This design analysis document outlines the proposed replacement of domestic water pumps and piping at Building 420 at Schriever Air Force Base. The project involves installing a combination of small, medium, and jockey pumps on variable frequency drives to provide water flows between 100 and 600 gallons per minute during normal operation. Three medium pumps will meet maximum day demand plus fire flow requirements, with a fourth identical pump as a standby. The existing diesel fire pump will remain. Pipe sizes will be increased and new valves and fittings installed for maintenance simplicity. Hydraulic modeling was performed to verify pump sizing at targeted distribution pressures of 84 psi normal and 110 psi for fire flow. The contractor must install a new fire department connection in an approved location.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 08 Planning - Project AF 66 Form - GLEN12-1027.xls | XLS spreadsheet | |
| 09 Wage Determination.pdf | ||
| 07 SAFB Environmental Supplement.docx | DOCX document | |
| 05 Existing Conditions Drawing - GLEN12-1027.pdf | ||
| 01 SOW GLEN 12-1027.docx | DOCX document | |
| 03 Requirements - 01 55 04 - SAFB Security Requirements.doc | DOC document | |
| Synopsis GLEN 12-1027.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
LOCATION MAP
SCALE: NONE
N
2315 BRIARGATE
PARKWAY, SUITE 150
COLORADO SPRINGS
COLORADO
DESIGN
REPAIR BY REPLACING DOMESTIC WATER
PUMPS AND PIPING, BUILDING 420
DATE
APPROVED
SAFETY
COMMUNICATIONS
BIO-ENVIRONMENTAL
AE PM
ENVIRONMENTAL
PROGRAMS
OFFICE
AFA PM
FIRE DEPARTMENT
OPERATIONS
CUSTOMER
SIGNATURE
COORDINATION
ENGINEERING
USING AGENCY/
ATO
SECURITY FORCES/
PREPARED FOR
SCHRIEVER AIR FORCE BASE
SECTION 26, TOWNSHIP 14S, RANGE 64W, 6TH P.M.
EL PASO COUNTY, COLORADO
GLEN 12-1027
Sheet
ID
Sheet
D es ig ne r:
R ev ie w er
Fi le
N am e:
D ra fte r
S ub m itt er
D ra w in g D at e:
S A
B F
P ro je ct
M gr
A
-E P ro je ct M gr
S ym b R ev is io ns
/A dd en da
D at e A pp r
S ca le
SCHRIEVER AIR FORCE BASE,
COLORADO
G
LE
N
2-
^G
-0
C O
V R
.D W
G
G-001
X X
X
N . W
A
LK
E R
J.
H
E A
LY
A
S S
H O
W N
/0
1/
S .C
O
LE
N . W
A
LK
E R
R . A
D A
M S
C O
V E
R S
H E
E T
S C
H R
IE
V
E R
A
IR
F O
R C
E B
A S
E R
E P
A
IR
B Y
R E
P
LA
C
IN
G D
O M
E S
T
IC
W A
T E
R P
U M
P S
A N
D P
IP
IN
G G
LE
N
2-
DRAWING
NO. SHEET NO SHEET NAME
1 G-001 COVER SHEET
2 G-002 LEGEND AND NOTES
3 G-003 SITE PLAN AND PUMP STATION BYPASS
4 G-004 PUMP STATION EXISTING CONDITIONS
5 M-001 PUMP STATION DEMOLITION PLAN
6 M-002 PUMP STATION PIPING PLAN
7 M-003 PUMP STATION PIPING SECTIONS
8 M-004 MECHANICAL DETAILS
9 E-001 GENERAL ELECTRICAL SYMBOLS
10 E-002 ELECTRICAL DEMOLITION PLAN
11 E-003 ELECTRICAL PLAN
12 E-004 ELECTRICAL ONE LINE DIAGRAM
13 I-001 INSTRUMENTATION LEGEND
14 I-002 PROCESS & INSTRUMENTATION DIAGRAM
15 I-003 STANDARD OPERATING PROCEDURE
16 I-004 PUMP CONTROL SCHEMATIC
SHEET INDEX
KEPLER AVE
BELTWAY
IRWIN AVE
BELTWAY
FALCON PARKWAY
E N
O C
H R
O A
D
2315 BRIARGATE
PARKWAY, SUITE 150
COLORADO SPRINGS
COLORADO
Sheet
ID
Sheet
D es ig ne r:
R ev ie w er
Fi le
N am e:
D ra fte r
S ub m itt er
D ra w in g D at e:
S A
B F
P ro je ct
M gr
A
-E P ro je ct M gr
S ym b R ev is io ns
/A dd en da
D at e A pp r
S ca le
SCHRIEVER AIR FORCE BASE,
COLORADO
G
LE
N
2-
^G
-0
N O
T.
D
W G
G-002
N . W
A
LK
E
RJ.
H E
A
LY
A S
S H
O W
N
/0 1/
S .C
O
LE
N . W
A
LK
E R
R . A
D A
M S
LE
G E
N D
A N
D N
O
TE
C
H R
IE
V
E R
A
IR
F O
R C
E B
A S
E R
E P
A
IR
B Y
R E
P
LA
C
IN
G D
O M
E S
T
IC
W A
T E
R P
U M
P S
A N
D P
IP
IN
G G
LE
N
2-
TYPICAL ABBREVIATIONS:
SD STORM AND DRAIN LINE
STRL STRUCTURAL
SSP STRUCTURAL SURVEY POINT
SYMM SYMMETRICAL
TAN TANGENT
TECH TECHNICAL
TEL TELEPHONE LINE
TEMP TEMPERATURE
THK THICK
THD THREAD
THRU THROUGH
T&B TOP AND BOTTOM
TC TOP OF CURB
T.O.S TOP OF STEEL
T.O.W TOP OF WALL
TOP TOP OF PIPE
TDH TOTAL DYNAMIC HEAD
TRANSV TRANSVERSE
TR TREAD
TP TURNING POINT
TYP TYPICAL
UGE UNDERGROUND ELECTRIC LINE
UBC UNIFORM BUILDING CODE
UNO UNLESS NOTED OTHERWISE
V VENT, VOLT or VERTICAL
VCP VERIFIED CLAY PIPE
VC VERTICAL CURVE
VERT VERTICAL
VPT VERTICAL POINT OF TANGENCY
WTR WATER
WL WATER LINE
WS WATER SURFACE
WSP WELDED STEEL PIPE
W WEST
W/ WITH
YD YARD
ABV ABOVE
AFF ABOVE FINISH FLOOR
ADDL ADDITIONAL
ADJ ADJUSTABLE
AGGR AGGREGATE
ABC AGGREGATE BASE COARSE
ARV AIR RELIEF VALVE
ALTN ALTERNATE
ACI AMERICAN CONCRETE INSTITUTE
AISC AMERICAN INSTITUTE OF STEEL CONSTRUCTION
ASTM AMERICAN SOCIETY FOR TESTING & MATERIALS
ASCE AMERICAN SOCIETY OF CIVIL ENGINEERS
AWWA AMERICAN WATER WORKS ASSOCIATION
AHR ANCHOR
AB ANCHOR BOLT
& AND
ANG ANGLE
APVD APPROVED
APPROX APPROXIMATE
A AREA
ACP ASPHALTIC CONCRETE PAVEMENT
@ AT
AUTO AUTOMATIC
AUX AUXILIARY
AVG AVERAGE
BV BALL VALVE, BUTTERFLY VALVE
BLW BELOW
BM BENCH MARK
BP BEGINNING POINT
BRG BEARING
BTWN BETWEEN
BF BLIND FLANGE
BOT BOTTOM
A.O. BOTTOM OF
CANT CANTILEVER
CES CIVIL ENGINEER SQUADRON
CEIE CES ENVIRONMENT
CTR CENTER
CTRD CENTERED
℄ CENTERLINE
C TO C CENTER TO CENTER
CC CENTER OF CURVATURE
C CHANNEL
CV CHECK VALVE
CL CLEAR
CO CLEANOUT or COLORADO
CRS COLD ROLLED STEEL
CONC CONCRETE
COL COLUMN
CMU CONCRETE MASONRY UNIT
CONN CONNECTION
CONST CONSTRUCTION
CTN'D CONTINUED
CONT CONTINUOUS
CP CONTROL POINT
COR CONTRACTING OFFICER'S REPRESENTATIVE
COORD COORDINATION
COP. COPPER
CMP CORRUGATED METAL PIPE
CPLG COUPLING
CU CUBIC
CU FT CUBIC FOOT
CU IN CUBIC INCH
CU YD CUBIC YARD
CIPP CURED IN PLACE PIPE
° DEGREES
DESC DESCRIPTION
Ø-DIA DIAMETER
DB DISTRIBUTION BOX
DIR DIRECTION
DN DOWN
DI DROP INLET
DR DRAIN
DCM DRAINAGE CRITERIA MANUAL
DWG DRAWING
DIP DUCTILE IRON PIPE
EA EACH
EW EACH WAY
E EAST, EASTING
EOC EDGE OF CONC
ELECT, ELEC ELECTRIC, ELECTRICAL
EL-ELEV ELEVATION
EP END POINT
EQ. EQL EQUAL
EQ. SPC. EQUALLY SPACED
EQPT EQUIPMENT
EX, EXIST EXISTING
FIMS FACILITY INFORMATION MANAGEMENT SYSTEM
FLG FLANGE
FES FLARED END SECTION
FLR FLOOR
FL FLOWLINE
FO FIBER OPTIC
FLTR FILTER
FIN,FNSH FINISH
FG FINISH GRADE
FIG FIGURE
FTG FOOTING
FT FOOT OR FEET
FWD FORWARD
FDN. FOUNDATION
GAL GALLON
GALS GALLONS
GPD GALLONS PER DAY
GPH GALLONS PER HOUR
GPM GALLONS PER MINUTE
GALV GALVANIZED
GSP GALVANIZED STEEL PIPE
GV GATE VALVE
GA GAUGE
GVL GRAVEL
g GRAVITY
GRND GROUND
HDW HARDWARE
HGT HEIGHT
HDPE HIGH DENSITY POLYETHYLENE
HPT HIGH POINT
HORIZ HORIZONTAL
IN INCH
INSTL INSTALL
INT INTERIOR
IBC INTERNATIONAL BUILDING CODE
ID INSIDE DIAMETER or IDENTIFICATION
INV INVERT
JT JOINT
LF LINEAR FEET
LP LIGHT POLE
LT LIGHT
LOC. LOCATION, LOCATE
LONG LONGITUDINAL
LPT LOW POINT
MH MANHOLE
MFR MANUFACTURER
MAX MAXIMUM
MJ MECHANICAL JOINT
MTL METAL
MGD MILLON GALLONS PER DAY
MIN MINIMUM
MISC MISCELLANEOUS
NEPA NATIONAL ENVIRONMENTAL POLICY ACT
NPDES NATIONAL POLLUTANT DISCHARGE
ELIMINATION SYSTEM
NPW NON-POTABLE WATER
NHWL NORMAL HIGH WATER LEVEL
N NORTH, NORTHING
NE NORTHEAST
NW NORTHWEST
NIC NOT IN CONTRACT
NTS NOT TO SCALE
#-NO NUMBER
OC ON CENTER
OPNG OPENING
OPNGS OPENINGS
OPP OPPOSITE
OZ OUNCE
OD OUTSIDE DIAMETER
OHE OVERHEAD ELECTRIC
OVFL OVERFLOW
% PERCENT
PERF PERFORATED
PL PLATE
PC POINT OF CURVE
POE POINT OF END
PT POINT OF TANGENCY
PI POINT OF INTERSECTION
PVI POINT OF VERTICAL INTERSECTION
PVC POLYVINYL CHLORIDE PLASTIC
PLD POROUS LANDSCAPE DETENTION
POT POTABLE
LBS POUNDS
PCI POUNDS PER CUBIC INCH
PCF POUNDS PER CUBIC FOOT
PSF POUNDS PER SQUARE FOOT
PSI POUNDS PER SQUARE INCH
PSIG POUNDS PER SQUARE INCH, GAUGE
PMJM PREBLE'S MEADOWS JUMPING MOUSE
PREFAB PREFABRICATED
PJF PREMOLDED JOINT FILLER
PRESS PRESSURE
PRI PRIMARY
PROP. PROPERTY
PBM PROJECT BENCHMARK
R, RAD RADIUS
RCP REINFORCED CONCRETE PIPE
RF REINFORCING/REINFORCEMENT
RST REINFORCING STEEL
RDCR REDUCER
ROV REMOTE OPERATED VEHICLE
REQD REQUIRED
ROW RIGHT OF WAY
RPP REINFORCED POLYPROPYLENE
SS SANITARY SEWER LINE
SEC SECONDARY, SECTION
SH SHEET
SIG SIGNAL
SIM SIMILAR
SLP SLOPE
S SOUTH
SE SOUTHEAST
SW SOUTHWEST
SP, SPA SPACE OR SPACING
SPEC SPECIFICATIONS
SPECD SPECIFIED
SQ SQUARE
SQ FT, SF SQUARE FEET
SQ IN SQUARE INCH
STD STANDARDS
SST STAINLESS STEEL
LEGEND:
SECTION LETTER
DETAIL BUBBLE:
DETAIL NUMBER
SHEET ID WHERE
DETAIL IS DRAWN
XXX
XXXXXXXX
SHEET ID WHERE
DETAIL IS CALLED OUT
SECTION BUBBLE:
EXISTING IRRIGATION PIT
EXISTING WATER VALVE
EXISTING WATER MANHOLE
EXISTING SANITARY MANHOLE
EXISTING ELECTRIC MANHOLE
EXISTING LIGHT POLE
EXISTING FIRE HYDRANT
EXISTING SIGN
SURVEY CONTROL MONUMENT
FILL SLOPE
CUT SLOPE
WATER SURFACE
EXST TREE, SHRUB OR GROVE
EXST PAD MOUNTED TRANSFORMER
EXST WATER PRESSURE REDUCING STATION
BH-1, BOREHOLE LOCATION
EXISTING PIEZOMETER LOCATION
LOCATED "PAINT MARK" OR "PIN FLAG" EVIDENCE FOR GAS LINE
LOCATED "PAINT MARK" OR "PIN FLAG" EVIDENCE FOR WATER LINE
LOCATED "PAINT MARK" OR "PIN FLAG" EVIDENCE FOR ELECTRIC LINE
LOCATED "PAINT MARK" OR "PIN FLAG" EVIDENCE FOR FIBER OPTIC LINE
X
CONCRETE
EXISTING CONCRETE
EXISTING UNDERGROUND NON-POTABLE WATER
(APPROXIMATE LOCATION)
PROPOSED UNDERGROUND NON-POTABLE WATER
PROPOSED UNDERGROUND ELECTRIC
(APPROXIMATE LOCATION)
EXISTING UNDERGROUND ELECTRIC
(APPROXIMATE LOCATION)
EXISTING UNDERGROUND GAS MAIN/SERVICE
(APPROXIMATE UNDERGROUND LOCATION)
EXISTING WATER LINE/SERVICE (APPROXIMATE
UNDERGROUND LOCATION)
EXISTING SANITARY SEWER MAIN/SERVICE
(APPROXIMATE UNDERGROUND LOCATION)
EXISTING STORM CULVERT MAIN/SERVICE
(APPROXIMATE UNDERGROUND LOCATION)
EXISTING UNDERGROUND COMMUNICATION LINE
ACCESS ROUTE
APPROXIMATE LIMITS OF DISTURBANCE &
CONSTRUCTION WORK LIMITS
•glm -
•wlm -
•elm -
•fom -
XXX
XXXXXXXX SHEET ID WHERE
SECTION IS DRAWN
SHEET ID WHERE
SECTION IS CALLED OUT
NPW
NPW
EU
E
G
W
SS
SD
COMM
1. ANY WELDING, CUTTING, BRAZING, SOLDERING OR OPEN FLAME
MUST HAVE A BURN PERMIT ISSUED FOR THE SPECIFIC WORK AREA
WHERE WORK IS TO BE PERFORMED.
