07 Public Works Agreement.pdf
PDF 312 KB Posted
- Solicitation number
- 147423
- Issued by
- Riverside County, California
About this file
This is a Public Works Agreement template from the City of Beaumont, California, establishing the contractual framework for construction services. The agreement outlines the contractor's obligations to furnish all labor, materials, equipment, and tools necessary to complete the specified project within established timelines. Work must commence within ten calendar days of receiving a written Notice of Award from the City or its Construction Manager. The scope of work is incorporated by reference from the Invitation for Bids and related project documents, and the contractor must coordinate with other contractors and project participants without delaying or hindering their work. The contract documents include the Notice Inviting Bids, Scope of Work, Bid Form, General and Supplemental Conditions, Project Construction Schedule, Plans and Specifications, and Addenda.
The contract sum is designated as XXX (specific amount to be filled in), with progress payments issued based on Applications for Payment submitted to the Engineer and Certificates for Payment issued by the Engineer, subject to California Public Contract Code Article 1.7 provisions requiring payment of undisputed requests within 30 days. Final payment is due no sooner than 35 days after a Notice of Completion is recorded. The project is funded with Community Development Block Grant (CDBG) funds under 24 CFR 570 and is subject to prevailing wage requirements per California Labor Code Sections 1770 and 1773, as well as Federal Davis-Bacon Act requirements, with the contractor required to pay the higher of Federal or State prevailing wage rates. The contractor must maintain comprehensive insurance coverage including general liability ($1,000,000 per occurrence, $2,000,000 aggregate), automobile liability ($1,000,000 combined single limit), workers' compensation, pollution liability ($1,000,000), and builder's risk insurance. The contractor must possess a current California Contractor's License and be registered with the California Department of Industrial Relations. The agreement incorporates extensive Federal requirements including compliance with Executive Order 11246 (Equal Employment Opportunity), the Copeland Anti-Kickback Act, Contract Work Hours and Safety Standards Act, Clean Air and Water Acts, Byrd Anti-Lobbying Amendment, debarment and suspension requirements, drug-free workplace certification, Section 3 employment preferences for low and very low-income persons, and Build America, Buy America (BABA) provisions.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 08 Appendix B - Prevailing Wage Determination.pdf | ||
| 08 Appendices.pdf | ||
| 06 Contract Drawings.pdf | ||
| 08 Appendix A - Work Descriptions by Address.pdf | ||
| 04 Special Conditions.pdf | ||
| 05 Technical Specs.pdf | ||
| 09 Bid Plans - Elm Street.pdf | ||
| 02 General Conditions.pdf | ||
| 001 IFB.docx | DOCX document | |
| 03 Special Federal Provisions.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Page 1 of 13 Public Works Agreement
CITY OF BEAUMONT
PUBLIC WORKS AGREEMENT
This PUBLIC WORKS AGREEMENT (“Agreement”) is made and effective ___________________, 2026 by and between the City of Beaumont, a municipal corporation (“CITY”), and ___________________, (“CONTRACTOR”), a California Corporation. In consideration of the mutual covenants and conditions set forth herein, the parties agree as follows:
I. SCOPE OF WORK
The CONTRACTOR shall perform within the time set forth in Article 2 of this Agreement and shall furnish all labor, materials, equipment, tools, utility services, and transportation and perform and complete all work required in connection with the ___________________________________ (hereinafter “Project”).
CONTRACTOR’s Bid, dated ___________, is attached hereto as Exhibit A and incorporated herein by this reference. The Scope of Work for the Project is set forth in the Invitation. In the event that any terms of the Bid are different from the Invitation for Bids, the Invitation for Bids shall control. Any additional terms in the Bid that purport to bind the City to any additional terms not contained in this Agreement and related attachments shall not be binding on the City.
By entering into this Agreement, CONTRACTOR acknowledges that there may be other contractors on the site whose work will be coordinated with that of its own. CONTRACTOR expressly warrants and agrees that it will cooperate with other contractors and will do nothing to delay, hinder, or interfere with the work of other separate contractors, the CITY, the Construction Manager, the Engineer, or utilities. CONTRACTOR also expressly agrees that, in the event its work is hindered, delayed, interfered with, or otherwise affected by a separate contractor, its sole remedy will be a direct action against the separate contractor. To the extent allowed by law, the CONTRACTOR will have no remedy, and hereby expressly waives any remedy against the CITY, the Construction Manager (if any), and the Engineer on account of delay, hindrance, interference or other events.
II. TIME FOR PROJECT COMPLETION
All of CONTRACTOR’s work on the Project shall be completed within durations established for the individual activities. All work shall commence ten (10) calendar days after receiving a written Notice of Award from the CITY or Construction Manager, if a Construction Manager is employed by CITY on the Project. CONTRACTOR shall refer to the invitations for bids, and Project Plans and Specifications, all of which, as set forth below, are incorporated herein by reference, for contractual obligations regarding individual activity durations.
Page 2 of 13 Public Works Agreement
III. THE CONTRACT SUM
The CITY shall pay to the CONTRACTOR for the performance of this Agreement, subject to any additions and deductions provided in the Project documents, the sum of XXX ($XXX).
IV. PROGRESS PAYMENTS
Based upon Applications for Payment submitted to the Engineer by the CONTRACTOR and Certificates for Payment issued by the Engineer, the CITY shall make progress payments on account of the Contract Sum to the CONTRACTOR as provided in the General Conditions, which are fully incorporated into this Agreement by this reference.
