This is Addendum 02 for the Central Lake Public Schools Elementary School Secure Vestibule and HS/MS Remodel project, issued by the school district in Central Lake, Michigan on February 4, 2026. The project encompasses renovation and remodeling work at both the elementary and middle/high school facilities, with Bid Package No. 1 focusing on MS/HS and Elementary renovations. The scope of work is divided into eleven prime contract work categories: Masonry (04-01), Structural Steel (05-01), General Trades (06-01), Roofing and Siding (07-01), Glass and Glazing (08-01), Walls and Ceilings (09-01), Flooring (09-02), Painting (09-03), Plumbing and Mechanical (23-01), Electrical (26-01), and Earthwork/Site Work (31-01). The bid due date remained unchanged at Monday, February 9, 2026 at 3:30 p.m., with bids to be submitted to Dr. Ryan Cunningham, Superintendent, at the MS/HS main office and opened publicly immediately thereafter in the MS/HS library. Post-bid interviews were scheduled for February 10-12, 2026 across multiple time slots for each work category. Addendum 02 includes 71 pages of documents providing clarifications to bid categories and specifications, updated project manual sections, requests for information responses, and French Associates drawing and specification addendums addressing fire alarm system modifications, wheelchair lift configurations, glazing specifications, and structural details.
The addendum addresses key modifications including the removal of fire alarm devices from bid documents due to system compatibility issues, specification of GL-5f 120-minute fire-rated glazing for applicable applications, and updates to wheelchair lift specifications with the Savaria V 1504 VPL 90-degree configuration as the basis of design. Each work category includes a contingency allowance ranging from $2,500 to $15,000, with contingency funds to be used for actual costs only without overhead and profit markup, and unused portions credited back through deductive change orders. The document provides detailed scope clarifications for all trades regarding demolition, coordination requirements, testing and commissioning, temporary protection, and final cleaning responsibilities. Requests for information addressed topics including existing ceiling insulation, aluminum storefront specifications, flooring demolition responsibilities, ground-penetrating radar locations, dumpster coordination, door access controls, and gym floor demo scheduling in relation to roof work. Moore Trosper Construction Company served as the general contractor managing the overall project coordination and scheduling.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM 02
February 5, 2026
Central Lake Public Schools Elementary School Secure Vestibule &
HS/MS Remodel & Secure Vestibule Addition Bid Package No.1
Project # 25-113
Addendum 2 is being issued to inform bidders of modifications/clarifications to the Bid Categories and/or the specifications and/or the plans and/or any additional information provided.
Documents included with this Addendum 2: 71 pages/sheets Information Sheet (this sheet) – 1 page Requests for Information – 3 pages Updated Project Manual Sections – 36 pages:
o Section 002413 Work Categories – 35 pages o Attachment D Post Bid Interview Schedule – 1 page
French Associates Addendum 02 Description dated 02/04/26 - 3 pages French Associates Addendum 01 Specifications Manual pages – 18 pages French Associates Addendum 01 Construction Drawings pages dated 01/26/26 – 10 sheets
1. Bid Due Date:
1.1. Bid Due Date Remains Unchanged, Bid Due Date is Monday, February 9, 2026 at 3:30 pm. Bids must be submitted to the district per the Project Manual. No email or Procore submissions will be accepted.
Lump sum sealed proposals will be received addressed to, Dr. Ryan Cunningham, Superintendent, Central Lake Public Schools, 8169 W. State Street, Central Lake, MI at the MS/HS main office by 3:30 pm on Monday February 9, 2026.
Proposals will only be accepted on the proposal form provided under specification section 004126. The bids will be opened publicly immediately after in the MS/HS library on the same date.
END OF ADDENDUM NO. 02
RFI LOG
# Revision Subject Status Responsible
Contractor Received From
Date Initiated
RFI
Manager
Assignee Ball In Court
Due Date
Closed Date
Location Schedule Impact
Cost Impact
Cost Code
Sub Job
RFI
Stage
Distribution List Private
PB-001 0
MS/HS - ACT
Demo and existing ceiling insulation
Closed Moore Trosper Con...
Halloran, Chris (Moore Trosper Construction Co.)
01/30/
Chris Halloran
Adler, Alexander Marchetti, Charle...
02/ 04/
02/02/
Heather Place (Moore Trosper Construction Co.), Charles Marchetti (French Associates), Chris Halloran (Moore Trosper Construction Co.), Alexander Adler (French Associates)
No
Q: Chris Halloran Sent Fri Jan 30, 2026 at 09:30 am EST ACT Demo - is there batt insulation laid on top of the existing ACT? If yes, are we to salvage and reinstall or remove and replace? Please advise.
A:
Chris Halloran (Moore Trosper Construction Co.) Responded Mon Feb 2, 2026 at 01:36 pm EST The insulation at the existing lobby area of the MS/HS is located to the underside of the metal deck. We anticipate this to remain in place.
The insulation in the media center is located on top of the existing suspended ACT system and will be removed and disposed of.
Alexander J Adler, RA NCARB 02.02.2026
RFI#1 Demo_and_existing_ceiling_insulation-2026-01-30.pdf
PB-002 0
Aluminum storefront clarification
Closed Moore Trosper Con...
Halloran, Chris (Moore Trosper Construction Co.)
01/30/
Chris Halloran
Halloran, Chris (...
Place, Heather (M...
02/ 04/
02/05/ 26 No
Q: Chris Halloran Sent Fri Jan 30, 2026 at 09:32 am EST Base spec listed 082133 includes aluminum storefront framing systems. Can this be clarified so that the general trades package does not carry any costs for the aluminum storefront systems since this is its own bid package.
A:
Chris Halloran (Moore Trosper Construction Co.) Responded Thu Feb 5, 2026 at 08:58 am EST WC 06-01 General Trades is to provide all hollow metal frames, hollow metal frame windows, wood doors, FRP doors, hardware, final cores. WC 08-01 Glass and Glazing is to provide all glass and glazing, safety films. See updated addendum 2 drawings changing aluminum frames to hollow metal. These WCs shall coordinate for proper glass within frames.
PB-003 0 Flooring Demo Closed Moore Trosper Con...
Halloran, Chris (Moore Trosper Construction Co.)