2. FIRE EXTINGUISHERS MUST BE KEPT OPERATIONAL AND ON HAND
AROUND HEAT PRODUCING EQUIPMENT AT ALL TIMES.
3. FLAMMABLE AND COMBUSTIBLE MATERIAL MUST BE STORED SAFELY
WHEN NOT IN USE AND DURING OPEN FLAME OPERATIONS.
4. WORK SITE MUST BE KEPT NEAT, ALL DEBRIS HAULED AWAY FROM
THE SITE ON A DAILY BASIS OR MORE FREQUENTLY AS NEEDED.
5. SMOKING IS NOT ALLOWED IN OR AROUND THE WORK SITE. THE
CONTRACTOR SHALL COORDINATE A DESIGNATED SMOKING AREA
AS NECESSARY.
6. ALL EMERGENCY REPORTING: DIAL 911.
FIRE PROTECTION NOTES:
GENERAL NOTES:
1. UTILITY LINES ARE PRESENT. THE CONTRACTOR SHALL BE
RESPONSIBLE FOR OBTAINING EXACT LOCATIONS AND ELEVATIONS
OF ALL UTILITIES PRIOR TO CONSTRUCTION. THIS ALSO APPLIES TO
TELECOM, CONDUIT AND EQUIPMENT.
2. CONTRACTOR IS RESPONSIBLE FOR REPLACING ALL PIPING AND
APPURTENANCES IN THE SAME ORIENTATION AS THEY ARE
CURRENTLY SITUATED (I.E., REPLACE "LIKE FOR LIKE").
3. THE AREA OF WORK FOR THIS PROJECT IS SHOWN ON THE PLANS.
CONTRACTOR IS TO MINIMIZE CONSTRUCTION ACTIVITIES AND
DISTURBANCES TO THIS AREA.
4. CONTRACTOR SHALL MEET ALL OF THE REQUIREMENTS SET FORTH
BY OSHA AS WELL AS OTHER REQUIREMENTS SHOWN IN THIS
DRAWING SET, IN THE PROJECT SPECIFICATIONS, AND AS INDICATED
BY THE CONTRACTING OFFICER.
5. CONTRACTOR SHALL BE RESPONSIBLE FOR SETTING TRAFFIC
BARRIERS TO PROPERLY BARRICADE THE WORK AREA.
6. THE CONTRACTOR SHALL SUBMIT FOR REVIEW AND APPROVAL A
TRAFFIC CONTROL PLAN, BY PHASE OF CONSTRUCTION. THE PLAN
SHALL INCLUDE ACCESS ROUTES TO AND FROM THE WORK SITE.
7. CONTRACTOR SHALL BE RESPONSIBLE FOR ALL TESTING,
OBSERVATION, AND INSPECTIONS UNLESS OTHERWISE NOTED.
8. EXCAVATION LIMITS SHOWN ON THESE PLANS ARE APPROXIMATE
BASED ON ESTIMATED SUBSURFACE CONDITIONS. CONTRACTOR IS
RESPONSIBLE FOR ESTABLISHING ACTUAL EXCAVATION LIMITS
BASED ON ENCOUNTERED CONDITIONS AND AS REQUIRED BY OSHA.
9. ALL HAZARDOUS MATERIALS (HMs) USED BY THE CONTRACTOR
MUST BE SUBMITTED, INCLUDING QUANTITIES, TO THE HAZMART ON
ELECTRONIC AF 3952 FORM WITH SDS FOR ENTRY INTO EESOH-MIS
NO LESS THAN 14 DAYS BEFORE BEGINNING CONSTRUCTION.
APPROVAL MUST COME FROM ENVIRONMENTAL AND ALL MATERIALS
LABELED PRIOR TO SAFB ENTRY. ALL UNUSED HM MUST BE
REMOVED BY CONTRACTOR. ALL WORK SHALL COMPLY WITH HMTA,
40 U.S.C. 1801-1819; E.O. 13834; AFI 32-7086; RCRA 42, U.S.C. 6901; 40
CFR SUBCHAPTER 1; CERLA 42 U.S.C. 9601; AFI 32-7042.
10. PERMIT CMD-0777 REQUIRES A 7-DAY NOTICE OF ANY WASTE WATER
DISCHARGE TO INCLUDE TIME, DATE, AMOUNT AND THAT NO
HAZARDOUS SUBSTANCE IS INCLUDED. DO NOT DISCHARGE
ANYTHING TO A DRAIN OR STORM SEWER WITHOUT CONTACTING
ENVIRONMENTAL FIRST.
11. CONTRACTOR MUST USE SAFB's RECYCLING PROGRAM. ANYTHING
RECYCLED OFF-SITE MUST HAVE A RETURNED RECEIPT OF FUNDS
FOR ENVIRONMENTAL FOR RECORD. ALL WORK MUST COMPLY WITH
FAR; EO 13834; RCRA SECTION 6002.
SITE PLAN
SCALE: 1"=30'
N
2315 BRIARGATE
PARKWAY, SUITE 150
COLORADO SPRINGS
COLORADO
Sheet
ID
Sheet
D es ig ne r:
R ev ie w er
Fi le
N am e:
D ra fte r
S ub m itt er
D ra w in g D at e:
S A
FB
P ro je ct M gr
A -E
P ro je ct
M gr
S ym b R ev is io ns
/A dd en da
D at e A pp r
S ca le
SCHRIEVER AIR FORCE BASE,
COLORADO
G
LE
N
2-
^G
-0
P
LN
.D W
G
G-003
N . W
A
LK
E
RJ.
H E
A
LY
A S
S H
O W
N
/0 1/
S . C
O
LE
N . W
A
LK
E R
R . A
D A
M S
S
IT
E P
LA
N
A N
D P
U M
P S
TA
TI
O N
B Y
P A
S S
S C
H R
IE
V
E R
A
IR
F O
R C
E B
A S
E R
E P
A
IR
B Y
R E
P
LA
C
IN
G D
O M
E S
T
IC
W A
T E
R P
U M
P S
A N
D P
IP
IN
G G
LE
N
2-
HORIZONTAL SCALE IN FEET
0 30' 60' 90'
O'MALLEY AVE
D
IS
C O
V E
R E
R S
T
BUILDING 420
WATER PUMPING
FACILITY
WATER STORAGE
TANK NO 1
1.9 MG
WATER STORAGE
TANK NO 2
1.9 MG
INLET VALVE
VAULT
PUMP STA TEMPORARY BYPASS PLAN
NOT TO SCALE
N
1. THE FOLLOWING BYPASS PLAN IS CONCEPTUAL. IT IS UP TO THE
CONTRACTOR TO DETERMINE THE OPTIMAL ROUTE OF THE 12" BYPASS
AROUND THE EXISTING PIPING TO ALLOW FOR CONSTRUCTION
OPERATIONS WHILE MAINTAINING EXISTING FLOW SUPPLY TO THE
WATER DISTRIBUTION SYSTEM.
2. A SHORT, LIMITED SHUTDOWN OF THE SYSTEM IS ALLOWED FOR THE
TEMPORARY BYPASS CONNECTION AND THE FINAL CONNECTION OF THE
PERMANENT PIPING SYSTEM. THE CONTRACTOR WILL WORK WITH THE
CONTRACTING OFFICER TO DEVELOP A CONSTRUCTION WORK PLAN. A
FULL AND COMPLETE PLAN, WHICH INCLUDES THE LENGTH OF
SHUTDOWN TIME REQUIRED FOR THE TEMPORARY BYPASS AND FINAL
CONNECTIONS, WILL BE SUBMITTED TO THE CONTRACTING OFFICER
FOR APPROVAL BEFORE CONSTRUCTION OPERATIONS BEGIN.
3. CONTRACTOR IS RESPONSIBLE FOR MAINTAINING THE FOLLOWING
DISTRIBUTION PRESSURE DURING CONSTRUCTION:
OPERATING PRESSURE : 84 PSIG
FIRE PRESSURE: 110 PSIG
4. EXIST WATER SUPPLY PUMP WS-2 TO REMAIN IN SERVICE TO PROVIDE
WATER DURING TEMP BYPASS OPERATIONS. EXISTING DIESEL FIRE
PUMP FP-3 TO REMAIN IN SERVICE TO PROVIDE FIRE FLOW DURING
TEMP BYPASS OPERATIONS.
5. CONSTRUCT FIELD ROUTED TEMPORARY BYPASS LINE CONNECTING
PUMPS WS-2 AND FP-3 SUCTION AND DISCHARGE. MAINTAIN ALL
APPURTENANCES AND CONTROL TO THESE PUMPS.
6. COORDINATE WITH SAFB TO DRAIN WATER STORAGE TANKS AND
TEMPORARY PUMP STATION SHUTDOWN TO INSTALL THE EXTERIOR
PIPING TO CONNECT TO EXIST SUCTION AND DISCHARGE. INSTALL
ISOLATION VALVES AT SUCTION LINES INTO THE PUMP STATION. WHEN
COMPLETE, PUMP STATION WILL BE OPERATING WITH PUMPS WS-2, FP-3,
WS-7, AND WS-4, EACH.
7. DEMO PUMPS WS-1, FP-1, FP-2, AND FP-3, INCLUDING CONNECTED
PIPING AND APPURTENANCES. INSTALL EQUIPMENT PADS, ALL
PERMANENT PIPING, PUMPS AND APPURTENANCES, ELECTRICAL AND
CONTROL FOR PUMPS MP-1, MP-2, MP-3, SP-1, SP-2 AND JP-4. TEST THE
NEW SYSTEM FOR STARTUP.
