About this file

This file contains project specifications for the construction of Bismarck Substation Station Service Upgrade in North Dakota. The work includes removing and disposing of existing electrical equipment, furnishing and installing new electrical equipment including current limiting reactors, combination interrupter switches and fuses, interrupter switches, a station service transformer, an outdoor distribution cabinet, and associated 25kV cables. It also involves sitework such as concrete foundations, cable trench, and steel structures. Submissions including a construction schedule and safety plan are due within 10 days of notice to proceed. The project specifications provide requirements for materials, construction methods, testing, safety, and submittals to complete the work in accordance with Western Area Power Administration standards. Work will be located at Bismarck Substation and must be completed between May 1, 2021 and December 31, 2021.

View the file

Other files

File Type Posted
Project Drawings - Amendment 0001.pdf PDF
Sol_89503420BWA000019_Amd_0001.pdf PDF
12. General Decision Number - North Dakota.docx DOCX document
12. Wage Determination for SD.docx DOCX document
05. WT Project Drawings.pdf PDF
05. BS Project Drawings.pdf PDF
21. Sol_89503420BWA000019.pdf PDF
05. WT Project Specifications.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION C

DESCRIPTION/SPECIFICATIONS

Solicitation No. 89503420BWA000019 Spec. No. 20WC136624-989

NORTH DAKOTA

BISMARK SUBSTATION

STATION SERVICE UPGRADE

SECTION C

DESCRIPTION/SPECIFICATIONS

BISMARK SUBSTATION STATION SERVICE UPGRADE

DIVISION 1 – GENERAL REQUIREMENTS

A. CONTRACT REQUIREMENT:

B. DESCRIPTION OF WORK:

1. The principal components of work include the following:

C. DESCRIPTION OF BIDDING SCHEDULE ITEM:

1. Bidding Schedule item “Mobilization and preparatory work”

D. COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK:

1. SUBMITTAL APPROVAL TIME:

2. OUTAGE RESTRICTIONS:

3. CONSTRUCTION SCHEDULE RESTRICTIONS:

4. PROTECTIVE GROUND LEADS:

5. MAXIMUM AVAILABLE FAULT CURRENT:

6. TYPICAL FOUNDATIONS FOR GOVERNMENT-FURNISHED ELECTRICAL EQUIPMENT: .. 5

7. TYPICAL FOUNDATIONS FOR CONTRACTOR-FURNISHED ELECTRICAL EQUIPMENT:

8. SAFETY AND HEALTH PROGRAM:

E. CONSTRUCTION SCHEDULE:

1. SUBMITTAL TIME:

2. FORMAT AND DETAIL:

F. MATERIAL:

1. POINTS-OF-DELIVERY:

G. RIGHTS-OF-WAY:

1. GENERAL:

H. GEOLOGIC INVESTIGATIONS:

I. ELECTRIC POWER FOR CONSTRUCTION PURPOSES:

J. WATER FOR CONSTRUCTION PURPOSES:

K. EXPLOSIVES AND BLASTING:

L. BURIED UTILITIES:

M. EMPLOYEE REQUIREMENTS:

N. ELECTRICAL MINIMUM APPROACH DISTANCES:

O. SUBMITTALS AND CORRESPONDENCE:

1. GENERAL:

2. TRANSMITTAL:

3. PHYSICAL SAMPLE SUBMITTALS:

4. SUBMITTAL RESPONSE:

5. APPROVAL TIME:

6. PROJECT PROTOCOL:

DIVISION 2 – SITEWORK

A. DESCRIPTION OF BIDDING SCHEDULE ITEMS:

1. Bidding Schedule item “Miscellaneous sitework”

2. Bidding Schedule item “Demolition”

3. Bidding Schedule does not contain separate items for the following

DIVISION 3 – CONCRETE

A. GENERAL:

1. MATERIAL:

2. TEST FOR POTENTIAL REACTIVITY OF SAND AND COARSE AGGREGATE:

3. REBAR DEVELOPMENT (LD) AND LAP LENGTH:

B. DESCRIPTION OF BIDDING SCHEDULE ITEMS:

1. Bidding Schedule item “Concrete foundations”

2. Bidding Schedule item “Cable trench”

DIVISION 4 – SUBSTATION METALWORK

A. GENERAL:

1. GOVERNMENT-FURNISHED DRAWINGS:

2. MEASUREMENT:

B. DESCRIPTION OF BIDDING SCHEDULE ITEM:

1. Bidding Schedule item “Steel structures, welded (galvanized)”

DIVISION 9 – SUBSTATION - ELECTRICAL

A. GENERAL:

1. Bidding Schedule for Government-furnished items

2. Bidding Schedule for items (not furnished by the Government)

3. Unless otherwise specified, associated support structures

4. Installation and painting of electrical equipment and material

B. DESCRIPTION OF BIDDING SCHEDULE ITEMS:

1. Bidding Schedule item “Current limiting reactor, 300-amps, single-phase (Government-furnished)”

2. Bidding Schedule item “Combination interrupter switch and fuses, 12.47-kV (Government-furnished)”

3. Bidding Schedule item “Interrupter switch, 12.47-kV”

4. Bidding Schedule item “Manual transfer switch, 240-V, 800A”

5. Bidding Schedule item “Fusible safety switch, 3-pole, 800-amps”

6. Bidding Schedule item “Station service transformer”

7. Bidding Schedule item “Outdoor AC distribution cabinet”

8. Bidding Schedule item “1/0 AWG, 25-kV, insulated copper cable”

9. Bidding Schedule item “Associated electrical equipment and material”

10. Bidding Schedule item “Existing outdoor electrical equipment and material”:

DIVISION 1 – GENERAL REQUIREMENTS

A. CONTRACT REQUIREMENT:

Construct and complete Bismarck Substation Station Service Upgrade, in accordance with the Construction Contract (Standard Form 1442); the Contract Clauses; Western Area Power Administration’s (WAPA) Construction Standards, including Standard 1 – General Requirements (September 2016), Standard 2 – Sitework (September 2016), Standard 3 – Concrete (September 2016), Standard 4 – Substation Metalwork and Transmission Line Lattice Structures (September 2016), Standard 5 – Transmission Line Steel Pole Structures (September 2016), Standard 6 – Light Duty Steel Pole Structures (September 2016), Standard 7 – Wood Poles (September 2016), Standard 8 – Glued Laminated Structures (September 2016), Standard 9 – Substation – Electrical (September 2016), Standard 10 – Transmission Line – Electrical (September 2016), Standard 11 – Service Building (September 2016), Standard 12 – Painting (September 2016), Standard 13 – Environmental Quality Protection (September 2016), Standard 14 – Communication Facilities (September 2016), Standard 15 – Drawings (September 2016); Standard Drawings; and these Project Specifications and Drawings.