01/30/
Chris Halloran
Halloran, Chris (...
Place, Heather (M...
02/ 04/
02/02/ 26 No
Q: Chris Halloran Sent Fri Jan 30, 2026 at 09:31 am EST Flooring demo - will it be the general trades responsibility to grid the floor after removal of the glue down carpet or will that fall under the flooring contractors scope?
A: Chris Halloran (Moore Trosper Construction Co.) Responded Mon Feb 2, 2026 at 02:50 pm EST General trades demo contractor shall provide full flooring demo including adhesives and glues for a clean substrate. Flooring contractor shall provide any floor patch or leveling as needed.
PB-004 0
Ground penetrating radar clarification
Closed Moore Trosper Con...
Halloran, Chris (Moore Trosper Construction Co.)
01/30/
Chris Halloran
Halloran, Chris (...
Place, Heather (M...
02/ 04/
02/02/ 26 No
Q: Chris Halloran Sent Fri Jan 30, 2026 at 09:32 am EST
Moore Trosper Construction Co.
Printed on Thu Feb 5, 2026 at 08:58 am EST
Job #: 25-113 Central Lake MS/HS and Elementary Renovations - BP1 8169 W. State Street
Central Lake, Michigan 49622 https://storage.procore.com/api/v5/files/us-east-1/pro-core.com/940355523431895-c/822144623431895-p/01KGFT8CRAEGWVGNEHMHFRSVG4?companyId=598134325553049&projectId=598134326441228&sig=85edcd67ccd157035c37cf871319640afd1d8b7f82dc40ebb48fb7a2e7f89578
Contractor
Received From
Date Initiated
RFI
Manager
Assignee Ball In Court
Due Date
Closed Date
Location Schedule Impact
Cost Impact
Cost Code
Sub Job
RFI
Stage
Distribution List Private
Ground Penetrating Radar - MEP contractors indicated that concrete cutting, removal, and replacement will be required to accommodate their scope. Can it be identified for what rooms will require the ground penetrating radar?
A: Chris Halloran (Moore Trosper Construction Co.) Responded Mon Feb 2, 2026 at 10:30 am EST Ground penetrating radar for locating existing infrastructure shall occur at any concrete floor cutting areas. These include Community Gym A153, Lobby A102, Corridor.
PB-005 0 Dumpsters clarification Closed Moore
Trosper Con...
Halloran, Chris (Moore Trosper Construction Co.)
01/30/
Chris Halloran
Place, Heather (M...
Halloran, Chris (...
02/ 04/
02/05/ 26 No
Q:
Chris Halloran Sent Fri Jan 30, 2026 at 09:33 am EST Dumpsters - In previous projects we've carried all the dumpster costs for the project. This is so that every contractor doesn't have their own dumpster set on the site. If we are to carry the dumpster costs for the whole project can it be identified how many to include for bidding purposes?
A: Chris Halloran (Moore Trosper Construction Co.) Responded Thu Feb 5, 2026 at 08:47 am EST WC 07-01 Roofing and Siding shall be the only WC to carry dumpsters for roof removal and new work. The CM will carry all other dumpsters.
PB-006 0
Fire alarm system non-compatibility
Closed Moore Trosper Con...
Halloran, Chris (Moore Trosper Construction Co.)
01/30/
Chris Halloran
Adler, Alexander Marchetti, Charle...
02/ 04/
02/05/
Heather Place (Moore Trosper Construction Co.), Charles Marchetti (French Associates), Chris Halloran (Moore Trosper Construction Co.), Alexander Adler (French Associates)
No
Q:
Chris Halloran Sent Fri Jan 30, 2026 at 02:11 pm EST I took pictures of the fire alarm panel for Simplex to see what they could do for the quote. They say the entire fire alarm would need to be replaced since they cannot tie new devices into the existing equipment. The new system would have to be the vocal fire alarm if replaced so the wiring would need to be change completely. Please advise.
A:
Alexander Adler (French Associates) Responded Thu Feb 5, 2026 at 07:49 am EST The proposed Fire Alarm devices have been removed from the bid documents.
Refer to Addendum #2
Alexander J Adler, RA NCARB 2.04.2026
PB-007 0
Door access controls clarification
Closed Moore Trosper Con...
Halloran, Chris (Moore Trosper Construction Co.)
01/30/
Chris Halloran
Marchetti, Charle...
Adler, Alexander
02/ 04/
02/05/
Heather Place (Moore Trosper Construction Co.), Charles Marchetti (French Associates), Chris Halloran (Moore Trosper Construction Co.), Alexander Adler (French Associates)
No
Q: Chris Halloran Sent Fri Jan 30, 2026 at 02:13 pm EST For the door access controls who supplies card readers, power supplies and electric strikes? Also, what manufacture do they use now?
A:
Chris Halloran (Moore Trosper Construction Co.) Responded Wed Feb 4, 2026 at 10:30 am EST Door access controls to be provide by Owner's security vendor. Power supplies and electric strikes by hardware contractor per hardware schedule.
Door Access Controls - Windemuller Electric Contractors Manufacturer - Verkada
Alexander J Adler, RA NCARB 02/03/2026
PB-008 0 Alternate 1 Closed Moore Halloran, Chris 02/02/ Chris Place, 02/ 02/02/ Heather Place (Moore Trosper Construction Co.), Chris No
Moore Trosper Construction Co.
Printed on Thu Feb 5, 2026 at 08:58 am EST
Job #: 25-113 Central Lake MS/HS and Elementary Renovations - BP1 8169 W. State Street
Central Lake, Michigan 49622
Contractor
Received From
Date Initiated
RFI
Manager
Assignee Ball In Court
Due Date
Closed Date
Location Schedule Impact
Cost Impact
Cost Code
Sub Job
RFI
Stage
Distribution List Private gym floor demo scheduling clarification
Trosper Con...
(Moore Trosper Construction Co.)
2026 Halloran Heather (M...
Halloran, Chris (...
07/ 2026 26 Halloran (Moore Trosper Construction Co.)
Q: Chris Halloran Sent Fri Jan 30, 2026 at 02:07 pm EST Can demo of gym floor take place prior to demo of roof if alternate 1 is accepted?
