Questions and Answers for Bothell and Denton Antenna Installations-sam.gov.docx

DOCX document 20 KB Posted

Attached to
Updated--Antenna Installations in Bothell, WA and Denton, TX Federal contract opportunity
Solicitation number
04072
Issued by
Federal Emergency Management Agency National Community Section

View the file

Other files for this federal contract opportunity

Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. Can the period of performance extend beyond 90 days for completion for both sites? Yes. Please provide a recommended period of performance when submitting your proposal.

2. Is there a Geotechnical Report available to confirm soil conditions for each site? No

3. Are there any manufacturer provided structural design criteria available for the TCI-613-3 towers, foundations, anchors, and wood pole? Yes, documentation is available at Mount Weather.

4. Will cables need to be removed?

Bothell- F. The contractor will remove and dispose of up to seven (7) unused transmission lines identified and marked by the TM from the cable vault to the antenna side of the bulkhead.

Denton G. The contractor will remove and dispose of two (2) unused transmission lines identified and marked by the TM from cable vault C through cable vault A to the antenna side of the bulkhead. The lines are 265’ in length and will be cut and caped in vault C.

5. The cable entrance into the vault is circled in RED. The manhole that allows human access to the vault is circled in Orange. (Picture attached to solicitation).