040ADV-25-R-0001.pdf
PDF 798 KB Posted
- Attached to
- GPO 5th Floor SID Smartcard Room Design/Build Construction Federal contract opportunity
- Solicitation number
- 040ADV-25-R-0001
- Issued by
- Government Publishing Office
About this file
This is a Request for Proposal (RFP) from the Government Publishing Office (GPO) for a Design-Build (DB) project to repair and renovate Room A-501 on the 5th floor of Building A to create a new Smart Card Reader manufacturing hub. The project requires development of a full design based on provided conceptual drawings, followed by renovation work including HVAC, electrical, architectural, fire protection, and security systems modifications.
The solicitation number is 040ADV-25-R-0001 with proposals due by February 18, 2025 at 12:01 PM EST. The contract will be awarded as a firm-fixed price contract with a 434-day period of performance starting 7 days after notice to proceed. Key requirements include creating a manufacturing space with cloud ceiling, three new offices plus IT room, secured storage areas, mantraps for controlled access, and HVAC systems capable of maintaining 70°F ±5°F with 40% ±5% relative humidity. The contractor must provide key personnel including a Project Manager, Quality Control Lead, and Safety Lead. Technical evaluation factors in descending order of importance are: Technical Capability and Management Plan, Past Performance (within past 6 years), and Key Personnel. A pre-bid site visit will be held on January 8, 2025 at 10:00 AM EST at GPO headquarters in Washington, DC. The magnitude of this construction project is between $1,000,000 and $5,000,000.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment J-1 - Pictures of the Renovation Site - Reduced.pdf | ||
| Attachment J-2 - Conceptual Drawings of the Overall Space Design.pdf | ||
| Attachment J-4 - HVAC Service Area for 5th Floor.pdf | ||
| Attachment J-5 - Sprinkler System Layout for 5th Floor.pdf | ||
| Attachment J-3 - Architectural and Existing Floor Plans of GPO Building A 5th Floor.pdf | ||
| Attachment J-6 - Lighting Layout for 5th Floor.jpg | JPG image | |
| Attachment J-9 - Past Performance Questionnaire.doc | DOC document | |
| Attachment J-8 -Cost-Price Proposal.xlsx | XLSX spreadsheet | |
| Attachment J-7 - Power Plan for 5th Floor.jpg | JPG image |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NUMBER
040ADV-25-R-0001
2. TYPE OF SOLICITATION
SEALED BID (IFB)
INVITATION FOR BID
NEGOTIATED (RFP)
REQUEST FOR PROPOSAL
3. DATE ISSUED
12/17/2024
PAGE OF PAGES
1 56
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NUMBER 5. REQUISITION/PURCHASE REQUEST NUMBER
PR-24-GPO-3175
6. PROJECT NUMBER
7. ISSUED BY CODE GPO 8. ADDRESS OFFER TO
GPO
732 North Capitol St NW Washington, DC, 20401, US
9. FOR
INFORMATION CALL:
a. NAME
WHITE, TROY D
b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
SOLICITATION
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
11. The contractor shall begin performance within 7 calendar days and complete it within 434 calendar days after receiving.
award, notice to proceed. This performance period is mandatory negotiable. (See SOW ).
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES", indicate within how many calendar days after award in Item 12b.)
YES NO
12b. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and 1 copies to perform the work required are due at the place specified in Item 8 by
12:01P
(hour) local time 02/18/2025
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
b. An offer guarantee is, is not required.
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than 90 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
STANDARD FORM 1442 (REV. 12/2022)
Prescribed by GSA - FAR (48 CFR) 53.236-1(d)
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM
See Schedule
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES
CODE AT
10 U.S.C. 3204(a) (
27. PAYMENT WILL BE MADE BY
) 41 U.S.C. 3304(a) ( )
26. ADMINISTERED BY
OFFER (Must be fully completed by offeror)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NUMBER (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14.)
CODE FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT
NUMBER
DATE
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA
BY
31c. DATE
STANDARD FORM 1442 (REV. 12/2022) BACK
AMOUNTS
TABLE OF CONTENTS:
1. Section B - Supplies or Services and Prices/Costs
2. Section C - Description/Specifications/Work Statement
3. Section D - Packaging and Marking
4. Section E - Inspection and Acceptance Terms
5. Section F - Delivery or Performance
6. Section G - Contract Administration Data
7. Section H - Special Contract Requirements
8. Section I - Contract Clauses
9. Section J - List of Documents, Exhibits, and other Attachments
10. Section K - Representations, Certifications, and Other Statements of Offerors
11. Section L - Instructions, Conditions and Notices to Offerors
12. Section M - Evaluation Factors for Award
Section B: Supplies or Services and Price/Cost
B.1 CONTRACT TYPE
The Government Publishing Office intends to issue a firm fixed price contract for the Secure & Intelligent Documents (SID) Design-Build (DB) project to repair/renovate Building A, 5th floor Room A-501 at the agency’s main campus in Washington DC.
The successful offeror will develop a full, realized design based off the provided conceptual drawing (see Attachment 2). The Contractor will also perform the required repairs and renovations for the facility to be utilized as a new smartcard reader manufacturing hub.