If a conflict occurs between the Project Specifications and the Construction Standards, the Project Specifications shall govern. The Project Specifications and the Drawings are used to take exceptions or provide additions to the Construction Standards. Some paragraphs in the Construction Standards will not apply to this job.

WAPA’s Construction Standards, Standard Drawings, and Electrical Equipment Standards are available at https://www.wapa.gov/DoingBusiness/SellingToWestern/Pages/what-western-buys.aspx.

WAPA Project Specifications and Construction Standards are explained in Standard 1 – General Requirements, Section 1.1.1, “Standards and Project Specifications”.

B. DESCRIPTION OF WORK:

1. The principal components of work include the following:

a. Removing and disposing of existing fuse FW4E and power transformer KW4E.

b. Removing and disposing of existing fuse FW4A and power transformer KW4A and associated foundation.

c. Removing and disposing of existing reactor KW4C and associated foundation.

d. Removing and disposing of existing interrupter switches WW3D and WW4C.

e. Furnishing and installing all conduit – excluding runs from DW4E to DW4A2 and DW4A3.

f. Furnishing and installing grounding.

g. Installing current limiting reactors KW3A and KW8A and foundations

h. Installing combination load interrupter and fuse disconnecting switches WW3A-FW3A and

WW8A-FW8A.

i. Furnishing and installing interrupter switches WW3B and WW3C.

j. Furnishing and installing 25-kV cable and install Load Break Elbows (LBE’s) 2821 and 2321 on conductors.

https://www.wapa.gov/DoingBusiness/SellingToWestern/Pages/what-western-buys.aspx

k. Furnishing and installing pad-mounted transformer KW4E.

l. Furnishing and installing outdoor switchboard.

m. Furnishing and installing generator terminal box.

n. Providing associated sitework, concrete foundations and steel supports to complete the work.

Paragraphs “Description of Bidding Schedule Items” in Divisions – 1, 2, 3, 4 and 9 describe the work to be performed.

The work is located at the Bismarck Substation which is located in Bismarck, North Dakota as shown on Drawing BS 0019.

C. DESCRIPTION OF BIDDING SCHEDULE ITEM:

1. Bidding Schedule item “Mobilization and preparatory work” includes the following:

a. Performing mobilization and preparatory work in accordance with Sections H and M of the contract clauses.

b. Preparing and submitting a Construction Schedule and furnishing a Safety and Health

Program.

c. Complying with applicable Environmental Standards.

d. Complying with DOE order 442.2, “Differing Professional Opinions for Technical Issues Involving Environment, Safety and Health”.

D. COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK: See FAR 52.211-10 in

Section F of the solicitation/contract.

1. SUBMITTAL APPROVAL TIME: Except as otherwise provided for specific submittals, WAPA will require 20-calendar days for review of drawings or data submitted for approval.

2. OUTAGE RESTRICTIONS: In addition to the restrictions listed in Construction Standard 1, the following outage restrictions shall apply:

a. The electrical operation of the transmission lines are under the jurisdiction of WAPA’s Watertown Operations Office. All outage requests by the Contractor shall be subject to the approval of the Contracting Officer’s Representative (COR). Approval or denial of an individual outage request will be based on transmission system electrical loads, system operating configurations and weather conditions at the time the outage is scheduled to begin. At any time because of transmission system electrical loads, system the transmission system operation or reliability, WAPA may deny an outage request or direct the Contractor to return facilities to operating conditions and release the applicable Special Work Permit.

b. Make all outage requests in writing to the COR a minimum of 3-weeks in advance.

c. Meeting the minimum advance notice requirement of 3-weeks does not guarantee an outage will be approved. To improve the chances of an outage being approved, all outages should be submitted with as much advance notice as practicable. Weather conditions and other system conditions such as other scheduled and nonscheduled (forced) outage must be evaluated against an outage request before approval can be granted.

d. Station service outages are only available from Fridays at 1800 to Monday at 0600 permitting weather is not below freezing.

3. CONSTRUCTION SCHEDULE RESTRICTIONS: The following Construction Schedule restrictions shall apply:

a. The Contractor shall not work more than 12-hours per day and no more than 60-hours in one (1) continuous period without approval from the COR.

b. Work at the site shall not commence until May 1, 2021.

4. PROTECTIVE GROUND LEADS: See WAPA Construction Standards, Standard 1 “General Requirements”, Section 1.4.14.3(1).

5. MAXIMUM AVAILABLE FAULT CURRENT: When protective ground leads are required, the protective ground leads shall be sized as defined below and shall meet the requirements of Standard 1 – General Requirements, Section 1.4 “Safety and Health” and the following:

a. The maximum available fault current in the 12.47-kV area is 29,100-amps and the X/R ratio is 20.3.

b. A minimum of one (1) 4/0 grounds shall be used in the 12.47-kV area.

6. TYPICAL FOUNDATIONS FOR GOVERNMENT-FURNISHED ELECTRICAL EQUIPMENT:

Typical foundations are shown on Drawing 2307. Regarding foundations noted as “Design not firm”: WAPA will design these foundations after receipt of informational drawings and data, including the seismic report from the equipment manufacturer. WAPA will forward the revised construction drawings for these foundations no later than 30-days after receipt and final approval of design information and data.

7. TYPICAL FOUNDATIONS FOR CONTRACTOR-FURNISHED ELECTRICAL EQUIPMENT:

Typical foundations are shown on Drawings BS 2308 and 2309. Regarding foundations noted as “design not firm”: WAPA will design these foundations after receipt and final approval of seismic qualification documents and informational drawings and data from the Contractor.

