05. WT Project Drawings.pdf
PDF 8 MB Posted
- Solicitation number
- 89503420BWA000019
About this file
This document package includes construction drawings and specifications for replacement of station service at the Watertown Substation in South Dakota and the Bismarck Substation in North Dakota. The work includes demolishing existing station service equipment and structures, installing new station service transformers, switchgear, distribution panels, grounding systems, cable trenches, and foundations. The drawings depict site plans, equipment arrangements, structural and foundation details. Relevant equipment is identified along with manufacturers. The solicitation is issued by the Western Area Power Administration to construct the replacement work according to the specifications and 78 pages of drawings provided.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Project Drawings - Amendment 0001.pdf | ||
| Sol_89503420BWA000019_Amd_0001.pdf | ||
| 12. General Decision Number - North Dakota.docx | DOCX document | |
| 12. Wage Determination for SD.docx | DOCX document | |
| 05. BS Project Drawings.pdf | ||
| 21. Sol_89503420BWA000019.pdf | ||
| 05. BS Project Specifications.pdf | ||
| 05. WT Project Specifications.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WATERTOWN SUBSTATION, STAGE 22
STATION SERVICE REPLACEMENT PROJECT
SOUTH DAKOTA
SECTION C
DESCRIPTION/SPECIFICATIONS
Solicitation No. 89503420BWA000019 Spec. No. 20WC135850-957
A. GENERAL:
CONSTRUCTION DRAWINGS: Construction drawings are the specification drawings and any additional drawings required for use in construction. The construction drawings will be issued after contract award and may include amendment changes and other details, which make the drawings suitable to use for construction purposes.
PROJECT DRAWINGS: Project drawings included herein are reduced reproductions and are not to scale.
Some project drawings show details of fabrication and other information not a part of the work. Disregard information and details, which are not applicable.
STANDARD DRAWINGS: Where details shown on standard drawings included herein differ from construction or project drawings or text, the details of construction or project drawings or text shall govern. A complete set of standard drawings are available at https://www.wapa.gov/DoingBusiness/SellingToWestern/Pages/what-western-buys.aspx.
INFORMATIONAL DRAWINGS: Some project drawings have the words “FOR INFORMATION ONLY” appearing above the title block. These drawings show some information, which may be required for bidding purposes. These drawings do not show items to be furnished or work to be performed.
EXISTING INSTALLATION DRAWINGS: Some project drawings have the words “EXISTING INSTALLATION” appearing above the title block. These drawings show the existing installations prior to modifications and may show some new work to be performed.
REFERENCE DRAWINGS: Reference drawings referred to on project drawings and not included herein, are not necessary for bidding purposes.
CONTRACTOR'S RESPONSIBILITY: Check all drawings and advise Western of any errors or omissions.
B. LIST OF DRAWINGS:
LOCATION MAP:
1. WT 0015 Rev. D – Location and Vicinity Map
ELECTRICAL:
2. WT 0001-1 Rev. H - 230kV Area - Switching Diagram (Sheet 1 of 2)