Period of Performance: Al l work shall be completed and delivered within 434 days from Notice to Proceed after award.
Price Breakdown – The price breakdown shall justify the contractor’s firm fixed price quote for this requirement.
Item Number
Base Item Number
Supplies/Services Quantity Unit
0001 Design Phase for 5th floor SID Smartcard Relocation Project
1 LOT
Contract Type: Firm Fixed Price Unit Price
Extended Price
Description:
Purchase Requisitions PR-24-GPO-3175
IDC Type: Not Applicable
Base Item
Number Supplies/Services Quantity Unit
0002 Construction Phase for 5th floor SID Smartcard Relocation Project
1 LOT
Contract Type: Firm Fixed Price
Base Item Number
Supplies/Services Quantity Unit
0003 Construction Period Services for 5th floor SID Smartcard Relocation
Project
1 LOT
Contract Type: Firm Fixed Price
Section C: Description/Specifications/Work Statement
Scope of Work for Design-Build
A-501 SID Card Reader Relocation (A&E Design-Build)
I. Overview
The Secure & Intelligent Documents (SID) business unit requires a Design-Build (DB) project to repair/renovate Building A 5th floor Room A-501 at Government Publishing Office (GPO) located in
Washington DC.
A Contractor will be required to develop a full realized design based off the provided conceptual drawing
(see Attachment 2). The Contractor will also perform the required repairs and renovations for the facility to be utilized as a new Smart Card Reader manufacturing hub.
Repair and Renovation should include all systems (HVAC, Electrical, Architecture of the interior and exterior, Fire Protection, and Security) in accordance with the applicable codes of National Design and
Construction standards.
II. Background and Facility
A. Existing Site Conditions
1. GPO is located at 732 N. Capitol Street Washington, DC 20401. Uses for Room A-501 previously included open-area office space for the Publication and Information Sales
Department. Directly Adjacent are the offices for Acquisitions and Information Technology.
2. A lot of the character defining features of room A-501 are well beyond their useful life expectancy and beyond repair.
3. Room A-501 is currently vacated and does not house any furniture. Anything temporarily occupying the space can be moved prior to the start of work. The floor is made up of a short carpet with sections in front of the bathroom being tiled with a Vinyl-type material. Bridge 51 has flooring made up of a mix between wood and cement blocks.
4. Room A-501 uses a 9.5-foot drop ceiling. The drop ceiling houses fluorescent lighting in a 2-by-4 pattern across the whole space. Please Refer to Attachment 6 for more information on the lighting plan.
5. Bridge 51 is currently not being used for anything other than a corridor connecting Building A with Building C.
6. Please refer to Attachment 2 for the conceptual design of the space.
7. AHU 15A is a constant volume, pneumatically controlled AHU that currently supplies air to most of the floor. It is in the Mechanical Room C530/541 and was installed around 1976. The equipment is in working condition but is nearing the end of its life cycle.
8. Heating is maintained via a series of reheat coils scattered around the space which are due for replacement. For cooling, there exists a chilled water line on-site if needed. Dehumidifiers provide the space with additional climate control and are also due for replacement.
9. Smoke Detectors in the space are EST3 light-detectors and were installed within the last 3 years. There exists no drawn layout of their placement so please refer to attachment 1 for visual reference.
10. A wet fire-suppression system is currently being utilized in A-501. The last time it was updated was over 10 years ago. Please Refer to Attachment 5 for drawings of the Sprinkler layout.
11. Power is being supplied to the area via the 208 substation. The connection to the substation can be found the C531A Transformer Room. Please Refer to Attachment 7 for more information on the electric grid within the A-501.
12. There is already a plan in place to abate Bridge 51 of any hazardous materials. The existing insulation on the ductwork contains hazardous material but it has yet to be removed since the ductwork can’t be left exposed without a plan to immediately re-insulate. The Safety Branch will coordinate with the contractor to abate according to the project timeline.
13. Results of lead testing done in Room A-501. Nondestructive Niton XLp 301A Lead Paint analysis showed the presence of lead-based paint in the following areas:
(i) Rm A510D, North Side – Brown Window Casement
(ii) Rm A510C, North Side – Brown Window Casement
(iii) Rm A510E, North Side – Brown Window Casement
(iv) Rm A510E, East Side – Brown Window Casement
All areas appear to be intact or in good condition. GPO’s safety officer doesn’t think it needs abatement so that decision will be left to the contractor. If any work will be required to disturb the areas listed above, then it will be the responsibilities of the contractor to complete.
14. The contractor is responsible for any further evaluation of the repairs, renovations, retentions, and additions and subsequently finalized by the COR.
B. Pre-Bid Walkthrough
A pre-bid walkthrough will be held on site and scheduled by the Contracting Officer (CO).
Questions may not be asked on site or directed to individuals. All questions shall be in writing and submitted to the CO by the specified deadline date. An attempt to provide responses for questions that do not make the deadline will be made, but there is no guarantee that they will be answered.
Parking information for the site-visit can be found in Chapter V, Article E, Section 5 of this document.