8. SAFETY AND HEALTH PROGRAM: Prior to the start of field construction operations at the jobsite, submit a Safety and Health Program. Prior to beginning onsite construction, a preconstruction safety meeting will be conducted with the Contractor’s supervisory personnel, any major subcontractors and WAPA.

E. CONSTRUCTION SCHEDULE:

1. SUBMITTAL TIME: Prepare and Submit a Construction Schedule to the Contracting Officer (CO) within 10-calendar days after date of Notice to Proceed.

2. FORMAT AND DETAIL: Dates for each item of Government-furnished material shall be provided.

Do not program dates earlier than the estimated delivery dates shown in the “Material” paragraph.

F. MATERIAL: Furnish all material for completing the work, except material furnished by WAPA as listed below:

Item Estimated

Weight (pounds)

Estimated Delivery

Date

Estimated Cost

Six (6) single-phase, current limiting reactor, 12.47-kV, 60-Hz, 1056.6-MVA 265 ea To Be Determined $40,000 total

Two (2) combination interrupter switch and fuses, 12.47-kV 1,000 ea NLT 11-01-20 $40,000 total

NST – No sooner than.

NLT – No later than.

1. POINTS-OF-DELIVERY: Material furnished by WAPA will be delivered to Bismarck Substation.

The Contractor shall inspect the equipment and report any damages to the COR.

G. RIGHTS-OF-WAY:

1. GENERAL: Orient construction methods and equipment to utilize Government-furnished rights-of-way and within Government property lines or obtain additional temporary access without additional cost to WAPA. Any additional temporary access acquired by the Contractor shall have prior COR approval. During the contract period, WAPA reserves the right to use Contractor-obtained access.

H. GEOLOGIC INVESTIGATIONS:

The 8000-series geologic logs of subsurface explorations included in the “Drawings” Division constitute the information and records of geologic investigations for the work. Locations of subsurface investigations are shown on the Drawings.

Samples and cores of recovered material were not retained. Bidders shall obtain their own samples and perform tests on the material to evaluate properties, which they believe to be significant. WAPA does not guarantee that the geologic information and records show the conditions that will be encountered in performing the work, but only that the geologic information and records show conditions encountered at the particular point and time the information and records were obtained.

The geologic information may not indicate variations, such as those caused by seasonal fluctuations in rainfall and other factors, which may affect the water level. The Contractor shall determine the nature of material to be excavated, the difficulties of making and maintaining required excavations, and doing other work affected by geology and ground water elevations at the worksite.

I. ELECTRIC POWER FOR CONSTRUCTION PURPOSES:

Electric power up to a maximum of approximately 10-kVA for construction purposes will be available without cost. Source of supply is located in the receptacles throughout the substation. Power made available by WAPA will be delivered as single-phase, 60-Hz, AC, at approximately 120-240-V. The Contractor may furnish power for his operations by other means at no additional cost to WAPA.

Coordinate with the COR for establishing electric power service. Provide necessary transmission lines, distribution circuits, transformers, and other electrical equipment for distributing the power to the places of use. At contract completion, remove temporary electrical equipment and distribution lines.

J. WATER FOR CONSTRUCTION PURPOSES:

Furnish water for construction purposes. Make arrangements for obtaining the water and provide for conveying the water to the points of use.

K. EXPLOSIVES AND BLASTING:

Explosives shall not be used.

L. BURIED UTILITIES:

Prior to excavation, examine the area and determine the location of buried utilities. Utilities shall be identified with a marker denoting the type of service.

M. EMPLOYEE REQUIREMENTS:

In addition to the requirements listed in WAPA Construction Standard 1.4.3 all employees are restricted from wearing a headset, headphone, or other listening device, other than a hearing aid or instrument for the improvement of defective human hearing, hearing protection worn as the hazard exists, or for communication purposes while on a WAPA jobsite.

N. ELECTRICAL MINIMUM APPROACH DISTANCES:

In addition to the requirements listed in WAPA Construction Standard 1.4.9 equipment other than cranes and derricks, conductive objects, or personnel, shall not be brought closer to energized facilities than the electrical minimum approach distances established by OSHA 1926.958(b), “Materials, Handling, and Storage”. The less stringent equipment clearance distances established by OSHA 1926.960, “Working On or Near Exposed Energized Parts”, Table V-5 and Table V-6, may only be used after the Contractor has completed and submitted WAPA’s Electrical Clearance Variance form and has received the signed form in return from the COR.

O. SUBMITTALS AND CORRESPONDENCE:

1. GENERAL: The Contractor shall furnish submittals via email as specified in the Construction Standards and this Project Specification to the email address listed under the Transmittal section below and with the following requirements:

a. Submittals shall be in standard PDF, Microsoft Word (.doc/.docx), Microsoft Excel

(.xls/.xlsx), or Electronic CAD (.dwg) (AutoCAD 2010 or 2014) formats. All submittals in .dwg format shall also be submitted in .pdf format.

b. All submittals shall include the WAPA Contract number, Specification number, WAPA project title, Bidding Schedule Contract Line Item Number (CLIN) and applicable division number.

c. Multiple CLIN’s on a single submittal are not permitted.

d. A cover transmittal letter in Microsoft Word or PDF format shall be included with each email submittal.

2. TRANSMITTAL: The Contractor shall transmit all submittals to the Construction Office.

Email: UGP-CS-B5600@WAPA.GOV

3. PHYSICAL SAMPLE SUBMITTALS: When physical specimens or digital media are required to be submitted for approval, (i.e. brick samples, roofing material samples, carpeting, CDs, DVDs, etc.) the Contractor shall provide a digital cover letter outlining the physical sample submittal prior to sending the sample (including tracking data when applicable) and shall deliver physical specimens to:

Western Area Power Administration Civil/Structural Design ATTN: 7920, Civil Engineering Manager 12155 W. Alameda Parkway Lakewood, CO 80228-2802

A courtesy copy of the submittal letter shall be emailed to the Construction office at the above address.