3. WT 0001-1 Rev. G EI - 230kV Area - Switching Diagram (Sheet 1 of 2) (Existing Installation)
4. WT 0001-2 Rev. J – 115kV and 69kV Areas - Switching Diagram (Sheet 2 of 2)
5. WT 0001-2 Rev. I EI – 115kV and 69kV Areas - Switching Diagram (Sheet 2 of 2) (Existing Installation)
6. WT 0010 Rev. I – General Plot Plan
7. WT 0010 Rev. H EI – General Plot Plan (Existing Installation)
8. WT 1004 Rev. C – 115kV Bus Structure - Grounding and Conduit Plan
9. WT 1004 Rev. B EI – 115kV Bus Structure - Grounding and Conduit Plan (Existing Installation)
10. WT 1005 Rev. F – 69kV Structures - Grounding and Conduit Plan
11. WT 1005 EI – 69kV Structures - Grounding and Conduit Plan (Existing Installation)
12. WT 1006 Rev. G – 230kV Bus Structure - Conduit and Grounding Plan
13. WT 1006 Rev. F EI – 230kV Bus Structure - Conduit and Grounding Plan (Existing Installation)
14. WT 1009 Rev. H – 230kV Struct. Bays V7 Thru V10 & 230kV XFMR Circuit KV8A - Grounding & Buried Cable Plan
15. WT 1009 Rev. G EI – 230kV Struct. Bays V7 Thru V10 & 230kV XFMR Circuit KV8A - Grounding & Buried Cable Plan (Existing Installation)
16. WT 1017 Rev. B – Unit Substation DYA, Service Bldg, Warehouse, and Garage Bldg Area - Duct Bank and Grounding
17. WT 1017 EI – Unit Substation DYA, Service Bldg, Warehouse, and Garage Bldg Area - Duct Bank and Grounding (Existing Installation)
18. WT 1007 Rev. B - Transformer KY3A & 13.2kV - Bus Structures - Plan
19. WT 1007 Rev. A EI – Transformer KY3A & 13.2kV - Bus Structures - Plan and Sections (Existing Installation)
20. WT 1008 Rev. D – 230kV Transformer KV8A - Plan
21. WT 1008 Rev. C EI – 230kV Transformer KV8A - Plan (Existing Installation)
22. WT 1010 Rev. E – 230kV Transformer KV8A - Sections E-E, F-F, G-G, H-H
23. WT 1010 Rev. D EI – 230kV Transformer KV8A - Sections E-E, F-F, G-G, H-H (Existing Installation)
24. WT 1027 Rev. F – 230kV Transformer KV2A - Plan
25. WT 1027 Rev. E EI – 230kV Transformer KV2A - Plan (Existing Installation)
26. WT 1100 Rev. E – 230kV Area - Equipment and Material Index (Sheet 1 of 2)
27. WT 1101 Rev. D – 230kV Area - Equipment and Material Index (Sheet 2 of 2)
28. WT 1103 – Substation Signs
29. WT 1122-2 – 230kV Transformer KV2A - Sections F-F, G-G, J-J and K-K
30. WT 1122 Rev. B EI – 230kV Transformer KV2A - Sections I-I, J-J and K-K (Existing Installation)
31. WT 1126 – 115kV Transformer KY3A - Sections A-A, B-B, C-C, and D-D
32. WT 1600 – Station Service Arrangement - Wiring Diagram
33. WT 1601 – 230kV Area AC Yard Panels - Wiring Diagram
34. WT 1602 – 115/69kV Area AC Yard Panels - Wiring Diagram
35. WT 1609 – General Lighting and Power - 480V Wiring Diagram
CONTROL BUILDING:
36. WT 1032 Rev. B FIO – Grounding and Buried Cable for Microwave Building and Pull Boxes E4, E5, and E6- Plans and Sections (For Information Only)
WATERTOWN SUBSTATION, STAGE 22
STATION SERVICE REPLACEMENT PROJECT
PROJECT DRAWINGS
https://www.wapa.gov/DoingBusiness/SellingToWestern/Pages/what-western-buys.aspx https://www.wapa.gov/DoingBusiness/SellingToWestern/Pages/what-western-buys.aspx
37. WT 4000 Rev. J - Service Building - Conduit, Arrangement & Grounding
38. WT 4000 Rev. I EI – Service Building - Conduit, Arrangement & Grounding (Existing Installation)