A: Chris Halloran (Moore Trosper Construction Co.) Responded Mon Feb 2, 2026 at 02:45 pm EST Yes, per the bidding schedule existing floor and subbase demo is before roof demo.
PB-010 0
Gym ceiling painting Alternate 1
Closed Moore Trosper Con...
Halloran, Chris (Moore Trosper Construction Co.)
02/02/
Chris Halloran
Marchetti, Charle...
Adler, Alexander
02/ 05/
02/04/
Heather Place (Moore Trosper Construction Co.), Charles Marchetti (French Associates), Chris Halloran (Moore Trosper Construction Co.), Alexander Adler (French Associates)
No
Q: Chris Halloran Sent Mon Feb 2, 2026 at 10:44 am EST Will painting be required at the gym ceiling, underneath roof deck and steel trusses, if alternate 1 is accepted? Also, is any painting of the upper gym walls over the existing acoustic spray insulation required? Please advise.
A:
Alexander Adler (French Associates) Responded Tue Feb 3, 2026 at 03:49 pm EST Yes. Painting will be required to the underside of the Gymnasium Roof Deck and Metal Joists (trusses), including exposed fasteners/ components if Alternate 1 is accepted.
Painting of the upper part of the Gym walls will be required with Alternate #1, including over the existing spray insulation.
Refer to Addendum #2.
Alexander J Adler, RA NCARB 02.03.2026
PB-011 0 Roof Material Substituion Closed Moore
Trosper Con...
Halloran, Chris (Moore Trosper Construction Co.)
02/02/
Heather Place
Place, Heather (M...
02/ 05/
02/02/ 26 No
Q:
Heather Place Sent Mon Feb 2, 2026 at 11:03 am EST Requesting substitution of Johns Manville for EPDM material.
0223_001.pdf
A: Heather Place (Moore Trosper Construction Co.) Responded Mon Feb 2, 2026 at 11:03 am EST The Johns Manville 60MIL EPDM is an acceptable product substitution per French Associates.
Moore Trosper Construction Co.
Printed on Thu Feb 5, 2026 at 08:58 am EST
Job #: 25-113 Central Lake MS/HS and Elementary Renovations - BP1 8169 W. State Street
Central Lake, Michigan 49622 https://storage.procore.com/api/v5/files/us-east-1/pro-core.com/940355523431895-c/822144623431895-p/01KGFHDZM5FWHAW89QA2VNHA52?companyId=598134325553049&projectId=598134326441228&sig=d143e88c390a776ba27ea1ff19f9bfbed63670d10c03c6a2a1ad12ed1cfa5559
CENTRAL LAKE PUBLIC SCHOOLS
BP 1 – MS/HS & ELEMENTARY RENOVATIONS
SECTION 002413
WORK CATEGORIES
MOORE-TROSPER CONSTRUCTION CO.
Project No. 25-113
Section 004126 - Page 1 of 35 Addendum 2 – 02/05/26
Section 002413 - Page 1 of 35
All work for Central Lake MS/HS & Elementary Renovations is to be completed per plans and specifications and captured within the following work categories. Each work category to be bid as full categories and issued as prime contracts. Allowances; listed and voluntary alternates; and unit costs incorporated at the Owners’ discretion.
• 04-01 Masonry
• 05-01 Structural Steel
• 06-01 General Trades
• 07-01 Roofing and Siding
• 08-01 Glass and Glazing
• 09-01 Walls and Ceilings
• 09-02 Flooring
• 09-03 Painting
• 23-01 Plumbing and Mechanical
• 26-01 Electrical
• 31-01 Earthwork / Soil Erosion / Site Concrete / Site Clearing / Seeding
Base Specifications and General Notes shall be applicable to ALL Work Categories. The Scope of Work of each work category shall include the following items required for, caused by or resulting from its Work.
BASE SPECIFICATIONS (INCLUDED IN ALL WORK CATEGORIES)
010001 ELECTRONIC MODEL/DRAWING FILE EXCHANGE AGREEMENT
099000 GEOTECHNICAL REPORT
012300 ALTERNATES
013300 SUBMITTAL PROCEDURES
014000 QUALITY REQUIREMENTS
014200 REFERENCES
016000 PRODUCT REQUIREMENTS
017300 EXECUTION REQUIREMENTS
017329 CUTTING AND PATCHING
GENERAL NOTES (INCLUDED IN ALL WORK CATEGORIES)
1. Coordinate and cooperate with all entities associated with the project including the Owner, Architect, Independent Testing and Inspection agencies, local and other governmental authorities and other Prime Contractors. Cost incurred as a result of lack of coordination of Work, deliveries, access required by others, testing/inspection, schedule, penetrations, etc., shall be the responsibility of the Prime Contractor failing to notify others of action to be taken or other requirements.
2. Provide written Daily Reports to include the following minimum information:
a. Description of Work performed
b. Trade personnel classification and hours
c. Equipment used
d. Significant events/issues
e. Weather
f. Deliveries and material orders
g. Other items as requested
These Daily Reports are required to be submitted to the project superintendent within 24 hours of the day that the work was performed. Failure to comply will be cause for withholding of payments.
3. Commencement of Work subsequent to associated Work by other Entities shall indicate acceptance of the condition of the Work by other Entities and/or existing conditions.
Section 004126 - Page 2 of 35
Section 002413 - Page 2 of 35
4. Delivery and storage of materials and equipment shall be the responsibility of each Prime Contractor and coordinated with the Construction Manager (Refer to “Temporary Facilities” section).
5. All means and methods, labor, material, tools, construction equipment and machinery necessary, including cranes, hoisting equipment, scaffolding, shoring and bracing, to complete the Work.
6. Perform all Work related to the Work of the Work Category included in “Temporary Facilities” section.
7. The Prime Contractor shall obtain and pay for all permits and fees associated with its Work and provide evidence of same to Owner and Construction Manager.
8. Minimal control points and elevations will be provided. Each Work Category is responsible for the layout of their own work as well as verifying that layout fits with work already completed as well as existing conditions. Any discrepancies need to be brought to the Construction Manager’s attention, in writing, immediately.