4. SUBMITTAL RESPONSE: WAPA will respond to submittals electronically with an “Accepted” or

“Not Accepted” status with comments as appropriate in accordance with the “Commencement, Prosecution, and Completion of Work” paragraph to the email address where the submittals originated.

5. APPROVAL TIME: Approval time for submittals shall be in accordance with the “Commencement, Prosecutions, and Completion of Work” paragraph.

6. PROJECT PROTOCOL:

a. Submittals – Electronic Correspondence:

SUBJECT LINE IN EMAIL -- SUBMITTAL FORMAT

CLIN + Submittal Name – Applicable Division Number or Drawing Number – Project Title – Specification Number – Contract Number Example: 0011 Concrete Mix Design – 3.A.1 – Bismarck Substation, Station Service Upgrade, ND – 20WC136624-989 – 89503420CWA0000XX

b. Payment Requests:

SUBJECT LINE IN EMAIL -- PAYMENT REQUEST FORMAT

Invoice Number – Project Title – Specification Number – Contract Number Example: Invoice 01 – Bismarck Substation, Station Service Upgrade, ND – 20WC136624-989

– 89503420CWA0000XX

c. Certified Payrolls – Prime and Sub-Contractors:

SUBJECT LINE IN EMAIL -- CERTIFIED PAYROLL FORMAT

Certified Payroll (CP) – Contractor Name – Week Ending (WE) – Project Title – Specification Number – Contract Number Example: CP – Bob’s Asphalt Repair – WE 08/13/16 & 08/20/16 – Bismarck Substation, Station Service Upgrade, ND – 20WC136624-989 – 89503420CWA0000XX mailto:UGP-CS-B5600@WAPA.GOV

d. Request for Information:

SUBJECT LINE IN EMAIL -- REQUEST FOR INFORMATION (RFI) FORMAT

RFI Number – Subject – Project Title – Specification Number – Contract Number Example: RFI 003 – Labeling Info – Bismarck Substation, Station Service Upgrade, ND –

20WC136624-989 – 89503420CWA0000XX

DIVISION 2 – SITEWORK

A. DESCRIPTION OF BIDDING SCHEDULE ITEMS:

1. Bidding Schedule item “Miscellaneous sitework” includes the following:

a. Replacing and protecting existing gravel surfacing.

b. Providing new gravel surfacing as needed due to foundation work.

c. Providing a soil-applied herbicide where gravel surfacing is placed.

2. Bidding Schedule item “Demolition” includes the following:

a. Completely removing and disposing of concrete foundations designated on Existing Installation Drawings BS 2002, BS 2089, BS 2090, and BS 2094.

b. Cutting off and disposing of existing concrete encased conduits minimum 1-foot-6-inches below grade as shown on Existing Installation Drawing BS 2089. Cap and seal existing conduits abandoned in place.

c. Removing and disposing of the following structures:

(1) 12.47-kV Reactor Support (Drawing BS 2034).

(2) 12.47-kV Cable Support Structure (Drawing BS 2611).

Existing Installation drawings are included showing typical structure details.

d. The Contractor shall include any credit to the Government for salvage of the equipment and/or materials in this bidding schedule item.

3. Bidding Schedule does not contain separate items for the following. Include these items in applicable Bidding Schedule items.

a. Excavations for foundations, structures and trenches.

b. Placing and compacting earth material and backfill.

c. Providing gravelfills under concrete foundations as shown on the Drawings.

d. Disposing of excavated material. Material from excavations not suitable or required for earthwork shall be removed from the substation and access road right-of-way. The Contractor shall make arrangements required for disposal of waste material in an approved landfill.

e. Expansion anchors and adhesive anchors.

DIVISION 3 – CONCRETE

A. GENERAL:

1. MATERIAL:

a. Cement: Type II cement in conjunction with Class F fly ash.

b. Compressive Strength: 4500-psi minimum at 28-days.

c. Water-Cement Ratio: Net water-cement ratio, exclusive of water absorbed by the aggregates, shall not exceed 0.45 by weight for NESC heavy or medium loading areas and moderate or severe frost-susceptible zones per ACI 318, Chapter 4 – Durability Requirements.

d. Type A and D water-reducing and retarding admixtures may be used if approved by the

COR.

e. Class F fly ash is required to neutralize severe alkali or ASR reaction in accordance with ASTM C 311 (regarding test data), ASTM C 618 (regarding material), and Standard 3 – Concrete (regarding WAPA-specific requirements). Proposed concrete mix designs shall incorporate fly ash up to a maximum of 20-percent; minimum 28-day compressive strength shall be maintained in mix design.

2. TEST FOR POTENTIAL REACTIVITY OF SAND AND COARSE AGGREGATE: Perform tests for potential reactivity for the sand and coarse aggregate to be used by the Contractor. If the tests determine the aggregate(s) to be unsuitable as a concrete aggregate, a suitable source will be obtained by the Contractor.

3. REBAR DEVELOPMENT (LD) AND LAP LENGTH:

a. Class B lap splices apply unless noted otherwise; refer to Table 3 on Standard Drawing

01 2004-1 General Outline and Reinforcement Notes.

b. Typical closed circular tie lap splice lengths for drilled piers and columns, 4,000 - 4,500-psi normal weight concrete, unless noted otherwise, are 18-inches for No. 3 ties, 24-inches for No. 4 ties, and 30-inches for No. 5 ties.

B. DESCRIPTION OF BIDDING SCHEDULE ITEMS:

1. Bidding Schedule item “Concrete foundations” includes the following:

a. Earthwork, formwork, reinforcement, material used in concrete, anchor bolts, curing, finishing, joints and other related work and material needed to complete the concrete construction.

b. Concrete foundations for steel structures.

c. Concrete foundations for electrical equipment.

d. Unwatering foundation excavations, if required.

e. Casing auger excavations, if required.

Measurement for quantities for concrete foundations will be made on the basis of concrete quantities shown on Drawing BS 2071-2. If separate quantities of formed and auger concrete for each type of foundation are shown on the Drawing, the concrete quantity shall be the total of the formed and auger concrete quantities. Regardless of the concrete quantities actually placed, payment will be based on the quantities of concrete shown on the Drawing.

2. Bidding Schedule item “Cable trench” includes providing precast concrete cable trench, complete with sandfill, polymer concrete covers and other accessories.