C. Government Furnished Information
1. Pictures taken by the Contractor are only permitted of the installation site and any equipment directly associated with the project.
2. All available record drawings will be provided upon request to the Contractor. They should not however, be considered “as built”. These drawing files are provided without warranty or obligation as to the accuracy or information contained in the files. All information in the files must be independently verified by the user. Any user must agree to indemnify and hold the
GPO harmless from all claims, damages, losses, and expenses, including, but not limited to, attorney fees arising out of the use of the Computer Aided Design and Drafting (CAD) drawing files.
3. The following architectural drawings and any other necessary documentation of the building shall be provided to the Contractors for their analysis:
(i) Pictures of the renovation site. Attached are pictures of the space including the walls, ceilings, and floors. Also included are the existing offices, the elevators, and the surrounding area such as the bathrooms and bridge 51.
(ii) Conceptual drawings of the overall space design.
(iii) Relevant Architectural and Floor Plans of GPO Building A 5th Floor.
(iv) HVAC Service Area For 5th Floor
(v) Sprinkler System Layout for 5th Floor
(vi) Lightning Layout for 5th Floor
(vii) Power Plan for 5th floor.
III. Project
A. Tasks
All the tasks listed in this section can be found in the supporting document named “Attachment 2
– Conceptual Design”. Please refer to this document for all information regarding the locations, dimensions, or technical of task items hereunder. Resolve any data conflicts with the COR.
1. Demolition
(i) The Contractor will construct and present a demolition plan for the space that takes into account all the commissioning party’s needs.
2. Architectural
(i) The Contractor shall ensure the manufacturing space utilizes a cloud ceiling in its final design.
(ii) The space has an expected occupancy of 15 people at any given time. The Contractor shall take this into consideration for design of the space.
(iii) The Contractor will design and erect dry walls in the space to make room for 3 new offices in addition to an IT room. The contractor shall also ensure the existing corner office is expanded.
(iv) The contractor shall design a small, secured-entry closet for the storage of all security systems.
(v) Adjacent to the Security System Closet, the Contractor shall design a small-caged room for the storage of UPS orders prior to shipping. The area does not need to be secured.
(vi) The Contractor shall design a caged room for the secure storage of raw material by
Column A5E (part of shaft 10).
(vii) The Contractor shall design a double-chamber, secured-entry caged room for the storage of finished goods. External entry into the cage shall be done with secured double doors and internal flow between the two chambers shall be with a secured sliding door.
(viii) The Contractor shall ensure the space is enclosed in all directions with multiple means of egress.
(ix) Entrance into the area should be secured. To this end, the Contractor shall design two mantraps at the north and southern walls of the facility. The northern entrance will serve as the visitor’s entrance and will take up the entire space of Bridge 51. The southern entrance will be the main employee entrance and will be located right outside bathrooms T151 and
T152.
(x) The Contractor will ensure there are at least two one-way exits as a means of egress. One will be located on the western wall by Elevators 10 and 11 while the other will be located on the southern wall by elevator 1. All exits shall be operated with push bars.
(xi) The contractor shall select new carpet for the offices according to GPO’s needs. There are no flooring requirements for these carpets in contrast to the ones on the production floor so decisions will be made on a comfort/aesthetic level.
(xii) The Contractor shall equip the main production area of A-501 with concrete flooring. The concrete shall be equipped with a protective finish to protect it from damage and improve its surface texture.
(xiii) The contractor shall repaint all the walls of the space to follow the customer’s desired theming. The contractor shall coordinate with the customer and GPO to fulfill the design requirements appropriately.
3. Mechanical
(i) The Contractor shall ensure there is new insulation for the duct work in Bridge 51. This work will need to be coordinated with GPO’s safety team for scheduling purposes.
(ii) The contractor will take the plumbing fixtures into consideration. The condition and useful life of the existing ones are not expected to be good.
(iii) The Contractor shall conduct a preliminary survey of the current HVAC’s capabilities.
(iv) The contractor shall ensure the HVAC system is able to perform as needed to satisfy the space’s requirements. Equipment such as Dedicated Outdoor Air Supply Unit, ductwork, Variable Air Volume (VAV) units, exhaust fans, and diffusers will need to be coordinated with the floor plan.
(v) Contractor must ensure that in the design of the HVAC unit that the supply air doesn’t blow unto the machinery. This is to prevent dust from contaminating the product line,
(vi) The contractor shall ensure that each individual office has access to an independent climate control panel. Sufficient VAV Units must be supplied to accommodate this demand.
(vii) The contractor will ensure that the IT server room has its unique needs addressed. Due to all the excess heat coming from the computers, there must be a sufficient exhaust and cooling to keep the space chilled.
(viii) The Contractor will design an HVAC system capable of maintaining the main room at an ambient temperature of 70 °F (± 5 °F) and a relative humidity of 40% (± 5%).
(ix) The contractor must ensure any modifications are compatible with the already existing
HVAC systems in the building. Refer to Attachment 4 for more information concerning the existing HVAC.
