03- Specification for Bridge Structure.pdf

PDF 364 KB Posted

Attached to
Fiber Reinforce Polymer Foot Bridge Elk State Fore
Solicitation number
6100047504
Issued by
Delaware County, Emporium Borough, Pennsylvania

About this file

This document contains specifications for a pre-fabricated fiber reinforced polymer (FRP) composite truss bridge to be provided to the Pennsylvania Department of Conservation and Natural Resources (DCNR) Bureau of Forestry. The bridge shall have a 40-foot span and 4-foot width, designed to support a uniform live load of 84 psf and a vehicle load of 85 psf. The bridge must meet serviceability criteria for deflection and vibration, with a minimum vertical frequency of 5.0 Hz and horizontal frequency of 3.0 Hz. The FRP composite materials shall have minimum strengths in tension, compression, shear, and bending, with a minimum thickness of 0.25 inches. The bridge will be delivered in component parts or partially assembled, with DCNR responsible for the construction of the abutments and/or footings. The bridge color shall be in natural earth tones, and no painting is required.

The document outlines the submittal requirements, including schematic drawings, diagrams, and structural calculations sealed by a Pennsylvania licensed professional engineer. Fabrication tolerances, railing specifications, and delivery logistics are also detailed. This document appears to be part of the bidding or procurement process for this bridge project, though specific information regarding the bid process, award criteria, or contract duration is not provided.

View the file

Other files

File Type Posted
02- Statement of Work.pdf PDF
Small Business Procurement Initiative_11-2018 Attachment.pdf PDF
Addendum Form.pdf PDF
Reciprocal Limitations Act Form.doc DOC document
01- Terms and Conditions.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PRE-FABRICATED BRIDGE SPECIFICATIONS

1.0 GENERAL

These specifications are for a fully engineered clear span bridge of Fiber Reinforced Polymer (FRP) composite construction and shall be regarded as minimum standards for design and construction as manufactured.

2.0 GENERAL FEATURES OF DESIGN

2.1 SPAN

Bridge span will be 40’-0” (straight line dimension) and shall be measured from each end of the bridge structure.

2.2 WIDTH

Bridge width shall be 4’0” and shall be measured from the inside face of structural elements at deck level.

2.3 BRIDGE SYSTEM TYPE

Bridge must be designed as a FRP Composite Truss Span

2.4 MEMBER COMPONENTS

All members shall be fabricated from pultruded FRP composite profiles and structural shapes a required

2.5 CAMBER

Bridge can be precambered to eliminate initial dead load deflections. Camber of 1% of the total span length can be provided on request

3.0 ENGINEERING

Structural design of the bridge structure shall be performed by or under the direct supervision of a Licensed Professional Engineer, licensed in the State of Pennsylvania and done in accordance with recognized engineering practices and principles

3.1 UNIFORM LIVE LOAD

Bridge shall be designed for 84 psf.

3.2 VEHICLE LOAD

Bridge shall be designed for 85 psf.

3.3 WIND LOAD

The bridge shall be designed for a minimum wind load of 23 psf. The wind is calculated on the entire vertical structure of the bridge as if fully enclosed

3.4 SEISMIC LOAD

Seismic loads shall be determined according to the criteria specified in the standard building codes (IBC 2002, /ASCE 7-02, BOCA, SBC or UBC) unless otherwise requested. Response Spectrum Analysis shall be performed in those designs that require complex seismic investigation.

All necessary response spectra information will be provided by the client for evaluation

3.5 ALLOWABLE STRESS DESIGN APPROACH

An allowable Stress Design (ASD) approach is to be used for the design of structural members, Bidders should comply with the design of FRP bridges are as follows unless otherwise specified:

(Based on the Ultimate Strength of the FRP material)

Tension 2.5

Compression 2.5

Shear 2.5

Bending 2.5

End Bending 2.5

Connections 3.0

3.6 SERVICEABILITY CRITERIA

Service loads are used for the design of all structural members when addressing deflection and vibration issues. Criteria used by Bidder in the design of FRP bridges should be as follows:

Deflection:

Live Load (LL) deflection = L/240

Vertical Frequency (fn): = 5.0Hz

The fundamental frequency of the pedestrian bridge (in the vertical direction) without live load should be greater than 5.0 hertz (Hz) to avoid any issues with the first and second harmonics.