DIVISION 4 – SUBSTATION METALWORK

A. GENERAL:

1. GOVERNMENT-FURNISHED DRAWINGS: Existing shop drawings for steel structures are not available.

2. MEASUREMENT: Measurement for quantities for Bidding Schedule items “Steel structures, welded (galvanized)” will be made on the basis of weights calculated in accordance with LRFD, “ AISC Code of Standard Practice for Steel Buildings and Bridges”, except that weights for nonrectangular shapes and plates are to be based on actual detailed dimensions.

a. Steel structure weights, calculated as noted above, shall be shown on the Contractor-furnished final shop drawings and payment will be based thereon. Steel estimated weights are shown on the specifications drawings for the structures requiring approval drawings as noted in the Bidding Schedule items “Steel structures, welded (galvanized)”.

B. DESCRIPTION OF BIDDING SCHEDULE ITEM:

1. Bidding Schedule item “Steel structures, welded (galvanized)” includes providing the following:

a. *Six (6) 12.47-kV bus poles - Type V. (Drawing BS 2621)

b. *Six (6) 12.47-kV tee poles – Type I. (Drawing BS 2622)

c. *Two (2) 12.47-kV switch and bus support – Type I. (Drawing BS 2623)

d. *One (1) station service arrangement support frame. (Drawings BS 2624 and 2625)

e. Two (2) single-switch operating platforms, including grating. (standard Drawing 31 2045)

*Denotes structures requiring approval drawings.

The above material including connection bolts, nuts, washers and lock nuts shall be galvanized.

DIVISION 9 – SUBSTATION - ELECTRICAL

A. GENERAL: Electrical equipment and material shall be as specified in WAPA’s “WAPA ES” standard equipment specifications, as shown on project drawings and in accordance with NEMA, ANSI, IEEE, ICEA, ASTM, NEC, NESC, UL and Federal specifications and standards as applicable. Applicable requirements shall be met under the following service conditions:

Ambient Temperatures:

Maximum ........................................................................................................... +40°C Maximum 24-Hour Average ............................................................................... +30°C Minimum ............................................................................................................ -50°C

Elevation:

Above Mean Sea Level ..................................................................................... 1,663-Feet

*ASCE-7 Wind Load Minimum Basic Wind Speed .............................................................................. 90 MPH Importance Factor ............................................................................................. 1.15

*IEEE 693 Seismic Qualification ................................................................................... Low

*May include support structure in accordance with STANDARD 9.1.1.2. Wind and seismic loads are nonsimultaneous

1. Bidding Schedule for Government-furnished items (including associated supporting structures when furnished) require the Contractor to provide:

a. Unless otherwise indicated, unloading and inspecting Government-furnished items.

b. Installing Government-furnished items as shown on drawings.

c. Furnishing equipment and material not furnished by WAPA.

2. Bidding Schedule for items (not furnished by the Government) shall be furnished by the

Contractor and shall include the following:

a. Providing (furnishing and installing) bidding schedule items.

b. Furnishing equipment and material not furnished by WAPA.

c. Installing bidding schedule items as shown on drawings.

3. Unless otherwise specified, associated support structures provided for each electrical equipment rated above 7-kV shall be 102-inches in height and hot-dip galvanized, if made of steel.

Instrument transformers that are seismically qualified shall be 96-inches in height. If tubular steel supports are furnished, they shall be galvanized internally and externally.

4. Installation and painting of electrical equipment and material shall be provided in accordance with

Standards 9 and 12 respectively.

B. DESCRIPTION OF BIDDING SCHEDULE ITEMS:

1. Bidding Schedule item “Current limiting reactor, 300-amps, single-phase (Government-furnished)” includes associated isolating insulators, base adapter plate, and support structure:

Designation (Single-phase) KW3A1,KW3A2,KW3A3, KW8A1,KW8A2,KW8A3

Manufacturer Coil Innovation Power Inductors

Type Outdoor, Air-Core, Dry- Type

System Voltage (kV) 12.47

Mounting Pedestal

Weight (LBS) (ea) 265

The equipment supplier is responsible for unloading the reactors.

2. Bidding Schedule item “Combination interrupter switch and fuses, 12.47-kV (Government-furnished)” includes furnishing all equipment not furnished by WAPA and installing the government-furnished combination interrupter switch and fuses in accordance with WAPA ES

8.2 equipment standard:

Designation WW3A-FW3A, WW8A-FW8A

Type

3-pole, single-throw, outdoor, manually group-operated, vertical break, rotating-insulator-type interrupter with single-pole hook-operated, low noise fuses, S&C

Electric Company SM Catalog no.

135332R4 or equal

System Nominal Voltage (kV) 12.47

Rated Maximum Voltage (kV) 15

Basic Impulse Insulation Level (kV) 110 Switch Continuous Current Rating (Amps) 600

Fuse Interrupting Ratings

RMS Symmetrical (Amps) 34,000 SMD type

Phase Spacing 5-0 Approximate Mounting Height Above Ground 15-0

Mounting position Vertical

Insulator Technical Reference No. 205

Approximate E Rating* 150E

3. Bidding Schedule item “Interrupter switch, 12.47-kV” includes furnishing and installing the interrupter switches in accordance with WAPA ES 8.2 equipment standard:

Designation WW3B, WW3C

3-pole, single-throw, outdoor, manually group-operated, vertical break, rotating-insulator-type interrupter

System Nominal Voltage (kV) 12.47

Rated Maximum Voltage (kV) 15

Basic Impulse Insulation Level (kV) 110 Switch Continuous Current Rating (Amps) 600

Phase Spacing 3-0 Approximate Mounting Height Above Ground 17-6

Mounting position Vertical

Insulator Technical Reference No. 205

4. Bidding Schedule item “Manual transfer switch, 240-V, 800A” includes providing outdoor manual source transfer switch Emerson Network Power’s ASCO 3NTSB3800FGXH type, or equal, as shown on the Drawings and in accordance with WAPA ES 2.3.5 Equipment Standards.

