04_Exhibit C_30% Construction Cost Estimate_Granite Street.pdf

PDF 82 KB Posted

Attached to
Downtown Complete Streets Plan - Granite Street Final Design State and local contract opportunity
Solicitation number
RFP_2024_2_23
Issued by
Sedgwick County, Colorado

About this file

This document is a 30% Level Engineers Opinion of Probable Construction Cost prepared by Toole Design Group for the Town of Frisco, Colorado, detailing the Granite Street Reconstruction project from Madison Avenue to Summit Boulevard. The comprehensive cost estimate itemizes approximately 40 distinct construction activities, including clearing and grubbing, tree and sidewalk removal, excavation, pavement work, utility modifications, and infrastructure improvements. The project involves installing new concrete and asphalt pavement, plastic pipes, manholes, inlets, sidewalks, curb ramps, brick pavers, lightposts, signage, and landscaping elements across various specified quantities and unit prices.

The total estimated construction cost is $10,229,000, which includes a breakdown of direct item costs ($5,792,461), additional allocations for right-of-way acquisitions and easements (5%), mobilization (10%), traffic maintenance (10%), construction engineering and inspection (7%), erosion control (5%), and a 25% miscellaneous item allowance. The cost estimate incorporates a 4.5% annual escalation factor and is based on 2022 dollars, with unit costs derived from historical data from CDOT and local bid tabulations. The document explicitly notes that the estimate does not include permitting, inspection, construction management, or ongoing maintenance costs, and Toole Design Group provides no guarantees about the accuracy of the final construction expenses.

View the file

Other files for this state and local contract opportunity

Other files attached to Downtown Complete Streets Plan - Granite Street Final Design, newest first.
File Type Posted
06_Exhibit E_Sample Contract.pdf PDF
Addendum 1_Questions _ Responses_Granite Street Design.pdf PDF
05_Exhibit D_Frisco-Downtown-Complete-Streets-Plan.pdf PDF
03_Exhibit B_30% Stormwater Report_Granite Street.pdf PDF
01_RFP_Downtown Complete Streets Plan_Granite Street Final Design.pdf PDF
02_Exhibit A_30% Design Plans_Granite Street.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT

ITEM NO.