Horizontal Frequency (fn): = 3.0 Hz

The fundamental frequency of the pedestrian bridge (in the horizontal position without live load should be greater than 3.0 hertz (Hz) to avoid any issues due to side to side motion involving the first and second harmonics

3.7 SNOW LOAD

Sustained snow load conditions shall be evaluated for time dependent effects (creep and relaxation) and expected recovery behavior

4.0 MATERIALS

4.1 FPR COMPOSITES

FRP bridge shall be fabricated from high-strength E-glass and isophthalic polyester resin unless otherwise specified

Weathering and ultraviolet light protection shall be provided by addition of a veil to the laminate Construction. Minimum materials strengths and properties are as follows:

Tension 33,000 psi

Compression 33,000 psi

Shear 4,500 psi Bending 33,000 psi Young’s Modulus 2,800,000 psi

The minimum thickness of FRP Composite shapes shall be as follow unless otherwise specified:

Square tube members (closed type shape) shall be 0.25 in. Wide-flange beams, channel sections, and angles (open type shapes) shall be a minimum thickness of 0.25 in. Standard plate shall be a minimum thickness of 0.25 in.

4.2 DECKING

Wood decking in No. 2 or better Southern Yellow Pine treated according to the American Wood Preservers Bureau. The standard three inches (3”) thick x twelve inches (12”) wide planks are provided for pedestrian loading conditions

4.3 HARDWARE

Bolted connections shall be A307 hot-dipped galvanized steel unless otherwise specified.

Mounting devices shall be galvanized or stainless steel.

5.0 SUBMITTALS

5.1 SUBMITTAL DRAWINGS

Schematic drawings and diagrams shall be submitted to DCNR for review after receipt of order.

As required, all drawings shall be signed and sealed by a Pennsylvania Licensed Professional Engineer.

5.2 SUBMITTAL CALCULATIONS

As required, structural calculations shall be submitted to the DCNR. All calculations will be signed and sealed by a Pennsylvania Licensed Professional Engineer

6.0 FABRICATION

6.1 TOLERANCES

All cutting and drilling fabrication to be done by experienced fiberglass workers using carbide or diamond-tipped tooling to a tolerance of 1/16”. No material deviations beyond industry standards are accepted. All cut edges to be cleaned and sealed.

7.0 RAILINGS

Railings for bridges will be a minimum of forty-two inches (42”) above the floor deck.

7.1 SAFETY RAILS

Continuous horizontal midrails shall be located on the inside of the bridge trusses. Maximum opening between the midrails shall be available as required, but should not be greater than nine inches (9”)

7.2 TOEPLATES

Toeplates are three inches (3”) green channels

8.0 FINISHING

Bridge color shall be Natural Earth Tones (brown, green, gray, etc.). No painting is required as the color is added during the manufacturing process.

9.0 DELIVERY

9.1 Delivery is made by truck to:

DCNR Bureau of Forestry 258 Sizerville Road Emporium., PA 15834

Bidder will notify DCNR in advance of the expected time of arrival at the site. Bridge will be shipped to the site in components parts or partially assembled. The spans can be completely assembled using standard hand tools.

9.2 ERECTION DIRECTION

For bridge shipped in components parts or partially assembled, Bidder shall provide assembly drawings and a recommended assembly procedure for building the bridge. Temporary supports or rigging equipment, if needed, is the responsibility of the DCNR.

9.3 SITE ISSUES and FOUNDATION DESIGN

DCNR shall procure all necessary information about the site and soil conditions. The construction of the bridge abutments, and/or footings shall be by DCNR.

File details come from the government source that posted it. Updated .