8. COORDINATE PUMP STATION SHUTDOWN TO DISCONNECT FLOW FROM
TEMPORARY BYPASS AND CONNECT TO NEW SYSTEM.
9. REPLACE DOMESTIC WATER PUMP WS-2 WITH THE NEW MEDIUM PUMP
MP-4 AND MAKE ANY IMPROVEMENTS AS REQUIRED TO FIRE PUMP FP-3.
10. STARTUP AND TEST NEW MEDIUM PUMP MP-4.
BYPASS OPERATION NOTES
DOMESTIC
WATER PUMP
WS-1, NOTE 3
PIPING PLAN LOWER PIPING PLAN UPPER
EXISTING
DIESEL FIRE
PUMP FP-3,
NOTE 4
NOTE 4
NOTE 4
NOTE 5
NOTE 5
NOTE 5
NOTE 4
SUCTION PIPING
FROM TANK NO 1
SUCTION PIPING
FROM TANK NO 2
TO
DISTRIBUTION
SYSTEM
COLORADO SPRINGS
COLORADO
Sheet
ID
Sheet
D es ig ne r:
R ev ie w er
Fi le
N am e:
D ra fte r
S ub m itt er
D ra w in g D at e:
S A
FB
P ro je ct M gr
A -E
P ro je ct
M gr
S ym b R ev is io ns
/A dd en da
D at e A pp r
S ca le
SCHRIEVER AIR FORCE BASE,
COLORADO
G
LE
N
2-
^G
-0
P
LN
.D W
G
G-004
N . W
A
LK
E
RJ.
H E
A
LY
A S
S H
O W
N
/0 1/
S .C
O
LE
N . W
A
LK
E R
R . A
D A
M S
P U
M P
S
TA
TI
O
N E
X
IS
TI
N
G C
O N
D
IT
IO
N
S
S C
H R
IE
V
E R
A
IR
F O
R C
E B
A S
E R
E P
A
IR
B Y
R E
P
LA
C
IN
G D
O M
E S
T
IC
W A
T E
R P
U M
P S
A N
D P
IP
IN
G G
LE
N
2-
W A
TE
R
S
TO
R A
G E
T A
N K
N O
CIRCULATION
PUMP WS-4 (TO
REMAIN)
"Ø
P W
12"Ø PW
DIESEL FIRE
PUMP FP-3
(TO REMAIN)
HYDROPNUEMATIC
TANKS TK-3/4/5
(TO REMAIN)
JOCKEY PUMP
FP-4 (DEMO)
SUMP PUMPS AND PIPING
(TO REMAIN)
W A
TE
R
S
TO
R A
G E
T A
N K
N O
ELECTRICAL
ROOM
CIRCULATION
PUMP WS-3 (TO
REMAIN)
DOMESTIC
WATER PUMP
WS-1(DEMO)
DOMESTIC
WATER PUMP
WS-2 (DEMO)
"Ø
P W
FIRE PUMP
FP-2 (DEMO)
FIRE PUMP FP-1
(DEMO)
8" Ø
P W
8"Ø
10"Ø
10"Ø
10"Ø
8" Ø
8" Ø
TO SEWER
COLORADO SPRINGS
COLORADO
Sheet
ID
Sheet
D es ig ne r:
R ev ie w er
Fi le
N am e:
D ra fte r
S ub m itt er
D ra w in g D at e:
S A
FB
P ro je ct M gr
A -E
P ro je ct
M gr
S ym b R ev is io ns
/A dd en da
D at e A pp r
S ca le
SCHRIEVER AIR FORCE BASE,
COLORADO
G
LE
N
2-
^M
D -0
P
LN
.D
W G
M-001
N . W
A
LK
E
RJ.
H E
A
LY
A S
S H
O W
N
/0 1/
S .C
O
LE
N . W
A
LK
E R
R . A
D A
M S
P U
M P
S
TA
TI
O
N D
E M
O
LI
TI
O
N P
LA
N
S C
H R
IE
V
E R
A
IR
F O
R C
E B
A S
E R
E P
A
IR
B Y
R E
P
LA
C
IN
G D
O M
E S
T
IC
W A
T E
R P
U M
P S
A N
D P
IP
IN
G G
LE
N
2-
W A
TE
R
S
TO
R A
G E
T A
N K
N O
CIRCULATION
PUMP WS-4 (TO
REMAIN)
"Ø
P W
12"Ø PW
DIESEL FIRE
PUMP FP-3
(TO REMAIN)
HYDROPNUEMATIC
TANKS TK-3/4/5
(TO REMAIN)
JOCKEY PUMP
FP-4 (DEMO)
SUMP PUMPS AND PIPING
(TO REMAIN)
W A
TE
R
S
TO
R A
G E
T A
N K
N O
ELECTRICAL
ROOM
CIRCULATION
PUMP WS-3
(TO REMAIN)
DOMESTIC WATER
PUMP WS-1 (DEMO)
DOMESTIC
WATER PUMP
WS-2 (DEMO)
"Ø
P W
FIRE PUMP
FP-2 (DEMO)
FIRE PUMP FP-1
(DEMO)
8" Ø
P W
8"Ø
10"Ø
10"Ø
10"Ø
8" Ø
8" Ø
'-0
'-0
ITEMS TO BE DEMOLISHED
'-0
1. CONTRACTOR IS RESPONSIBLE FOR SURVEY AND ANALYSIS
OF LEAD BASED PAINT (LBP) PRIOR TO COMMENCING
DEMOLITION OPERATIONS. IF LEAD IS PRESENT,
CONTRACTOR IS RESPONSIBLE FOR MITIGATING ADVERSE
EFFECTS THAT MAY ARISE FROM DEMOLITION OPERATIONS
TO PREVENT INHALATION, INGESTION, OR ANY OTHER
HAZARDS TO WORKERS AND BASE PERSONNEL.
2. CONTRACTOR IS RESPONSIBLE FOR SURVEY OF ASBESTOS
CONTAINING MATERIALS (ACM) PRIOR TO COMMENCING
DEMOLITION OPERATIONS. CONTRACTOR MUST FOLLOW
COLORADO DEPARTMENT OF PUBLIC HEALTH AND
ENVIRONMENT (CDPHE) REQUIREMENTS FOR REMODELING,
RENOVATION, OR DEMOLITION. CDPHE GUIDELINES
REQUIRE PROJECT INSPECTION FOR ACM BY A COLORADO
CERTIFIED ASBESTOS BUILDING INSPECTOR BEFORE
STARTING WORK. CONTRACTOR WILL COORDINATE ALL
ACTIVITIES.
3. SCRAP METAL PRODUCED DURING DEMOLITION
OPERATIONS WILL RELINQUISHED TO 50 CES
ENVIRONMENTAL (CEIE) AS LONG AS LBP OR ACM IS NOT
PRESENT. CEIE MAY REQUEST A METAL RECYCLE VENDOR
PROVIDE 40-CUBIC YARD ROLL-OFF DUMPSTER'S TO
COLLECT DEMOLISHED AND SCRAPPED METAL PIECES
DURING THE DEMOLITION PHASE OF THE PROJECT AND
HAVE THE VENDOR RECYCLE THE COLLECTED SCRAP
METAL. CONTRACTOR WILL COORDINATE AND PAY FOR
THIS SERVICE.
DEMOLITION NOTES:
TO SEWER
EQUIPMENT
PAD (TYP)
2315 BRIARGATE
PARKWAY, SUITE 150
COLORADO SPRINGS
COLORADO
Sheet
ID
Sheet
D es ig ne r:
R ev ie w er
Fi le
N am e:
D ra fte r
S ub m itt er
D ra w in g D at e:
S A
FB
P ro je ct M gr
A -E
P ro je ct
M gr
S ym b R ev is io ns
/A dd en da
D at e A pp r
S ca le
SCHRIEVER AIR FORCE BASE,
COLORADO
G
LE
N
2-
^M
-0
P
LN
.D W
G
M-002
N . W
A
LK
E
RJ.
H E
A
LY
A S
S H
O W
N
/0 1/
S . C
O
LE
N . W
A
LK
E R
R .A
D A
M S
P U
M P
S
TA
TI
O
N P
IP
IN
G P
LA
N
S C
H R
IE
V
E R
A
IR
F O
R C
E B
A S
E R
E P
A
IR
B Y
R E
P
LA
C
IN
G D
O M
E S
T
IC
W A
T E
R P
U M
P S
A N
D P
IP
IN
G G
LE
N
2-
W A
TE
R
S
TO
R A
G E
T A
N K
N O
1. LINES TO BE CONFIRMED DURING DURING
CONSTRUCTION AND REPLACE AT TRANSITION
POINT TO DIP UP TO 10' FROM WALL.
2. SEE SHEET M-003 FOR TABLE OF NUMBERED
CALLOUTS
3. REPLACE ALL APPURTENANCES, AIRVAC VALVES
AND PRESSURE GAUGES ON NEW PIPES TO
MATCH EXISTING.
4. EXISTING FIRE SUPPRESSION SYSTEM TO
REMAIN, RECONNECT TO NEW PIPE SYSTEM AS
REQ'D.
NOTES:
EXISTING
CIRCULATION
PUMP WS-4
"Ø
12"Ø PW
EXISTING
DIESEL FIRE
PUMP FP-3
HYDROPNUEMATIC
TANKS TK-3/4/5
JOCKEY PUMP
JP-4
SUMP PUMPS
TO REMAIN
"Ø
P W
"Ø
12"Ø
W A
TE
R
S
TO
R A
G E
T A
N K
N O
ELECTRICAL
ROOM
EXISTING
CIRCULATION
PUMP WS-3
"Ø
SMALL
PUMP SP-2
SMALL
PUMP SP-1
"Ø
P W
"Ø
P W
8"Ø
"Ø
8" Ø
8" Ø
8" Ø
6"Ø
8" Ø
8" Ø
8"Ø
'-0
4"Ø
8"Ø
8"Ø
3'-6"
1'-0"
6"Ø
6"Ø
'-0
HYDROPNUEMATIC
TANKS TK-3/4/5
SMALL PUMP
SP-1
DISCHARGE
SMALL PUMP
SP-2
DISCHARGE
12'-0"32'-0"
'-0
9' -6
'-6
8'
-6
6' -3
6'
-3
6' -1
'-0
2'-6"
3' -7
'-0
'-8
1' -3
4'
-7
9' -9
9'
-6
CHLORINATION
ROOM
FIN FLOOR
111'-0"
EXISTING
CIRCULATION
PUMP WS-4
EXISTING
DIESEL FIRE
PUMP FP-3
EXISTING CIRCULATION
PUMP WS-3
FU
E
L
TA
N K
ELECTMEDIUM
PUMP MP-1
6"Ø
6"Ø
6"Ø
6" Ø
3" Ø
EQUIPMENT
PAD
M-004
M-004
8"Ø TO FIRE PUMP
TEST CONNECTION
MEDIUM
PUMP MP-2
MEDIUM
PUMP MP-3
MEDIUM
PUMP MP-4
MEDIUM
PUMP MP-1
MEDIUM
PUMP MP-2
MEDIUM
PUMP MP-3
MEDIUM
PUMP MP-4
SEE NOTE 4
8" Ø
P W
4"Ø PW
4"Ø PW
A M
-0
'-0
A M
-0
B M
-003
B M
-003
C M-003
6" Ø
3" Ø
NEW PIPE
(SEE NOTE 1)
D M
-0 03 D
M -0
TO SANITARY
SEWER MH
CONNECT TO
EXIST DIP
ARV (TYP)
2 4
8" Ø
P E
R M
A N
E N
T B
Y P
A S
S
4' -0
ELECTRICAL
EQUIPMENT, SEE
SHEET E-003
10 10
4 24
E M-003
E M-003
27 28
27 28
27 28
5'-10"
3'-0"
6'-9"
SEE NOTE 4
AIRVAC, SEE
NOTE 3 (TYP)
CATHODIC PROTECTION,
SEE DETAIL 9, SHEET M-004
CONNECT TO
EXIST DIP
12"Ø
TO DISTRIBUTION
SYSTEM
8"Ø PERMANENT
BYPASS
8"Ø PERMANENT
BYPASS FROM
TK-2 TO MP-1
FROM TK-2
TO WS-3
FROM FP-3
TO TK-2
FROM WS-3
TO TK-2
FROM TK-2
CATHODIC PROTECTION,
SEE DETAIL 9, SHEET M-004
CATHODIC PROTECTION,
SEE DETAIL 9, SHEET M-004
FROM TK-1
FROM WS-4 TO TK-1
FROM TK-1 TO WS-4
FROM FP-3 TO TK-1
COLORADO SPRINGS
COLORADO
Sheet
ID
Sheet
D es ig ne r:
R ev ie w er
Fi le
N am e:
D ra fte r
S ub m itt er
D ra w in g D at e:
S A
FB
P ro je ct M gr
A -E
P ro je ct
M gr
S ym b R ev is io ns
/A dd en da
D at e A pp r
S ca le
SCHRIEVER AIR FORCE BASE,
COLORADO
G
LE
N
2-
^M
-0
S E
C .D
W G
M-003
N . W
A
LK
E
RJ.
