030ADV250181 Q and A.xlsx

XLSX spreadsheet 12 KB Posted

Attached to
Telecommunications Backup Power
Solicitation number
030ADV25Q0181
Issued by

About this file

This file is a Questions and Answers (Q&A) document for RFQ 030ADV25Q0181, a telecommunications backup power system maintenance solicitation by the Library of Congress. The document provides detailed information about existing battery and UPS installation dates for multiple Library of Congress locations, including James Madison, John Adams, Thomas Jefferson, High Density Storage Facility, Ft. Meade, Library of Congress Child Care Center, and Cabin Branch facilities. The current contract number for the incumbent is LCCIO21P0085, and the Q&A confirms the existence of various backup power systems with battery installations ranging from 1/31/22 to 7/15/24.

The Q&A document reveals that the solicitation requires service, support, and maintenance for telecommunications backup power systems across facilities in Washington D.C. and Maryland, with a minimum eight-hour backup requirement for voice telecommunications equipment. The maintenance includes full replacement of all systems and components at no additional cost to the Library. Importantly, the document indicates that there are currently no existing power plant or battery alarms. The solicitation is structured as a combined synopsis/solicitation for commercial items, with questions regarding the solicitation due by August 18, 2025 at 10:00 AM.

View the file

Other files

File Type Posted
030ADV25Q0181 0002.pdf PDF
030ADV25Q0181 0001.pdf PDF
030ADV25Q0181.pdf PDF
Attachment J1 - Equipment List_Labor Categories_and Pricing.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

RFQ Notice 030ADV25Q0181
8/20/25
ID #SectionReferenceQuestionLibrary Answer
1N/AN/AIs there an incumbent performing these services? If so, could the current contract number please be provided?Yes. LCCIO21P0085
2C.2James Madison Backup Power SystemWhat are the Battery installation dates for the 40 existing batteries at Madison?5/31/18
3C.2John Adams Backup Power SystemWhat are the Battery installation dates for the 12 existing batteries at Adams?7/1/22
4C.2Thomas Jefferson Backup Power SystemWhat are the Battery installation dates for the 12 existing batteries at Jefferson?7/1/22
5C.2High Density Storage Facility Backup Power SystemWhat are the Battery installation dates for the High Density Storage Facility Emerson Netsure 211 20kVA power plant?4/30/23
6C.2Ft. Meade Backup Power SystemWhat are the Battery installation dates for the 8 existing batteries at Ft. Meade, MD?4/30/23
7C.2Library of Congress Child Care Center Backup Power SystemWhat are the Battery and UPS installation dates for the UPS: Eaton PW9130 1.5kVA 120V rack mount w/SNMP card with 4 batteries at the Library of Congress Child Care Center?1/31/22
8C.2Cabin Branch - Copyright Backup Power SystemWhat are the Battery and UPS installation dates for the UPS: Eaton 9PX5K with 2 Extended Battery Modules EBM: 9PX series (w/8 batteries each) at the Cabin Branch Landover, MD?7/15/24
9C.2Cabin Branch Storage Facility Backup Power SystemWhat are the Battery and UPS installation dates for the Eaton 9130 UPS 3kvA rack mount 120V EBM: Eaton 9130 – 3kvA, (3 EBM’s w/6 batteries each) at the Cabin Branch Storage Facility Landover MD?2/18/22
10C.3.2AlarmsAre there presently any existing power plant or battery alarms?No