4. Electrical
(i) The contractor shall redesign the current lighting system to deliver even and bright light across the floor via energy efficient LEDs. There should be more lights around points of interest such as the machines and workstations.
(ii) The Contractor shall run electricity and Cat5E to all the security camera installation locations shown in Attachment 2. The camera installation itself will be conducted by others.
(iii) The Contractor shall run electricity to all PACS (Physical Access Control Systems) card readers installation locations shown in Attachment 2. The scanners installation will be conducted by others.
(iv) The Contractor shall connect all security systems to a centrally located Security closet.
Installation of the equipment in the closet will be handled by others.
(v) The Contractor shall run electricity to all the future locations of equipment such as the card issuance machines. The power requirements for the machines can be found in Attachment
2.
(vi) The Contractor shall run electricity and install new standard 120v outlets in the space wherever needed by the commissioning agent. The placement and quantity of which will be coordinated with GPO.
(vii) The Contractor shall ensure all the lighting has a proper connection to the building’s electrical systems.
(viii) The Contractor shall provide Telecommunications for the facility. The bandwidth requirements are 50 Mb/s per person, and the potential for up to 50 devices in use at a time will be needed.
(ix) The contractor shall upgrade the existing electrical panel with one that can support all the planned machinery plus some spare slots for future proofing.
(x) The Contractor is not responsible for the design/install of computer equipment in the IT room. Those aspects will be handled by others.
5. Fire & Safety
(i) The contractor shall design a fire detection system that is in accordance with all applicable codes. The fire detection system shall remain consistent to the building’s present EST3 standard.
(ii) The contractors shall ensure that each office is equipped with smoke detectors and sprinklers.
(iii) The Contractor is not responsible for independently supplying the smoke detectors to be used in the space. The contractor shall work with GPO’s Fire Guard to fulfill this need instead.
(iv) The Contractor shall establish connections between all the smoke detectors and the databox. They must ensure all the hardware is functional and in good condition.
(v) The contractor shall leave the smoke detectors as a dead data line. The contractor isn’t responsible for programming the fire detectors into the fire detection network. That work will be performed by others.
(vi) The contractor shall incorporate the use of, at minimum, 3 Speaker Strobes in the final design of the fire detection system.
(vii) The contractor shall design and provide a dry fire suppression system for the facility.
Automatic sprinkler protection shall be accordance with the requirements of NFPA 72.
Architectural elements such as cloud ceiling should be taken into consideration as well.
(viii) The Contractor shall collaborate with the building’s facilities management staff for the development of any fire detection/protection services.
B. General Contractor Requirements
1. The Contractor will perform all work and provide all the labor, materials, and equipment needed to meet this Scope of Work. The government shall not loan or provide any labor or equipment.
2. The government is not responsible for costs incurred due to mismanagement of labor or lack of proper equipment.
3. The Contractor shall provide a certified Construction/Project Manager as outlined in the specifications to oversee and provide Quality Control during the construction period.
4. Personnel assigned to perform services under this scope shall always be under the direction and control of the Contractor. The Contractor shall monitor the performance of its employees to ensure all aspects of this scope are properly fulfilled.
5. If the Contractor finds clarification necessary with respect to the scope of the services to be performed hereunder, he/she shall request, in writing, such clarification from the CO or COR.
6. The Contractor shall provide a minimum notice of 72 hours to the COR for any work that is required to be done by others so the COR can schedule the work in advance.
IV. Design Period
A. Design Requirements
1. The Contractor must develop plans from field verification on-site and GPO-provided supplementary drawings. The contractor is responsible for on-site verification of existing conditions affecting design which may include crawling, use of ladders, and discussions with engineering personnel.
2. The Contractor must consider adjacent systems and components (architectural as well as utility systems) to avoid construction change orders due to unforeseen site conditions.
3. The Contractor must attend 4 interim review project meetings at 35%, 65%, 95% and 100% milestone deliverables with COR and designated GPO staff. The contractor will record and provide meeting minutes within 35 hours to all attendees for review, comment, and concurrence. Incorporate appropriate comments, finalize the meeting minutes, and submit the final meeting minutes within one week of meetings.
4. The Contractor must provide design period services to include drawings, and specifications reflecting specific tasks identified herein, in addition to on-site meetings with professional and administrative staff, site investigative work, and review of supplementary documents.
5. The Contractor is responsible for professional quality and technical accuracy in providing
GPO with documents.
6. The Contractor must provide competent design period services with staff and consultants adequately knowledgeable in:
(i) manufacturing space design and construction
(ii) the various subordinate design disciplines including but not limited to mechanical, electrical, plumbing, structural, fire protection, life safety
(iii) other building/utility systems as required.
7. DB Team must verify necessary building architectural and utility system components to provide for a full and complete design of replacement architectural elements and utility system components. This includes, but is not limited to items such as:
(i) Existing conditions verification – upgrades to meet current codes.
(ii) ABAA/ADA accessibility requirements
(iii) Above ceiling verification – conflicts/interstitial space
(iv) Verification of spare circuits on electrical panels
(v) Mechanical systems and distribution verification
(vi) Plumbing verification (dead legs existing conditions)
(vii) Fire sprinkler reconfigurations/change in pendant type/elevation to meet current code.