H E
A
LY
A S
S H
O W
N
/0 1/
S . C
O
LE
N . W
A
LK
E R
R .A
D A
M S
P U
M P
S
TA
TI
O
N P
IP
IN
G S
E C
TI
O
N S
S C
H R
IE
V
E R
A
IR
F O
R C
E B
A S
E R
E P
A
IR
B Y
R E
P
LA
C
IN
G D
O M
E S
T
IC
W A
T E
R P
U M
P S
A N
D P
IP
IN
G G
LE
N
2-
1. SEE SHEET M-002 FOR NUMBERED CALLOUT
LOCATIONS.
NOTES:
EXISTING
CIRCULATION
PUMP WS-4
8"Ø
EXISTING
CIRCULATION
PUMP WS-3
SMALL
PUMP SP-2
SMALL
PUMP SP-1
MEDIUM
PUMP MP-1
MEDIUM
PUMP MP-2
PUMP STATION SECTION
SCALE: 1/4" =1'-0"
A M-002
PUMP STATION SECTION
SCALE: 1/4" =1'-0"
B M-002
12"Ø
12"Ø
MEDIUM
PUMP MP-3
MEDIUM
PUMP MP-4
6"Ø
116'-0"
111'-5"
109'-8"
107'-0"
102'-8"
T.O. FLOOR 100'-0"
8"Ø
8"Ø
EXISTING
DIESEL FIRE
PUMP FP-3
FUEL TANK
ELECT
102'-8"
111'-5"
DRESSER
COUPLINGS OR
EQUAL
PUMP STATION SECTION
SCALE: 1/4" =1'-0"
C M-002
10"Ø
8"Ø
12"Ø
12"Ø
METER
111'-5"
102'-8"
105'-8"
105'-8"
3"Ø
6"Ø
8"Ø
12"Ø
12"Ø
TK-5
JOCKEY
PUMP J-4
TK-4TK-3
4"Ø2"Ø
JOCKEY
PUMP J-4
6"Ø3"Ø
113'-0"
109'-8"
107'-8"
102'-8"
109'-8"
105'-8"
PCV PIPE DETAIL
SECTION
SCALE: 1/4" =1'-0"
D M-002
UPPER
PIPING PLAN
108'-0"
LOWER
PIPING PLAN
113'-0"
UPPER
PIPING PLAN
108'-0"
LOWER
PIPING PLAN
113'-0"
UPPER
PIPING PLAN
108'-0"
LOWER
PIPING PLAN
ARV (TYP)
SUMP
(BEYOND)
8"Ø BYPASS
6"Ø 6"Ø
6"Ø 8"Ø BYPASS
107'-8"
105'-8"105'-8"
105'-8"
EQUIPMENT LIST
ITEM DESCRIPTION
12"Ø DRESSER STYLE ELECTRICALLY
ISOLATED COUPLING
EXIST 12"Ø WALL SLEEVE
12"Ø ELECTRICALLY ISOLATED COUPLING
12"Ø BFV
12"Ø CHECK VALVE
8"Ø BVF
3"Ø PRESSURE CONTROL VALVE
3"Ø OR 6"Ø BFV
4"Ø EXPANSION JOINT
VALVE AND CONNECTION TO EXIST
HYDROPNUEMATIC TANKS AS REQUIRED
NEW PIPE AND VALVES TO CONNECT TO
JOCKEY PUMP, MATCH EXISTING
6"Ø BFV
CONNECT TO EXIST FIRE PUMP AS
REQUIRED
8"Ø DRESSER STYLE ELECTRICALLY
ISOLATED COUPLING
EXIST 8"Ø WALL SLEEVE
CORE DRILL AND WALL SLEEVE FOR 8"Ø
BYPASS
8"Ø ELECTRICALLY ISOLATED COUPLING
6"Ø EXPANSION JOINT
PRESSURE GAUGE W/ CONNECTION
DIELECTRIC UNION AND VALVE TO MATCH
EXIST
MAGNETIC FLOW METER
12"Ø WAFER CHECK VALVE
2" CAV WITH 1/2" ORIFICE
8"Ø 90° BEND AND 12"x12"x8" TEE ROTATED
AS REQUIRE TO ALIGN PIPE CONNECTIONS
8"Ø GATE VALVE
PRESSURE RELIEF VALVE, MIN 2.5 SQ IN.
ORIFICE
8"Øx4"Ø REDUCER
4"Ø FLANGED RESTRAINED COUPLING
ADAPTOR
3"Ø FLANGED RESTRAINED COUPLING
ADAPTOR
4"Ø CHECK VALVE
3"Ø CHECK VALVE
4"Ø BUTTERFLY VALVE
12"Ø EXPANSION JOINT
1.5" CAV WITH 1/8" ORIFACE
T.O. FLOOR
100"-0"
102'-8"
109'-8"
105'-8"
107'-8"
111'-5"
T.O. FLOOR
100"-0"
SECTION
SCALE: 1/4" =1'-0"
E M-002
MEDIUM
PUMP MP-1
6"Ø
6"Ø
12"Ø
8"Ø
PCV PIPING
12"Ø
8"Ø
8"Ø
4"Ø
3" Ø
4" Ø 4" Ø
T.O. FLOOR
100"-0"
34 34 34
COLORADO SPRINGS
COLORADO
Sheet
ID
Sheet
D es ig ne r:
R ev ie w er
Fi le
N am e:
D ra fte r
S ub m itt er
D ra w in g D at e:
S A
FB
P ro je ct M gr
A -E
P ro je ct
M gr
S ym b R ev is io ns
/A dd en da
D at e A pp r
S ca le
SCHRIEVER AIR FORCE BASE,
COLORADO
G
LE
N
2-
^M
-0
D E
T.
D
W G
M-004
N . W
A
LK
E
RJ.
H E
A
LY
A S
S H
O W
N
/0 1/
S . C
O
LE
N . W
A
LK
E R
R .A
D A
M S
M E
C H
A N
IC
A
L D
E
TA
IL
S
S C
H R
IE
V
E R
A
IR
F O
R C
E B
A S
E R
E P
A
IR
B Y
R E
P
LA
C
IN
G D
O M
E S
T
IC
W A
T E
R P
U M
P S
A N
D P
IP
IN
G G
LE
N
2-
EQUIPMENT PAD DETAIL
NOT TO SCALE
M-002
PIPE BEDDING DETAIL
NOT TO SCALE
PROPOSED
WALL SLEEVE
NOT TO SCALE
AIR RELEASE VALVE
INSTALLATION
NOT TO SCALE
PRESSURE GAUGE
NOT TO SCALE
PRESSURE GAUGE W/SWITCH
OR TRANSMITTER
NOT TO SCALE
INSULATING GASKET
NOT TO SCALE
TYPICAL
PIPE SUPPORT
NOT TO SCALE
CATHODIC PROTECTION
NOT TO SCALE
MINIMUM 18" OF
SLACK IN WIRES
FOR SETTLEMENT
AND MOVEMENT
2.
5'
TESTOX 900
7 TERMINAL
TEST STATION
3" SCH 40 GALV.
STEEL PIPE
CONC PAD
12"
3" INSULATED END
BUSHING
PIPE AND ANODE
LEADS
PUMP STATION
SEE SHEET M-002
8' -0
1' -0
THERMITE WELD
& HANDY CAP (TYP)
CONNECT TO
PIPE BELOW
9 LB HIGH
POTENTIAL
MAGNESIUM
ANODE
ANODE LEAD #1
3'-0"
ANODE LEAD #2
CATHODIC
TEST STA
NORTH
4'-0"
PIPE LEAD #2
3'-0"
THERMITE WELD &
HANDY CAP
PIPE LEAD #5, SEE
NOTE 1
ANODE LEAD #3
NORTH TERMINAL
BOARD LAYOUT
2.
5'
PIPE LEADS #1B,
2B,3B,4B
ANODE LEAD #1
AND #2
9 LB HIGH
POTENTIAL
MAGNESIUM
ANODE
9 LB HIGH POTENTIAL
MAGNESIUM ANODE
CATHODIC
TEST STA
SOUTH
4'-0"
PIPE LEAD #4A
PIPE LEAD #3A
PIPE LEAD #1A
PIPE LEAD #2A
ANODE LEAD #3
PIPE LEAD #5A
PIPE LEAD #5B
0.1 OHM SHUNT
0.1 OHM SHUNT
NOTE:
1. EACH PIPELINE HAS 2 WIRES, A AND B
PIPE LEAD #4,
SEE NOTE 1
PIPE LEAD #1, SEE NOTE 1
PIPE LEAD #2, SEE NOTE 1
PIPE LEAD #3, SEE NOTE 1
COLORADO SPRINGS
COLORADO
Sheet
ID
Sheet
D es ig ne r:
R ev ie w er
Fi le
N am e:
D ra fte r
S ub m itt er
D ra w in g D at e:
S A
FB
P ro je ct M gr
A -E
P ro je ct
M gr
S ym b R ev is io ns
/A dd en da
D at e A pp r
S ca le
SCHRIEVER AIR FORCE BASE,
COLORADO
G
LE
N
2-
^E
-0
L E
G .D
W G
E-001
N . W
A
LK
E
RJ.