This Agreement is subject to the provisions of Article 1.7 (commencing at Section 20104.50) of Division 2, Part 3 of the Public Contract Code regarding prompt payment of contractors by local governments. Article 1.7 mandates certain procedures for the payment of undisputed and properly submitted payment requests within 30 days after receipt, for the review of payment requests, for notice to Contractor of improper payment requests, and provides for the payment of interest on progress payment requests which are not timely made in accordance with that Article. This Agreement hereby incorporates the provisions of Article 1.7 as though fully set forth herein.
V. INDEMNITY, DEFENSE AND HOLD HARMLESS AGREEMENT
CONTRACTOR shall indemnify, defend with legal counsel approved by CITY, and hold harmless CITY, its officers, officials, employees and volunteers from and against all liability, loss, damage, expense, cost (including without limitation reasonable legal counsel fees, expert fees and all other costs and fees of litigation) of every nature arising out of or in connection with CONTRACTOR’s negligence, recklessness or willful misconduct in the performance of work hereunder or its failure to comply with any of its obligations contained in this Agreement, except such loss or damage which is caused by the sole or active negligence or willful misconduct of the CITY. Should conflict of interest principles preclude a single legal counsel from representing both CITY and CONTRACTOR, or should CITY otherwise find CONTRACTOR’s legal counsel unacceptable, then CONTRACTOR shall reimburse the CITY its costs of defense, including without limitation reasonable legal counsels fees, expert fees and all other costs and fees of litigation. The CONTRACTOR shall promptly pay any final judgment rendered against the CITY (and its officers, officials, employees and volunteers) with respect to claims determined by a trier of fact to have been the result of the CONTRACTOR’s negligent, reckless or wrongful performance. It is expressly understood and agreed that the foregoing provisions are intended to be as broad and inclusive as is permitted by the law of the State of California and will survive termination of this Agreement.
Page 3 of 13 Public Works Agreement
CONTRACTOR obligations under this section apply regardless of whether or not such claim, charge, damage, demand, action, proceeding, loss, stop notice, cost, expense, judgment, civil fine or penalty, or liability was caused in part or contributed to by an Indemnitee. However, without affecting the rights of CITY under any provision of this agreement, CONTRACTOR shall not be required to indemnify and hold harmless CITY for liability attributable to the active negligence of CITY, provided such active negligence is determined by agreement between the parties or by the findings of a court of competent jurisdiction. In instances where CITY is shown to have been actively negligent and where CITY active negligence accounts for only a percentage of the liability involved, the obligation of CONTRACTOR will be for that entire portion or percentage of liability not attributable to the active negligence of CITY.
VI. PREVAILING WAGES
A. Contractor shall comply with all applicable laws and regulations relating to prevailing wages. Wage rates for this Project shall be in accordance with the “General Wage Determination Made By the Director of Industrial Relations Pursuant To California Labor Code, Part 7, Chapter 1, Article 2, Sections 1770, 1773 and 1773.1”, for Riverside County. Wage rates shall conform with those posted at Beaumont City Hall and the Project site.
B. The following Labor Code sections are hereby referenced and made a part of this Agreement:
1. Section 1775 - Penalty for Failure to Comply with Prevailing Wage Rates.
2. Section 1777.4 - Apprenticeship Requirements.
3. Section 1777.5 - Apprenticeship Requirements.
4. Section 1813 - Penalty for Failure to Pay Overtime.
5. Sections 1810 and 1811 - Working Hour Restrictions.
6. Section 1775 - Payroll Records.
7. Section 1773.8 - Travel and Subsistence Pay.
VII. RECORD AUDIT
In accordance with Government Code, Section 8546.7, records of both the CITY and the CONTRACTOR shall be subject to examination and audit by the Auditor General for a period of three (3) years after final payment.
VIII. FINAL PAYMENT
Final payment, constituting the entire unpaid balance of the Agreement Sum, shall be paid by the CITY to the CONTRACTOR no sooner than thirty-five (35) days after a Notice of Completion has been recorded, unless otherwise stipulated
Page 4 of 13 Public Works Agreement in the Notice of Completion, provided the work has then been completed, the Agreement fully performed, and a final Certificate for Payment has been issued by the Engineer.
IX. CONTRACTOR’S FAILURE TO PROCURE COMPLETION OF PROJECT
In the event CONTRACTOR fails to furnish tools, equipment, or labor in the necessary quantity or quality, or fails to prosecute the work or any part thereof contemplated by this Agreement in a diligent and workmanlike manner, and if the CONTRACTOR for a period of three (3) calendar days after receipt of written demand from CITY or its designated representative to do so, fails to furnish tools, equipment, or labor in the necessary quantity or quality, and to prosecute its work and all parts thereof in a diligent and workmanlike manner, or after commencing to do so within said three (3) calendar days, fails to continue to do so; then the CITY may exclude the CONTRACTOR from the premises, or any portion thereof, and take possession of said premises or any portion thereof, together with all material and equipment thereon, and may complete the work contemplated by this Agreement or any portion of said work, either by furnishing the tools, equipment, labor or material necessary, or by letting the unfinished portion of said work, or the portion taken over by the CITY to another contractor or by a combination of such methods. In any event, the procuring of the completion of said work, or the portion thereof taken over by the CITY, shall be a charge against the CONTRACTOR, and may be deducted from any money due or becoming due to CONTRACTOR from the CITY, or the CONTRACTOR shall pay the CITY the amount of said charge, or the portion thereof unsatisfied. The sureties, provided for under this Agreement shall become liable for payment should CONTRACTOR fail to pay in full any said cost incurred by the CITY.
X. INSURANCE
Prior to the beginning of and throughout the duration of the Project, CONTRACTOR and its subcontractors shall maintain insurance in conformance with the requirements set forth below. Attached hereto as Exhibit C are copies of Certificates of Insurance and the waiver of subrogation endorsement as required by Section 6.B.1. CONTRACTOR will use existing coverage to comply with these requirements. If that existing coverage does not meet the requirements set forth herein, CONTRACTOR agrees to amend, supplement or endorse the existing coverage to do so.
CONTRACTOR acknowledges that the insurance coverage and policy limits set forth in this section constitute the minimum amount of coverage required. Any insurance proceeds available to CONTRACTOR or its subcontractors in excess of the limits and coverage identified in this Agreement and which is applicable to a given loss, claim or demand, will be equally available to CITY.
A. Types of Insurance
Page 5 of 13 Public Works Agreement
Without limiting CONTRACTOR’s indemnification of CITY, and prior to commencement of Work, CONTRACTOR shall obtain, provide and maintain at its own expense during the term of this Agreement, policies of insurance of the type and amounts described below and in a form satisfactory to CITY:
1. General liability insurance. CONTRACTOR shall maintain commercial general liability insurance with coverage at least as broad as Insurance Services Office form CG 00 01, in an amount not less than $1,000,000 per occurrence, $2,000,000 general aggregate, for bodily injury, personal injury, and property damage, and a $2,000,000 completed operations aggregate. The policy must include contractual liability that has not been amended. Any endorsement restricting standard ISO “insured contract” language will not be accepted.
2. Automobile liability insurance. CONTRACTOR shall maintain automobile insurance at least as broad as Insurance Services Office form CA 00 01 covering bodily injury and property damage for all activities of the CONTRACTOR arising out of or in connection with Work to be performed under this Agreement, including coverage for any owned, hired, non-owned or rented vehicles, in an amount not less than $1,000,000 combined single limit for each accident.
3. Umbrella or excess liability insurance. If CONTRACTOR is using umbrella coverage to meet part of its liability insurance requirements under Paragraph 1 of this Section, CONTRACTOR shall obtain and maintain an umbrella or excess liability insurance that will provide bodily injury, personal injury, completed operations and property damage liability coverage at least as broad as the primary coverages set forth above, including commercial general liability and employer’s liability. Such policy or policies shall include the following terms and conditions:
• A drop down feature requiring the policy to respond in the event that any primary insurance that would otherwise have applied proves to be uncollectable in whole or in part for any reason;
• Pay on behalf of wording as opposed to reimbursement;
• Concurrency of effective dates with primary policies;
• Policies shall “follow form” to the underlying primary policies;
and
• Insureds under primary policies shall also be insureds under the umbrella or excess policies.
4. Workers’ compensation insurance. CONTRACTOR shall maintain Workers’ Compensation Insurance (Statutory Limits) and Employer’s Liability Insurance (with limits of at least $1,000,000) for
Page 6 of 13 Public Works Agreement
CONTRACTOR’s employees in accordance with the laws of the State of California, Section 3700 of the Labor Code. In addition, CONTRACTOR shall require each subcontractor to similarly maintain Workers’ Compensation Insurance and Employer’s Liability Insurance in accordance with the laws of the State of California, Section 3700 for all of the subcontractor’s employees.
CONTRACTOR shall submit to CITY, along with the certificate of insurance, a Waiver of Subrogation endorsement in favor of CITY, its officers, agents, employees and volunteers.
5. Pollution liability insurance. Environmental Impairment Liability Insurance shall be written on a CONTRACTOR’s Pollution Liability form or other form acceptable to CITY providing coverage for liability arising out of sudden, accidental and gradual pollution and remediation. The policy limit shall be no less than $1,000,000 dollars per claim and in the aggregate. All activities contemplated in this Agreement shall be specifically scheduled on the policy as “covered operations.” The policy shall provide coverage for the hauling of waste from the project site to the final disposal location, including non-owned disposal sites.
Products/completed operations coverage shall extend a minimum of three
(3) years after project completion. Coverage shall be included on behalf of the insured for covered claims arising out of the actions of independent contractors.
If the insured is using subcontractors, the Policy must include work performed “by or on behalf” of the insured. Policy shall contain no language that would invalidate or remove the insurer’s duty to defend or indemnify for claims or suits expressly excluded from coverage. Policy shall specifically provide for a duty to defend on the part of the insurer. The CITY, its officials, officers, agents, and employees, shall be included as insureds under the policy.
6. Builder’s risk insurance. Upon commencement of construction and with approval of CITY, CONTRACTOR shall obtain and maintain builder’s risk insurance for the entire duration of the Project until only the CITY has an insurable interest. The Builder’s Risk coverage shall include the coverages as specified below.
The named insureds shall be CONTRACTOR and CITY, including its officers, officials, employees, and agents. All Subcontractors (excluding those solely responsible for design Work) of any tier and suppliers shall be included as additional insureds as their interests may appear. CONTRACTOR shall not be required to maintain property insurance for any portion of the Project following transfer of control thereof to CITY. The policy shall contain a provision that all proceeds
Page 7 of 13 Public Works Agreement from the builder’s risk policy shall be made payable to the CITY. The CITY will act as a fiduciary for all other interests in the Project.
Policy shall be provided for replacement value on an “all risk” basis for the completed value of the project. There shall be no coinsurance penalty or provisional limit provision in any such policy. Policy must include: (1) coverage for any ensuing loss from faulty workmanship, Nonconforming Work, omission or deficiency in design or specifications; (2) coverage against machinery accidents and operational testing; (3) coverage for removal of debris, and insuring the buildings, structures, machinery, equipment, materials, facilities, fixtures and all other properties constituting a part of the Project; (4) Ordinance or law coverage for contingent rebuilding, demolition, and increased costs of construction; (5) transit coverage (unless insured by the supplier or receiving contractor), with sub-limits sufficient to insure the full replacement value of any key equipment item; (6) Ocean marine cargo coverage insuring any Project materials or supplies, if applicable; (7) coverage with sub-limits sufficient to insure the full replacement value of any property or equipment stored either on or off the Site or any staging area. Such insurance shall be on a form acceptable to CITY to ensure adequacy of terms and sublimits and shall be submitted to the CITY prior to commencement of construction.