9. Barricades, traffic maintenance and control as required.
10. Protection and safekeeping of Prime Contractor’s own materials and equipment stored on the premises.
11. Take care and protect as required to avoid damaging Work in place by other Entities. In the event of damage to Work in place, the Prime Contractor causing the damage will be responsible for cost of repair. In the event the responsible Prime Contractor cannot be identified, the cost of repair will be prorated on a man hour basis to those Prime Contractors reasonably considered to be in the area of the damage.
12. Protect all existing structures, equipment, trees, landscaping, etc., to remain.
13. Dust control to prevent nuisance and hazard.
14. Cleaning streets of mud, dirt and debris (Refer to “Temporary Facilities” section) is the responsibility of each contractor (or sub-contractor/suppliers to said contractor) whose work has caused the mess.
Daily or more frequent sweeping may be required
15. Daily clean-up shall include broom cleaning and removal of identifiable debris and rubbish to the on-site dumpster. (Refer to “Temporary Facilities” section for specific construction cleaning and cleaning of Work in place).
16. Each Prime Contractor will be responsible for removal and disposal of their own construction debris.
CM will provide dumpsters, with the exception of roofing.
17. Each Prime Contractor will be responsible for the necessary minor demolition required for their scope of work.
18. Each Prime Contractor will be responsible for their own generator electrical power as needed to perform the Work of their respective work category.
19. Minor pumping of water required to perform the Work. Site-work is responsible for any required large-scale dewatering.
20. Temporary utilities as needed to perform the Work (Refer to “Temporary Facilities” section for specific temporary utility information).
21. Cutting, coring, patching and penetrations of any structural, architectural, mechanical and electrical materials required to complete the Work unless noted otherwise (Refer to “Cutting and Patching” specification section for specific cutting and patching requirements).
Section 004126 - Page 3 of 35
Section 002413 - Page 3 of 35
22. Prime Contractor to provide a representative with knowledge of the project scope and timelines for attendance at each weekly contractor progress meeting, scheduled by Construction Manager, upon commencement of the project and throughout the duration of construction. Any absence, unless excused with the Construction Manager 48 hours in advance, will be subject to a $200 cost per instance.
23. Prime Contractor is required to perform weekly toolbox talk safety meetings and submit signed verification to CM.
24. Each Prime Contractor welding, cutting or performing any Work which gas has potential to result in a fire, shall provide approved fire extinguishing apparatus in the immediate area.
25. Prime Contractor shall be responsible for attic stock per the contract documents. Coordinate delivery with CM/Owner.
26. Use of tobacco products, including vapes, will not be allowed on the school district’s property, including adjacent property.
27. Where direction is given by the Engineer/Architects in their specifications or on the drawings that conflict with the scopes of work, the most stringent performing shall supersede at the discretion of the Construction Manager, Owner and/or Architect.
28. All warrantees and guarantees will start at substantial completion of the entire project. In the event items need correction after the Substantial Completion Date, the Warranty for that item shall begin again from the date corrections were made.
Section 004126 - Page 4 of 35
Section 002413 - Page 4 of 35
WORK CATEGORY 04-01 MASONRY
GENERAL – The following shall not be interpreted as a complete itemization of the work to be performed under this Work Category. This Work Category Prime Contractor will be responsible to perform all work reasonably interpreted to be included in its scope of work in accordance with the drawings, sketches, any additional information, specifications, base specifications, and intent, with and/or in addition to the following Work Category Notes of clarification.
REFERENCE SPECIFICATION – (Include portions of the Work specified as noted below relevant to the intent of your work category)
079200 JOINT SEALANTS
081113 HOLLOW METAL DOORS AND FRAMES
INCLUDE ALL BASE SPECIFICATIONS LISTED BELOW – (Include all Work specified or reasonably inferred). Include all Division 1 Requirements.
BASE SPECIFICATIONS:
042000 UNIT MASONRY
071113 BITUMINOUS DAMPPROOFING
072100 THERMAL INSULATION
076200 SHEET METAL FLASHING AND TRIM
078400 FIRESTOPPING
WORK CATEGORY 04-01 NOTES - Include (Provide and Install):
1. Coordinate, achieve, verify and provide evidence of utility shut offs and/or disconnects, MISS DIG contact clearance before any excavation or demolition begins.
2. MIOSHA/OSHA Approved Company Safety Plan must be submitted before work commences.
3. Pre-Task specific safety coordination required. Written confirmation must be submitted/obtained via the onsite project team and owner prior to performing each task to include but not limited to hot work permits, traffic controls management, hoisting plans, utility shutdowns, etc.
4. Each Prime Contractor welding, cutting or performing any Work which gas has potential to result in a fire, shall provide approved fire extinguishing apparatus in the immediate area.
5. Dust control for the duration of the work of this work category.
6. Minor demolition for completion of this work scope. Mass demolition is by others.
7. Provide all necessary submittals in a timely manner to allow for Architect/Engineer review and approval, and any corrections to be made prior to fabrication without impacting the construction schedule.
8. Provide full-time on-site supervision by superintendent whenever any masonry personnel or masonry subcontractor’s personnel are on site. The superintendent shall participate in all coordination and safety meetings. They shall be on-site whenever the masonry contractor and any tier subcontractor are performing work to ensure quality workmanship, schedule compliance, and proper safety and shall be on-site during final inspections.
9. Provide solid grouting and dry packing at any new bearing locations and as indicated on the plans to achieve appropriate bearing.
10. Protect exposed floors from mortar and other damage. Clean floors upon completion of the Work or more frequently as required.
11. Review special conditions (e.g. joining of dissimilar masonry and other materials, etc.) with the Owner and Architect prior to beginning the Work.
12. Coordinate location of masonry weeps with the Work of other Entities.
13. Furnish and install masonry wall flashings including thru-wall and counterflashing, reglets and other accessories for a complete installation. Do not cover flashings prior to inspection by Owner and/or Architect.
14. Protect and prevent wall cavities from mortar build up. Maintain cavity and weep system clean for proper drainage.
Section 004126 - Page 5 of 35
Section 002413 - Page 5 of 35
15. Miscellaneous clips, angles, reinforcing steel, etc., to attach the Work of this work category to the Work of others.
16. Furnish and install all new masonry including CMU and brick, any insulation and through wall flashings as shown in the construction documents. Provide all reinforcing steel required and indicated in the drawings to tie new walls into existing concrete slab.