39. WT 6045 Rev. A – DHA and DHB - AC Distribution Panels
PULL BOXES:
40. WT 1713 – Pull Boxes SS1 and SS2 - Plan and Sections
CIVIL AND SITE DRAWINGS:
41. WT 2000 Rev. G FIO – Grading and Plot Plan (For Information Only)
FOUNDATION AND STRUCTURAL DRAWING INDEX:
42. WT 2099 Rev. E – Foundation/Structural Data and Drawing Index (Sh 1 of 3)
43. WT 2100 Rev. C – Foundation/Structural Data and Drawing Index (Sh 2 of 3)
44. WT 2101 Rev. E – Foundation/Structural Data and Drawing Index (Sh 3 of 3)
CONCRETE:
45. WT 2010 Rev. Q – Foundation General Plan
46. WT 2010 Rev. P EI – Foundation General Plan (Existing Installation)
47. WT 2011 Rev. E – Foundation Plan - 69kV Area
48. WT 2011 Rev. D EI – Foundation Plan - 69kV Area (Existing Installation)
49. WT 2014 Rev. F – Concrete Structures – Foundations - Outline and Reinforcement
50. WT 2016 Rev. G – Foundation Plan - 115kV Area
51. WT 2018 Rev. J – Foundation Plan - 230kV and XFMR - Reactor Areas
52. WT 2018 Rev. I EI – Foundation Plan - 230kV and XFMR - Reactor Areas (Existing Installation)
53. WT 2020 Rev. C - Concrete Structures – Foundations - Outline and Reinforcement
54. WT 2030 Rev. K – Foundation Plan - 230kV and XFMR - Reactor Areas
55. WT 2031 Rev. A – Foundation Plan - Service Building Area
56. WT 2306 – Foundations - Outline and Reinforcement
57. WT 2307 – Foundations - Outline and Reinforcement
58. WT 2308 – Foundations - Outline and Reinforcement
59. WT 2309 – Foundations - Outline and Reinforcement
60. WT 2310 – Foundations - Outline and Reinforcement
CABLE TRENCH:
61. WT 2500 – Cable Trench for Station Service Arrangement
62. WT 2501 – Cable Trench for 69/115kV AC Yard Panels
63. WT 2502 – Cable Trench for 230kV AC Yard Panels
STEEL STRUCTURES:
64. WT 2033 Rev. A FIO – 12.47kV Switch and Take-Off Structure (For Information Only)
65. WT 2072 Rev. A FIO – Bus Poles and Anchor Bolts (For Information Only)
66. 31 1073 Rev. D FIO – Lighting Fixture - Pole and Bracket Mounting (For Information Only)
67. WT 2551 – Anchor Bolts
68. WT 2615 – Combination Fuse Disconnect Switch Structure - Type I
69. WT 2616 – Combination Fuse Disconnect Switch Structure - Type II
70. WT 2617 – Ground Fault Detection Structure
71. WT 2618 – Station Service Arrangement - Support Frame - Elevation
72. WT 2619 – Station Service Arrangement - Support Frame - Details
73. WT 2620 –69/115kV AC Yard Panels - Support Frame - Elevation and Details
74. WT 2621 – 230kV AC Yard Panels - Support Frame - Elevation and Details
75. WT 2927 – Switch Operating Platforms - Steel Design and Details
GEOLOGY:
76. WT 8000 Rev. A – Location and Logs of Exploration
77. WT 8001 Rev. A – Location of Exploration
STANDARD DRAWINGS:
78. 31 2043 – Bollard Details
WATERTOWN SUBSTATION, STAGE 22
STATION SERVICE REPLACEMENT PROJECT
PROJECT DRAWINGS
I
SECTION A-A
CABLE AND CONDUIT TO
DH3A TO REMAIN FOR
STAGE 22. CABLE TO
BE RE-TERMINATED TO
NEW COMBINATION SWITCH.
PLAN
/wt 1020!
REMOVE & REPLACE
10 15
SCALE OF FEET
1/s" :: I FOOT
REMOVE
, � 3'.3'' j ' "I ,,J-J .-.
�J F
REMOVE
DETAIL A
REFERENGE DETAILS
ITEM DESCRIPTION ,:, o� R
�f ;1�e�gE: r, I Disconnecting Switch WW2B (DI B-68036-A (II 2 Disconnecting Fuse FW2A DG- 5850 3 Disconnecting Fuse FW3A /New Refill Units DC- 6850 ) (DI B-68036•A/3) 4 Bus Support WT 2032,.