H E
A
LY
A S
S H
O W
N
/0 1/
S . C
O
LE
N . W
A
LK
E R
K . S
P R
R O
W
G E
N E
R A
L E
LE
C
TR
IC
A L
S Y
M B
O
LS
S C
H R
IE
V
E R
A
IR
F O
R C
E B
A S
E R
E P
A
IR
B Y
R E
P
LA
C
IN
G D
O M
E S
T
IC
W A
T E
R P
U M
P S
A N
D P
IP
IN
G G
LE
N
2-
DATA OUTLET, WALL MOUNTED (#
REFERS TO QUANTITY IF MORE
THAN ONE)
LT/C
POLE MOUNTED LIGHT WITH CONCRETE BASE
HOME RUN WITH 1 NEUTRAL, 1
HOT, 1 GROUND
POLE MOUNTED LUMINAIRE
ENCASED DUCT
PRIMARY POWER CIRCUIT IN CONCRETE
PRIE UNDERGROUND ELECTRICAL
E UNDERGROUND ELECTRICAL
C UNDERGROUND COMMUNICATIONS DUCTS
a
T THERMOSTAT
ELECTRIC WATER COOLEREWC
1 = INDICATES NEMA STARTER SIZE
MAGNETIC STARTER
30A = INDICATES DISCONNECT RATING
1 = INDICATES NEMA STARTER SIZE
COMBINATION MAGNETIC STARTER
30A
CONNECTION POINT
MANUAL OR AUTOMATIC TRANSFER SWITCH
DRAWOUT BREAKER
FUSE, RATING AS NOTED
AT = TRIP RATING IN AMPERES
AF = FRAME RATING IN AMPERES
CIRCUIT BREAKER
DISCONNECT SWITCH, RATED AS NOTED100A
100AT
100AF
TRANSFORMER, DELTA-WYE CONNECTION
ONE-LINE DIAGRAM
FIRE ALARM ANNUNCIATOR PANEL
END OF LINE RESISTOR
PRESSURE SWITCH
FLOW SWITCH
TAMPER SWITCH
SMOKE DETECTOR
COMBINATION TYPE, CEILING MOUNTED
FIRE ALARM HEAT DETECTOR,
WALL MOUNTED
FIRE ALARM FLASHING STROBE LIGHT,
WALL MOUNTED
FIRE ALARM HORN/STROBE, ONE ASSEMBLY,
WALL MOUNTED
DUCT DETECTOR
FIRE ALARM BELL, WALL MOUNTED
FIRE ALARM MANUAL PULL STATION,
FIRE ALARM CONTROL PANEL
FIRE ALARM SYSTEM
INTERCOM OUTLET, WALL MOUNTED
IN FLOOR BOX (1 VOICE; 2 DATA JACKS)
COMBINATION TELEPHONE/DATA OUTLET,
WALL MOUNTED (1 VOICE; 2 DATA JACKS)
CCTV CAMERA, WALL MOUNTED
TELEPHONE OUTLET, WALL MOUNTED
COMBINATION TELEPHONE/DATA OUTLET,
ABBREVIATIONSSYMBOLS
COMMUNICATIONS/SPECIAL SYSTEMS
JUNCTION BOX, FLUSH IN FLOOR
JUNCTION BOX, WALL MOUNTED
JUNCTION BOX, RECESSED/CEILING MOUNTED
RATING AS NOTED)
SPECIAL PURPOSE RECEPTACLE, GROUNDING
TYPE, CEILING MOUNTED (NEMA TYPE & AMP
RATING AS NOTED)
SPECIAL PURPOSE RECEPTACLE, GROUNDING
TYPE, WALL MOUNTED (NEMA TYPE & AMP
20A, 120V, DOUBLE DUPLEX RECEPTACLE,
IN FLOOR BOX
20A, 120V, DOUBLE DUPLEX RECEPTACLE,
CEILING MOUNTED
20A, 120V, DOUBLE DUPLEX RECEPTACLE
20A, 120V, DUPLEX RECEPTACLE,
IN FLOOR BOX
20A, 120V, DUPLEX RECEPTACLE,
CEILING MOUNTED
WEATHERPROOF COVER
20A, 120V, GROUND FAULT CIRCUITGFCI
WP INTERRUPTER DUPLEX RECEPTACLE WITH
20A, 120V, DUPLEX RECEPTACLE
20A, 120V, SIMPLEX RECEPTACLE
RECEPTACLES/J-BOXES
GROUNDING BUS BAR
GROUNDING ROD
GROUND CONNECTION
EXOTHERMIC WELD
CONNECTION POINT
AIR TERMINAL
GROUNDING/LIGHTNING PROTECTION
MOTOR, NUMBER INDICATES HORSEPOWER
POWER PANELBOARD
LIGHTING PANELBOARD
PP-x
PANELBOARDS/POWER EQUIPMENT
PAD MOUNTED TRANSFORMER
LP-x
CEILING SPEAKER, FLUSH MOUNTED
WALL MOUNTED SPEAKER
WP = WEATHERPROOFWP
EXTERIOR PUBLIC ADDRESS SPEAKER
NUMBER INDICATES SWITCH SIZE
NON-FUSIBLE DISCONNECT SWITCH,
FUSIBLE DISCONNECT SWITCH
MOTION DETECTOR
a LOWER CASE LETTER DENOTES CONTROL
SINGLE POLE SWITCH, 20A, 120/277V,
SENSOR (LIGHTING)
CEILING MOUNTED ULTRASONIC OCCUPANCYOS
MOTION DETECTOR
OVERRIDE SWITCH (LIGHTING)
WALL MOUNTED OCCUPANCY SENSOR WITH
TYPE) UNLESS OTHERWISE NOTED
DIMMER SWITCH, 1500 WATT (FLUORESCENT
OVERLOAD PROTECTION
MOTOR RATED SWITCH, WITH THERMAL
FOUR-WAY SWITCH, 20A, 120/277V
THREE-WAY SWITCH, 20A, 120/277V
SWITCHES
LIGHTING
RECHARGEABLE TYPE
EMERGENCY LIGHT FIXTURE,
WALL MOUNTED EXIT LIGHT
X
X
EXIT LIGHT
CEILING MOUNTED SINGLE FACE X
ARROW DENOTES DIRECTIONAL ARROWS
LIGHT, LETTER DENOTES FIXTURE TYPE,
CEILING MOUNTED DOUBLE FACE EXIT
FIXTURE TYPE
LIGHT FIXTURE, LETTER DENOTES
WALL MOUNTED INCANDESCENT
LETTER DENOTES FIXTURE TYPE
INCANDESCENT LIGHT FIXTURE,
RECESSED OR CEILING MOUNTED
FIXTURE TYPE, SUBSCRIPT INDICATES CONTROL
A
A
A
A
LIGHT FIXTURE, LETTER DENOTES
CEILING OR PENDANT MOUNTED
BATTERY PACK
EMERGENCY BALLAST OR EMERGENCY
1'X4' FLUORESCENT LIGHT FIXTURE WITH
BATTERY PACK
EMERGENCY BALLAST OR EMERGENCY
2'X4' FLUORESCENT LIGHT FIXTURE WITH
a = SWITCH CONTROLLING FIXTURE
1 = CIRCUIT NUMBER
A = FIXTURE TYPE
2'X2' FLUORESCENT LIGHT FIXTURE
LIGHT FIXTURE
1'X4' WALL MOUNTED FLUORESCENT
a = SWITCH CONTROLLING FIXTURE
1 = CIRCUIT NUMBER
A = FIXTURE TYPE
1'X4' FLUORESCENT LIGHT FIXTURE
a = SWITCH CONTROLLING FIXTURE
1 = CIRCUIT NUMBER
A = FIXTURE TYPE
2'X4' FLUORESCENT LIGHT FIXTURE
MD
OS
A
1, a
A
A
1, a
1, a
A
F
UH UNIT HEATER
HPS HIGH PRESSURE SODIUM
DPI DOMESTIC WATER PUMP PR PAIR
MI MOTOR INDICATOR
M METER
LAN LOCAL AREA NETWORK
GRS GALAVANIZED RIDGID STEEL
LC CENTER LINE
AWG AMERICAN WIRE GAUGE
A AMPERE
CB
C
BC BARE COPPER
CONDUIT
AIC
A.F.F. ABOVE FINISHED FLOOR
AMPERES INTERRUPTING CAPACITY
CIRCUIT BREAKER
CU
CT
COPPER
CIRCUITCKT
FA FIRE ALARM
EMH
EMCS
GFCI
GROUND
HH HANDHOLE
HPF
HID
GND
KILOWATT-HOUR
KCMIL
KWH
KVA
INCAND
ELECTRICAL MANHOLE
THOUSAND CIRCULAR MILLS
GROUND FAULT CIRCUIT INTERRUPTER
CURRENT TRANSFORMER
ENERGY MONITORING & CONTROL SYSTEM
HIGH INTENSITY DISCHARGE
HIGH POWER FACTOR
INCANDESCENT
KILOVOLT AMPERE
LP
MAXIMUM
MDP
MC
MAX
O/L OVERLOAD
PB
PA
PULL BOX
N/A
RM
PP
ROOM
ST
RP
SHORT TIME
RGS
PVC
RMS
RSC
T
TC
TVSS
UON
TTB
SYMMETRICALSYM
PT
RIGID GALVANIZED STEEL
POLYVINYL CHLORIDE
ROOT MEAN SQUARE
TRANSIENT VOLTAGE SURGE
TRANSFORMER
POWER PANEL / POWER POLE
RECEPTACLE PANEL
MAIN DISTRIBUTION PANELBOARD
LIGHTING PANEL
MOTOR CONTROL
NOT APPLICABLE
PUBLIC ADDRESS
POTENTIAL TRANSFORMER
RIGID STEEL CONDUIT
TERMINAL CABINET
TELEPHONE TERMINAL BOARD
UNLESS OTHERWISE NOTED
V VOLT
W WATT
WP
XFMR
XP
TRANSFORMER
WEATHERPROOF
EXPLOSION PROOF
LT LONG TIME
NOTES:
CAV COMBINATION AIR VALVE
FACP FIRE ALARM CONTROL PANEL
FE FLOW ELEMENT
FI FLOW INDICATOR
FIT FLOW EDICATOR TRANSMITTER
FQI FLOW EDICATOR TRANSMITTER
HOA HIGH POWER FACTOR
MCC MOTOR CONTROL CENTER
MA MOTOR ALARM
mm MILLIMETER
NC NORMALLY CLOSED
NO NORMALLY OPEN
OH OVERHEAD
O/L OVERLOAD
O/O ON/OFF
LOR LOCAL OFF REMOTE
PAH PRESSURE ALARM HIGH
PI PRESSURE INDICATOR
PIT PRESSURE INDICATOR TRANSMITTER
PAL PRESSURE ALARM LOW
PSH PRESSURE SWITCH HIGH
PSL PRESSURE INDICATOR TRANSMITTER
PSV PRESSURE SAFETY VALVE
PW POTABLE WATER
SIC SPEED INDICATING CONTROL
SOP STANDARD OPERATING PROCEDURE
START/STOPS/S
HS HAND SWITCH
VAV VACUUM AIR VALVE
XA EVENT ALARM
SUPPRESSION & FILTERING
TSP TWISTED SHIELDED PAIR
1. MINIMUM POWER CABLE SIZE FOR THIS INSTALLATION SHALL BE
#12 AWG.
2. MINIMUM CONDUIT SIZE IS 3 /4".
3. NFPA 20 STANDARD FOR INSTALLATION OF STATIONARY PUMPS
FOR FIRE PROTECTION IS NOT APPLICABLE TO THE DOMESTIC
PUMPS IN BUILDING 420. IN ACCORDANCE WITH EXPLANATORY
MATERIAL CONTAINED IN NFPA 20 ARTICLE A.4.7.1, THE
DOMESTIC PUMPS IN THIS PUMP STATION ARE NOT CLASSIFIED
AS FIRE PUMPS. FURTHERMORE, NOT BEING CLASSIFIED AS
FIRE PUMPS, THE ARTICLE STATES THAT DOMESTIC PUMPS ARE
NOT EXPECTED TO MEET THE REQUIREMENTS OF THE NFPA 20
STANDARD REGARDING FIRE PUMPS.
4. THE EXISTING FIRE PUMP IS NOT BEING MODIFIED AND IS
OUTSIDE THE SCOPE OF THIS PROJECT. AS SUCH UFC 3-600-01
DOES NOT APPLY TO THIS PROJECT AND IT DOES NOT REQUIRE
REVIEW BY A FIRE PROTECTION ENGINEER.
COLORADO SPRINGS
COLORADO
Sheet
ID
Sheet
D es ig ne r:
R ev ie w er
Fi le
N am e:
D ra fte r
S ub m itt er
D ra w in g D at e:
S A
FB
P ro je ct M gr
A -E
P ro je ct
M gr
S ym b R ev is io ns
/A dd en da
D at e A pp r
S ca le
SCHRIEVER AIR FORCE BASE,
COLORADO
G
LE
N
2-
^E
-0
D P
LN
.D
W G
E-002
N . W
A
LK
E
RJ.
H E
A
LY
A S
S H
O W
N
/0 1/
S .C
O
LE
N . W
A
LK
E R
K . S
P A
R R
O W
E
LE
C
TR
IC
A
L D
E M
O
LI
TI
O
N P
LA
N
S C
H R
IE
V
E R
A
IR
F O
R C
E B
A S
E R
E P
A
IR
B Y
R E
P
LA
C
IN
G D
O M
E S
T
IC
W A
T E
R P
U M
P S
A N
D P
IP
IN
G G
LE
N
2-
CIRCULATION
PUMP WS-4
"Ø
P W
12"Ø PW
DIESEL FIRE
PUMP FP-3
HYDROPNUEMATIC
TANKS TK-3/4/5
JOCKEY PUMP
FP-4
SUMP PUMPS
W A
TE
R
S
TO
R A
G E
T A
N K
N O
ELECTRICAL
ROOM
CIRCULATION
PUMP WS-3
DOMESTIC
WATER PUMP
WS-1
DOMESTIC
WATER PUMP
WS-2
"Ø
P W
FIRE PUMP
FP-2
FIRE PUMP
WS-1
ITEMS TO BE DEMOLISHED
1. SEE M-001 FOR MECHANICAL DEMOLITION.
NOTE:
MCC F2
FIRE PUMP
CONTROLLER WS-2
VFD-125
VFD-126
PDP-FP
FIRE PUMP
CONTROLLER WS-1
FIRE ENGINE PUMP
CONTROLLER
TANK CP
DISCONNECT
STARTER WS-4 1. CONTRACTOR IS RESPONSIBLE FOR SURVEY AND ANALYSIS
OF LEAD BASED PAINT (LBP) PRIOR TO COMMENCING
DEMOLITION OPERATIONS. IF LEAD IS PRESENT,
CONTRACTOR IS RESPONSIBLE FOR MITIGATING ADVERSE
EFFECTS THAT MAY ARISE FROM DEMOLITION OPERATIONS
TO PREVENT INHALATION, INGESTION, OR ANY OTHER
HAZARDS TO WORKERS AND BASE PERSONNEL.
2. CONTRACTOR IS RESPONSIBLE FOR SURVEY OF ASBESTOS
CONTAINING MATERIALS (ACM) PRIOR TO COMMENCING
DEMOLITION OPERATIONS. CONTRACTOR MUST FOLLOW
COLORADO DEPARTMENT OF PUBLIC HEALTH AND
ENVIRONMENT (CDPHE) REQUIREMENTS FOR REMODELING,
RENOVATION, OR DEMOLITION. CDPHE GUIDELINES
REQUIRE PROJECT INSPECTION FOR ACM BY A COLORADO
CERTIFIED ASBESTOS BUILDING INSPECTOR BEFORE
STARTING WORK.
3. SCRAP METAL PRODUCED DURING DEMOLITION
OPERATIONS WILL BE RELINQUISHED TO 50 CES
ENVIRONMENTAL (CEIE) AS LONG AS LBP OR ACM IS NOT
PRESENT. CEIE MAY REQUEST A METAL RECYCLE VENDOR
PROVIDE 40-CUBIC YARD ROLL-OFF DUMPSTER'S TO
COLLECT DEMOLISHED AND SCRAPPED METAL PIECES
DURING THE DEMOLITION PHASE OF THE PROJECT AND
HAVE THE VENDOR RECYCLE THE COLLECTED SCRAP
METAL.
