ensuring appropriate actions taken for sub-consultant personnel.
e. Maintaining and submitting organized project files for record tracking and auditing.
f. Developing, organizing, facilitating, and attending scheduled coordination meetings, and preparation and distribution of meeting minutes.
g. Implementing and maintaining quality control procedures to manage conflicts, insure product accuracy, and identify critical reviews and milestones.
h. Assuring that all applicable safety measures are in place.
i. Providing invoices in a timely manner and providing monthly contract expenditures.
j. Reviewing invoices for accuracy and completion before billing to Caltrans.
k. Managing sub-consultants.
l. Managing overall budget for the contract and provide report to the
Caltrans contract manager.
m. Monitoring and maintaining required DBE or DVBE involvement.
n. Ensuring compliance with the provisions in this contract and all specific task order requirements.
o. Knowledge, experience, and familiarity with prevailing wage issues and requirements in State of California.
3. Consultant Task Order Manager
For each task order, the consultant must provide a consultant task order manager to coordinate the consultant task order operations with the Caltrans contract manager in coordination with the Caltrans task order manager.
The consultant task order manager must be accessible to the Caltrans contract manager in coordination with the Caltrans task order manager during normal Caltrans working hours that task order work is underway.
The consultant task order manager (who may not be the consultant contract manager) must be assigned to conduct, or direct the conduct of, all work assigned under a single task order. The consultant task order manager must be a Professional Land Surveyor or a pre-January 1, 1982 Registered Professional Civil Engineer licensed in the State of California and be in good standing with the BPELSG during the Contract period. The consultant task order manager must be the primary contact for the assigned task order and be available for communication with Caltrans.
4. Consultant Task Order Lead person.
The consultant task order lead person (who may not be the consultant CM) must be assigned to conduct, or direct the conduct of, all work assigned under a single task order. The consultant task order lead person must be the primary contact for the assigned task order and be available for communication with Caltrans.
5. Consultant Personnel and Team Member Qualifications.
The consultant team member must be capable of assisting the consultant contract manager in all aspects of the required work. The consultant team member’s required professional qualifications must be identified in each task order.
6. In this contract, a person authorized to review and approve consultant land surveying deliverables in place of the consultant task order manager must be called the consultant land surveying responsible person (responsible charge registrant). The consultant land surveying responsible person, must be a Professional Land Surveyor or a pre-January 1, 1982 Registered Professional Civil Engineer licensed in the State of California and be in good standing with the BPELSG during the contract period.
7. All deliverables under this contract not fully approved by Caltrans bearing the signature of the consultant land surveying responsible person who is no longer employed by the consultant or its sub-consultants, must be replaced with deliverables under this contract bearing the signature of a qualified replacement consultant land surveying responsible person currently employed by the consultant or its sub-consultants. In such an event, no additional time will be allowed or cost reimbursed to the consultant without the prior written approval of the Caltrans contract manager.
8. All of the consultant’s work must be conducted under the direction of the consultant contract manager who must have the experience as described in this contract. All deliverables under this contract requiring the consultant land surveying responsible person’s signature, must be produced by the responsible consultant personnel having appropriate experience, and must be signed by a consultant land surveying responsible person.
9. Party Chiefs
Party Chiefs must fulfill one of the following requirements:
a. A Professional Land Surveyor licensed in the State of California and be in good standing with the BPELSG.
b. A pre-January 1, 1982, Registered Professional Civil Engineer licensed in the State of California and be in good standing with the BPELSG.
c. An experienced surveyor/union-certified party chief/journeyman with a documented minimum of five years of field surveying experience who serves as chief under the direction and supervision of a person who is a Professional Land Surveyor licensed in the State of California or pre- January 1, 1982, Registered Professional Civil Engineer licensed in the State of California and be in good standing with the BPELSG. This direction and supervision must be provided in a manner and with a span of control and immediacy that enables the supervisor to be in “Responsible Charge” of the work as defined in the Business and Professions Code, Division 3, Chapter 15 (The Land Surveyors Act).
Party Chief: The duties of the survey party chief include, but are not limited to:
plan, coordinate and direct the daily operations and/or assignments of a field survey party, oversees tailgate safety meetings every ten working days or more often as the work location requires, insures the survey party is working in a secure and safe manner; direct the survey party in procedures to be used in fieldwork that conforms with the Caltrans Surveys Manual; verify project datum and project control; check the accuracy of the survey data collected and construction stakes set; and produce a daily Field Surveys Party Report, which verifies the survey party time and project charges.
10. Project Surveyor
Project Surveyor must fulfill one of these licensing requirements and be in good standing with the BPELSG during the Contract period.
a. A Professional Land Surveyor licensed in the State of California.
b. A pre-January 1, 1982, Registered Professional Civil Engineer licensed in the State of California.