17. Install steel lintels and header beams at openings and as indicated and specified. Steel lintels provided by others. Include metal lintel flashing with drip at typical head details.
18. Furnish and install structural masonry lintels.
19. Furnish and install 2 hour expansion joint between masonry materials.
20. Furnish and install all bituminous damp proofing as shown and specified.
21. Provide masonry cavity materials as shown and specified (e.g. pea gravel, sand, insulation
(spray, rigid, and/or batt), etc.).
22. Coordinate setting of door frames in masonry by others. Confirm and maintain correct positioning while performing and upon completion of the Work of this work category.
23. Grout hollow metal frames as required.
24. Provide masonry toothing in as required at new openings in existing walls, etc or where needed.
Reuse old brick when possible.
25. Temporary shoring and bracing as required.
26. Provide CMU infill / tooth in of interior masonry which may be required for new plumbing to sink locations. This contractor is responsible for infill only. Demo of walls by others.
27. Coordinate dowel and anchor location requirements with other Entities.
28. Finished visual masonry with defects will not be accepted and will be removed at this Contractors expense.
29. Coordinate location and confirm elevation of materials within masonry by other Entities prior to performing the Work (e.g. cleanouts, electrical boxes, access panels, etc.).
30. Install misc. steel fabrications provided by others. (e.g. imbed angles, plates, anchor bolts, bearing plates, etc.). Include grouting as required.
31. Protect anchor bolts and other embeds with approved means.
32. Confirm curing and/or sealer compounds and other materials applied to surfaces are compatible with finish materials..
33. Masonry mockups for Owner/Architect approval as required.
34. Cleaning and sealing of masonry as specified.
35. Contractor shall verify existing conditions and prepare field dimensions and quantities prior to fabrication and erection.
36. Contractor shall coordinate related framing and penetrations with other trades during detailing phase and prior to fabrication and shall provide framing plans to mechanical contractor for verification. Contractor shall notify the CM in writing of any discrepancies immediately, as not to delay the construction schedule.
37. Remove debris from the site in a timely manner.
38. Provide daily cleanup, or more frequently, as directed by the CM
39. Legal disposal of material off site.
40. Layout for this work category scope.
41. Contractor to inform CM of any substrate deficiencies. Work over top of substrate confirms acceptance.
42. Provide your own disposal containers.
43. Scope may require multiple mobilizations.
44. All hoisting and scaffolding materials as required.
45. Embed plans and setting plans shall be submitted to avoid delaying the project schedule and not later than one week following award of Contract or Notice to Proceed.
46. Prime Contractor shall be responsible for attic stock per the contract documents. Coordinate delivery with CM/Owner.
47. Temporary shoring and bracing as required.
48. Protect anchor bolts and other embeds with approved means.
49. Coordination, participation, and cooperation with all construction entities required.
50. Contractor to adhere to CM project schedule and subsequent variances.
51. Final cleaning as result of this Work Category required.
EXCLUDE:
Section 004126 - Page 6 of 35
Section 002413 - Page 6 of 35
1. Mass masonry demo (by WC 06-01)
2. Furnish of steel lintels, beams and misc. steel (by WC 05-01)
ALLOWANCE:
1. Include a $10,000.00 Contingency Allowance in your base bid. Use of any Allowance amount shall not include Overhead and Profit, only actual cost of material, labor, and equipment will be allowed. Any unused portion of the Allowance will be credited back to the owner through a deductive Change Order.
ALTERNATES:
1. N/A
UNIT COST:
1. Provide Square Foot (SF) unit cost to patch and repair masonry brick.
2. Provide Square Foot (SF) unit cost to patch and repair masonry block.
END OF WORK CATEGORY 04-01 MASONRY
Section 004126 - Page 7 of 35
Section 002413 - Page 7 of 35
WORK CATEGORY 05-01 STRUCTURAL STEEL
GENERAL – The following shall not be interpreted as a complete itemization of the work to be performed under this Work Category. This Work Category Prime Contractor will be responsible to perform all work reasonably interpreted to be included in its scope of work in accordance with the drawings, sketches, any additional information, specifications, base specifications, and intent, with and/or in addition to the following Work Category Notes of clarification.
REFERENCE SPECIFICATION – (Include portions of the Work specified as noted below relevant to the intent of your work category)
072100 THERMAL INSULATION
079200 JOINT SEALANTS
081113 HOLLOW METAL DOORS AND FRAMES
INCLUDE ALL BASE SPECIFICATIONS LISTED BELOW – (Include all Work specified or reasonably inferred). Include all Division 1 Requirements.
BASE SPECIFICATIONS:
051200 STRUCTURAL STEEL FRAMING
052100 STEEL JOIST FRAMING
053100 STEEL DECKING
054000 COLD FORMED METAL FRAMING
055000 METAL FABRICATIONS
055213 PIPE AND TUBE RAILINGS
078400 FIRESTOPPING
WORK CATEGORY 05-01 NOTES - Include (Provide and Install):
1. Coordinate, achieve, verify and provide evidence of utility shut offs and/or disconnects, MISS DIG
2. MIOSHA/OSHA Approved Company Safety Plan must be submitted before work commences.
3. Pre-Task specific safety coordination required. Written confirmation must be submitted/obtained via the onsite project team and owner prior to performing each task to include but not limited to hot work permits, traffic controls management, hoisting plans, utility shutdowns, etc.
4. Each Prime Contractor welding, cutting or performing any Work which gas has potential to result in a fire, shall provide approved fire extinguishing apparatus in the immediate area.
5. Dust control for the duration of the work of this work category.
6. Provide full-time on-site supervision by superintendent whenever any steel personnel or steel subcontractor’s personnel are on site. The superintendent shall participate in all coordination and safety meetings. They shall be on-site whenever the steel contractor and any tier subcontractor are performing work to ensure quality workmanship, schedule compliance, and proper safety and shall be on-site during final inspections.
7. Demolition for completion of this work scope.
8. Furnish and install all structural steel framing, steel joist framing, steel columns, structural roof decking, metal fabrications, and miscellaneous steel as indicated in the contract documents or as required for a complete installation including all materials, labor, and equipment.
9. Furnish and install pre-engineered metal stair systems. Concrete infill by others.
10. Furnish and install pipe and tube steel railings.
11. Provide all necessary submittals in a timely manner to allow for Architect/Engineer review and approval, and any corrections to be made prior to fabrication without impacting the construction schedule.