DEMOLITION NOTES:
COLORADO SPRINGS
COLORADO
Sheet
ID
Sheet
D es ig ne r:
R ev ie w er
Fi le
N am e:
D ra fte r
S ub m itt er
D ra w in g D at e:
S A
FB
P ro je ct M gr
A -E
P ro je ct
M gr
S ym b R ev is io ns
/A dd en da
D at e A pp r
S ca le
SCHRIEVER AIR FORCE BASE,
COLORADO
G
LE
N
2-
^E
-0
P
LN
.D W
G
E-003
N . W
A
LK
E
RJ.
H E
A
LY
A S
S H
O W
N
/0 1/
S . C
O
LE
N . W
A
LK
E R
K . S
P R
R O
W
E
LE
C
TR
IC
A
L P
LA
N
S C
H R
IE
V
E R
A
IR
F O
R C
E B
A S
E R
E P
A
IR
B Y
R E
P
LA
C
IN
G D
O M
E S
T
IC
W A
T E
R P
U M
P S
A N
D P
IP
IN
G G
LE
N
2-
EXISTING
CIRCULATION
PUMP WS-4
"Ø
12"Ø PW
EXISTING
DIESEL FIRE
PUMP FP-3
HYDROPNUEMATIC
TANKS TK-3/4/5
JOCKEY PUMP
JP-4
SUMP PUMPS
"Ø
P W
"Ø
W A
TE
R
S
TO
R A
G E
T A
N K
N O
ELECTRICAL
ROOM
EXISTING
CIRCULATION
PUMP WS-3
"Ø
WATER PUMP VFD MP-4
SMALL
PUMP SP-1
4"Ø
8"Ø
8"Ø
6"Ø
6"Ø
FU
E
L
TA
N K
ELECT
MEDIUM
PUMP MP-1
PRESSURE
CONTROL
VALVE
3" Ø
MEDIUM
PUMP MP-2
MEDIUM
PUMP MP-3
MEDIUM
PUMP MP-4
DRESSER
COUPLINGS OR
EQUAL
1. VFD DESIGN BASED ON ABB ACTIVE FRONT END
DRIVE ACQ800. COORDINATE ACTUAL DIMENSIONS
WITH FIELD CONDITIONS AND MANUFACTURERS
EQUIPMENT SUBMITTALS.
2. CONFIRM EXISTING EQUIPMENT LOCATIONS AND
AVAILABLE SPACE PRIOR TO DEMOLITION OF
EXISTING EQUIPMENT AND INSTALLATION OF NEW
EQUIPMENT.
3. ONLY NEW PLC CONNECTIONS SHOWN.ALL
EXISTING PLC CONNECTIONS TO REMAIN, EXCEPT
AS REMOVED WITH MOTOR STARTER DEMOLITION.
4. CONTROL WIRING INFORMATION BETWEEN THE
NEW PUMP VFD'S AND THE ATCC PANEL IS
PROVIDED FOR THE BASE'S USE IN INTEGRATING
THE VFD'S INTO THE ATCC SYSTEM. INTEGRATION
BY THE BASE TO CONSIST OF CONFIRMATION, AND
ADDITION, IF NECESSARY, OF AVAILABLE I/O
COUNTS AND TYPES REQUIRED FOR THE VFD'S.
BASE INTEGRATION INCLUDES ANY PROGRAMMING
CHANGES REQUIRED TO THE ATCC SYSTEM TO
PERFORM THE PUMP CONTROLS AS DESCRIBED IN
THE PUMP CONTROL SEQUENCE ON I003.
NOTES:
WATER PUMP VFD SP-2
WATER PUMP VFD MP-1
WATER PUMP VFD MP-2
WATER PUMP VFD MP-3
WATER PUMP VFD SP-1
SMALL
PUMP SP-2
HSQ/PLC
PANEL
TELEMETRY PANEL ONE-LINE DIAGRAM
Scale: NONE
3/ 4"
C , 2
3/ 4"
C , 2
3/ 4"
C , 1
4- #1
3/ 4"
C , 2
T S
P , C
A T
3/ 4"
C , 2
3/ 4"
C , 2
3/ 4"
C , 1
4- #1
3/ 4"
C , 2
T S
P , C
A T
3/ 4"
C , 2
3/ 4"
C , 2
3/ 4"
C , 1
4- #1
3/ 4"
C , 2
T S
P , C
A T
3/ 4"
C , 2
3/ 4"
C , 2
3/ 4"
C , 1
4- #1
3/ 4"
C , 2
T S
P , C
A T
3/ 4"
C , 2
3/ 4"
C , 2
3/ 4"
C , 1
4- #1
3/ 4"
C , 2
T S
P , C
A T
3/ 4"
C , 2
3/ 4"
C , 2
3/ 4"
C , 1
4- #1
3/ 4"
C , 2
T S
P , C
A T
3/ 4"
C , 2
A AS
0.5 0.5 7.5 7.5
VM
VS
600A, 480V, 3Ø , 3W, 42,000 AIC
1 1 1 1
600AF
600AT
600A, 480V, 3Ø, 3W, 42,000 AIC
600AF 600AF
600AF
400AT
600AF
400AT
MCC-F1
MCC-F2
2"C, 3-1/c #4/0 W/#4GND
SUMP PUMP
W/S 1
SUMP PUMP
W/S 2
CIRCULATING
PUMP
WS-3
CIRCULATING
PUMP
WS-4
2-[3"C, 3-1/C #350 KCMIL
W/#1/0 GND]
12,470 - 480/277 V
LIGHTING
PANEL
FL1
TO EMCS
CONTACTOR
SPACESPACE
VFD
MP-2
VFD
SP-1
1200AF
600AT
1200AF
600AT
100AF
100AT
100AF
100AT
100AF
NA
100AF
NA
100AF
70AT
SPARE
100AF
70AT
100AF
70AT
PANEL SLNW
480V, 3Ø, 3W
480V LIGHTING
CONTACTOR
PANEL
WITH 12-3P
CONTACTORS
TO SECURITY
FENCE LIGHTING
TO SELECTOR SWITCH
AT SITE SUPPORT BLDG
IN SECURITY ROOM VIA
J-BOX TO MHP-1
4"C, 24-1/C #8 W/#10 GND
3/4"C, 3-1/C #10
1 1/2"C, 3-1/C #2
1 1/2"C, 3-1/C #2 W/#8 GND
2-[2 12"C, 3-1/C #4/0 W/#2 GND]
400AF
200AT
400AF
200AT
100AF
40 AT
2-[3"C, 3-1/C #350MCM W/#1/0 GND]
NEMA 2
COMBINATION
STARTER
WITH 40 A FUSE
100 100 15
WATER PUMP
MP-3
FLA = 124A
SPARE1"C, 3-1/c #8
W/#10 GND
1"C, 3-1/c #8
W/#10 GND
100A, 480V, 3Ø, 3W, 22kA SCR
PDP-E1
PDP-FP
800A, 480V, 3Ø, 3W, 22kA SCR
50E
100AF
15AT
100AF
20AT
100AF
20AT
100AF
20AT
100AF
50AT
2"C, 3-1/c #4/0 W/#4GND
SPACE
4"C, 24-1/C #8 W/#10 GND
SPACE
225A
225A 60A
PQM OR
EQUAL
2-[3"C, 3-1/C #350 W/#1/0 GND]
2-[3"C, 3-1/C #350 W/#1/0 GND]
2-[3"C, 3-1/C #350MCM W/#1/0 GND]
2-[2 12"C, 3-1/C #4/0 W/#2 GND]
2-[2 12"C, 3-1/C #4/0 W/#2 GND] 2-[2 12"C, 3-1/C #4/0 W/#2 GND]
M3
600:5
INTERMEDIATE
MAIN BREAKER
"A"
INTERMEDIATE
MAIN BREAKER
"B"
1"C, 3-1/c #6, #10 GND
WATER
PUMP
MP-1
FLA = 124A
225A
VFD
MP-1
A
N3 FROM 12.47 kV
DISTRIBUTION
PMH-9
"SGD3SGC/K3A-B"
50E
FIRE PUMPS
BREAKER
"B"
FIRE PUMPS
BREAKER
"A"
SECURITY
BREAKER
"A"
SECURITY
BREAKER
"B"
4"C, 3-1/C #4/0 W/ GND
750 KVA,
3 PH
60 Hz.
XFMR FT1
"K3ASG/420"
750 KVA,
3 PH
60 Hz.
12,470 - 480/277 V
XFMR FT2
"K3ASG/420"
S.A. S.A.
Z = 5.75%Z = 5.75%
30 KVA,
3 PH
60 Hz.
480 - 208/120 V
VFD
MP-4
VFD
MP-3
100AF
60AT
VFD
SP-2
1"C, 3-1/c #6 W/
#10 GND
100 20
WATER PUMP
MP-4
FLA = 124A
JOCKEY PUMP
JP-4
FLA = 21A
WATER
PUMP
MP-2
FLA = 124A
WATER
PUMP
SP-1
FLA = 27A
1"C, 3-1/c #6, #10 GND
1"C, 3-1/c #6 W/ #10 GND
600AF
600AT
600AF
600AT
SPARE
SEE NOTE 1
2"C, 3-1/c #3/O
W/#6 GND
2"C, 3-1/c #3/O
W/#6 GND
2"C, 3-1/c #3/O
W/#6 GND
2"C, 3-1/c #3/O
W/#6 GND
1. EXISTING 600A PUMP FEEDER BREAKERS
TO REMAIN AND RELABELED AS SPARE.
2. COORDINATE ELECTRICAL EQUIPMENT
WITH PUMP SUBMITTAL DATA.
NOTE:
WATER PUMP
SP-2
FLA = 27A
2315 BRIARGATE
PARKWAY, SUITE 150
COLORADO SPRINGS
COLORADO
Sheet
ID
Sheet
D es ig ne r:
R ev ie w er
Fi le
N am e:
D ra fte r
S ub m itt er
D ra w in g D at e:
S A
FB
P ro je ct M gr
A -E
P ro je ct
M gr
S ym b R ev is io ns
/A dd en da
D at e A pp r
S ca le
SCHRIEVER AIR FORCE BASE,
COLORADO
G
LE
N
2-
E
-0
LI
N E
.D W
G
E-004
N . W
A
LK
E
RJ.
H E
A
LY
A S
S H
O W
N
/0 1/
S . C
O
LE
N . W
A
LK
E R
K . S
P A
R R
O W
E
LE
C
TR
IC
A
L O
N E
L
IN
E D
IA
G
R A
M
S C
H R
IE
V
E R
A
IR
F O
R C
E B
A S
E R
E P
A
IR
B Y
R E
P
LA
C
IN
G D
O M
E S
T
IC
W A
T E
R P
U M
P S
A N
D P
IP
IN
G G
LE
N
2-
THIS IS A STANDARD LEGEND. THEREFORE, NOT
ALL OF THIS INFORMATION MAY BE USED ON THIS
PROJECT.
GENERAL NOTES INSTRUMENT IDENTIFICATION TAG LETTER TABLE (ISA)
XXXXXXX
EQUIPMENT
ABBREVIATION
EQUIPMENT NUMBER
INSTRUMENT IDENTIFICATION
TAG NUMBER
ABBREVIATIONS & LETTER SYMBOLS
1.
