Summary

This Statement of Objectives (SOO) for the LeMay Center describes a maglock software upgrade project for Building 693 at Maxwell Air Force Base, Alabama. The primary objective is to add two additional classified access points to the building by upgrading the existing maglock access control system to support Common Access Card (CAC) authentication. The contractor must be an authorized vendor capable of programming components within the Continuum Software platform and must be a Schneider Electric EcoXpert Certified Partner in access control. Performance objectives include installing CAC readers for two pre-existing doors with all required components (door controllers, readers, power supplies, locking hardware, and cabling), installing software and firmware for two doors, installing two recessed door strikes, and ensuring seamless integration with the existing Access Expert platform through system configuration updates, access group modifications, and user credential management. All hardware and software must be compatible with Access Expert, and the installer must provide certification documentation prior to commencing work.

Work must be performed at 55 Twinning Street, Building 693, Maxwell AFB, Alabama 36112, during building operating hours (0730-1630 Monday through Friday, excluding federal holidays). The contractor is responsible for complete installation including the maglock software update, must provide operator training and documentation for Access Control System (ACS) administration to government personnel, and shall provide OEM standard commercial warranties at no additional cost. All items must be brand new; refurbished items are not authorized. Additional security requirements for unclassified services include contractor notification to the contracting officer 30 days before on-base performance, obtaining base identification and vehicle passes for all personnel, compliance with REAL ID Act requirements, vehicle inspection protocols, base traffic regulations, and restrictions on firearms, weapons, and wireless electronic devices. The Point of Contact is Mr. Bill Lynn at 334-953-5376 or william.lynn.8@us.af.mil.

View the file

Other files

File Type Posted
Intent to Sole Source - Maglocks.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Objectives (SOO) LeMay Center

BLDG B693 Maglock Software Upgrade

1.0 OBJECTIVE: A d d t w o a d d i t i o n a l c l a s s f i e d a c c e s s p o i n t s t o B 6 9 3 . Contractor must be an authorized vendor to program components within the Continuum Software. The LeMay Center requests the replacement of the existing maglock access control system in building 693. By replacing, the existing maglock system, LeMay Center will be able to fully execute its intelligence, surveillance, and reconnaissance mission without regard to expanding or constricting requirements.

2.0 DESCRIPTION OF REQUIREMENT. Computerized Security system enabling CAC access requirements. System allows scheduled locking and unlocking authorized entrances and exit points within building 693. Adding two additional classified access points to B693.

2.1 PERFORMANCE OBJECTIVES:

2.1. System Expansion

• Installation of CAC Readers for two (2) pre-existing doors o Supply and install all required components (door controllers, readers, power supplies, locking hardware, cabling, etc.) to integrate four new doors into the current access control system.

o All doors must be fully compatible and operational with the Access Expert platform.

2.2. Lockdown Functionality

3.0 DELIVERY REQUIREMENTS: Building operating hours are 0730 – 1630 Monday through Friday, excluding Federal Holidays. All contract services must be performed during these hours. Address 55 Twinning Street B 693 Maxwell AFb, AL 36112. POC Mr. Bill Lynn, 334-953-5376, william.lynn.8@us.af.mil.

4.0 INSTALLATION REQUIREMENTS: Contractor is responsible for all installation to include the Maglock Software Update.

5.0 TRAINING REQUIREMENTS: Contractor shall provide operator training and documentation for ACS administration to government personnel sufficient in detail to ensure full user capability of operations.

6.0 STANDARD WARRANTY: The contractor shall provide any Original Equipment Manufacturer (OEM) standard commercial warranty applicable to the products being purchased at no additional cost to the Government.

6.1 Prior to project acceptance, the contractor shall provide the customer with all manufacturer warranties as needed for any component incorporated into this project such as equipment manuals,

• Install Software and Firmware for 2 doors

2.3 Recessed Doors

• Install two (2) recessedd door Strikes

• Ensure all repaired readers are fully tested and operational.

2.4. System Integration

• Ensure all new and repaired components are seamlessly integrated with the existing Access Expert platform.