12. Provide engineered shop drawings for structural framing and miscellaneous. Drawings must include a valid engineers stamp acceptable to the authorities having jurisdiction.
13. Provide all loose lintels and header beams in masonry to be installed by others.
14. Provide all necessary welding and mill certificates as required by the contract documents or as required by the CM.
Section 004126 - Page 8 of 35
Section 002413 - Page 8 of 35
15. Contractor shall verify existing conditions and prepare field dimensions and quantities prior to fabrication and erection.
16. Contractor shall coordinate related framing and penetrations with other trades during detailing phase and prior to fabrication and shall provide framing plans to mechanical contractor for verification. Contractor shall notify the CM in writing of any discrepancies immediately, as not to delay the construction schedule.
17. An approved steel erection plan shall be maintained and made available at the project site and a copy provided to the CM, Owner and Architect.
18. Remove all rust, scale, and slag from steel in areas that will be exposed or will receive paint or other finishes.
19. Remove debris from the site in a timely manner.
20. Provide daily cleanup, or more frequently, as directed by the CM
21. Legal disposal of material off site.
22. Layout for this work category scope.
23. Contractor to inform CM of any substrate deficiencies. Work over top of substrate confirms acceptance.
24. Provide your own disposal containers.
25. Scope may require multiple mobilizations.
26. Miscellaneous clips, angles, reinforcing steel, etc., to attach the Work of this work category to the
Work of others.
27. All hoisting and scaffolding materials as required.
28. Embed plans and setting plans shall be submitted to avoid delaying the project schedule and not later than one week following award of Contract or Notice to Proceed.
29. Prime Contractor shall be responsible for attic stock per the contract documents. Coordinate delivery with CM/Owner.
30. Temporary shoring and bracing as required.
31. Protect anchor bolts and other embeds with approved means.
32. Coordination, participation, and cooperation with all construction entities required.
33. Contractor to adhere to CM project schedule and subsequent variances.
34. Final cleaning as result of this Work Category required.
1. Install of lintels or header beams (by WC 04-01).
2. Light gauge framing systems (by WC 09-01).
2. Include a $10,000.00 Contingency Allowance in your base bid. Use of any Allowance amount
1. A1: Provide demo of existing steel structure / furnish and install of new steel structure as related to gymnasium deck and structure replacement per the construction documents. Light gauge framing by others. Demo to include roof deck and existing steel trusses needed for rework. Roof membrane and insulation demo by others. Include barricading of outside area where crane work will be required per the site logistics plan and to be coordinated with the CM.
1. Provide SF unit cost for structural roof deck replacement.
END OF WORK CATEGORY 05-01 STRUCTURAL STEEL
Section 004126 - Page 9 of 35
Section 002413 - Page 9 of 35
WORK CATEGORY 06-01 GENERAL TRADES
GENERAL – The following shall not be interpreted as a complete itemization of the work to be performed under this Work Category. This Work Category Prime Contractor will be responsible to perform all work reasonably interpreted to be included in its scope of work in accordance with the drawings, sketches, any additional information, specifications, base specifications, and intent, with and/or in addition to the following Work Category Notes of clarification.
REFERENCE SPECIFICATION – (Include portions of the Work specified as noted below relevant to the intent of your work category)
051200 STRUCTURAL STEEL FRAMING
055213 PIPE AND TUBE RAILINGS
INCLUDE ALL BASE SPECIFICATIONS LISTED BELOW – (Include all Work specified or reasonably inferred). Include all Division 1 Requirements.
BASE SPECIFICATIONS:
024119 SELECTIVE DEMOLITION
033000 CAST IN PLACE CONCRETE
061000 ROUGH CARPENTRY
071410 UNDER-SLAB VAPOR BARRIER
072100 THERMAL INSULATION
078413 FIRESTOPPING
079200 JOINT SEALANTS
081113 HOLLOW METAL DOORS AND FRAMES
081416 FLUSH WOOD DOORS
082133 FLUSH FIBERGLASS REINFORCED POLYESTER FRP DOORS, MONUMENTAL DOORS,
DOOR PERIMETER FRAMING AND ALUMINUM STOREFRONT FRAMING SYSTEMS
087100 DOOR HARDWARE
101413 SIGNS
102800 TOILET AND BATH ACCESSORIES
104400 FIRE PROTECTION SPECIALTIES
116633 GYMNASIUM EQUIPMENT
126600 TELESCOPING STANDS
144200 WHEELCHAIR LIFTS
WORK CATEGORY 06-01 NOTES - Include (Provide and Install):
Category headings below are for convenience purposes only.
1. Coordinate, achieve, verify and provide evidence of utility shut offs and/or disconnects, MISS DIG contact clearance before any excavation demolition begins.
2. MIOSHA/OSHA Approved Company Safety Plan must be submitted before work commences.
3. Pre-Task specific safety coordination required. Written confirmation must be submitted/obtained via the onsite project team and owner prior to performing each task to include but not limited to hot work permits, traffic controls management, hoisting plans, utility shutdowns, etc.
4. Provide dust control for the duration of the work of this work category.
5. Maintain Streets and public areas free of dirt, odor, mud and debris. Daily or more frequent road sweeping as required when debris is tracked onto roads or lots.
6. Maintain Emergency Egress at all times. It will be required of this Work Category to provide any temporary ramps/walkways until such time a permanent Emergency Egress can be maintained.
This will require additional mobilizations as needed and removal of material.
7. Remove debris from the site in a timely manner.
8. Provide daily cleanup, or more frequently, as directed by the CM
9. Coordinate turnover of salvaged material with the owner.
10. Legal disposal of material off site.
Section 004126 - Page 10 of 35
Section 002413 - Page 10 of 35
11. Temporary guardrails, handrails, protection systems, doors, and windows.
12. Removal and disposal of temporary protection system installed in openings.
13. Provide layout for this work category scope.
14. Contractor to inform CM of any substrate deficiencies. Work over top of substrate confirms acceptance.
15. Pumping water to accomplish the work of this work category.
16. Work area security and safety barricading with construction signs.
17. Protect existing structures and/or trees and landscaping to remain. Contractor shall be responsible for any and all damages that result from improper protection.