FIRST ISA LETTER(S)
SUCCEEDING ISA LETTER(S)
INSTRUMENT LOOP NUMBER
EQUIPMENT IDENTIFICATION
LINE IDENTIFICATION
CCS
CNTRL
COMM
CS
DCS
DR
FC
FO
GW
HMI
HOA
HOR
I/O
MA
MH
MPR
NC
NO
P&ID
PERMIS
PLC
SD
SP
VAC
VFD
VS
CENTRAL CONTROL SYSTEM
CONTROL
COMMUNICATION
CONSTANT SPEED
DISTRIBUTION CONTROL PANEL
DRAIN
FAIL CLOSE
FAIL OPEN
GROUND WATER
HUMAN MACHINE INTERFACE
HAND-OFF-AUTO
HAND-OFF-REMOTE
INPUT/OUTPUT
MANUAL-AUTO
MANHOLE
MOTOR PROTECTION RELAY
NORMALLY CLOSED
OPERATING WATER LEVEL
PROCESS AND INSTRUMENTATION DIAGRAM
PERMISSIVE
PROGRAMMABLE LOGIC CONTROLLER
SHUT DOWN
SET POINT
VACUUM
VARIABLE FREQUENCY DRIVE
VARIABLE SPEED
A B C D E F G
H I J K
L M N O P
Q
R S T U V
W X Y
Z
PROCESS OR INITIATING
VARIABLE
ANALYSIS
BURNER, COMBUSTION
UV
DENSITY (S.G)
VOLTAGE
FLOW RATE
MOTOR
HAND (MANUAL)
CURRENT (ELECTRICAL)
POWER
TIME, TIME
SCHEDULE
LEVEL
MOTION
USER'S CHOICE
USER'S CHOICE
PRESSURE, VACUUM
QUANTITY
RADIATION
SPEED, FREQUENCY
TEMPERATURE
MULTIVARIABLE
VIBRATION,MECHANICAL
ANALYSIS
WEIGHT, FORCE
UNCLASSIFIED (+)
EVENT, STATE OR
PRESENCE
POSITION, DIMENSION
FIRST-LETTER
DIFFERENTIAL
RATIO
SCAN
TIME RATE
OF CHANGE
MOMENTARY
INTEGRATE,
TOTALIZE
SAFETY
X AXIS
Y AXIS
Z AXIS
ALARM
BINARY
PRIMARY ELEMENT
GLASS, GAUGE
VIEWING DEVICE
INDICATE
LIGHT (PILOT)
USER'S CHOICE
ORIFICE, RESTRICTION
(TEST CONNECTION)
POINT
RECORD OR PRINT
MULTIFUNCTION
WELL
UNCLASSIFIED
SUCCEEDING-LETTERS
"OR" FUNCTION
CONTROL
CONTROL STATION
USER'S CHOICE
SWITCH
TRANSMIT
MULTIFUNCTION
VALVE, DAMPER,
LOUVER
UNCLASSIFIED
RELAY, COMPUTE,
CONVERT
DRIVE, ACTUATOR,
UNCLASSIFIED
FINAL CONTROL
ELEMENT
INTERLOCK
CLOSE
HIGH
LOW
MIDDLE
USER'S CHOICE
OPEN
MULTIFUNCTION
UNCLASSIFIED
READOUT OR
PASSIVE FUNCTION OUTPUT FUNCTION MODIFIERMODIFIER
LETTER
LINE SERVICE
GW GROUNDWATER
SURGE ANTICIPATION
VALVE
PUMP CONTROL VALVE
MODULATING
VALVE CONTROLLER
GENERAL INSTRUMENT OR FUNCTION SYMBOLS
VALVE SYMBOLS
MISCELLANEOUS SYMBOLS
ACTUATOR SYMBOLS
GATE
KNIFE GATE
BUTTERFLY
PLUG
SEAT PORT
ECCENTRIC PLUG
DIAPHRAGM
PINCH
NEEDLE
SWING CHECK
BALL CHECK NORMALLY CLOSED (NC)
NORMALLY OPEN (NO)
SAMPLE
MULTI-PORT VALVES (BALL VALVE SHOWN,
FOR OTHER VALVE TYPES, APPROPRIATE
VALVE SYMBOL SHOWN. ) ARROWS
INDICATE FLOW PATTERN. SEAT PORTS
ARE IMPLIED BY INDICATED FLOW
PATTERN.
PRESSURE CONTROL
REGULATED SIDE
AIR AND/OR VACUUM RELEASE
PRESSURE
RELIEF
SLEEVE
PNEUMATIC DIAPHRAM
SPRING-OPPOSED, SINGLE
OR DOUBLE ACTING
PNEUMATIC CYLINDER
SINGLE OR DOUBLE
ACTING ACTUATED BY
ONE INPUT
ROTARY
MOTOR
SOLENOID
HYDRAULIC
MANUAL
ELECTROHYDRAULIC
NOTE:
ON LOSS OF PRIMARY POWER
(PNEUMATIC, ELECTRICAL OR HYDRAULIC)
XX: FO =FAIL OPEN
FC =FAIL CLOSED
FLP=FAIL TO LAST POSITION
PUMP
BALL
10"-DI-GW-XXX-YYY
PIPE MATERIAL
ST STEEL
CO COPPER
DI DUCTILE IRON
PIPE SIZE
PIPE MATERIAL
PIPE SERVICE
INSULATION
CODE
LINE NUMBER
PIPING SYMBOLS
ET ELECTRIC
GT GLYCOL
ST STEAM
INSULATION TYPE
A ANTISWEAT
B BURN PROTECTION
C COLD RETENTION
H HEAT CONSERVATION
INSULATION CODE
INSULATION
THICKNESS
HEAT TRACE TYPE
2" H/GT
INSULATION TYPE
LI
MECHANICAL LINK
LOGIC OR SOFTWARE LINK
ELECTROMAGNETIC OR
SONIC SIGNAL
CAPILLARY TUBE
PNEUMATIC SIGNAL
ELECTRICAL SIGNAL
HYDRAULIC SIGNAL
PROCESS_PRIMARY
PROCESS_SECONDARY
OR CONNECTION TO PROCESS
FIELD BUS
INSTRUMENT SUPPLY,
TRAP
AIR GAP IN OPEN DRAIN
OPEN DRAIN
BLIND FLANGE
CONCENTRIC REDUCER
CLOSED DRAIN
F F
1 = SATELLITE CONTROL ROOM 1, 1A FIELD MOUNTED PANEL BELOW REF 1 REACTORS,
= SATELLITE CONTROL ROOM WHERE INSTRUMENT IS LOCATED (i.e. NC = NERVE CENTER
DCS SHARED DISPLAY, SHARED CONTROL
DCS SHARED DISPLAY, SHARED CONTROL
PANEL MOUNTED PATCHBOARD PT. 12
DCS SHARED DISPLAY, SHARED CONTROL
DCS SHARED DISPLAY, SHARED CONTROL
DCS SHARED DISPLAY, SHARED CONTROL
IN AUXILIARY LOCATION
INSTRUMENT SHARING
2 = SATELLITE CONTROL ROOM 2)
COMMON HOUSING
LIGHT PANEL MOUNT
NORMALLY INACCESSIBLE
IN PRIMARY LOCATION
NORMALLY INACCESSIBLE
IN AUXILIARY LOCATION
NORMALLY ACCESSIBLE
IN PRIMARY LOCATION
NORMALLY ACCESSIBLE
FIELD MOUNTED
IN AUXILIARY LOCATION
RESET FOR LATCH-TYPE ACTUATOR
PURGE OR FLUSHING DEVICE
UNDEFINED INTERLOCK LOGIC
NORMALLY INACCESSIBLE
PROGRAMMABLE LOGIC CONTROLLER
IN PRIMARY LOCATION
NORMALLY INACCESSIBLE
PROGRAMMABLE LOGIC CONTROLLER
IN AUXILIARY LOCATION
NORMALLY ACCESSIBLE
PROGRAMMABLE LOGIC CONTROLLER
IN PRIMARY LOCATION
NORMALLY ACCESSIBLE
PROGRAMMABLE LOGIC CONTROLLER
FIELD MOUNTED
PROGRAMMABLE LOGIC CONTROLLER
NORMALLY INACCESSIBLE
IN AUXILIARY LOCATION
NORMALLY INACCESSIBLE
DISCRETE INSTRUMENT
IN PRIMARY LOCATION
IN AUXILIARY LOCATION
NORMALLY ACCESSIBLE
DISCRETE INSTRUMENT
DISCRETE INSTRUMENT
IN PRIMARY LOCATION
NORMALLY ACCESSIBLE
DISCRETE INSTRUMENT
FIELD MOUNTED
DISCRETE INSTRUMENT
IN AUXILIARY LOCATION
NORMALLY INACCESSIBLE
COMPUTER FUNCTION
IN PRIMARY LOCATION
NORMALLY INACCESSIBLE
COMPUTER FUNCTION
IN AUXILIARY LOCATION
NORMALLY ACCESSIBLE
COMPUTER FUNCTION
IN PRIMARY LOCATION
NORMALLY ACCESSIBLE
COMPUTER FUNCTION
FIELD MOUNTED
COMPUTER FUNCTION
F
L L L L L
MAGNETIC FLOW METER
PIPING SPECIALTY ITEM
LINE LEGEND
HEAT TRACE TYPE
EQUIPMENT ABBREVIATION
P PUMP
XOR GATE
2315 BRIARGATE
PARKWAY, SUITE 150
COLORADO SPRINGS
COLORADO
Sheet
ID
Sheet
D es ig ne r:
R ev ie w er
Fi le
N am e:
D ra fte r
S ub m itt er
D ra w in g D at e:
S A
FB
P ro je ct M gr
A -E
P ro je ct
M gr
S ym b R ev is io ns
/A dd en da
D at e A pp r
S ca le
SCHRIEVER AIR FORCE BASE,
COLORADO
G
LE
N
2-
I-
IN
LE
G .D
W G
I-001
N . W
A
LK
E
RJ.
H E
A
LY
A S
S H
O W
N
/0 1/
S . C
O
LE
N . W
A
LK
E R
K . S
P A
R R
O W
IN
S
TR
U
M E
N
TA
TI
O
N L
E G
E N
D
S C
H R
IE
V
E R
A
IR
F O
R C
E B
A S
E R
E P
A
IR
B Y
R E
P
LA
C
IN
G D
O M
E S
T
IC
W A
T E
R P
U M
P S
A N
D P
IP
IN
G G
LE
N
2-
HYDROPNEUMATIC
TANKS
PS
PS
WATER MAIN
BLDG. 50
WS3
M
CIRCULATION
PUMP
WS4
PIT
PIT
12x8 6x8
8"
CAV PSH
HS
S/S
HS MC MI MA PAH
HOA O/L
HS HS MC MI MA PAH
HOA O/L
PI PI
DPI
TK-1
WATER STORAGE
TANK 1
M
MP-1
PIT
8x4 3x6
8"
PSH
MA
O/L
MI MC HS HSSIC
HOA S/S
YA
FAIL
PAH
MA
O/L
MI MC HS HSSIC
HOA S/S
YA
FAIL
PAH
PIDPI PIT PI
PS-6
M
WS3
PIT
12x8 6x8
8"
HS
S/S
HS MC MI MA PAH
HOA O/L
HS HS MC MI MA PAH
HOA O/L
PI PI
DPI
M
MP-2
PIT
8x4 3x6
8"
PSH
MA
O/L
MI MC HS HSSIC
HOA S/S
YA
FAIL
PAH
MA
O/L
MI MC HS HSSIC
HOA S/S
YA
FAIL
PAH
PIDPI PIT PI
PS-7
M
MP-3
PIT
8x4 3x6
8"
PSH
MA
O/L
MI MC HS HSSIC
HOA S/S
YA
FAIL
PAH
MA
O/L
MI MC HS HSSIC
HOA S/S
YA
FAIL
PAH
PIDPI PIT PI
PS-8
M
MP-4
PIT
8x4 3x6
8" 6"
PSH
MA
O/L
MI MC HS HSSIC
HOA S/S
YA
FAIL
PAH
MA
O/L
MI MC HS HSSIC
HOA S/S
YA
FAIL
PAH
PIDPI
PIT PI
PS-9
MP-1
MEDIUM PUMP 1
MAX DAY DEMAND
PLUS FIRE FLOW
MP-2
MEDIUM PUMP 2
MAX DAY DEMAND
PLUS FIRE FLOW
MP-3
MEDIUM PUMP 3
MAX DAY DEMAND
PLUS FIRE FLOW
MP-4
MEDIUM PUMP 4
MAX DAY DEMAND
PLUS FIRE FLOW
M
JP-4
PIT
2x1.5 1x1.5
2"
PSH
MA
O/L
MIHS
HOAS/S
HS PAH
PIT
PS-2
M
FP-WS3
PIT
12x6 5x10
12"
PSH
MI
O/L
MA SIC YA PAHMC
HOA FAIL
HS
S/S
HS
PIT
PI
PS-5
MI
O/L
MA SIC YA PAHMC
HOA FAIL
HS
S/S
HS
PI
DPI
10"
M
SP-2
PIT
6X3 1.5x4
6"
PSH
MI
O/L
MA SIC YA PAHMC
HOA FAIL
HS
S/S
HS
PIT
PI
PS-4
MI
O/L
MA SIC YA PAHMC
HOA FAIL
HS
S/S
HS
PI
DPI
4"
M
SP-1
PIT
6X3 1.5x4
6"
PSH
MI
O/L
MA SIC YA PAHMC
HOA FAIL
HS
S/S
HS
PIT
PI
PS-3
MI
O/L
MA SIC YA PAHMC
HOA FAIL
HS
S/S
HS
PI
DPI
4"
MC
MA
O/L
MIHS
HOAS/S
HS PAHMC
PI PI
DPI
1.5"
ATCC
6"
6"
6"
ATCC
3/8" 3/8"
CHLORINATOR
TK-1
TK
-3
TK
-4
TK
-5
TK-2
SUMP PUMPS
TO SEWER
MANHOLE
ATCC
WATER MAIN
12"
LI
LILSLAHLAL
LSLAHLAL
8"
12"
CHLORINE
ANALYZER
AND
RECORDER
CHLORINE
ANALYZER
AND
RECORDER
PSL PAL PAL
PS-1 PS-1 PS-1
TK-2
WATER STORAGE
TANK 2
3/ 4"
L
O
LU
TI
O
N R
E
TU
R N
3/ 4"
L
O
LU
TI
O
N R
E
TU
R N
WATER TO
DISTRIBUTION
FIRE PUMP TEST
CONNECTIONS
M
FE
FIT
FQI FIT
PIT
PIT
PI
PI
PCV
PCV
WS4
CIRCULATION
PUMP
SP-1
SMALL PUMP 1
AVERAGE DAY
DEMAND
SP-2
SMALL PUMP 2
AVERAGE DAY
DEMAND
FP-WS3
DIESEL FIRE
PUMP
TK-3/4/5
HYDROPNUEMATIC
TANKS
JP-4
JOCKEY PUMP
12"
8"
12"
6"
3" PVC
1"
S/SLCV
LCV
M
S/S
PS-11
PIT
PSH
PS-10
SET AT
115psig
SET AT
115psig
10X12
8"
NC
8"
1.5x4
4"
3"3" 3"
12"
CAV
CAV
CAV
CAV
CAV
CAV
6x3 3x6
CAV
CAV
CAV
CAV
M
VFD
VFD
VFD
VFD
VFD
VFD
MOTOR
STARTER
8" P
U M
P S
TA
B
Y P
A S
S
8" PUMP STA BYPASS
8" P
U M
P S
TA
B
Y P
A S
S
CAV
CAV
101 101 101 101 101 101 101 101
101101101101101101101101
102 102 102 102 102 102 102 102
102102102102102102102102
103 103 103 103 103 103 103 103
103103103103103103103103
104 104 104 104 104 104 104 104
104104104104104104104104 107 107 107 107 107 107
107 107 107 107 107 107
105 105 105 105 105 105 105 105
105105105105105105105105
106 106 106 106 106 106 106 106
106106106106106106106106
106106
108108
119 119
PSV
PRV
8"
8"
2315 BRIARGATE
PARKWAY, SUITE 150
COLORADO SPRINGS
COLORADO
Sheet
ID
Sheet
D es ig ne r:
R ev ie w er
Fi le
N am e:
D ra fte r
S ub m itt er
D ra w in g D at e:
S A
FB
P ro je ct M gr
A -E
P ro je ct
M gr
S ym b R ev is io ns
/A dd en da
D at e A pp r
S ca le
SCHRIEVER AIR FORCE BASE,
COLORADO
G
LE
N
2-
I-
P
ID
.D W
G
I-002
N . W
A
LK
E
RJ.