5 Switch and Toks off Structure l!rn� 6 Switch-Operating Platform (Single) 40-0-4874 7 Tube to bar connector I Roya( Type HA) DC- 8 Fle,ible connector (Royal cat. no. 7312) lenofh as required DC- 9 5 Inch metallic conduit DC- 10 Disconnecting Switch. WW3A (DJ 8-68036-M21 II Tee connector ( Burndy Type NT) DC-
12 I5-KV Polhead ( G 8 W Electric Specialty Co. shape Bi DC-
I 3 Insulator Assembly SG-6 Tech. Rer. No. 4 14 % A.W.G. Bare copper cal>le DC-
15 1 11,'- IPS Copper Tubing DC- 6850 /6 Fixed Support Burndy UH
I 7 Ligntning Arrester Structure WT 2035 18 4" Female Adopter (Type EPC-40-PVC) oc- 61 50 /9 4"-'90 ° Elbow - 30" Radius (Type £PC- 40- PVC) oc 20 4" Clectricaf Plastic Conduit /Type E:PG-40-PVC) DC
21 I5-KV Pothead IG and W Electric Specialty Co., Shape BJ DC
22 End Connector (Burndy Type N£) DC 23 4-inch Me fa/lie Conduit DC 24 Post Insulator /Tech. Ref No. 205) DC 25 Slidi.ng Bus Support /Burndy · Type UH) DC 26 Terminal (Burndy Type NA) DC 27 4/o AWG Copper Cable DC 28 2-inch JPS Aluminum Tubing DC 29 r-Cannector (Burndy Type-NNr-A) DC 30 .4/o AWG .Afum-lnl.Jm Cable DC 31 Terminal /Burndy Type NA-90."Wi .. DC 32 Terminal /Burndy Type NAR-A) DC 33 Bus Support Clomp (Mderson f:lectri'c Type ACS) DC ·34 Single Switch Operating Platform /Dwg. No. 40-D-4874) DC 35 4" Coupler /Type EPC-40-PVC) DC- 6850
60 250 MCM Copper Coble Project 61 ll/4" IPS -250 MCM Cu. -Brundy N£ 1629 Project 62 .I s" M�rol.lic -.cou,1rJer i ,.,, DC- 7/60
* Moteriols to be equivalent to types referenced.
5EGTI0N F- F
0£ TAIL D
C) EXPLANATION
INDICATES .STAGE 22 DEMO
REFERENCE DRAWINGS
GE:NERAL PLOT P-LAN .. __________________ __________ WT 0/0d, rRANSl'ORMc/1 BUS PLAN AND 69-KV, BAY XJ ____________ WT 102/J:
13.2-KV SHUNT REACTOR AND BUS STRUCTURES
PLAN ANO SECTIONS _________________________ WT 1018
NOTE
Contractor furnished equipment and materials for Stage 12 additions.
Denotes additions under specifications no. DC -
EXISTING INSTALLATION
2 - .,._ 83 AS BU/Lr er F0/00,/..TR. 6-1-82
;,.t- /i(,.9,- /?EV/S£0 TlrLE BlfJCK AND AD/JED WESTERN DWG NU.MSEN.
TAPPeo TERTIARY BUS OF' TFMNSFORMER l(Y3A FOR ALTERNATE
FEE() TO UNIT SUBSTATION .DH3A,
REVISED AND TRACED FOR STAGE· 12 ADDITIONS, AND
HAN8c0 TITU.
STATION SERVICE XFMR
KW29A
13.2KV-480V 1MVA PRI
STATION SERVICE XFMR
KW34A
13.2KV-480V 1MVA SEC
TRANSFORMER KW29A
AW29A
SURGE ARRESTER
TRANSFORMER KW34A
AW34A
SURGE ARRESTER
SSA
WT 2911
1200A 480V SAFTEY SWITCH
SSB
WT 3411
1200A 480V SAFETY SWITCH
STATION SERVICE
ATS
1200A 480V
STATION SERVICE
DWA
480V MAIN DIST. PANEL
STATION SERVICE XFMR
K6
480-120/240V 100KVA 1PH
STATION SERVICE XFMR
K8
480-240/120V 75KVA 3PH
STATION SERVICE XFMR
K7
480-120/240V 100KVA 1PH
STATION SERVICE
DWB
120/240V 1PH
STATION SERVICE
DWC
120/240V 1PH
STATION SERVICE
DWD
120/240V 1PH
STATION SERVICE
DWD1
240/120V 3PH
NHA
3-PH 480V
DHB
1-PH 120/240V
DHA
1-PH 120/240V
STATION SERVICE
WT 2823
FUSE FW28A 13.2KV
STATION SERVICE
WT 2821
INT SW WW28A 13.2KV
230KV YARD
LCU
YARD LIGHTS
69/115KV YARD
LCU
YARD LIGHTS
STATION SERVICE
WT 3923
FUSE FW39A 13.2KV
STATION SERVICE
WT 3921
INT SW WW39A 13.2KV
STATION SERVICE
WT 8923
FUSE FW89A 13.2KV
STATION SERVICE
WT 8921
DISC SW WW89A 13.2KV
STATION SERVICE
WT 3423
FUSE FW34A 13.2KV
STATION SERVICE
WT 3421