201−00001 CLEARING AND GRUBBING ACRE $25,000.00 2.2 $55,000.00

202−00010 REMOVAL OF TREE EACH $500.00 8 $4,000.00

202−00200 REMOVAL OF SIDEWALK SY $50.00 1,150 $57,500.00

202−00203 REMOVAL OF CURB AND GUTTER LF $10.00 1,970 $19,700.00

202−00210 REMOVAL OF CONCRETE PAVEMENT SY $80.00 2,550 $204,000.00

202−00220 REMOVAL OF ASPHALT MAT SY $15.00 13,980 $209,700.00

202−00700 REMOVAL OF LIGHT STANDARD EACH $1,000.00 9 $9,000.00

202−00810 REMOVAL OF GROUND SIGN EACH $200.00 33 $6,600.00

202−05030 SAWING ASPHALT MATERIAL (10 INCH) LF $5.00 650 $3,250.00

203−00000 UNCLASSIFIED EXCAVATION CY $50.00 6,900 $345,000.00

210−01000 RESET FENCE LF $25.00 25 $625.00

210−04010 ADJUST MANHOLE EACH $1,500.00 4 $6,000.00

210−04015 MODIFY MANHOLE EACH $4,000.00 1 $4,000.00

210−04020 MODIFY INLET EACH $3,000.00 2 $6,000.00

212−xxxxx TREE PROTECTION FENCE LF $7.00 330 $2,310.00

212−00006 SEEDING (NATIVE) ACRE $10,000.00 0.72 $7,200.00

213−00002 MULCHING (WEED FREE HAY) ACRE $3,000.00 0.05 $150.00

214−00240 DECIDUOUS TREE (4 INCH CALIPER) EACH $795.00 107 $85,065.00

304−06007 AGGREGATE BASE COURSE (CLASS 6) CY $65.00 4,400 $286,000.00

403−34631 HOT MIX ASPHALT (GRADING SX) (50) (PG 58−34) TON $145.00 1,870 $271,150.00

403−34721 HOT MIX ASPHALT (GRADING SX) (75) (PG 58−28) TON $175.00 6,830 $1,195,250.00

411−10255 EMULSIFIED ASPHALT (SLOW−SETTING) GAL $10.00 1,620 $16,200.00

412−00600 CONCRETE PAVEMENT (6 INCH) SY $120.00 1,155 $138,600.00

412−00800 CONCRETE PAVEMENT (8 INCH) SY $150.00 50 $7,500.00

603−50018 18 INCH PLASTIC PIPE LF $200.00 330 $66,000.00

603−50024 24 INCH PLASTIC PIPE LF $220.00 2,330 $512,600.00

603−50036 36 INCH PLASTIC PIPE LF $240.00 305 $73,200.00

604−13005 INLET TYPE 13 (5 FOOT) EACH $6,000.00 19 $114,000.00

604−30005 MANHOLE SLAB BASE (5 FOOT) EACH $8,000.00 16 $128,000.00

604−xxxxx WATER QUALITY STRUCTURE EACH $10,000.00 1 $10,000.00

604−50200 MANHOLE RING AND COVER EACH $850.00 17 $14,450.00

608−00000 CONCRETE SIDEWALK SY $98.00 3,110 $304,780.00

608−00010 CONCRETE CURB RAMP SY $220.00 750 $165,000.00

608−00015 DETECTABLE WARNINGS SF $150.00 790 $118,500.00

608−00050 BRICK PAVERS SF $70.00 4,780 $334,600.00

609−21010 CURB AND GUTTER TYPE 2 (SECTION I−B) LF $40.00 2,370 $94,800.00

609−21020 CURB AND GUTTER TYPE 2 (SECTION II−B) LF $50.00 4,490 $224,500.00

613−xxxxx TOWN OF FRISCO STANDARD LIGHTPOST EACH $8,000.00 64 $512,000.00

614−00011 SIGN PANEL (CLASS I) SF $35.00 415 $14,525.00

TOTAL COST

PROJECT TOTALPROJECT TOTAL

UNIT PRICE

TOOLE DESIGN GROUP

October 11, 2023

CONTRACT ITEM UNIT

PLAN AS CONST.

SUMMARY OF APPROXIMATE QUANTITIES

GRANITE STREET RECONSTRUCTION

TOWN OF FRISCO, CO

MADISON AVE TO SUMMIT BLVD

30% LEVEL ENGINEERS OPINION OF PROBABLE CONSTRUCTION COST

PREPARED BY

CONTRACT

ITEM NO.

TOTAL COST

PROJECT TOTALPROJECT TOTAL

UNIT PRICECONTRACT ITEM UNIT

PLAN AS CONST.

614−00216 STEEL SIGNPOST (2X2 INCH TUBING) LF $20.00 670 $13,400.00

625−00000 CONSTRUCTION SURVEYING LS $40,000.00 1 $40,000.00

627−00005 EPOXY PAVEMENT MARKING GAL $260.00 55 $14,300.00

627−00070 PREFORMED THERMOPLASTIC PAVEMENT MARKING SF $80.00 80 $6,400.00

627−30405 PREFORMED THERMOPLASTIC PAVEMENT MARKING (WORD− SYMBOL) SF $80.00 195 $15,606.40

627−30410 PREFORMED THERMOPLASTIC PAVEMENT MARKING (XWALK−STOP LINE) SF $20.00 1,800 $36,000.00

700−xxxxx UTILITY MODIFICATIONS/ADJUSTMENTS LS $20,000.00 1 $20,000.00

700−xxxxx WATER ADJUSTMENTS/RELOCATIONS LS $20,000.00 1 $20,000.00

TOTAL ITEM COSTS $5,792,461

ROW AQUISITIONS AND EASEMENTS 5.0% $289,623

MOBILIZATION 10.0% $579,246

MAINTENANCE OF TRAFFIC 10.0% $579,246

7% CONSTRUCTION ENGINEERING AND INSPECTION 7.0% $405,472

EROSION CONTROL 5.0% $289,623

MISCELLANEOUS ITEM ALLOWANCE 25.0% $1,448,115

SUBTOTAL $9,383,787

YEARS UNTIL CONSTRUCTION 2

ESCALATION (4.5%/YEAR) 4.5% $844,541

TOTAL CONSTRUCTION COST $10,228,328

TOTAL CONSTRUCTION COST (ROUNDED) $10,229,000

This cost opinion was developed by identifying pay items and establishing quantities based on the current 30% Level construction documents. Additional pay items have been assigned based on approximate lump sum prices based on a percentage of the anticipated construction cost. The cost opinion also includes a 25% MISCELLANEOUS ITEM ALLOWANCE to cover items that are unidentified and are typically unknown prior to final design. Unit costs are based on 2022 dollars and were assigned based on historical cost data from CDOT Unit Cost Data for 2022 and 2021-2022 CCD Bid

Tabulations. This cost estimate includes a percentage for easement and cost, based on discussions with the Town and past project experience. This cost opinion does not include permitting, inspection, construction management, or the cost for ongoing maintenance. An approximate escalation based on the information known as of when this estimate was prepared, is included. This cost estimate is provided for the Client’s information, and is based on the design professional’s recent experience, adjusted for factors known at the time of preparation. Toole Design Group, LLC has no control over the cost of labor and material, competitive bidding, or market conditions; and makes no warranties, expressed or implied, concerning the accuracy of this cost opinion as compared to actual bids or cost to the

Client.