(viii) Fire alarm upgrades to current code
(ix) Low Voltage access control capacity on existing panels
(x) Structural conflicts - through floor penetrations, etc.
8. GPO design period services to include Design Development, Construction Documents, and
Quality Assurance/Quality Control (QA/QC). All submissions and related work for each design phase must conform to the requirements in this document.
9. The Contractor must resolve Conflicting Criteria with the COR.
B. Submission Requirements
1. Design Development
Design Development includes initial work of The Contractor required to represent the project as a set of drawings conveying the major intent of the project work. At this stage of project design, the physical layout of the new work should be shown.
2. Construction Documents
The Contractor must provide a checklist of all submittals, certifications, tests, and inspections required per drawing and specification section. This checklist will show all products requiring submittals in the form of shop drawings, data sheets, manufacturer cut sheets, etc. as well as all other items shown as required submittal items including, but not limited to, reports, system evaluations, testing, operating and maintenance manuals, etc.
Recommendations for rehabilitation by SID has been made based on their requirements. However, further evaluation of repair, renovations, retention, and addition of the relocation site must be performed by the Contractor and finalized by the COR.
The Contractor must provide 100% drawings in AutoCAD/Revit and pdf. Specifications in Word electronic formats for construction period use by GPO. A share-point site or email with hyperlink click and download such as Procore is encouraged for ease of transfer.
DB Team is responsible for professional quality and technical accuracy in providing GPO with documents. Services include but are not necessarily limited to:
• Contract Administration
• Architectural design documents and calculations in detail of construction documents including all plans, elevations, sections, details, and schedules.
• Mechanical design documents and calculations in detail of construction documents including all plans, elevations, sections, details, schedules, calculations to size all HVAC and plumbing components.
• Electrical design documents in detail of construction documents including all plans, elevations, sections, details, diagrams, schedules, showing power distribution systems, lighting, and signal systems.
• Fire Protection design documents in detail of construction documents including all plans, elevations, sections, details, diagrams, and schedules.
• Presentation and review submissions. Meetings with GPO representatives, and field technical personnel.
3. Drawings
• Drawings must be normally in plan view, at a scale where work required is clear, legible, and easy to interpret.
• Drawings must be independent for demolition, architectural, mechanical, structural, civil, etc., and must show, on separate views, required demolition and reconstruction details for each function.
• Drawings must be prepared using AutoCAD/Revit 2018 or newer (or equivalent) and plotted on 30" x 42” sheets.
• Final drawings must bear GPO title block and nomenclature. Drawings must be on the same type and size sheets. All views, elevations, sections, etc., must be complete to ensure total contractor compliance without any ambiguities, or subject to various interpretations.
• All drawings are required to show existing conditions as of the date of the design submission.
• All sheets of drawings must contain A/E official stamp with professional seal and signature along with the name and address of the firm.
4. Specifications
• Specifications must be prepared and submitted individually in latest version of Microsoft
Word.
• The Contractor must review and edit applicable sections of the specifications for completeness, relevance, and correctness. The intent is to provide specifications suitable for the project intention and detailed enough to enable the contractor to perform the work in the simplest and practical manner.
• Where a particular item is referenced in the specifications, consult with COR for direction on which item to select. The contractor must not be provided options or choices to make selections but must be provided the specific selection.
• The Contractor must obtain the name and type of specialty materials and equipment required for use on the project. All items shown in the specifications must, if named specifically by brand or trade name, carry the statement "or approved equal" with salient characteristics listed.
(a) Exception may occur due to previously purchased or installed items interacting with new construction. In this situation, items used should be the same as existing or matched accordingly. Information on such items must be obtained by the contractor from GPO.
• Construction tolerances must be specified in detail in all specification sections or identified on plans.
• Legal precedence of "specifications over drawings" must not be used to resolve design ambiguities between drawings and specifications, or to justify omission of drawings or notes required for clarity.
• Contradiction, ambiguity, or statements subject to various interpretations, must be corrected to reflect a single clear intention.
C. Quality Assurance/ Quality Control (QA/QC)
To reduce design errors and omissions, the Contractor must develop and execute a QA/QC plan that demonstrates the project plans and specifications have gone through a rigorous, thorough review and coordination effort.
These plans must include, but is not limited to, methods to verify the leveling and vibrational tolerances of the machine. The Contractor will work with the Machine Manufacturer to validate the acceptance of the 8-Color press foundation.
The COR, GPO, AHJ, or other Safety Personnel may conduct inspections of work or working environment at any time; full cooperation with reviewing personnel is mandatory. The Contractor shall accomplish corrective work required prior to performing further construction.
D. Code Compliance
1. All NEC/NFPA and other applicable healthcare facility codes referred to in specification Any deviations or work that is non-conformant to standards, regulations, or specification shall be removed and corrected at no cost to the Government. The GPO adopts the most current versions of the NFPA and other applicable publications.