18. Provide a minimum of 20 pound U.L. rated multi-purpose (Type A, B, C) fire extinguishers on stands spaced throughout the building at all times spaced such that the travel distance to a fire extinguisher shall not exceed 100 feet. Fire extinguisher stand shall be “Fire-Safety Mate” of equal as manufactured by Goria Corporation, (telephone 888.464.6742).
19. Prime Contractor welding, cutting or performing any Work which gas has potential to result in a fire, shall provide approved fire extinguishing apparatus in the immediate area.
20. Provide your own disposal containers.
21. Scope may require multiple mobilizations.
22. Verify existing grades, lines, dimensions, etc. prior to performing the work. Report discrepancies to the CM in writing.
23. Review special conditions (e.g. joining of dissimilar materials, etc.) with the Owner and Architect prior to beginning the Work.
24. Field touch-up of shop primers, paint, galvanizing, etc.
25. Prime Contractor shall be responsible for attic stock per the contract documents. Coordinate delivery with CM/Owner.
26. Coordinate metal stud layout with requirements of other Entities. Report layout discrepancies to
CM in writing.
27. Provide removal and relocation of items designated to be returned to the owner to a safe location on site as directed by the CM and/or Owner.
28. Provide full time on-site supervision by superintendent whenever any general trades personnel or general trades subcontractor’s personnel are on site. The superintendent shall participate in all coordination and safety meetings. They shall be on-site whenever the general trades contractors are performing work to ensure quality workmanship, schedule compliance, and proper safety and shall be on-site during final inspections.
29. Furnish and install all interior concrete, footings, foundation walls, floor slabs, entrance canopy piers frost slabs, metal stair infill, etc. as indicated on plans and specs or as necessary. Include all necessary excavations, reinforcing steel, under slab vapor barrier, etc. as indicated. Limit of interior concrete scope ends at East exterior wall line of A101 Secure Vestibule.
30. Provide saw cut and infill at slab areas as shown on the drawings or needed but not shown. This contractor shall coordinate with the plumbing contractor or others who will mark out the areas needed for demo. Provide ground penetrating radar and utility locating prior to saw cut.
31. Provide temporary protection after wall demo and according to the Temp Protection Plans.
32. Coordinate setting of door frames in masonry by others. Confirm and maintain correct positioning while performing and upon completion of the Work of this work category.
33. Grout hollow metal frames as required.
34. Temporary shoring and bracing as required.
35. Coordinate dowel and anchor location requirements with other Entities.
36. Protect anchor bolts and other embeds with approved means.
37. Confirm curing and/or sealer compounds and other materials applied to surfaces are compatible with finish materials.
38. Grout hollow metal frames as required. Mason to grout frames in new masonry walls.
39. Provide a complete architectural demolition as shown on the Demo plans, including but not limited to visual display boards, gypsum walls with stud framing, CMU walls, gypsum ceiling, steel framing, casework, acoustical ceilings and grid, flooring and adhesive, tile floors and walls, doors and frames, etc. Existing casework, millwork, countertops to be saved at Owner’s request.
40. This work category includes complete demolition and off-site disposal of all items shown and/or specified.
41. This work category to provide its own dumpsters. Include removal, hauling and legal disposal to an offsite location in a prompt manner. Dumpsters will be provided by CM.
Section 004126 - Page 11 of 35
Section 002413 - Page 11 of 35
42. This work category is responsible for all necessary temp shoring, temp support, rigging as required by the demolition activities. All temp shoring and supports shall be designed, engineered, and stamped for approval by a licensed professional engineer.
43. When removing any flooring material, special steps must be taken to remove any adhesives and residue and to provide a clean substrate for the new material.
44. Seal off and protect lockers with plastic ensuring they will remain dust free before the start of demolition and leave in place for the duration of construction, as indicated in the Temp Protection Plan.
45. Provide temp protection at exterior doors per the temp protection plans.
46. Provide RAM Board floor protection or approved equal product at locations indicated in the Temp
Protection Plan by this work category. Include all taping as required.
47. Provide protection to any surfaces, fixtures, or furnishings that remain during the completion of this work category.
48. Furnish and install all signage.
49. Weather protection as required to complete the Work of this work category in accordance with the project schedule.
50. Furnish and install wood blocking indicated in the documents, including blocking for specialties, openings, casework, equipment, etc as required. Coordinate blocking requirements with equipment suppliers and other Entities. Blocking for roof parapet and metal panel by roofing contractor.
51. Furnish and install all doors and frames in masonry and other wall types. Confirm correct positioning upon completion of the Work. This also includes hollow metal window frames.
52. Coordinate and perform undercutting of doors with floor finishes.
53. Construction cores and final keying of all hardware furnished and installed by this work category.
54. Substrate surface preparation including minor filling and grinding as required prior to performing the Work.
55. Furnish and install all toilet and bathroom accessories.
56. Furnish and install all gymnasium equipment or provide removal and reinstall as shown and specified. See alternate 1. Protect and keep safe of equipment after removal for reinstall at a later date. CM / Owner to provide area at or near site for equipment salvage.
57. Furnish and install wheelchair lifts and all accessories as shown in the construction documents.
58. Provide specified smoke and fire stopping for your work scope per the construction documents.
59. All hoisting and scaffolding materials as required.
60. Embed plans and setting plans shall be submitted to avoid delaying the project schedule and not later than one week following award of Contract or Notice to Proceed.
61. Temporary shoring and bracing as required.
62. Coordinate dowel and anchor location requirements with other Entities.
63. Coordinate location and confirm elevation of materials within Work by other Entities prior to performing the Work (e.g. cleanouts, electrical boxes, access panels, etc.).
64. Cold weather protection as well as protection of all work throughout construction.
65. Finished visual defects will not be accepted and will be removed at this Contractors expense.
66. Perform all required testing immediately following installation and provide written final result reports within one week of inspection.
67. Includes all labor, material, equipment, accessories, etc. required to complete this work category.
68. Coordination, participation, and cooperation with all construction Entities required.
69. Mockups for Owner/Architect approval as required.
70. Cleaning, and sealing as specified.
71. Contractor to adhere to CM project schedule and subsequent variances.
72. Final cleaning as result of this Work Category required.
73. Provide removal, modification, and reinstallation of telescoping bleachers in gymnasium per bidding schedule. Contact Interkal LLC for turnkey quotation.