• Update system configuration, access groups, and user credentials as necessary.

• Provide validation and testing to confirm full system functionality.

2.5 Technical and Certification Requirements

• All hardware and software must be compatible with Access Expert.

• Installer must be a Schneider Electric EcoXpert Certified Partner in access control.

• Provide certification documentation prior to commencing work.

2.6 Additional Notes

• All work must comply with local building codes, electrical standards, and security requirements.

• Work to be conducted with minimal disruption to day-to-day operations.

mailto:william.lynn.8@us.af.mil literature, CDs and DVDs and other documentation on all equipment and software. [Note: If there is no requirement for software, delete this language].

6.2 Prior to project acceptance, the contractor shall provide written procedures, points of contact within company, and required information for all warranty services prior to project acceptance. This information shall include written confirmation of the warranty period, phone numbers and contact information/procedures for technical support, troubleshooting assistance, and replacement of faulty equipment and software [Note: If there is no requirement for software, delete this language].

7.0 GENERAL INFORMATION: Items must be brand new. Refurbished items are not authorized.

Melissa Edwards

Budget Analyst, LeMay Center

SECURITY REQUIREMENTS FOR UNCLASSIFIED SERVICES ONLY

No CAC REQUIRED

1. Contractor Notification Responsibilities: The contractor shall notify the contracting officer within 30 days before on-base performance of the service. The notification shall include:

a. Name, address, and telephone number of contractor employees working on the contract.

b. The contract number and contracting agency.

c. The location(s) of service performance and future performance, if known.

d. The date service performance begins.

e. Any change to information previously provided under this paragraph.

2. Installation Access Requirements: As prescribed by the DAFFARS 5352.242-9000, Contractor access to Air Force installations, AFI 31-218, Motor Vehicle Traffic

Supervision, and DoDM5200.08v3_AFMAN31-101v3, Installation Perimeter Access

Control.

The contractor shall obtain base identification and vehicle passes, if required, for all contractor personnel who make frequent visits to or perform work on the Department of the Air Force installation(s) cited in the contract. Contractor personnel are required to wear or prominently display installation identification badges or contractor-furnished contractor identification badges while visiting or performing work on the installation.

The contractor shall submit a written request on company letterhead to the Contracting

Officer (CO) listing the following: contract number, location of work site, start and stop dates, and names of employees and subcontractor employees needing access to the base.

The letter will also specify the individual(s) authorized to sign a request for base identification credentials or vehicle passes. The contracting officer will endorse the request and forward it to the issuing base pass and registration office or Security Forces for processing. When reporting to the registration office, the authorized contractor individual(s) should provide a valid driver’s license, current vehicle registration, and valid vehicle insurance certificate to obtain a vehicle pass.

During performance of the service, the contractor shall be responsible for obtaining the required identification for newly assigned personnel and for prompt return of credentials for any employee who no longer requires access to the work site.

Upon completion or termination of the contract or expiration of the identification passes, the prime contractor shall ensure that all base identification passes issued to employees and subcontractor employees are returned to the issuing office.

Failure to comply with these requirements may result in the withholding of final payment.

Vehicle Inspections. All commercial vehicles will be directed to Gate 3 (Kelly St) or

Gate 4 (Congressman Dickenson for Gunter) for processing through the Commercial

Vehicle Inspection (CVI) Area, when operational. During non-duty hours and holidays, commercial vehicle inspections will be conducted at Gate 1 (Maxwell Blvd) or Gate 4

(Congressman Dickinson Drive) only. Inspection members will conduct thorough inspections of the interior and exterior of the vehicle for items prohibited from the installation such as explosive devices, weapons and ammunition, drugs, and open or closed alcohol containers.

3. REAL ID Act: All Maxwell Air Force Base and Gunter Annex visitors must present a REAL ID-compliant credential to be issued a pass.

REAL ID-compliant cards have a star marking ⭐️on the upper portion of the card. If the card does not have a star marking, it is not REAL ID-compliant and won’t be accepted as proof of identity to board commercial aircraft or access military installations like

Maxwell or Gunter.