H E
A
LY
A S
S H
O W
N
/0 1/
S . C
O
LE
N . W
A
LK
E R
R . A
D A
M S
P R
O C
E S
S
IN
S
TR
U
M E
N
TA
TI
O
N D
IA
G
R A
M
S C
H R
IE
V
E R
A
IR
F O
R C
E B
A S
E R
E P
A
IR
B Y
R E
P
LA
C
IN
G D
O M
E S
T
IC
W A
T E
R P
U M
P S
A N
D P
IP
IN
G G
LE
N
2-
SMALL PUMPS OPERATING PROCEDURE:
A. TWO "SMALL" IDENTICAL PUMPS SP-1 AND SP-2 (1 DUTY AND 1
STANDBY) WILL SUPPLY WATER TO SCHRIEVER AIR FORCE BASE
DURING AVERAGE DAY DEMAND CONDITIONS. EACH PUMP SHALL
BE EQUIPPED WITH AN HOA SWITCH. THE “HAND” MODE IS
INTENDED FOR MAINTENANCE OR TESTING PURPOSES. THE
"AUTO” MODE IS INTENDED FOR NORMAL OPERATING
CONDITIONS. THE PUMPS SHALL OPERATE ACCORDING TO THE
SEQUENCE OF OPERATIONS DESCRIBED BELOW WHEN
OPERATING IN “AUTO” MODE.
B. EACH "SMALL" PUMPS SHALL BE PROVIDED WITH A VFD.
C. THE PUMPS SHALL OPERATE IN A LEAD/LAG MANNER. FAILURE OF
THE LEAD PUMP SHALL ENERGIZE THE LAG PUMP AND
DE-ENERGIZE THE LEAD PUMP. THE LEAD PUMP SHALL
ALTERNATE EVERY 24 HOURS (SELECTABLE). THERE SHALL BE 5
MINUTE (ADJUSTABLE) MINIMUM “ON” AND “OFF” TIMES TO
PREVENT EXCESSIVE CYCLING. THE SMALL PUMPS SHALL NOT
START AND OPERATE AT THE SAME TIME.
D. EITHER PUMP CAN BE SELECTED AS A LEAD PUMP BY THE
OPERATOR AT THE CONTROL SYSTEM.
E. WHEN THE PRESSURE IN THE DISTRIBUTION SYSTEM FALLS
BELOW THE LOW PRESSURE SET POINT WITH THE JOCKEY PUMP,
AND THE "MEDIUM" PUMPS ARE NOT IN SERVICE, THE CONTROL
SYSTEM SHALL START THE LEAD SMALL PUMP AFTER AN
ADJUSTABLE TIME DELAY.
● LOW PRESSURE SET POINT IN THE DISTRIBUTION LINE: 70
PSIG
F. DURING AVERAGE DAY DEMAND FLOW CONDITIONS THE VFDS
SHALL REGULATE THE SMALL MOTOR SPEED TO MAINTAIN THE
OPERATING PRESSURE SET POINT IN THE DISTRIBUTION SYSTEM
MEASURED BY PIT-103 AND PIT-104.
● OPERATING PRESSURE SET POINT : 84 PSIG
G. WHEN THE OPERATING SMALL PUMP IS OPERATING AT 30% OF
ITS MAXIMUM SPEED (ADJUSTABLE), THE CONTROL SYSTEM
SHALL SHUT DOWN THE "SMALL" PUMP.
H. WHEN ANY MEDIUM PUMP STARTS, THE SYSTEM SHALL SHUT
DOWN THE OPERATING SMALL PUMP (WITH ADJUSTABLE TIME
DELAY)
I. WHEN THE FLOWRATE IN THE DISTRIBUTION LINE REDUCES TO 40
GPM, THE CONTROL SYSTEM SHALL SHUT DOWN THE OPERATING
SMALL PUMP (WITH ADJUSTABLE TIME DELAY)
ALARMS AND SAFETY CONTROLS:
A. IN THE EVENT OF LOW OR HIGH PRESSURE IN THE DISTRIBUTION
LINE, VARIOUS ALARMS AND RESPONSES WILL BE TRIGGERED:
● LOW LOW PRESSURE IN THE DISTRIBUTION LINE: 50 PSIG
(ADJUSTABLE), MEASURED BY PIT_103/104, WILL TRIGGER AN
ALARM AND DE-ENERGIZE ALL PUMPS IN SERVICE. THIS
CONDITION REQUIRES A MANUAL RESET.
● LOW PRESSURE IN THE DISTRIBUTION LINE: 60 PSIG
(ADJUSTABLE), MEASURED BY PIT_103/104, WILL TRIGGER AN
ALARM.
● HIGH PRESSURE IN THE DISTRIBUTION LINE: 120 PSIG
(ADJUSTABLE), MEASURED BY PIT_103/104, WILL TRIGGER AN
ALARM AND DE-ENERGIZE ALL PUMPS IN SERVICE EXCEPT THE
DIESEL FIRE PUMP IF IT IS RUNNING. THIS CONDITION
REQUIRES A MANUAL RESET.
B. LOW PRESSURE ALARM IN THE PUMPS SUCTION HEADER WILL BE
TRIGGERED WHEN PRESSURE SWITCH PS-1 IS ACTIVATED. THIS
SWITCH WILL DE-ENERGIZE ALL PUMPS IN SERVICE. THIS
CONDITION REQUIRES A MANUAL RESET.
MEDIUM PUMPS OPERATING PROCEDURE:
A. FOUR "MEDIUM" IDENTICAL PUMPS (1-3 RUNNING, 1 STANDBY)
WILL SUPPLY WATER DURING MAXIMUM DAY DEMAND, PEAK HOUR,
AND FIRE FLOW CONDITIONS.
B. THE "MEDIUM" PUMPS WILL COME ONLINE SEQUENTIALLY AS
NEEDED WHEN DEMAND EXCEEDS 200 GPM, AFTER AN AJUSTABLE
TIME DELAY.
C. EACH "MEDIUM" PUMP SHALL BE PROVIDED WITH A VFD.
D. THE FIRST "MEDIUM" PUMP WILL START WHEN THE FLOW
EXCEEDS 200 GPM. THE "MEDIUM" LEAD PUMP SHALL BE
ENERGIZED PRIOR TO DE-ENERGIZING THE "SMALL" LEAD PUMP
TO PROVIDE CONTINUOUS WATER FLOW
E. THE PUMPS SHALL OPERATE IN A LEAD/LAG MANNER. FAILURE OF
THE LEAD PUMP SHALL ENERGIZE THE LAG PUMP AND
DE-ENERGIZE THE LEAD PUMP. THE LEAD PUMP SHALL
ALTERNATE EVERY 24 HOURS (SELECTABLE). THERE SHALL BE 5
MINUTE (ADJUSTABLE) MINIMUM “ON” AND “OFF” TIMES TO
PREVENT SHORT CYCLING. THE "MEDIUM" PUMPS SHALL NOT
START AT THE SAME TIME. THERE SHALL BE A 60 SECOND
(ADJUSTABLE) DELAY BETWEEN PUMP STARTS. THE LAG PUMP
SHALL BE ENERGIZED PRIOR TO DE-ENERGIZING THE LEAD PUMP
TO PROVIDE CONTINUOUS WATER FLOW.
F. THE VFDS SHALL REGULATE THE PUMP MOTOR SPEEDS TO
MAINTAIN THE OPERATING PRESSURE SET POINT IN THE
DISTRIBUTION SYSTEM MEASURED BY PIT-103/104.
● OPERATING SET POINT IN THE DISTRIBUTION LINE: 84 PSIG
G. WHEN THE LEAD PUMP MOTOR SPEED IS OPERATING AT 90% AND
THE PRESSURE IN THE DISTRIBUTION LINE IS BELOW THE
OPERATING SET POINT, THE CONTROL SYSTEM SHALL START THE
SECOND "MEDIUM" PUMP AFTER AN ADJUSTABLE TIME DELAY PER
PUMPS STARTING SEQUENCE. IF THE OPERATING PRESSURE
CONTINUES TO DECLINE, AND THE FIRST AND SECOND PUMP
MOTOR SPEEDS ARE OPERATING AT 90% OF THEIR MAXIMUM
SPEED OR ABOVE, THE CONTROL SYSTEM SHALL START THE
THIRD "MEDIUM" PUMP.
H. WHEN TWO OR MORE "MEDIUM" PUMPS ARE OPERATING AT THE
SAME TIME, THEIR MOTORS SHALL RUN AT THE SAME SPEED.
I. WHEN "MEDIUM" PUMPS ARE IN SERVICE AND FLOWS ARE OVER
1,000 GPM MONITORED BY FIT-101, PUMPS VFDS SHALL REGULATE
THE MOTOR SPEED TO MAINTAIN A PRESSURE IN THE
DISTRIBUTION SYSTEM EQUAL TO THE FIRE PRESSURE SET POINT
MEASURED BY PIT-103/104. WHEN THE FLOW IS BELOW 1,000 GPM,
THE VFDS SHALL REGULATE THE SPEED OF THE MOTORS TO
MAINTAIN THE OPERATING SET POINT PRESSURE AS DESCRIBED
ABOVE.
● FIRE PRESSURE SET POINT: 110 PSIG
J. WHEN THE PUMPS ARE OPERATING AT 30% OF THEIR MAXIMUM
SPEED (ADJUSTABLE), THE PUMPS SHALL SHUT DOWN IN THE
SAME ORDER AS THE PUMP STARTING SEQUENCE. THE LAST
PUMP TO TURN ON (LAG PUMP) IS THE LAST PUMP TO SHUT DOWN.
WHEN THE LEAD PUMP SHUTS DOWN,THE LAG PUMPS SHALL BE
KEPT IN SERVICE UNTIL ONE OF THE SHUTDOWN CONDITIONS IS
MET AFTER AN ADJUSTABLE TIME DELAY.
K. THE DIESEL PUMP WILL START AUTOMATICALLY IF THE "MEDIUM"
PUMPS FAIL. THE DIESEL PUMP CAN BE STARTED LOCALLY AT THE
PUMP OR…