INT SW WW34A 13.2KV
STATION SERVICE
WT 2923
FUSE FW29A 13.2KV
STATION SERVICE
WT 2921
INT SW WW29A 13.2KV
STATION SERVICE XFMR
K9
480-240/120V 100KVA 1PH
KY3A GND FAULT DET
RW3A
RESISTOR 208V
KY3A TERT GND FAULT DET
VW3A
INST XFMR 13.2KV
EW3A
VW34A SECONDARY FUSES
STATION SERVICE
WT 8919
CURRENT LIMITER FW89B
STATION SERVICE
WT 3919
CURRENT LIMITER FW39B
STATION SERVICE
WT 3419
CURRENT LIMITER FW34B
STATION SERVICE
WT 2919
CURRENT LIMITER FW29B
STATION SERVICE
WT 2819
CURRENT LIMITER FW28B
denton For Information Only
S U
I T
A B
L E
F
O R
C
N
S T
R U
C T
I O
N
A
S
O
D e c p m
I T
A B
N
S T
R U
C T
I O
N
A
S
O c p
I T
A B
N
S T
R U
C T
I O
N
A
S
O c p
I T
A B
N
S T
R U
C T
I O
N
A
S
O c p
FIO
FIO
I T
A
B
N
S
T
R
U
C
T
I
N
A
M a y a
Message from the Administrator At Western Area Power Administration (WAPA), we show our commitment to safety every day through the actions we take, the training we offer and the work conditions we provide. We expect the same commitment to safety from each of our contractors who provide products or services to WAPA. In performing work for WAPA, all contractors must make the right decisions to ensure that the work environment is as safe as possible.
Our safety program is based on four points:
Safety procedures or common sense must be applied by each Federal and contract employee. Safety should not be set aside to meet a project schedule or for personal convenience.
Employees and contractors must believe that they have the right and the responsibility to identify and take action to reduce, if not eliminate, hazardous work environments and hazardous work practices.
Managers and supervisors must lead by example and execute their responsibility to ensure each job is accomplished in a safe and healthy way.
Safety is a personal responsibility. Each individual makes the decision on what action to take to accomplish a task.
By integrating these principles into every task we take, together we can ensure WAPA is a safe place to work.
Mark A. Gabriel Administrator and CEO
Mark A Gabriel
| Cover Page |
| Drawing Index 1 |
| Drawing Index 2 |
| wt_0015d |
| wt_0001_1h |
| wt_0001_1g_ei |
| wt_0001_2j |
| wt_0001_2i_ei |
| wt_0010i |
| wt_0010h_ei |
| wt_1004c |
| wt_1004b_ei |
| wt_1005f |
| wt_1005e_ei |
| wt_1006g |
| wt_1006f_ei |
| wt_1009h |
| wt_1009g_ei |
| wt_1017b |
| wt_1017a_ei |
| wt_1007b |
| wt_1007a__ei |
| wt_1008d |
| wt_1008c_ei |
| wt_1010e |
| wt_1010d_ei |
| wt_1027f |
| wt_1027e_ei |
| wt_1100e |
| wt_1101d |
| wt_1103 |
| wt_1122_2 |
| wt_1122b_ei |
| wt_1126 |
| wt_1600 |
| wt_1601 |
| wt_1602 |
| wt_1609 |
| wt_1032b_fio |
| wt_4000j |
| wt_4000i_ei |
| wt_6045 |
| wt_1713 |
| wt_2000g_fio |
| wt_2099e |
| wt_2100c |
| wt_2101e |
| wt_2010q |
| wt_2010p_ei |
| wt_2011e |
| wt_2011d_ei |
| wt_2014f |
| wt_2016g |
| wt_2018j |
| wt_2018i_ei |
| wt_2020c |
| wt_2030k |
| wt_2031a |
| wt_2306 |
| wt_2307 |
| wt_2308 |
| wt_2309 |
| wt_2310 |
| wt_2500 |
| wt_2501 |
| wt_2502 |
| wt_2033a_fio |
| wt_2072a_fio |
| 31_1073d_fio |
| wt_2551 |
| wt_2615 |
| wt_2616 |
| wt_2617 |
| wt_2618 |
| wt_2619 |
| wt_2620 |
| wt_2621 |
| wt_2927 |
| wt_8000a |
| wt_8001a |
| 31_2043 |
| WAPA Message |
| DOE Symbol |
File details come from the government source that posted it. Updated .