Section 004126 - Page 12 of 35
Section 002413 - Page 12 of 35
1. Caulking of all frames by painter (WC 09-03).
2. Storefronts, windows, glazing, films (by WC 08-01)
3. Door HW of Aluminum storefronts (by WC 08-01).
4. Exterior blocking for roof parapet. (by WC 07-01)
5. CFMF, light gauge, metal studs, drywall. (by WC 09-01)
6. Interior / Exterior concrete and excavation. (by WC 31-01)
7. Demo of exterior sitework or concrete. (by WC 31-01)
8. Demo of materials with present asbestos by owner.
9. Demo of mechanical, plumbing and electrical by their respective WC.
10. Demo of steel structure at gym alternate. (by WC 05-01)
11. Gym bleacher removal, modification and reinstallation. (by Owner)
12. Any owner furnishings.
1. Include a $10,000.00 Contingency Allowance in your base bid. Use of any Allowance amount
1. A1: HS/MS – Provide cost associated with Alternate A1 architectural demo items. Demo of interior and exterior items including but not limited to wall framing, siding, blocking, brick, block, etc. Roofing, coping, metal deck, steel truss demo by others. Provide gym equipment work associated with alternate. Include removal and reinstallation of gym banners and signs.
1. Provide hourly rate for additional progress cleaning.
2. Provide Square Foot (SF) Unit Cost for Ram board flooring protection for additional work not shown in temporary protection plan.
END OF WORK CATEGORY 06-01 GENERAL TRADES
Section 004126 - Page 13 of 35
Section 002413 - Page 13 of 35
WORK CATEGORY 07-01 ROOFING AND SIDING
GENERAL – The following shall not be interpreted as a complete itemization of the work to be performed under this Work Category. This Work Category Prime Contractor will be responsible to perform all work reasonably interpreted to be included in its scope of work in accordance with the drawings, sketches, any additional information, specifications, base specifications, and intent, with and/or in addition to the following Work Category Notes of clarification.
REFERENCE SPECIFICATION – (Include portions of the Work specified as noted below relevant to the intent of your work category)
051200 STRUCTURAL STEEL FRAMING
053100 STEEL DECKING
INCLUDE ALL BASE SPECIFICATIONS LISTED BELOW – (Include all Work specified or reasonably inferred). Include all Division 1 Requirements.
BASE SPECIFICATIONS:
024119 SELECTIVE DEMOLITION
061000 ROUGH CARPENTRY
070150 PREPARATION FOR RE-ROOFING
072100 THERMAL INSULATION
074213 METAL WALL PANELS
074293 METAL SOFFIT PANELS
075325 EPDM – FULLY ADHERED MEMBRANE ROOFING SYSTEM
076200 SHEET METAL FLASHING AND TRIM
077200 ROOF SPECIALTIES
077200 ROOF ACCESSORIES
079200 JOINT SEALANTS
079500 EXPANSION CONTROL
WORK CATEGORY 07-01 NOTES - Include (Provide and Install):
1. Coordinate, achieve, verify and provide evidence of utility shut offs and/or disconnects, MISS DIG
2. MIOSHA/OSHA Approved Company Safety Plan must be submitted before work commences.
3. Pre-Task specific safety coordination required. Written confirmation must be submitted/obtained via the onsite project team and owner prior to performing each task to include but not limited to hot work permits, traffic controls management, hoisting plans, utility shutdowns, etc.
4. Each Prime Contractor welding, cutting or performing any Work which gas has potential to result in a fire, shall provide approved fire extinguishing apparatus in the immediate area.
5. Dust control for the duration of the work of this work category.
6. Furnish and install all membrane roofing, built up roofing, roof insulation, flashings, roof expansion joints, roof hatches and accessories, scuppers, ballast, copings, gravel stops, termination bars, sealants, ice and water shield and full removal and replacement as defined in the Construction Documents (not limited to the roof plan) or as required for a complete installation.
7. Provide patch and repair of roofing as indicated in the construction documents.
8. Furnish and install all metal wall and soffit panels including all components, fasteners, flashings, and sealants for a complete system.
9. Furnish and install all sheathing, misc. blocking, air and vapor barrier, hat track or other furring as needed behind metal panel and soffit systems. Metal framing by others.
10. Furnish and install all pre-finished metal roof copings, gravel stops, and/or fascia for all top of wall parapet and roof edge conditions.
11. Provide roof accessories as required for a complete system whether shown or not shown in the documents.
12. Provide flashing of all penetrations, piping, and conduits by other work categories.
Section 004126 - Page 14 of 35
Section 002413 - Page 14 of 35
13. Coordinate the installation of roof drains installed by other work categories.
14. Furnish and install wood blocking for new parapet details.
15. Provide wood blocking for any mechanical curbs shown in the drawings or not shown but needed.
16. Selective demolition as related to this work category. Removal of the existing roof system off site and as indicated in the construction documents.
17. Provide all hoisting, rigging, lifting, and handling of materials as required.
18. Provide and utilize fall protection systems, warning lines, guard rails, safety nets, etc. and in accordance with the regulatory Safety Authorities.
19. Contractor to field verify existing conditions and any areas needing removal and notify the CM in writing of any discrepancies.
20. Contractor is responsible for keeping the building weathertight at all times.
21. Contractor to protect the interior of building from all dust and debris for this scope of work.
22. Remove debris from the site in a timely manner.
23. Provide daily cleanup, or more frequently, as directed by the CM.
24. This work category is responsible for their own dumpsters.
25. Legal disposal of material off site.
26. Layout for this work category scope.
27. Contractor to inform CM of any substrate deficiencies. Work over top of substrate confirms acceptance.
28. Embed plans and setting plans shall be submitted to avoid delaying the project schedule and not later than one week following award of Contract or Notice to Proceed.
29. Scope may require multiple mobilizations.
30. Provide cleaning of the roof deck prior to installation.
31. Prime Contractor shall be responsible for attic stock per the contract documents. Coordinate delivery with CM/Owner.
32. Contractor to adhere to CM project schedule and subsequent variances.