Project Surveyor: The duties of the project surveyor in the office include, but are not limited to: prepare survey requests and supporting information for the field survey; analyze, reduce and/or adjust field survey data to produce maps, reports, digital terrain models, project control maps, and related documents to determine property and right of way boundaries; and, research public records from counties, cities, utility companies, and other agencies to produce, signs and seals, documents and maps defining the existing location of, acquisition of, and disposal of State Right of Way, including but not limited to: legal descriptions, acquisition deeds, resolutions of necessities (Condemnation), land net maps, appraisal maps, relinquishment or vacation maps, federal application maps, final record maps and Record of Survey Maps.
11. Land Surveying Assistants
The Land Surveying Assistants must fulfill one of the following requirements:
a. A degree (Associate, Bachelors, Masters, or higher) in land surveying or surveying engineering from an ABET accredited institution (College or University) and a minimum of two years of qualifying experience in land surveying.
b. Possession of a valid Land Surveyor-in-Training certificate issued or accepted by the BPELSG, and a minimum of two years of qualifying experience in land surveying.
c. An experienced surveyor with a documented minimum of four years of surveying experience who works under the direction and supervision of a Professional Land Surveyor licensed in the State of California or pre- January 1, 1982, Registered Professional Civil Engineer licensed in the State of California and be in good standing with the BPELSG.
The land surveying assistants to the party chiefs and project surveyor must be capable of assisting in all required and associated field and office land surveying work, able to perform difficult survey and complex professional land surveying work involving duties in the field or office with little direct supervision. Duties include, but are not limited to, assist party chief in construction staking, design, and right of way surveys, assist office chief or project surveyor in preparing right of way maps using Computer-Aided Design (CAD), maintaining right of way records and geospatial information systems, research and compile a wide variety of data from public records, geospatial information systems and other sources using both manual and computerized processes, and survey support.
12. Land Surveying Technicians
The land surveying technicians must work under the direction of a Professional Land Surveyor licensed in the State of California or a pre-January 1, 1982 Registered Professional Civil Engineer licensed in the State of California and be in good standing with the BPELSG. The land surveying technicians must fulfill one of these criteria:
a. The equivalent of a two-year college degree, preferably with an emphasis in mathematics and engineering and a minimum of one year of qualifying experience in land surveying.
b. A documented minimum two years of demonstrated experience acceptable to Caltrans in a land surveying services related field, under the direction of a Professional Land Surveyor licensed in the State of California.
The land surveying technicians must be capable of assisting in all required office and/or field land surveying services work.
13. Instrument person
The instrument person must be union certified as an instrument person or have a minimum six years of qualifying experience in land surveying. The instrument person reports to the party chief and must be capable of assisting the party chief in all required field and office surveying work.
14. Rod person
A rod person must have a minimum two years of qualifying experience in land surveying and may augment a party comprising at a minimum one party chief and one instrument person as the project task workload dictates, and as preapproved by the Caltrans contract manager.
15. Surveying Journeymen Chainman
The surveying journeymen chainman must be union certified as a journeyman or have a minimum four years of qualifying experience in land surveying. The surveying journeyman chainman to the party chief must be capable of assisting the party chief in all required field and office surveying work.
16. Apprentice Chainman
A surveying apprentice must have a minimum one year of qualifying experience in land surveying. The surveying apprentice may augment a party comprising at a minimum one party chief and one instrument person as the project task workload dictates, and as pre-approved by the Caltrans contract manager.
Compensation for the journeyman/apprentice chainman must be under the contract and supported by documentation from the Northern or Southern California Surveyors Joint Apprenticeship Committee and in compliance with the Division of Apprenticeship Standards (DAS). The apprentice chainman must be enrolled in the Northern or Southern California Surveyors Joint Apprenticeship Program and have union level certification for the level achieved.
17. The consultant must have personnel with documented and demonstrated expertise and experience in the fields of Geographic Information Systems (GIS) and geodetic survey control.
18. Minimum Requirements for Survey Party Membership:
Unless otherwise specified in the task order, each survey party must comprise a party chief and up to three assistants, unless additional survey party members are required for safety. At a minimum, one assistant to the party chief must be capable of assuming temporary leadership of the survey party, absent a party chief, or in emergencies.
G. Consultant Availability and Work Hours
1. The typical workday includes all hours worked as identified in the task order or as directed by the Caltrans contract manager. Unless otherwise specified in a task order or directed by the Caltrans contract manager, the normal work week must comprise forty (40) hours.
2. If Caltrans determines that the work cannot be performed during normal business hours or the work is necessary at off hours to avoid danger to life or property, the consultant's operations may be…