2. Installation of electrical systems shall be performed by licensed or journeymen electrician;
provide documentation via submittal. Installation of communications systems shall meet the applicable codes. The contractor shall coordinate with GPO with all aspects to revised
Physical Security requirements. These requirements may be revised and modified in the construction phase with evolving requirements and constraints applicable to a 100% fully functioning GPO Security System.
3. In the development of submissions, must utilize certain GPO and other design and construction criteria. The design is not limited to these items and must be the result of compliance with applicable codes and standards, the user requests, and The Contractors expertise and creativity.
4. NFPA Codes including, but not limited to: NFPA 101, Life Safety Code; NFPA 99, Healthcare Facilities; NFPA 70, National Electrical Code (NEC)
5. The Facilities Guidelines Institute (FGI) 2022 Guidelines
6. Compliance to all known applicable codes must be reflected in the completed design and construction contract documents.
V. Construction Period
A. General Requirements
1. The Contractor will make any required modifications to the space as indicated by the
Construction Documents.
2. The Contractor shall follow the designer’s recommendations for any work entailed by their design such as materials or methods to be used. Any disagreements shall be resolved by the
COR.
3. The Contractor shall give the COR advance notice of any demolition in the work schedule, whether it be for investigation or construction.
4. Contractor shall ensure all nearby adjacent surfaces and areas are protected from damage during the period of construction and should any damage occur, it will be the responsibility of the Contractor to repair before the end of the contract period.
5. In the event of accidents of any kind, the Contractor shall furnish GPO with copies of all accident reports at the same time they are forwarded to any other parties, without delay, for review.
6. The Contractor must maintain all construction permits visible and updated as required.
7. The Contractor shall prohibit smoking in and adjacent to construction areas.
8. The Contractor will prevent accidental smoke detector operation.
B. Fire and Safety
1. Develop a plan detailing project specific, fire-safety measures. Conduct meetings with the building’s facilities management to determine the type and capabilities of the fire-suppression systems on site.
2. Maintain site and building access free and unobstructed to facility emergency services.
3. All temporary construction partitions must meet fire-safety requirements.
4. Temporary heating and electrical installations must comply with OSHA 1926, NFPA 241 and
NFPA 70.
5. Contractor furnished fire extinguishers must be provided and maintained in construction areas and in temporary storage areas. Extinguishers must be raised two feet off the floor.
6. Flammable and combustible liquids must be stored, disposed and used in accordance with
OSHA 1926, NFPA 241 and NFPA 30.
7. Existing fire protection must not be impaired, and a fire watch must be provided should protection become impaired. Notify the COR and Fire Inspector if these conditions are expected or occur.
8. Perform Hot Work in accordance with NFPA 241 and NFPA 51B. The Contractor must obtain and fill out a GPO Hot work permit from the COR prior to the start of Hot Work
C. Site Protection
1. No dust and debris should get into the production area on the same floor.
2. The Contractor shall provide, erect, and maintain catch platforms, lights, barriers/walls, weather protection, warning signs and other items as required for proper protection of the public, occupants of the building, and workmen engaged in work and adjacent construction.
3. The Contractor shall not close or obstruct walkways, passageways or stairways. The
Contractor shall also not store or place materials in passageways, stairs or other means of egress and shall conduct operations with minimum traffic interference.
D. Cleanup and Restoration
1. Contractor shall remove waste generated from the worksite on a scheduled basis. Waste shall be deposited in an appropriate dumpster provided by the Contractor, located in an area approved by the COR and removed from the grounds weekly or when full. The Contractor is responsible for the procurement of waste services, and no government leased, or owned dumpster shall be used to dispose of construction waste.
2. Damage of interior and exterior items such as walls, ceiling tile, and any other Government owned equipment shall be repaired/replaced at no cost to the Government.
3. Should the Lead-containing material outlined in the “existing site conditions” section of this document be disturbed, the following regulations apply:
(i) The Contractor is totally responsible for all the cost for the abatement work if they would fail to find the hazardous materials during the site visit and would not include the cost in the bid price.
(ii) Contractor will abate and remediate areas containing asbestos materials, lead based paint, rectify any code deficiencies including gaps in the Conceptual design and as required by
GPO. Even though GPO tried to find all the hazardous materials in the area, there might still be some which were not discovered in the survey. If the Contractor suspects new ACM or lead-based paint, the COR shall be contacted immediately.
(iii) The removal and disposal of any hazardous material shall be in accordance with EPA
Regulations and the Contractor shall submit the related documents to the COR. The
Primary Contractor shall be responsible for submitting any documents that are required by
EPA Regulations.
4. Upon completion of work, the Contractor is responsible for any punch list items accrued during the final walkthrough by the COR. This contract will not be fulfilled until all items are addressed in a timely manner, inspected by the COR, and have written approval.
E. Government Furnishings
1. Services
• GPO will provide house services such as 120V house Electrical, water, etc.
2. GPO will oversee all matters relating to facilities equipment and systems such as HVAC, electricity, plumbing, etc. Any adjustments to these utilities will be handled internally by the
Facilities Management or by others.
3. Loading Dock
• Loading Dock hours of operations are from 7:00 AM to 2:30 PM, Monday thru Friday.
Coordinate with the COR for usage.
• The address of loading dock is 44 H Street, NW, Washington, DC 20401.
• Equipment or materials shall not exceed what can be handled by GPO’s elevators as listed below.
• Oversized payloads will require special handling by the Contractor. If any part or equipment exceeds 20,000 lbs., it shall be delivered through the wall or windows. If the wall or window is demolished for the work, the Contractor restores the wall and window to the original condition.
4. Elevators
• Use of freight elevators for the transportation of materials and equipment is provided. The max specifications of the freight elevators are as follows:
(a) Height - 7' 6"
(b) Width - 7' 0"
(c) Length - 10' 0"
(d) Weight - 20,000 lbs.
5. Material Storage
• The Contractor shall confine storage of materials on the job site to areas approved by the COR and shall not unnecessarily encumber the premises or overload any portion with materials to a greater extent than the structure design load.
• Verify available storage space at the job site with COR prior to bid opening. Any additional off-site space required is the responsibility of the Contractor. Allocate the available storage areas and coordinate their use with the other trades on the job.
6. Parking
• The Contractor is to pay $9/day/vehicle and the space is limited due to multiple ongoing construction projects. The Contractor shall limit the number of Contractor vehicles on site to an appropriate level. Coordinate with the COR for proper parking if standard lot spaces are not being used.
F. GPO Regulations
1. Crane Work
• Any crane work will be scheduled on weekends (Saturdays and Sundays) or Federal Holidays approved by the COR. The cost resulting from weekend work and Federal Holidays shall be included in the bid price.
2. Gas-Powered Vehicles
• Propane Gas Powered Forklifts shall be used during weekend work, Federal holidays, or off hours (4pm-10:30pm) with GPO’s approval and permission.
3. Security
• Contractor’s vehicles, work bags, toolboxes, material, etc. will be inspected upon arrival and checked when leaving the premises of the building. Luis Gallegos (COR, work cell: 202-285-
8480) will be the Point of Contact and escort the Contractors to the locations when they arrive.
Andrew Watts (COR, work cell: 202-904-8358)
• The Contractor shall safeguard all Government Property in the work area. At the close of each work period, equipment shall be secured and/or taken away from the work site daily.
• The Contractor shall cooperate with those in authority on the premises to prevent the entrance and exit of all workers and/or others whose presence is forbidden or undesirable.
• Follow the FY24/FY25 Contractor Security Requirements.
VI. Period Of Performance
A. A timeline based on A/E contract award of approximately July 2024 is offered below.
B. During the process of the work the CO and COR will conduct periodic reviews with The Contractor to review progress. The Contractor must perform the work required within the limits of the following schedule.
Predesign Meeting with GPO staff Day 0
Technical Kickoff Meeting +7 days, Day 7
Design Submit 35% Conceptual Design
Development (DD) Review Package
+45 days, Day 52
GPO Review +14 days, Day 66
Design Submit 65% Design Development
(DD) Review Package
+30 days, Day 96
GPO Review +14 Days, Day 110
Design Submit 95% Design Development
(DD) Review Package
+30 days, Day 130
GPO Review +7 days, Day 137
Submit 100% Construction Document (CD)
Review Package
+30 days, Day 167
Administrative NTP for contracts, submittals and long lead items
+60 days, Day 227
Construction NTP and Multi-Phased
Construction
+200 days, Day 427
QA/QC of Construction, Substantial
Completion, and Punchlist Review.
+7 Days, Day 434
C. All work to be completed within 63 weeks (434 days) of the Notice to Proceed (NTP).
Submission of Design timeline, safety plans, quality control plan, schedules, pre‐construction submittals, etc. shall be required to be submitted within 14 days of the Construction NTP.
D. Contractor must submit a Critical Path Method (CPM) schedule for both the Design and Construction phase with estimated dates and itemized cost of work to the Contracting Officer for review and approval before Notice to proceed.
E. Federal Legal Holidays
New Year’s Day January 1
Martin Luther King’s Birthday Third Monday in January
President’s Day Third Monday in February
Memorial Day Last Monday in May
Juneteenth June 19
Independence Day July 4
Labor Day First Monday in September
F. Work Schedule
Work will be performed during normal business hours 7:00 AM until 3:00 PM. Coordinate working schedule with the COR prior to beginning construction. Any work to be performed outside normal business hours and on weekends or holidays will need to be coordinated with the
COR three (3) days prior.
VII. Privacy Statement
Information Security: The C&A requirements do not apply; a Security Accreditation Package is not required. Incidental exposure to protected health information may occur from accessing the work site. Staff will follow all Privacy & Security policies and procedures.
VIII. Post Construction Quality Validation and Contract Close-out
A. MMAR 52.246‐21 Warranty of Construction, the Contractor is to provide a one (1) year warranty period, from the date of final acceptance of the work, covering defects related to all work performed and any materials/equipment included in the project.
B. Closeout – The Contractor shall provide a two week notice to the COR for the onsite Final
Walkthrough and Punch List for Acceptance as well as other planned milestones.
C. The Contractor must submit the record drawings showing any changes or modifications to the
Bid Documents reflected on the hard-copy set of “as-builts”; Drawings must be individually marked “Record Drawing” and submitted in a single package as follows;
1. Drawings in AutoCAD (DWG) or Revit (RVT) format of the entire project shall be delivered electronically.
2. Drawings must represent final project with all demolished and/or removed items deleted from the .dwg/.rvt files.
3. Drawings in (PDF) format of the entire project in addition to 1 set of full size 30 x 42" drawings.
IX. Key Personnel
Key personnel are essential to the work being performed. The education, experience, and capabilities of key personnel will be evaluated to determine the degree to which they possess the qualifications to perform their proposed duties under the contract. Offerors must provide proof of adequate and qualified personnel for each category described in this Statement of Work. This includes responsibilities, technical competencies, experience, and education. Experience with the design and construction of similarly sized spaces for office and light manufacturing work are desired. Disciplinary diversity (architectural, mechanical, electrical engineering) among the key personnel is also desired. The Government will evaluate all key personnel for this solicitation, but the following personnel are the mandatory minimum for this project:
Columbus Day Second Monday in November
Veteran’s Day November 11
Thanksgiving Day Fourth Thursday in November
Christmas Day December 25
Project Manager
Responsibilities Performs safety inspections of third-party contractor constructions activities. Document and review compliance with safety standards and ensure safe work practices.
Minimum Experience Ten (10) Years
Minimum Education Bachelor’s Degree in Engineering, Architecture, Construction, Project Management, or a related field. Waived for 15 years’ experience in a similar role
Quality Control Lead
Responsibilities Works with COR and third-party contractors to ensure all work conforms to the contract requirements including workmanship, materials, and equipment. Manages coordination of inspections and ensures appropriate team members are on site during each definable feature of work.
Minimum Experience Five (5) Years
Minimum Education Bachelor’s Degree in Engineering, Architecture, Construction, Project Management, or a related field. Waived for 10 years’ experience in a similar role
Safety Lead
Responsibilities Performs safety inspections of third-party contractor constructions activities. Document and review compliance with safety standards and ensure safe work practices.
Minimum Experience Five (5) Years
Minimum Education Bachelor’s Degree in Occupational Health or a related field. Waived for 10 years’ experience in the Construction Safety Field
Section D - Packaging and Marking: None
Section E - Inspection and Acceptance Terms:
E.1 MATERIALS MANAGEMENT ACQUISITION REGULATION (MMAR) 46.503
PLACE OF ACCEPTANCE (APR 2010)
The Contracting Officer or the duly authorized representative will accept supplies and services to be provided under this contract. The place of acceptance will be: United States Government Publishing
Office 732 North Capital Street NW Washington DC 20002.
E.2 RESPONSIBILITY FOR INSPECTION AND ACCEPTANCE
The Contracting Officer’s Representative (COR), as appointed/designated by letter per the information listed in Section G of this document, is the Government's official responsible for inspection and acceptance of required services under the terms and conditions of this contract. The Government may designate additional representative(s)to provide periodic inspections or observations during the performance of this contract. However, Government inspections are for the sole benefit of the
Government and do not relieve the Contractor of its responsibilities to provide adequate quality control for the works described in Section J Attachments: Plans and Specifications. The Contractor is responsible for inspection of its own work to ensure that all work performed conforms to the terms and conditions of the contract.
E.3. NOTICE LISTING CONTRACT CLAUSES INCORPORATED BY REFERENCE
The following Contract clauses pertinent to this section are hereby incorporated by reference (by Citation, Number, Title, and Date) in accordance with the clause at MMAR 52.252 2 CLAUSES
INCORPORATED BY REFERENCE in Section I of this Contract. Full text of the clauses is available at:
https://www.gpo.gov
52.236-2 Differing Site Conditions
52.236-3 Site Investigation and Conditions Affecting the Work
52.236-5 Material and Workmanship
52.236-6 Superintendence by the Contractor
52.236-7 Permits and Responsibilities
52.236-8 Other Contracts
52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities and
Improvements
52.236-10 Operations and Storage Areas
52.236-12 Cleaning Up
52.236-13 Accident Prevention
52.236-15 Schedules for Construction Contracts
52.236-17 Layout of Work
52.236-21 Specifications and Drawings for Construction
52.236-23 Responsibility of the Architect-Engineer Contractor
52.236-27 Site Visit (Construction)
CONTRACT CLAUSES INCORPORATED BY FULL TEXT:
52.246-12 Inspection of Construction.
INSPECTION OF CONSTRUCTION (AUG 1996)
(a) Definition."Work" includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.
(b) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The
Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to http://www.gpo.gov/
Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.
(c) Government inspections and tests are for the sole benefit of the Government and do not-
(1) Relieve the Contractor of responsibility for providing adequate quality control measures;
(2) Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;
(3) Constitute or imply acceptance; or
(4) Affect the continuing rights of the Government after acceptance of the completed work under paragraph (i) of this- section.
(d) The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer’s written authorization.
(e) The Contractor shall promptly furnish, at no increase in contract price, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer. The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes reinspection or retest necessary. The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.
(f) The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .