05 - G005 CONSTRUCTION PHASING PLAN - REV01.pdf

PDF 1 MB Posted

Attached to
Y1NB--Replace Air Handling Unit No. 2 and 3 Federal contract opportunity
Solicitation number
Not on record
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 8

About this file

This construction phasing plan outlines the replacement of two air handling units at a Department of Veterans Affairs medical facility. The project involves demolishing the existing AHUs serving the 5th floor PCT clinic and 4th floor pharmacy areas. A new AHU-60 unit will then be installed on the existing concrete platform and connected to ductwork serving the 5th floor clinic and roof penetrations. The plan details the phasing of moving clinic occupants to swing space, conducting pre-construction airflow measurements, demolishing the old units, installing and commissioning the new AHU-60, and returning occupants to the renovated space. Contractors must submit a comprehensive phasing plan for approval prior to commencing work.

View the file

Other files for this federal contract opportunity

Other files attached to Y1NB--Replace Air Handling Unit No. 2 and 3, newest first.
File Type Posted
SUPPLEMENTAL INFORMATION - 01.pdf PDF
S02 - SF30 Amendment 36C24822R0103 0002.pdf PDF
Attachment 07 Wage Determination (Rev).pdf PDF
43 - MH-406C MECHANICAL ENLARGED NEW PLAN - LEVEL 6 AREA C - REV01.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

7891011121314

D

E

F

G

H

J

Ward 5D PCT Clinic

Phase 5: Demolish AHU-38

1 2

34567891011121314

D

E

F

G

H

J

K

L

M

Phase 5: Install AHU-60

3603 NW 98th Street, Suite B Gainesville, FL 32606 Phone: (352) 474-6124 Fax: (352) 553-4437

COA: FL #29758

AKEA Project No. AD183-19

Design, Inc.

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT / ENGINEER OF RECORDCONSULTANT

321 4 5 6 7 8 9 10

ENGINEER - OF - RECORD FL. P.E. NO.

REPLACE AIR HANDLING UNIT

(AHU) 3

573-18-603

GAINESVILLE, FLORIDA

FINAL DESIGN SUBMITTAL

APPROVED FOR CONSTRUCTION

This item has been electronically signed and sealed by the individual named at right.

Printed copies of this document are not considered signed and sealed and the signature must be verified on any electronic copies.

/3

/2

:5

:5

A

M

JHK JHK

WILLIAM RODRIGUEZ 69663

JUNE 4, 2021

G005

CONSTRUCTION PHASING PLAN

Phasing Notes:

Phase 5: AHU-60 Installation and Ward 5D PCT Clinic Work

1. Move Ward 5D PCT Clinic occupants to swing space.

2. Pre-construction measurement: Take traverse readings at existing AC-3’s main duct connected to Shaft

#1 and #2 and at existing duct serving 5D PCT Clinic through roof penetration. Measure airflow rate and static pressure.

3. Demolition of existing AHUs on concrete platform for cooling tower

a. Remove existing AHUs on cooling tower pad serving 5D PCT Clinic and 4C Pharmacy 464. During demolition of AHU-54, room A464, Pharmacy Compounding, will be out of service until completion of AHU-60 installation.

4. AHU-60 installation and AHU-3 demolition

a. Install AHU-60 on existing concrete platform for cooling tower

b. Provide new CHW and steam distribution to AHU-60

c. Remove existing AC-3, ducts, pipes and appurtenances. Coordinate temporary shutdown with VA.

d. Connect new supply duct from AHU-60 to Shaft #1 and Shaft #2

e. Connect new supply and return ducts to 5D PCT Clinic. Install new reheat coil in hot deck.

f. Connect new CHW and steam pipes to AHU-60 coils.

g. Operate AHU-60 and match with the pre-construction airflow and pressure readings at Shaft #1, Shaft #2, and 5D PCT Clinic's supply and return ducts.

h. Perform testing, balancing, and commissioning

5. Move PCT Clinic occupants back to 5th floor.

6. Minimize the duration of the 5th floor occupants to occupy the 3rd floor swing space.

1/16" = 1'-0"

5th Floor Phasing Plan

1/16" = 1'-0"

Roof Level Phasing Plan AHU-60 Scope

1. CONTRACTOR SHALL PREPARE AND SUBMIT COMPREHENSIVE

CONSTRUCTION PHASING PLAN FOR ACCEPTANCE BY OWNER

PRIOR TO COMMENCEMENT OF WORK. COORDINATE WITH COR.

1. SEE DRAWING MD406C, MH406C, AND MH406D

2. CONNECT SUPPLY AND RETURN DUCTS TO AHU-60. INSTALL

NEW REHEAT COIL IN HOT DECK ON ROOFTOP.

3. SEE DRAWING S103, S502, MH406B, MH406C, ED104, EP206,

AND FA200

SHEET KEYNOTES

SHEET NOTES

Revisions: Date:

1 SI-01 8/30/2022SIGNED AND SEALED BY WILLIAM RODRIGUEZ, P.E.

Sheets
G005 - CONSTRUCTION PHASING PLAN
2022-08-30T15:28:24-0400
William Rodriguez, P.E.
2022-08-30T15:29:18-0400
William Rodriguez, P.E.

File details come from the government source that posted it. Updated .