DESIGNATION MTS

Type metal enclosed,3-phase,3-pole, switched neutral, 60 Hz, outdoor

Required Voltage Rating 240/120-V

Enclosure NEMA 4X Source Continuous Current Rating (amps) 800

Switched Neutral Yes Cabinet Heater Yes Mounting configuration Horizontal Beam mounted

a. Mounting configuration is shown on Drawings BS 1601.

5. Bidding Schedule item “Fusible safety switch, 3-pole, 800-amps” includes providing fusible safety switch with fuses designated SSA. The safety switches shall be heavy duty, 3-phase, 3-pole, manual single throw, 4-wire, 240-V AC, 800 amperes frame size continuous current with associated 800 ampere fuses. Safety Switch enclosures shall be NEMA 4X. There shall be a provision to padlock SSA in the open position. The safety switch shall be installed as shown on Drawing BS 1601.

6. Bidding Schedule item “Station service transformer” includes providing station service transformer in accordance with WAPA ES 2.1 equipment standard:

Designation KW4E

Pad mounted, 3 phase, 60 Hz, outdoor, self-cooled, mineral oil filled, Loop Feed, dead front

Voltage Rating 12.47-kV delta to 240/120V center tapped delta

High-Voltage Taps (percent) ±2.5, ±5.0

Capacity (kVA) 300

High-Side Internal Transformer Fuse (FW4E)

Bay-o-net type or equal, 15E rating at 12.47kV, 25kA interrupting rating

Number of High-Voltage Bushing Wells 6

Number of Low-Voltage Bushings with NEMA Pads 4

High-Voltage BIL (kV) 125 High Voltage Surge Arresters Duty Cycle (kV) 25

High Voltage Surge Arresters MCOV (kV) 15.3

Low-Voltage BIL (kV) 30

Transformer shall be Eaton Cooper transformer type or equal, and be qualified to meet the service conditions specified in paragraph A. General and as follows:

*IEEE 693 Seismic Qualification ................................................................................. Low *In accordance with STANDARD 9.1.1.2. Wind load per paragraph A. General and seismic loads are nonsimultaneous.

a. For transformer KW4E supply the following accessories:

(1) High voltage parking stands mounted adjacent to high-voltage bushing wells.

(2) Six (6) 25-kV Class, 200-amp loadbreak terminating elbows.

(3) Six (6) 25-kV Class Bushing well inserts.

(4) Six (6) 25-kV Class Bushing wells.

(5) Six (6) 25-kV Class stand-off insulators.

(6) Six (6) 25-kV Class insulated protective bushing well plugs.

(7) Six (6) 25-kV Class deadfront posi-break elbow metal oxide varistor (M.O.V.E) surge arresters.

(8) One (1) 25-kV elbow connector tool, Chance Catalog No. C403-0391, or equal.

7. Bidding Schedule item “Outdoor AC distribution cabinet” includes providing outdoor pad mounted AC distribution board system DW4E as shown on Drawing BS 1600. Panelboards shall be Square D I-Line or equal and shall have three (3) flat bus bars stacked and aligned vertically with glass reinforced polyester insulators laminated between phases. The molded polyester insulators shall support and provide phase isolation to the entire length of bus distribution cabinet enclosure shall be NEMA 4X and large enough to house branch circuit breakers and condensation heater as shown on Drawings BS 1601 and shall be at a minimum 48-inches-wide by 86-inches-high. The distribution board shall be in accordance with WAPA ES 2.3.3, 2.3.4 and

2.3.11 Equipment Standard. Provide Hoffman enclosure clamp assemblies No. AFC412SS or equal in lieu of the standard NEMA 4X door clamps.

8. Bidding Schedule item “1/0 AWG, 25-kV, insulated copper cable” includes providing 1/0

AWG, 25-kV, insulated copper power cable type MV-105, 100-percent insulation level, Southwire Simpull NL-EPR or equal, as shown on the Drawings. Cables shall run between FW3A to KW4E and FW8A to KW4E as shown on drawings. Cable runs are 3-phase.

9. Bidding Schedule item “Associated electrical equipment and material” includes providing equipment, material and services required to complete the following substation installations as shown on the Drawings:

a. Electrical Testing: Includes providing electrical testing in accordance with Standard 9, paragraph 9.1.2 Acceptance Tests - Method A.

b. Substation Grounding System: Complete the substation grounding system. Unless otherwise specified on drawings, splices, connections, and other fittings may be compression type (DMC Power’s Swage, AFL Swage system, or equal. It’s recommended to obtain the necessary tooling from the respective manufacturer). All new exposed ground wire shall be copper clad steel. NOTE: The included drawings and standards have not been revised to show this new requirement. NOTE: copper clad steel shown on drawings and standard drawings as 7 No. 5 shall be 7 No. 4, or 19 No.8, in lieu of 7 No. 5. New cable trench grounding shall be two (2) 7 No. 4, or two (2) 19 No. 8, copper-clad steel conductors in lieu of two (2) 2/0 AWG copper conductor as indicated in WAPA Standard 9.2.1.2 (7) as shown on Drawing 31 1061. (For clarification, 7 No. 4 is seven individual number 4 conductors, stranded together to form a single conductor. 19 No. 8 is nineteen individual number 8 conductors, stranded together to form a single conductor.)

c. Electrical Conduit System: Electrical conduit system including embedded and exposed conduit. Conduit entering the cable trench with a 90-degree bend is allowed to be Schedule 40-PVC as shown on standard Drawing 31 1006. All other 90-degree bends shall be rigid metal. A red or yellow polyethylene warning tape shall be installed directly above each conduit run and located 12 inches below finished grade. Providing sand backfill around buried conduits as insulated electrical cables and 2-inch by 8-inch plastic lumber over the sand as shown on standard Drawing 31 1006. Provide pull ropes in all conduit.