Those without a REAL ID-compliant driver’s license may also use a U.S. passport or passport card, a Transportation Worker Identification Card (TWIC), a Veteran Health

Identification Card (VHIC), or a combination of the following documents to be issued a pass:

• An original or certified true copy of a birth certificate with a raised seal

• A social security card

• A driver’s license issued by a state, territory, or the District of Columbia that is not REAL ID-compliant.

All three documents must reflect the same name (or a documented former name through legal name change documents such as a court order, marriage certificate, or divorce decree).

More information about accessing Maxwell can be found here: https://www.maxwell.af.mil/About-Us/Fact-Sheets/Display/Article/4024201/base-access-information/

4. Controlled/Restricted Areas: If work under this contract requires unescorted entry to controlled or restricted areas, the contractor shall comply with DAFI 31-101, Integrated

Defense, and DoDM5200.02_DAFMAN 16-1405, Air Force Personnel Security

Program.

If unescorted access is not authorized and the contractor requires access to controlled/restricted areas, they must be escorted by appropriately cleared government personnel at all times.

If work is required in a classified environment, the area must be sanitized, and the contractor will be escorted at all times by appropriately cleared government personnel.

5. Reporting Requirements: The contractor shall comply with DAFI 71-101, Volume-1, Criminal Investigations, and AFI 71-101, Volume-2, Protective Service Matters, requirements. Contractor personnel shall report to 42d Air Base Wing Information

Protection Office, any information or circumstances of which they are aware may pose a threat to the security of DoD personnel, contractor personnel, resources, and classified or unclassified defense information. Contractor employees shall be briefed by their immediate supervisor upon initial on-base assignment and as required thereafter.

6. Traffic Laws: The contractor and their employees shall comply with base traffic regulations set forth in AFI 31-218, Motor Vehicle Traffic Supervision and

DoDM5200.08v3_AFMAN31-101v3, Installation Perimeter Access Control. Personnel in violation may be issued a Central Violations Bureau Form 1805 traffic ticket.

7. Random Installation Entry/Exit Checks: Entry/exit vehicle checks are conducted by order of the 42 ABW Commander. These checks are conducted for the purpose of safeguarding the base and protecting government property by discovering and seizing stolen property, classified information, and contraband. Refusal to submit to an installation (entry/exit) vehicle check may result in the loss of base driving privileges, revocation of base registration, or debarment action.

8. Cellular Phone Operation Policy: The use of cellular phones while operating a motorized vehicle is prohibited on Maxwell-Gunter. Although discouraged, drivers are authorized to use devices, i.e. ear bud or ear boom, which allows their cellular phone to be operated hands-free. The device must not cover both ears. This policy applies to everyone driving on Maxwell AFB and Gunter Annex. Personnel in violation may be issued a Central Violations Bureau Form 1805 traffic ticket.

9. Wireless Electronic Devices: The contractor will not establish their own Information

Technology (IT) systems or networks (Local Area Networks [LAN], Wide Area Network

[WAN], Cellular phone/USB Modem as WAN, Wi-Fi as WAN, etc.), or camera system without the direct permission of the Program Manager and governing communications and responsible information systems office (42 CS).

10. Firearms and Ammunition: Transporting weapons or ammunition, concealed or otherwise, IS NOT permitted by any non-law enforcement personnel on Maxwell

AFB/Gunter Annex at any time regardless of state issued concealed weapons/LEOSA permits. Violations may result in criminal prosecution under applicable federal laws.

11. Illegal Weapons. The weapons below are considered illegal, unless specifically authorized by competent authority and are prohibited on Maxwell

AFB/Gunter Annex. Violations may result in criminal prosecution under applicable federal laws.

a. Switchblade knives or knives with any type of automatic blade release.

b. An incendiary/explosive weapon (e.g., grenades, flash bangs).

c. Fireworks

d. Homemade mortars, aka "tennis ball launchers" or similar devices.