Questions and Answers for Bothell and Denton Antenna Installations-sam.gov.docx
DOCX document 20 KB Posted
- Attached to
- Updated--Antenna Installations in Bothell, WA and Denton, TX Federal contract opportunity
- Solicitation number
- 04072
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 2.2.1-RFP_Antenna Installation_SAM_Denton.docx | DOCX document | |
| 2.2.1-RFP_Antenna Installation_SAM_Bothell.docx | DOCX document | |
| 1.1.4 SOW_Bothell TCI Install v.12.docx | DOCX document | |
| 1.4 SOW Denton TCI Install v.13.docx | DOCX document | |
| 2.2.1-RFP_Antenna Installation_SAM_Extension.pdf | ||
| Questions and Answers for Bothell and Denton Antenna Installations-sam.gov.docx | DOCX document | |
| Vault Question Picture.png | PNG image | |
| 2.2 Attachment to RFQ_Davis Bacon Wage Determination_Denton.pdf | ||
| 2.2 Attachment to RFQ_Davis Bacon Wage Determination_Bothell.pdf | ||
| 2.2 Attachment to RFQ_Wage Determination_Denton_updated.pdf | ||
| 2.2 Attachment to RFQ_Wage Determination_Bothell_updated.pdf | ||
| 1.1.4 Bothell and Denton TCI Install SOW_updated.docx | DOCX document | |
| 2.2.1-RFP_Antenna Installation_SAM.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. Can the period of performance extend beyond 90 days for completion for both sites? Yes. Please provide a recommended period of performance when submitting your proposal.
2. Is there a Geotechnical Report available to confirm soil conditions for each site? No
3. Are there any manufacturer provided structural design criteria available for the TCI-613-3 towers, foundations, anchors, and wood pole? Yes, documentation is available at Mount Weather.
4. Will cables need to be removed?
Bothell- F. The contractor will remove and dispose of up to seven (7) unused transmission lines identified and marked by the TM from the cable vault to the antenna side of the bulkhead.
Denton G. The contractor will remove and dispose of two (2) unused transmission lines identified and marked by the TM from cable vault C through cable vault A to the antenna side of the bulkhead. The lines are 265’ in length and will be cut and caped in vault C.