B. Other provisions or requirements
1. Proof of insurance. CONTRACTOR shall provide certificates of insurance to CITY as evidence of the insurance coverage required herein, along with a waiver of subrogation endorsement for workers’ compensation. Insurance certificates and endorsements must be approved by CITY’s risk manager prior to commencement of performance. Current certification of insurance shall be kept on file with CITY at all times during the term of this contract. CITY reserves the right to require complete, certified copies of all required insurance policies, at any time.
2. Duration of coverage. CONTRACTOR shall procure and maintain for the duration of the contract insurance against claims for injuries to persons or damages to property, which may arise from or in connection with the performance of the Work hereunder by CONTRACTOR, his agents, representatives, employees or subcontractors. CONTRACTOR must maintain general liability and umbrella or excess liability insurance for as long as there is a statutory exposure to completed operations claims. CITY and its officers, officials, employees, and agents shall continue as additional insureds under such policies.
Page 8 of 13 Public Works Agreement
3. Primary/noncontributing. Coverage provided by CONTRACTOR shall be primary and any insurance or self-insurance procured or maintained by CITY shall not be required to contribute with it. The limits of insurance required herein may be satisfied by a combination of primary and umbrella or excess insurance. Any umbrella or excess insurance shall contain or be endorsed to contain a provision that such coverage shall also apply on a primary and non-contributory basis for the benefit of CITY before the CITY’s own insurance or self-insurance shall be called upon to protect it as a named insured.
4. CITY’s rights of enforcement. In the event any policy of insurance required under this Agreement does not comply with these requirements or is canceled and not replaced, CITY has the right but not the duty to obtain the insurance it deems necessary and any premium paid by CITY will be promptly reimbursed by CONTRACTOR or CITY will withhold amounts sufficient to pay premium from CONTRACTOR payments. In the alternative, CITY may cancel this Agreement.
5. Acceptable insurers. All insurance policies shall be issued by an insurance company currently authorized by the Insurance Commissioner to transact business of insurance or is on the List of Approved Surplus Line Insurers in the State of California, with an assigned policyholders’ Rating of A- (or higher) and Financial Size Category Class VII (or larger) in accordance with the latest edition of Best’s Key Rating Guide, unless otherwise approved by the CITY’s risk manager.
6. Waiver of subrogation. All insurance coverage maintained or procured pursuant to this agreement shall be endorsed to waive subrogation against CITY, its elected or appointed officers, agents, officials, employees and volunteers or shall specifically allow CONTRACTOR or others providing insurance evidence in compliance with these specifications to waive their right of recovery prior to a loss.
CONTRACTOR hereby waives its own right of recovery against CITY, and shall require similar written express waivers and insurance clauses from each of its subconsultants.
7. Enforcement of contract provisions (non estoppel).
CONTRACTOR acknowledges and agrees that any actual or alleged failure on the part of the CITY to inform CONTRACTOR of non-compliance with any requirement imposes no additional obligations on the CITY nor does it waive any rights hereunder.
8. Requirements not limiting. Requirements of specific coverage features or limits contained in this Section are not intended as a
Page 9 of 13 Public Works Agreement limitation on coverage, limits or other requirements, or a waiver of any coverage normally provided by any insurance. Specific reference to a given coverage feature is for purposes of clarification only as it pertains to a given issue and is not intended by any party or insured to be all inclusive, or to the exclusion of other coverage, or a waiver of any type.
If the CONTRACTOR maintains higher limits than the minimums shown above, the CITY requires and shall be entitled to coverage for the higher limits maintained by the CONTRACTOR. Any available insurance proceeds in excess of the specified minimum limits of insurance and coverage shall be available to the CITY.
9. Notice of cancellation. CONTRACTOR agrees to oblige its insurance agent or broker and insurers to provide to CITY with a thirty (30) day notice of cancellation (except for nonpayment for which a ten (10) day notice is required) or nonrenewal of coverage for each required coverage.
10. Additional insured status. General liability policies shall provide or be endorsed to provide that CITY and its officers, officials, employees, agents, and volunteers shall be additional insureds under such policies. This provision shall also apply to any excess/umbrella liability policies.
11. Prohibition of undisclosed coverage limitations. None of the coverages required herein will be in compliance with these requirements if they include any limiting endorsement of any kind that has not been first submitted to CITY and approved of in writing.
12. Separation of insureds. A severability of interests provision must apply for all additional insureds ensuring that CONTRACTOR’s insurance shall apply separately to each insured against whom claim is made or suit is brought, except with respect to the insurer’s limits of liability. The policy(ies) shall not contain any cross-liability exclusions.
13. Pass through clause. CONTRACTOR agrees to ensure that its subconsultants, subcontractors, and any other party involved with the project who is brought onto or involved in the project by CONTRACTOR, provide the same minimum insurance coverage and endorsements required of CONTRACTOR. CONTRACTOR agrees to monitor and review all such coverage and assumes all responsibility for ensuring that such coverage is provided in conformity with the requirements of this section. CONTRACTOR agrees that upon request, all agreements with consultants, subcontractors, and others engaged in the project will be submitted to CITY for review.
Page 10 of 13 Public Works Agreement
14. CITY’s right to revise requirements. The CITY reserves the right at any time during the term of the contract to change the amounts and types of insurance required by giving the CONTRACTOR a ninety (90) day advance written notice of such change. If such change results in substantial additional cost to the CONTRACTOR, the CITY and CONTRACTOR may renegotiate CONTRACTOR’s compensation.
15. Self-insured retentions. Any self-insured retentions must be declared to and approved by CITY. CITY reserves the right to require that self-insured retentions be eliminated, lowered, or replaced by a deductible.
Self-insurance will not be considered to comply with these specifications unless approved by CITY.
16. Timely notice of claims. CONTRACTOR shall give CITY prompt and timely notice of claims made or suits instituted that arise out of or result from CONTRACTOR’s performance under this Agreement, and that involve or may involve coverage under any of the required liability policies.
17. Additional insurance. CONTRACTOR shall also procure and maintain, at its own cost and expense, any additional kinds of insurance, which in its own judgment may be necessary for its proper protection and prosecution of the Work.
XI. CONTRACTOR’S LICENSE
CONTRACTOR must possess at the time of commencing work and throughout the Project duration, a Contractor’s License, issued by the State of California, which is current and in good standing. CONTRACTOR shall ensure that any subcontractor working on the Project possesses at the time of commencing work and throughout the Project duration, a Contractor’s License, issued by the State of California, which is current and in good standing.
XII. REGISTRATION REQUIREMENTS
A. Pursuant to Section 1771.1(a) of the Labor Code:
“A contractor or subcontractor shall not be qualified to bid on, be listed in a bid proposal, subject to the requirements of Section 4104 of the Public Contract Code, or engage in the performance of any contract for public work, as defined in this chapter, unless currently registered and qualified to perform public work pursuant to Section 1725.5. It is not a violation of this section for an unregistered contractor to submit a bid that is authorized by Section 7029.1 of the Business and Professions Code or by Section 10164 or 20103.5 of the Public Contract
Page 11 of 13 Public Works Agreement
Code, provided the contractor is registered to perform public work pursuant to Section 1725.5 at the time the contract is awarded.”
B. CONTRACTOR must be registered with the Department of Industrial Relations (DIR) of the State of California in order to be eligible to work on public works projects. CONTRACTOR must ensure registration with the DIR that is active and in good standing.
C. No contractor or subcontractor may be listed on a bid proposal for a public works project (submitted on or after March 1, 2015) unless registered with the Department of Industrial Relations pursuant to Labor Code section 1725.5 [with limited exceptions from this requirement for bid purposes only under Labor Code section 1771.1(a)].
No contractor or subcontractor may be awarded a contract for public work on a public works project unless registered with the Department of Industrial Relations pursuant to Labor Code section 1725.5.
This project is subject to compliance monitoring and enforcement by the Department of Industrial Relations.
D. The CONTRACTOR is not subject to public works requirements (including registration with the DIR) if the public works project is under $1,000, unless the CITY knows that the same CONTRACTOR will be awarded total project costs in excess of $1,000 for a given year.
XIII. CORPORATION IN GOOD STANDING
If CONTRACTOR is a corporation, the undersigned hereby represents and warrants that the corporation is duly incorporated and in good standing in the State of California, and that David Van Dyke whose title is President is authorized to act for and bind the corporation.
XIV. PROVISIONS REQUIRED BY LAW
Each and every provision of law and clause required by law to be inserted in this Agreement shall be deemed to be inserted herein and the Agreement shall be read and enforced as though it were included herein, and if through mistake or otherwise any such provision is not inserted, or is not currently inserted, then upon application of either party the Agreement shall forthwith be physically amended to make such insertion or correction.
XV. SUBSURFACE HAZARDOUS MATERIALS
Page 12 of 13 Public Works Agreement
A. In the event trenches or other excavations extend deeper than four (4) feet below the surface, the CONTRACTOR shall promptly, and before the following conditions are disturbed, notify the CITY in writing of any:
1. Material that the CONTRACTOR believes may be material that is hazardous waste, as defined in Section 25117 of the Health and Safety Code that is required to be removed to a Class I, Class II or Class III disposal site in accordance with the provisions of existing law.
2. Subsurface or latent physical conditions at the site differing from those indicated.
3. Unknown physical conditions at the site of any unusual nature, different materially from those ordinarily encountered and generally recognized as inherent in the Work or the character provided for in the CONTRACT.
B. Upon receipt of said notification the CITY will investigate the conditions, and if it finds that the conditions do materially so differ, or do involve hazardous waste, and cause a decrease or increase in the CONTRACTOR’s cost of or the time required for performance of any part of the work, the CITY will issue a change order under the procedures described in the General Conditions.
C. In the event that a dispute arises between the CITY and the
CONTRACTOR whether the conditions materially differ, or involve hazardous waste or cause a decrease or increase in the CONTRACTOR’s cost of or time required for performance of any part of the work, the CONTRACTOR shall not be excused from any scheduled completion date provided for by the Agreement, but shall proceed with all work to be performed under the Agreement. The CONTRACTOR shall retain any and all rights provided either by Agreement or by law which pertain to the resolution of disputes and protests between the contracting parties.
XVI. COMPONENT PARTS OF THE CONTRACT
This Agreement entered into consists of the following CONTRACT DOCUMENTS, all of which are component parts of the Agreement as if herein set out in full or attached hereto:
Notice Inviting Bids Scope of Work Summary Information for Bidders Bid Form Non-Collusion Affidavit Site Visit Certification Faithful Performance Bond
Labor and Materials Payment Bond General and Supplemental Conditions Special Conditions Project Construction Schedule Proposed Subcontractors
Page 13 of 13 Public Works Agreement
Bid Bond Information Required of Bidder Construction Services Agreement Certificate Regarding Worker’s Compensation Drug-free Workplace Certification Plans and Specifications
Addenda Drawings Change Orders Shop Drawing Transmittals Contractor’s Certificate Regarding Non-Asbestos Containing Materials
All of the above-named CONTRACT DOCUMENTS are intended to be complementary. Work required by one of the above-named CONTRACT DOCUMENTS and not by others shall be done as if required by all.
Exhibit D, titled “COMMUNITY DEVELOPMENT BLOCK GRANT TERMS AND CONDITIONS,” is attached hereto and incorporated into this Agreement in its entirety as a CONTRACT DOCUMENT. Exhibit D includes the Special Federal Requirements and Additional Federal Requirements applicable to the Project, and CITY and CONTRACTOR agree to comply with all requirements set forth therein. CONTRACTOR shall ensure that each subcontractor and subconsultant performing any portion of the Work complies with all provisions of Exhibit D applicable to that subcontractor or subconsultant. Notwithstanding any other provision of this Agreement or any other CONTRACT DOCUMENT, if any conflict, inconsistency, or ambiguity exists between Exhibit D and this Agreement or any other CONTRACT DOCUMENT, Exhibit D shall govern and control.
XVII. ENTIRE CONTRACT
This Agreement constitutes the entire contract of the parties. No other agreements or contracts, whether oral or written, pertaining to the work to be performed, exists between the parties. This Agreement can be modified only by an amendment in writing, signed by both parties.
[Signatures on following page.]
SIGNATURE PAGE TO
CITY:
By:
Chris Boatman, City Manager
CONTRACTOR:
XXX
By: ______________________________
Print Name: _______________________
Title: _____________________________
EXHIBIT “A”
CITY’S FEBRUARY 9, 2023
INVITATION FOR BIDS
EXHIBIT “B”
CONTRACTOR’S Bid
EXHIBIT “C”
Insurance Certificates and Endorsements
EXHIBIT “D”
COMMUNITY DEVELOPMENT BLOCK GRANT
TERMS AND CONDITIONS
Special Federal Requirements
1. CONTRACTOR and CITY do hereby acknowledge that this project will be partially or fully funded with Community Development Block Grant (CDBG) funds [24 CFR 570] and is therefore subject to applicable Federal procurement, labor, environmental, equal opportunity, and other regulations.
2. CONTRACTOR shall maintain and keep books and records on a current basis, recording all transactions pertaining to this agreement in a form in accordance with generally acceptable accounting principles. Said books and records shall be made available to the County, the State of California, the Federal government, and to any authorized representative thereof for the purposes of audit at all reasonable times and places. All such books and records shall be retained for such periods of time as required by law, provided, however, notwithstanding any shorter periods of retention, all books, records, and supporting detail shall be retained for a period of at least four (4) years after the expiration of the term of this Agreement.
3. CONTRACTOR shall comply with the Davis-Bacon Fair Labor Standards Act (40 USC a-276, a-5) and the implementation regulations thereof. CONTRACTOR shall comply with the U.S. Department of Housing and Urban Development’s Federal Labor Standards Provisions (HUD 4010).
4. CONTRACTOR acknowledges that work under this contract is subject to the payment of prevailing wages pursuant to Section 1770 and 1773 et seq. of the Labor Code of the State of California, the Director of Industrial Relations (State Prevailing Wages), and the U.S. Department of Housing and Urban Development’s Federal Labor Standards Provisions (Davis-Bacon Act Prevailing Wages). The CONTRACTOR to whom the contract is awarded, and all subcontractors under him, shall pay the higher of the Federal or State prevailing wage rate for any given classification employed in the performance of this contract.
CONTRACTOR acknowledges that the applicable Wage Determination for this project is:
General Decision Number: CA___________ Modification Number: ______ Date: ____________
Additional Federal Requirements
Whereas, the work under this Agreement is subject to applicable Federal, State, and local laws and regulations, including but not limited to the regulations pertaining to the Community Development Block Grant program (24 CFR Part 570) and the Uniform Administrative Requirement, Cost Principles, and Audit Requirements for Federal Awards (2 CFR Part 200).
CONTRACTOR, sub-contractors, Consultants, and sub-consultants agree to comply with, and are subject to, all applicable requirements as follows:
Equal Employment Opportunity - Compliance with Executive Order 11246 of September 24, 1965, entitled "Equal Employment Opportunity", as amended by Executive Order 11375 of October 13, 1967, and as supplemented in Department of Labor regulations (41 CFR Part 60).
The CONTRACTOR/Consultant will not discriminate against any employee or applicant for employment because of race, color, religion, sex, sexual orientation, general identity or national origin. CONTRACTOR/Consultant will ensure that all qualified applicants will receive consideration for employment without regard to race, color, religion, sex sexual orientation, general identity or national origin. The CONTRACTOR/Consultant will take affirmative action to ensure that applicants are employed and the employees are treated during employment, without regard to their race color, religion, sex, sexual orientation, general identity or national origin. Such actions shall include, but are not limited to, the following: employment, up-grading, demotion, or transfer; recruitment or recruitment advertising; rates of pay or other forms of compensation; and selection for training, including apprenticeship. The CONTRACTOR/Consultant agrees to post in a conspicuous place, available to employees and applicants for employment, notices to be provided by the County setting forth the provisions of this non-discriminating clause.
2. Copeland “Anti-Kickback” Act (18 U.S.C. 874 and 40 U.S.C.A. Section 3145): All contracts and subgrants in excess of $2,000 for construction or repair awarded by recipients and subrecipients shall include a provision for compliance with the Copeland “Anti-Kickback” Act (18 U.S.C. 874), as supplemented by Department of Labor regulations (29 CFR Part 3, “Contractors and Subcontractors on Public Building or Public Work Financed in Whole or in Part by Loans or Grants from the United States”). The Act provides that each contractor or subrecipient shall be prohibited from inducing, by any means, any person employed in the construction, completion, or repair of public work, to give up any part of the compensation to which he is otherwise entitled. The recipient shall report all suspected or reported violations to
HUD.
3. Davis-Bacon Act, as amended (40 U.S.C.A. Section 3141-3148): When required by Federal program legislation, all construction contracts awarded by the recipients and subrecipients of more than $2000 shall include a provision for compliance with the Davis-Bacon Act (40 U.S.C. A. Section 3141-3148) and as supplemented by Department of Labor regulations (29 CFR Part 5, “Labor Standards Provisions Applicable to Contracts Governing Federally Financed and Assisted Construction”). Under the Davis Bacon Act, contractors shall be required to pay wages to laborers and mechanics at a rate not less than the minimum wages specified in a wage determination made by the U.S. Secretary of Labor. In addition, contractors shall be required to pay wages not less than once a week. The recipient shall place a copy of the current prevailing wage determination issued by the U.S. Department of Labor in each solicitation and the award of a contract shall be conditioned upon the acceptance of the wage determination. The recipient shall report all suspected or reported violations to HUD.
4. Contract Work Hours and Safety Standards Act (40 U.S.CA.. 32701 through 3708):
Where applicable, all contracts awarded by recipients in excess of $2,000 for construction contracts and in excess of $2,500 for other contracts that involve the employment of mechanics or laborers shall include a provision for compliance with the Contract Work Hours and Safety Standards (40 U.S.C.A. 32701–3708), as supplemented by Department of Labor Regulations (29 CFR Part 5). Under Section 40 U.S.C.A. 3702, each contractor shall be required to compute the wages of every mechanic and laborer on the basis of a standard workweek of 40 hours. Work in excess of the standard workweek is permissible provided that the worker is compensated at a rate of not less than 1 1/2 times the basic rate of pay for all hours worked in excess of 40 hours in the workweek. 40 U.S.C.A. 3704of the Act is applicable to construction work and provides that no laborer or mechanic shall be required to work in surroundings or under working conditions which are unsanitary, hazardous or dangerous. These requirements do not apply to the purchases of supplies or materials or articles ordinarily available on the open market, or contracts for transportation or transmission of intelligence.
5. Rights to Inventions Made Under a Contract or Agreement— Contracts or agreements for the performance of experimental, developmental, or research work shall provide for the rights of the Federal Government and the recipient in any resulting invention in accordance with 37 CFR part 401, “Rights to Inventions Made by Nonprofit Organizations and Small Business Firms Under Government Grants, Contracts and Cooperative Agreements,” and any implementing regulations issued by HUD.
6. Rights to Data and Copyrights – Contractors and consultants agree to comply with all applicable provisions pertaining to the use of data and copyrights pursuant to 48 CFR Part 27.404-3, Federal Acquisition Regulations (FAR).
7. Air Pollution Prevention and Control (formally known as the Clean Air Act) (42 U.S.C.A. 7401 et seq.) and the Federal Water Pollution Control Act (33 U.S.C.A. Section 1251 et seq.), as amended:—Contracts and subgrants of amounts in excess of $100,000 shall contain a provision that requires the recipient to agree to comply with all applicable standards, orders or regulations issued pursuant to the Clean Air Act (42 U.S.C. 7401 et seq.) and the Federal Water Pollution Control Act as amended (33 U.S.C.A. 1251 et seq.). Violations shall be reported to HUD and the Regional Office of the Environmental Protection Agency (EPA).
8. Byrd Anti-Lobbying Amendment (31 U.S.C.A. 1352)— Contractors who apply or bid for an award of $100,000 or more shall file the required certification. Each tier certifies to the tier above that it will not and has not used Federal appropriated funds to pay any person or organization for influencing or attempting to influence an officer or employee of any agency, a member of Congress, officer or employee of Congress, or an employee of a member of Congress in connection with obtaining any Federal contract, grant or any other award covered by 31
U.S.C. 1352. Each tier shall also disclose any lobbying with non-Federal funds that takes place in connection with obtaining any Federal award. Such disclosures are forwarded from tier to tier up to the recipient.
9. Debarment and Suspension (Executive Orders (E.O. s) 12549 and 12689)—No contract shall be made to parties listed on the General Services Administration's List of Parties Excluded from Federal Procurement or Nonprocurement Programs in accordance with E.O.s 12549 and 12689, “Debarment and Suspension,” as set forth at 24 CFR part 2424. This list contains the names of parties debarred, suspended, or otherwise excluded by agencies, and contractors declared ineligible under statutory or regulatory authority other than E.O. 12549. Contractors with awards that exceed the small purchase threshold shall provide the required certification regarding its exclusion status and that of its principal employees.
10. Drug-Free Workplace Requirements— The Anti-Drug Abuse Act of 1988 (41 U.S.C.A.
Section 8101-8103)requires grantees (including individuals) of federal agencies, as a prior condition of being awarded a grant, to certify that they will provide drug-free workplaces. Each potential recipient must certify that it will comply with drug-free workplace requirements in accordance with the Act and with HUD's rules at 24 CFR part 2425.
11. Access to Records and Records Retention: The Consultant or CONTRACTOR, and any sub-consultants or sub-contractors, shall allow all duly authorized Federal, State, and/or County officials or authorized representatives access to the work area, as well as all books, documents, materials, papers, and records of the Consultant or CONTRACTOR, and any sub-consultants or sub-contractors, that are directly pertinent to a specific program for the purpose of making audits, examinations, excerpts, and transcriptions. The Consultant or CONTRACTOR, and any sub-consultants or sub-contractors, further agree to maintain and keep such books, documents, materials, papers, and records, on a current basis, recording all transactions pertaining to this agreement in a form in accordance with generally acceptable accounting principles. All such books and records shall be retained for such periods of time as required by law, provided, however, notwithstanding any shorter periods of retention, all books, records, and supporting detail shall be retained for a period of at least four (4) years after the expiration of the term of this Agreement.
12. Federal Employee Benefit Clause: No member of or delegate to the congress of the United States, and no Resident Commissioner shall be admitted to any share or part of this agreement or to any benefit to arise from the same.
Energy Efficiency: Mandatory standards and policies relating to energy efficiency which are contained in the State energy conservation plan issued in compliance with the Energy Policy and Conservation Act (Pub. L. 94A 163, Dec. 22, 1975; 42 U.S.C.A. Section 6201, et. seq., 89 Stat.
871).
Procurement of Recovered Materials (2 CFR 200.322.) A non-Federal entity that is a state agency or agency of a political subdivision of a state and its contractors must comply with 42 U.S.C. Section 6962 of the Solid Waste Disposal Act (42 U.S.C.A. Section 6901, et seq.), as amended by the Resource Conservation and Recovery Act. The requirements of Section 6002 include procuring only items designated in guidelines of the Environmental Protection Agency (EPA) at 40 CFR part 247 that contain the highest percentage of recovered materials practicable, consistent with maintaining a satisfactory level of competition, where the purchase price of the item exceeds $10,000 or the value of the quantity acquired by the preceding fiscal year exceeded $10,000; procuring solid waste management services in a manner that maximizes energy and resource recovery; and establishing an affirmative procurement program for procurement of recovered materials identified in the EPA guidelines.
15. Build America, Buy America (BABA) Act: The Grantee must comply with the requirements of the Build America, Buy America (BABA) Act, 41 USC 8301 note, and all applicable rules and notices, as may be amended, if applicable to the Grantee’s infrastructure project. Pursuant to HUD’s Notice, “Public Interest Phased Implementation Waiver for FY 2022 and 2023 of Build America, Buy America Provisions as Applied to Recipients of HUD Federal Financial Assistance” (88 FR 17001), any funds obligated by HUD on or after the applicable listed effective dates, are subject to BABA requirements, unless excepted by a waiver.
16. Violence Against Women Act (VAWA): VAWA provides housing protections for survivors of domestic and dating violence, sexual assault and stalking (‘domestic violence”). VAWA 2022 reauthorizes, amends, and strengthens the VAWA of 1994, as amended (Pub. L. 103-322, tit. IV, sec. 40001-40703; 34 U.S.C. 12291 et seq.) HUD’s implementing regulations for VAWA’S protections, rights, and responsibilities are codified in 24 CFR part 5, subpart L, and related provisions in HUD’s program regulations (HUD’s VAWA regulations). VAWA 2022 amendments took effect on October 1, 2022 and 2022 VAWA’s reauthorization includes new implementation requirements. Grantees, subrecipients and developers shall ensure compliance with all requirements of VAWA including but not limited to: (a) Assure domestic violence survivors are not denied assistance as an applicant, or evicted, or have assistance terminated as a tenant because applicant or tenant is or has been a victim of domestic violence; (b) Implement an emergency transfer plan allowing domestic violence survivor to move to another safe and available unit; (c) Provide protections against denial, terminations, and evictions that directly result from being a victim of domestic violence; (d) Implement a low barrier certification process and allow self-certification of domestic violence.
17. Section 3 Contract Language:
I. The work to be performed under this contract is subject to the requirements of Section 3 of the Housing and Urban Development Act of 1968, as amended, 12 USC.1701u (Section 3). The purpose of Section 3 is to ensure that employment and other economic opportunities generated by HUD assistance, or HUD-assisted projects covered by Section 3, shall to the greatest extent feasible be directed to low and very low-income persons, particularly persons who are recipients of HUD assistance for housing.
II. The parties to this contract agree to comply with HUD's regulations in 24 CFR part 75, which implement Section 3. As evidenced by their execution of this contract, the parties to this contract certify that they are under no contractual or other impediment that would prevent them from complying with the part 75 regulations.
III. The contractor agrees to send to each labor organization or representative of workers with which the contractor has a collective bargaining agreement or other understanding, if any, a notice advising the labor organization or workers' representative of the contractor's commitments under this Section 3 Clause and will post copies of the notice in conspicuous places at the work site where both employees and applicants for training and employment positions can see the notice. The notice shall describe the Section 3 preference, shall set forth minimum number and job titles subject to hire, availability of apprenticeship and training positions, the qualifications for each; the name and location of the person(s) taking applications for each of the positions; and the anticipated date the work shall begin.
IV. The contractor agrees to include this Section 3 Clause in every subcontract subject to compliance with regulations in 24 CFR part 75, and agrees to take appropriate actions, as provided in an applicable provision of the subcontract or in this Section 3 Clause, upon a finding that the subcontractor is in violation of the regulations in 24 CFR part 75. The contractor will not subcontract with any subcontractor where the contractor has notice or knowledge that the subcontractor has been found in violation of the regulations in 24 CFR part 75.
V. The contractor will certify that any vacant employment positions, including training positions, that are filled (1) after the contractor is selected but before the contract is executed, and (2) with persons other than those to whom the regulations of 24 CFR part 75 require employment opportunities to be directed, were not filled to circumvent the contractor's obligations under 24 CFR part 75.
VI.…
This is the start of the file's text. The full file is on GovTribe.