All conduits shall have sealing compound installed at both ends. Informational drawings and data are not required for this item.

d. Outdoor Bus System: Outdoor strain and jumper buses, rigid buses and overhead ground wire unless otherwise specified on the Drawings, splices, elbows, pad type terminal connectors and other fittings used on rigid or cable buses may be compression type (DMC Power’s Bus & Cable Connectors and Swage System, AFL Swage system, or equal. If required, tools shall be obtained from respective manufacturers.). Post insulators for new structures shall use industry standard 3, 5, or 7-inch base cap bolt circles in lieu of WAPA Standard 9.3.1.1.3.2 and Drawing 31 1081. Replacement insulators shall match existing bolt circles. Insulators shall be ANSI 70 gray. Informational drawings and data are required for the rigid bus, conductors, overhead ground wire, and insulators only.

e. Insulated Conductors: Insulated conductors and cables except 5/c and12/c No. 10 AWG control cable and power cable with insulation greater than 15,000-V. Informational drawings and data are not required for this item.

f. Terminal Box: Terminal box internal components arrangements shown on Drawings

31 1086 are typical and the Contractor shall provide internal components for Type H terminal box configuration. Actual internal arrangements will be determined by the COR Note: On standard Drawing 31 1086, note 7 should be: “Ground all boxes to the main ground grid with 3 conductor No. 7 bare copper-clad cable. 7 conductor No. 4 bare copper-clad cable may be substituted.” Regardless, the Contractor shall size and provide the ground connector, item 4, to fit the provided grounding conductor in lieu of Burndy ground connector type K2C20B1.

g. Cable Terminators: Cable terminators of the self-supporting type. The cable terminators shall include molded rubber caps, crimp rings, nontracking terminator housings, stress relief, ground straps, mounting brackets and lugs suitable for connecting to electrical equipment with a NEMA 2-hole pad.

h. Phase Identification Signs (standard Drawing 31 1000):

(1) One (1) on each phase at both ends of main and transfer buses, at each high voltage circuit terminating structure and on each phase of an instrument transformer or single-phase transformer:

(a) Phase A - 2 required

(b) Phase B - 2 required

(c) Phase C - 2 required

i. Equipment Identification Signs (standard Drawing 31 1000): Lettering on the signs shall be as shown on Drawing BS 1105.

10. Bidding Schedule item “Existing outdoor electrical equipment and material”:

a. Material to be removed and disposed of is as follows:

(1) Replaced equipment signs.

(2) Substation control, power cables and conduit as designated on the Drawings.

Portions of cables in conduit, trench, and/or trays shall be removed and disposed of.

(3) Fuses designated FW4A and FW4E.

(4) Current limiting reactor designated KW4C.

(5) Transformers designated KW4A and KW4E

(6) Interrupter switches designated WW3D and WW4C

b. The Contractor shall include any credit to the Government for salvage of the equipment and/or materials in this bid item.

Message from the Administrator

At Western Area Power Administration (WAPA), we show our commitment to safety every day through the actions we take, the training we offer and the work conditions we provide. We expect the same commitment to safety from each of our contractors who provide products or services to WAPA. In performing work for WAPA, all contractors must make the right decisions to ensure that the work environment is as safe as possible.

Our safety program is based on four points:

Safety procedures or common sense must be applied by each Federal and contract employee. Safety should not be set aside to meet a project schedule or for personal convenience.

Employees and contractors must believe that they have the right and the responsibility to identify and take action to reduce, if not eliminate, hazardous work environments and hazardous work practices.

Managers and supervisors must lead by example and execute their responsibility to ensure each job is accomplished in a safe and healthy way.

Safety is a personal responsibility. Each individual makes the decision on what action to take to accomplish a task.

By integrating these principles into every task we take, together we can ensure WAPA is a safe place to work.

Mark A. Gabriel Administrator and CEO

DIVISION 1 – GENERAL REQUIREMENTS
A. CONTRACT REQUIREMENT:
B. DESCRIPTION OF WORK:
1. The principal components of work include the following:
C. DESCRIPTION OF BIDDING SCHEDULE ITEM:
1. Bidding Schedule item “Mobilization and preparatory work” includes the following:
D. COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK: See FAR 52.211-10 in Section F of the solicitation/contract.
1. SUBMITTAL APPROVAL TIME: Except as otherwise provided for specific submittals, WAPA will require 20-calendar days for review of drawings or data submitted for approval.
2. OUTAGE RESTRICTIONS: In addition to the restrictions listed in Construction Standard 1, the following outage restrictions shall apply:
3. CONSTRUCTION SCHEDULE RESTRICTIONS: The following Construction Schedule restrictions shall apply:
4. PROTECTIVE GROUND LEADS: See WAPA Construction Standards, Standard 1 “General Requirements”, Section 1.4.14.3(1).
5. MAXIMUM AVAILABLE FAULT CURRENT: When protective ground leads are required, the protective ground leads shall be sized as defined below and shall meet the requirements of Standard 1 – General Requirements, Section 1.4 “Safety and Health” and the f...
6. TYPICAL FOUNDATIONS FOR GOVERNMENT-FURNISHED ELECTRICAL EQUIPMENT: Typical foundations are shown on Drawing 2307. Regarding foundations noted as “Design not firm”: WAPA will design these foundations after receipt of informational drawings and da...
7. TYPICAL FOUNDATIONS FOR CONTRACTOR-FURNISHED ELECTRICAL EQUIPMENT: Typical foundations are shown on Drawings BS 2308 and 2309. Regarding foundations noted as “design not firm”: WAPA will design these foundations after receipt and final approval ...
8. SAFETY AND HEALTH PROGRAM: Prior to the start of field construction operations at the jobsite, submit a Safety and Health Program. Prior to beginning onsite construction, a preconstruction safety meeting will be conducted with the Contractor’s su...
E. CONSTRUCTION SCHEDULE:
1. SUBMITTAL TIME: Prepare and Submit a Construction Schedule to the Contracting Officer (CO) within 10-calendar days after date of Notice to Proceed.
2. FORMAT AND DETAIL: Dates for each item of Government-furnished material shall be provided. Do not program dates earlier than the estimated delivery dates shown in the “Material” paragraph.
F. MATERIAL: Furnish all material for completing the work, except material furnished by WAPA as listed below:
1. POINTS-OF-DELIVERY: Material furnished by WAPA will be delivered to Bismarck Substation. The Contractor shall inspect the equipment and report any damages to the COR.
G. RIGHTS-OF-WAY:
1. GENERAL: Orient construction methods and equipment to utilize Government-furnished rights-of-way and within Government property lines or obtain additional temporary access without additional cost to WAPA. Any additional temporary access acquired ...
H. GEOLOGIC INVESTIGATIONS:
I. ELECTRIC POWER FOR CONSTRUCTION PURPOSES:
J. WATER FOR CONSTRUCTION PURPOSES:
K. EXPLOSIVES AND BLASTING:
L. BURIED UTILITIES:
M. EMPLOYEE REQUIREMENTS:
N. ELECTRICAL MINIMUM APPROACH DISTANCES:
O. SUBMITTALS AND CORRESPONDENCE:
1. GENERAL: The Contractor shall furnish submittals via email as specified in the Construction Standards and this Project Specification to the email address listed under the Transmittal section below and with the following requirements:
2. TRANSMITTAL: The Contractor shall transmit all submittals to the Construction Office.
3. PHYSICAL SAMPLE SUBMITTALS: When physical specimens or digital media are required to be submitted for approval, (i.e. brick samples, roofing material samples, carpeting, CDs, DVDs, etc.) the Contractor shall provide a digital cover letter outlinin...
A courtesy copy of the submittal letter shall be emailed to the Construction office at the above address.
4. SUBMITTAL RESPONSE: WAPA will respond to submittals electronically with an “Accepted” or “Not Accepted” status with comments as appropriate in accordance with the “Commencement, Prosecution, and Completion of Work” paragraph to the email address w...
5. APPROVAL TIME: Approval time for submittals shall be in accordance with the “Commencement, Prosecutions, and Completion of Work” paragraph.
6. PROJECT PROTOCOL:
DIVISION 2 – SITEWORK
A. DESCRIPTION OF BIDDING SCHEDULE ITEMS:
1. Bidding Schedule item “Miscellaneous sitework” includes the following:
2. Bidding Schedule item “Demolition” includes the following:
3. Bidding Schedule does not contain separate items for the following. Include these items in applicable Bidding Schedule items.
DIVISION 3 – CONCRETE
A. GENERAL:
1. MATERIAL:
2. TEST FOR POTENTIAL REACTIVITY OF SAND AND COARSE AGGREGATE: Perform tests for potential reactivity for the sand and coarse aggregate to be used by the Contractor. If the tests determine the aggregate(s) to be unsuitable as a concrete aggregate, a...
3. REBAR DEVELOPMENT (LD) AND LAP LENGTH:
B. DESCRIPTION OF BIDDING SCHEDULE ITEMS:
1. Bidding Schedule item “Concrete foundations” includes the following:
2. Bidding Schedule item “Cable trench” includes providing precast concrete cable trench, complete with sandfill, polymer concrete covers and other accessories.
DIVISION 4 – SUBSTATION METALWORK
A. GENERAL:
1. GOVERNMENT-FURNISHED DRAWINGS: Existing shop drawings for steel structures are not available.
2. MEASUREMENT: Measurement for quantities for Bidding Schedule items “Steel structures, welded (galvanized)” will be made on the basis of weights calculated in accordance with LRFD, “ AISC Code of Standard Practice for Steel Buildings and Bridges”, ...
B. DESCRIPTION OF BIDDING SCHEDULE ITEM:
1. Bidding Schedule item “Steel structures, welded (galvanized)” includes providing the following:
DIVISION 9 – SUBSTATION - ELECTRICAL
A. GENERAL: Electrical equipment and material shall be as specified in WAPA’s “WAPA ES” standard equipment specifications, as shown on project drawings and in accordance with NEMA, ANSI, IEEE, ICEA, ASTM, NEC, NESC, UL and Federal specifications and ...
1. Bidding Schedule for Government-furnished items (including associated supporting structures when furnished) require the Contractor to provide:
2. Bidding Schedule for items (not furnished by the Government) shall be furnished by the Contractor and shall include the following:
3. Unless otherwise specified, associated support structures provided for each electrical equipment rated above 7-kV shall be 102-inches in height and hot-dip galvanized, if made of steel. Instrument transformers that are seismically qualified shall ...
4. Installation and painting of electrical equipment and material shall be provided in accordance with Standards 9 and 12 respectively.
B. DESCRIPTION OF BIDDING SCHEDULE ITEMS:
1. Bidding Schedule item “Current limiting reactor, 300-amps, single-phase (Government-furnished)” includes associated isolating insulators, base adapter plate, and support structure:
2. Bidding Schedule item “Combination interrupter switch and fuses, 12.47-kV (Government-furnished)” includes furnishing all equipment not furnished by WAPA and installing the government-furnished combination interrupter switch and fuses in accordance...
3. Bidding Schedule item “Interrupter switch, 12.47-kV” includes furnishing and installing the interrupter switches in accordance with WAPA ES 8.2 equipment standard:
4. Bidding Schedule item “Manual transfer switch, 240-V, 800A” includes providing outdoor manual source transfer switch Emerson Network Power’s ASCO 3NTSB3800FGXH type, or equal, as shown on the Drawings and in accordance with WAPA ES 2.3.5 Equipment ...
5. Bidding Schedule item “Fusible safety switch, 3-pole, 800-amps” includes providing fusible safety switch with fuses designated SSA. The safety switches shall be heavy duty, 3-phase, 3-pole, manual single throw, 4-wire, 240-V AC, 800 amperes frame ...
6. Bidding Schedule item “Station service transformer” includes providing station service transformer in accordance with WAPA ES 2.1 equipment standard:
7. Bidding Schedule item “Outdoor AC distribution cabinet” includes providing outdoor pad mounted AC distribution board system DW4E as shown on Drawing BS 1600. Panelboards shall be Square D I-Line or equal and shall have three (3) flat bus bars stac...
8. Bidding Schedule item “1/0 AWG, 25-kV, insulated copper cable” includes providing 1/0 AWG, 25-kV, insulated copper power cable type MV-105, 100-percent insulation level, Southwire Simpull NL-EPR or equal, as shown on the Drawings. Cables shall run...
9. Bidding Schedule item “Associated electrical equipment and material” includes providing equipment, material and services required to complete the following substation installations as shown on the Drawings:
10. Bidding Schedule item “Existing outdoor electrical equipment and material”: